Page 1: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

OPSM 301 Operations Management

Class 26:

Project Management:

Introduction and CPM

Koç University

Zeynep [email protected]

Page 2: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Announcements

Last Module: Project Management From readings in course pack Next class on Monday December 26 will

be in SOS 180

Page 3: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Why project management?

Competition through new product development

Information-intensive products: costly to produce, cheap to reproduce

Flatter organizations Systems approach Project approach

Page 4: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Project

A single “product” is obtained from the completion of a project

The differentiating characteristic of projects from processes is the intense uncertainty in projects

Two types of project– With absolute deadline: olympic stadium

– With relative deadline : new product development project

Successful project management: To finish on time without going over budget and without sacrificing from the scope of the project

Page 5: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Project Management

Examples– Construction– R & D– Computer system implementation– Product development– Advertising campaign– Business Plan

Page 6: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Project Management

Resources

BudgetSco

pe

Schedule

Page 7: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Projects are Balancing Acts

Precedence Structure

Statistical Variation

HumanBehavior

Quality andScope

Timing andSchedule

BudgetedCosts

Page 8: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Some observations

Most projects – Either go over time– or over budget– or the promised content cannot be delivered

Little’s law: more projects in the system (WIP), longer completion times

Page 9: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Modern Project Management

The process of project management has two dimensions: the “science” and the “art” of project management– Technical: defining, planning and controlling– Socio-Cultural:

• stimulating teamwork and personal motivation• identifying and resolving problems• shaping customer expectations• sustaining political support of top management• monitoring subcontractors• negotiating with functional managers

Page 10: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

10

Planning Objectives Resources Work break-

down schedule Organization

Scheduling Project

activities Start & end

times Network

Controlling Monitor, compare,

revise, action

Project Management Activities

Page 11: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Project Planning, Scheduling, and Controlling

Page 12: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Work Breakdown Structure

1. Project 2. Major tasks in the project 3. Subtasks in the major tasks 4. Activities (or work packages)

to be completed

Page 13: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

The Work Breakdown Structure

1. House

1.2 Heating System

WP-F1WP-F2

WP-P1WP-P2WP-P3

1.2.3 Fuel Tank

1.2.2 Furnace

1.2.1 Piping

1.3 Interior Design

1.1 Building/Structure

1.4 Garden/Parking

1.2.4 Solar Panels

WP-FT1WP-FT2WP-FT3

WP-SP1 WP-SP4 WP-SP2 WP-SP5WP-SP3

Page 14: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

14

Gantt chart Critical Path Method (CPM) Program Evaluation &

Review Technique (PERT)

Project Scheduling and Controlling

Page 15: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

15

Network techniques Developed in 1950’s

– CPM by DuPont for chemical plants (1957)– PERT by Booz, Allen & Hamilton with the U.S.

Navy, for Polaris missile (1958)

Consider precedence relationships and interdependencies

Each uses a different estimate of activity times

PERT and CPM

Page 16: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

16

Is the project on schedule, ahead of schedule, or behind schedule?

Is the project over or under cost budget?

Are there enough resources available to finish the project on time?

If the project must be finished in less than the scheduled amount of time, what is the way to accomplish this at least cost?

Questions Which May Be Addressed by PERT & CPM

Page 17: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

17

The Six Steps Common to PERT & CPM

1. Define the project and prepare the work breakdown structure,

2. Develop relationships among the activities. (Decide which activities must precede and which must follow others.)

3. Draw the network connecting all of the activities

4. Assign time and/or cost estimates to each activity

5. Compute the longest time path through the network. This is called the critical path

6. Use the network to help plan, schedule, monitor, and control the project

Page 18: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

18

Precedence Relations

Activity Immediate Predecessor Duration (days)

A (Start) 4

B A 3

C A 5

D B,C 2

Page 19: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

19

Simple Project Network

A

B

C

D

Activity “A”precedes Activity “B”

precedence relations as “arcs”

Page 20: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

20

Provides activity information– Earliest (ES) & latest (LS) start– Earliest (EF) & latest (LF) finish– Slack (S): Allowable delay

Identifies critical path– Longest path in network– Shortest time project can be completed– Any delay on critical path activities delays

project– Critical path activities have 0 slack

Critical Path Analysis

Page 21: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

21

Begin at starting event and work forward ES = 0 for starting activities

– ES is earliest start

EF = ES + Activity time– EF is earliest finish

ES = Maximum EF of all predecessors for non-starting activities

Earliest Start and Finish Steps

Page 22: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

22

Begin at ending event and work backward

LF = Maximum EF for ending activities– LF is latest finish; EF is earliest finish

LS = LF - Activity time– LS is latest start

LF = Minimum LS of all successors for non-ending activities

Latest Start and Finish Steps

Page 23: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Latest Start and Finish Steps

Latest Finish

ES

LS

EF

LF

Earliest Finish

Latest Start

Earliest Start

Activity Nam

eActivity Duration

Page 24: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Finding the Critical Path

A D

C

B

4

3

5

20 4

4

4

7

9

9 11

119

9

9

6

4

40

Activity Slack:S = LS-ES, orS = LF-EF

Start attime t=0

ES

LS

EF

LF

Page 25: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

Finding the Critical Path

A D

C

B

4

3

5

20 4

4

4

7

9

9 11

119

9

9

6

4

40

S=0S=0

S=0

S=2

Critical Path: Path with zero activity slacks

Activity Slack:S = LS-ES, orS = LF-EF

Page 26: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

26

Yozgat Paper Manufacturing Activities

Activity Description Immediate Predecessors

Time

(weeks)

A Build internal components - 2

B Modify roof and floor - 3

C Construct collection stack A 2

D Pour concrete and install frame

A, B 4

E Build high-temperature burner

C 4

F Install pollution control system

C 3

G Install air pollution device D, E 5

H Inspect and test F, G 2

Page 27: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

27

AON Network for Yozgat Paper Manufacturing

Start

A

B

C

D

F

F

G

H

Page 28: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

28

Critical Path for Yozgat Paper Manufacturing

Start

A

B

C

D

E

F

G

H

Page 29: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

29

AON Network for Yozgat Paper Manufacturing

Slack=0

Start

A

B

C

D

F

F

G

HH

1313

2

1515

HG

88

5

1313

HF

410

3

713

HC

22

2

44

HE

44

4

88

HD

34

4

78

HB

01

3

34

HA

00

2

22

H00

0

00

Slack=0 Slack=0

Slack=0

Slack=0

Slack=6

Slack=1Slack=1

Start

Page 30: OPSM 301 Operations Management Class 26: Project Management: Introduction and CPM Koç University Zeynep Aksin zaksin@ku.edu.tr.

30

Gantt ChartEarliest Start and Finish

Yozgat Paper ManufacturingYozgat Paper Manufacturing

A Build internal components

B Modify roof and floor

C Construct collection stack

D Pour concrete and install frame

E Build high-temperature burner

F Install pollution control system

G Install air pollution device

H Inspect and test

1 2 3 4 5 6 7 8 9 10 1112 13 1415 16