Land Development Update
NAIOP/NVBIA Joint MeetingMarch 10, 2015
05/01/2023 2
Booster Shot Hiring
Agency Division Classification Status Comments1 CAP Engineer III S27 1 - Filled Street Light Focus 2 DPZ Zoning Administration Planner III S27 1 - Filled 3 DPZ Zoning Evaluation Planner III S27 1 - Filled 4 DPZ Zoning Evaluation Planner III S27 1 - Filled Filled as Planner III5 FCDOT Transportation Planner II S24 1 - Filled 6 FCDOT Transportation Planner II S24 1 - Filled 7 Fire Marshal Fire Inspector II S20 1 - Filled 8 Fire Marshal Fire Inspector II S20 1 - Filled 9 Fire Marshal Administrative Assistant II S13 1 - Filled
10 Fire Marshal Engineer III S27 1 - Filled
11Health Department Environmental Health Environmental Health Spec II S23 1 - Filled
12 LDS Building Plan Review & Inspections Code Specialist II S24 1 - Filled 13 LDS Director's Office Management Analyst I S21 1 - Filled 14 LDS Code Development & Compliance Engineer Tech II S18 1 - Filled 15 LDS Code Development & Compliance Code Specialist II S24 1 - Filled 16 LDS Site Development & Inspections Senior Engineer III S28 1 - Filled 17 LDS Code Development & Compliance Code Specialist II S24 1 - Filled 18 LDS Code Development & Compliance Engineer Tech III S21 1 - Filled 19 LDS IT Business Analyst III S27 1 - Filled 20 LDS Director's Office Planner IV S29 1 - Filled 21 LDS Building Plan Review & Inspections Engineer III S27 1 - Filled 22 LDS Site Development & Inspections Sr Engineer III S28 1 - Filled Reclassified; filled23 LDS Site Development & Inspections Senior Engineering Inspector S21 1 - Filled 24 Urban Forestry Urban Forester II S24 1 - Filled 25 LDS Director's Office Assistant Director S34 2 - Interviews LDS Operations Director26 LDS HR Human Resources Generalist II S24 2 - Interviews 27 LDS Building Plan Review & Inspections Engineer IV S29 2 - Interviews Reclassified from Eng III to Eng IV28 Fire Marshal Engineer III S27 3 - Advertising re-advertising; offer declined
05/01/2023 3
Average Site Plan Timelines
Plan Types Target Dec – Feb Last Period (Nov-Jan)
Average for 2015
Average for 2014
Infill Lot Grading Plan (INF, Non-bonded Single Family) 21 30 30 26.0 25.9
Major Plan First Submission (SP, SD, PI) 60 61 60 58.5 66.8
Major (SP, SD, PI) Second DPE 14 / 28 28 24 22.2 33.1
Major (SP, SD, PI) Subsequent Non-DPE 45 57 64 62.1 68.6
05/01/2023 4
Average Review TimeResidential Building
05/01/2023 5
Average Review Time Commercial Building
05/01/2023 6
Average Review Time Commercial Building
7
Building Official’s Blog
http://www.fairfaxcounty.gov/dpwes/blogs/building-official.htm
05/01/2023 8
Fire Marshal’s Office
Plan Type No. on Hand Oldest Date Work Day Lag
Sprinkler, Tenant plans without calculations 4 3-1-16 0
Sprinkler, Tenant plans with calculations 4 2-25-16 3
Sprinkler, Shell Bldgs., NFPA 13 systems 6 2-10-16 13
Sprinkler, Shell Bldgs., NFPA 13-R & 13-D systems 0 -- 0
Town of Herndon Building Tenant 1 2-24-16 4
Fire Alarm, Tenant plans 18 2-23-16 5
Fire Alarm, Shell Bldgs. 0 -- 0
Door Lock / Security plans 2 3-1-16 0
Range Hood/Tanks/Foam/Public Safety Plans /Misc. 6 2-25-16 3
Site Plans/Rezoning 10 / 0 2-18-16 8
High-Piled Storage Plans 1 2-16-16 10
Evacuation / Lockdown Plans 0 -- 0
Burkholder Building Summary 52 2-10-16 XXXXXXXXX
FM Architectural Review done at Herrity Building(Class 4 and Greater Building Plans) 10 2-10-16 13
FM Architectural Review (Fast Track Tenant Plans) 6 3-1-16 0
FM Arch. Review (non-Fast Track Tenant Plans) 23 2-24-16 4
Herrity Building (B-2) Summary 39 2-10-16 XXXXXXXXX
PLANS REVIEW INVENTORY
05/01/20239
WORKDAY TURNAROUND AVERAGES
05/01/202310
WORKDAY TURNAROUND AVERAGES
05/01/202311
PLAN REVIEW WORKDAY TURNAROUND AVERAGES
SHELL INTERIOR BUILDINGS ALTERATIONS (NON-FAST TRACK TENANT PLANS)2015: 8.3 DAYS 1.2 DAYS 2014: 17.4 DAYS 4.4 DAYS ---------------------------------------------------------------------IMPROVEMENT:
9.1 DAYS 3.2 DAYS (52% DECREASE) (73% DECREASE)
05/01/202312
ACCEPTANCE TESTING OF FIRE PROTECTION SYSTEMS
Currently at 3 days Buildings are required to be posted for 24 hours prior to
fire alarm testing.
Walk-through Program Next day inspection is offered
05/01/202313
SPRINKLER SAVES SINCE DECEMBER 19, 2015
05/01/202314
05/01/2023 15
Planning & Zoning
16
ZONING EVALUATION DIVISION METRICS
FY 2013 FY 2014 FY 2015 FY 2016 (to date)
020406080
100120140
Average Calendar Days for Acceptance
05/01/2023
ZONING EVALUATION DIVISION METRICS
FY 2013 FY 2014 FY 2015 FY 2016 (to date)
02468
1012
Average Time to Board of Supervisors Action
05/01/2023 17
05/01/2023 18
New NVBIA/NAIOP Webpage
http://www.fairfaxcounty.gov/dpwes/committees/nvbia-naiop-fairfax-committee.htm
05/01/2023 19
Thank you