OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin [email protected]
25

OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin [email protected].

Dec 28, 2015

Download

Documents

Jocelin Skinner
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

OPSM 501: Operations Management

Week 5:

Batching

EOQ

Koç University Graduate School of BusinessMBA Program

Zeynep [email protected]

Page 2: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

High-Inventory Manufacturing

D : 3/4 hr/unit

B : 1/10 hr/unit

C : 1 hr/unit

B : 1/10 hr/unit

A : 1/2 hr/unit

Time (hours) 1000 2000

4 months (24 hrs a day, 7 days a week)

inventory

avg.inventory

Order :1000 units

Page 3: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Low-Inventory Manufacturing

D : 3/4 hr/unit

B : 1/10 hr/unit

C : 1 hr/unit

B : 1/10 hr/unit

A : 1/2 hr/unit

Time (hours) 1000 2000

2 months

avg.inventory

Order :1000 units

inventory

Move batches of 200Release materials according to the bottleneck

Page 4: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

When do you detect quality problems?

D

B

C

B

A

Damage done

Quality control

Page 5: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

How do you incorporate engineering changes?

D

B

C

B

A

Engineering change one month after start of order

Page 6: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Shorter Lead time - High margins

D

B

C

B

A

overtime No overtime

Quoted lead time of the order is 3 months

Page 7: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Due-date performance

D

B

C

B

A

Forecast validity

Page 8: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Production with large batches Production with small batches

CycleInventory

End ofMonth

Beginning ofMonth

CycleInventory

End ofMonth

Beginning ofMonth

Produce Sedan

Produce Station wagon

Production with large batches Production with small batches

CycleInventory

End ofMonth

Beginning ofMonth

CycleInventory

End ofMonth

Beginning ofMonth

Produce Sedan

Produce Station wagon

Production with large batches Production with small batches

CycleInventory

End ofMonth

Beginning ofMonth

CycleInventory

End ofMonth

Beginning ofMonth

Produce Sedan

Produce Station wagon

Production with large batches Production with small batches

CycleInventory

End ofMonth

Beginning ofMonth

CycleInventory

End ofMonth

Beginning ofMonth

Produce Sedan

Produce Station wagon

• SMED (Single minute exchange of die): reduce set-up times

Batch Flow Operations Carry a Lot of Inventory

Page 9: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Things that influence flow time

Process control Lotsize

– Before I move from one product run to another, how much will I produce

• Physical constraints

• Customer order size

• Managerial decisions

Set-up time/production time

Page 10: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Batching in practice

• Common in low volume manufacturing (including a lot of high-tech)

• Also: transportation, education / training• Example: mailing list development• Creates an inherent mismatch between demand

and supply

Page 11: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Lotsize decision

Three products: P1, P2, P3 Produce 100 units of each Alternatives

– 100 P1 100 P2 100P3

– 1P1 1P2 1P3 1P1 1P2 1P3• 100 times

Set-up time– Cutting tools, cleaning, calibration, loading programs, etc.

Page 12: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Set-up times

Set-up time does not depend on lotsize and is the same for all lotsizes.

Production time depends on lotsize– Not always (baking, heat treat)

Long set-up times large lotsizes

Page 13: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Example

P1,P2,P3 example– Set-up time 60 min.– Production time 10 min/unit– Need 3 of each type

Try the alternatives– 1P1, 1P2, 1P3, 1P1, 1P2, 1P3, 1P1, 1P2, 1P3

– 3P1, 3P2, 3P3

Page 14: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Responsiveness

Costs

High

Low

High perunit costs

Low perunit costs

Now

Smaller batches

Largerbatches

Reduce set-up times

Higherfrontier

Product Space, Efficient frontier

Page 15: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

• Capacity calculation changes:

• Note: Capacity increases with batch size:

• Note further: … and so does inventory (and thus flow time)

Batch Size

Set-up time + Batch-size*Time per unitCapacity given Batch Size=

Capacity 1/p

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0.4

0.45

0.5

10

50

90

13

0

17

0

21

0

25

0

29

0

33

0

37

0

41

0

45

0

49

0

53

0

57

0

61

0

65

0 Batch Size

See chapter 5

Process Analysis with Batching

Page 16: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Example

MillingS=120 minp= 2 min/unit

AssemblyS=0p=3 min/unit

B=12? B=300? Recommended B=?

Page 17: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Economies of Scale:Inventory Management for a Retailer

The South Face retail shop in the SapphireTower has observed a stable monthly demand for its line of Gore-Tex jackets on the order of 100 jackets per month. The retail shop incurs a fixed cost of $2,000 every time it places an order to the Adana warehouse for stock replenishment. The marginal cost of a jacket is $200, and South Face’s cost of capital is approximately 25%.

What order size would you recommend for The South Face?

retailerwarehouse

Page 18: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Economies of Scale: Inventory Build-Up Diagram

R: Annual demand rate,

Q: Number of jackets per replenishment order

Number of orders per year = R/Q.

Average number of jackets in inventory = Q/2 .

Q

Time t

Inventory Profile:# of jackets in inventory over time.

R = Demand rate

Inventory

Page 19: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Find most economical order quantity: Spreadsheet for The South Face

Number of units Number ofper order/batch Batches per Annual Annual Annual

Q Year: R/Q Setup Cost Holding Cost Total Cost

50 24 48000 1250 49250100 12 24000 2500 26500150 8 16000 3750 19750200 6 12000 5000 17000250 5 9600 6250 15850260 5 9231 6500 15731270 4 8889 6750 15639280 4 8571 7000 15571290 4 8276 7250 15526300 4 8000 7500 15500310 4 7742 7750 15492320 4 7500 8000 15500330 4 7273 8250 15523340 4 7059 8500 15559350 3 6857 8750 15607400 3 6000 10000 16000500 2 4800 12500 17300600 2 4000 15000 19000700 2 3429 17500 20929

Page 20: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

H2

Q S +

Q

RTC = RC +

Total Annual CostTotal Annual Cost

Total Annual Cost = Annual

PurchasingCost

AnnualOrdering

Cost

AnnualHolding

Cost+ +

Using calculus, we can take the derivative of the total cost function and set the derivative (slope) equal to zero

We can also use economic intuition

Page 21: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Economies of Scale: Economic Order Quantity EOQ

R : Demand per year,

S : Setup or Order Cost ($/setup; $/order),

H : Marginal annual holding cost ($/per unit per year),

Q : Order quantity.

C : Cost per unit ($/unit),

r : Cost of capital (%/yr),

h : Physical unit holding cost

($/unit,yr),

H = (h + r) C.

H

SRQEOQ

2

Batch Size Q

Total annual costs

H Q/2: Annual holding cost

S R /Q:Annual setup cost

EOQ

Page 22: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

EOQ Model: if there is a lead time LEOQ Model: if there is a lead time LEOQ Model: if there is a lead time LEOQ Model: if there is a lead time L

ROP = Reorder point L = Lead time (constant)Q = Economic order quantity

L L

ROP

Time

# U

nit

s on

han

dQEOQ

Page 23: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Economic Order Quantity (EOQ) Model

Economic Order Quantity (EOQ) Model– Robust, widely used

– Insensitive to errors in estimating parameters (40-20-2 Rule):

• 40% error in one of the parameters

• 20% error in Q

•< 2% of total cost penalty

Page 24: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.

Learning Objectives: Batching & Economies of Scale

Increasing batch size of production (or purchase) increases average inventories (and thus cycle times).

Average inventory for a batch size of Q is Q/2. The optimal batch size trades off setup cost and holding cost. To reduce batch size, one has to reduce setup cost (time). Square-root relationship between Q and (R, S):

– If demand increases by a factor of 4, it is optimal to increase batch size by a factor of 2 and produce (order) twice as often.

– To reduce batch size by a factor of 2, setup cost has to be reduced by a factor of 4.

Page 25: OPSM 501: Operations Management Week 5: Batching EOQ Koç University Graduate School of Business MBA Program Zeynep Aksin zaksin@ku.edu.tr.