Schedule 9 – Part 1 Practical Completion 07/01/2013 Part 1 Page 1 of 21 Part 1 – Practical Completion 1 For the purposes of this Schedule 9 only, the South Kirkby Main RCV Facility shall be deemed to be a Non-Acceptance Test Facility and references to New Waste Management Facilities shall exclude the Carrwood Road TLS. 2 Where applicable each New Waste Management Facility and the South Kirkby Main Site shall for the purposes of Practical Completion satisfy the following requirements in accordance with the Works Delivery Plan and all Necessary Consents:- a) has been designed and constructed on the relevant Site; b) has had any relevant landscaped areas completed; c) has had any other facilities shown on the appropriate drawings completed; d) all external fencing, gates, security equipment, vehicular and pedestrian accesses have been completed; e) is secure from intrusion and uncontrolled public access; f) all buildings are weatherproof and watertight as appropriate; g) all building services, drains, fire and any security related equipment have been completed; h) all surface water drainage connections have been completed in accordance with the requirements of the land drainage authority and any damage has been made good; i) any foul sewer diversion has been completed; j) all buildings, and the relevant parts of each Site are clean and tidy and all debris and rubbish have been removed; k) all mechanical and electrical installations, plant and equipment have been installed, tested, certified and are safe for use; l) all weighbridges have been calibrated and are operational; m) is entitled to operate lawfully and accept Contract Waste; n) all health and safety systems are operational; and o) all roads and hard-standings required for the delivery of Contract Waste have been constructed and completed including surface dressings, kerbs, drainage and road markings.
21
Embed
Schedule 9 Part 1 Practical Completion Part 1 ... - Wakefield
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Schedule 9 – Part 1 Practical Completion
07/01/2013 Part 1
Page 1 of 21
Part 1 – Practical Completion
1 For the purposes of this Schedule 9 only, the South Kirkby Main RCV Facility shall be deemed to be a Non-Acceptance Test Facility and references to New Waste Management Facilities shall exclude the Carrwood Road TLS.
2 Where applicable each New Waste Management Facility and the South Kirkby Main Site shall for the purposes of Practical Completion satisfy the following requirements in accordance with the Works Delivery Plan and all Necessary Consents:-
a) has been designed and constructed on the relevant Site;
b) has had any relevant landscaped areas completed;
c) has had any other facilities shown on the appropriate drawings completed;
d) all external fencing, gates, security equipment, vehicular and pedestrian accesses have been completed;
e) is secure from intrusion and uncontrolled public access;
f) all buildings are weatherproof and watertight as appropriate;
g) all building services, drains, fire and any security related equipment have been completed;
h) all surface water drainage connections have been completed in accordance with the requirements of the land drainage authority and any damage has been made good;
i) any foul sewer diversion has been completed;
j) all buildings, and the relevant parts of each Site are clean and tidy and all debris and rubbish have been removed;
k) all mechanical and electrical installations, plant and equipment have been installed, tested, certified and are safe for use;
l) all weighbridges have been calibrated and are operational;
m) is entitled to operate lawfully and accept Contract Waste;
n) all health and safety systems are operational; and
o) all roads and hard-standings required for the delivery of Contract Waste have been constructed and completed including surface dressings, kerbs, drainage and road markings.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 2 of 21
Part 2 – Acceptance Tests
Acceptance Tests will be carried out using Contract Waste only and no Non-Contract
Waste will be processed during the conduct of these Acceptance Tests.
The Acceptance Tests shall be carried out in accordance with the agreed Acceptance
Test Programme.
The Acceptance Tests shall be supervised by the Independent Certifier and the
Contractor.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 3 of 21
1. South Kirkby Main Composting Facility
1.1 The Acceptance Test
1.1.1 The Acceptance Test will demonstrate that the South Kirkby Main Composting Facility can process the Composting Input without breaching the Environmental Permit and produce Composted Material in accordance with test 1.1 of Table 1 below.
1.1.2 In order to complete the test in a reasonable period of time the Acceptance Test will be restricted to the processing of four (4) composting tunnels worth of Composting Input over a complete composting cycle using the normal operational Composting procedure as set out in section 2.10.4.1 of the Works Delivery Plan and the Operating Manuals.
1.1.3 Four (4) of the first stage composting tunnels will be filled to their design operating capacities so that the required composting conditions are achieved and maintained throughout the period of the Acceptance Test. The time taken to fill the four (4) tunnels will depend on the delivery rate of Composting Input.
1.1.4 The criteria being monitored or measured are defined in Table 1 below.
1.1.5 The Acceptance Test of the South Kirkby Main Composting Facility shall be deemed passed provided the pass criteria defined in Table 1 below are achieved
1.1.6 Should the pass criteria in test 1.1 of Table 1 below not be achieved then, following modification to the South Kirkby Main Composting Facility, test 1.1 shall be repeated with a duration that shall be agreed with the Independent Certifier.
1.1.7 Should the pass criteria in tests 1.3, 1.4, or 1.5 of Table 1 below not be achieved then, following modification to the South Kirkby Main Composting Facility, that test shall be repeated within the remaining period of the Acceptance Test or the period of the Acceptance Test shall be increased to accommodate the retest as agreed with the Independent Certifier.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 4 of 21
Table 1 South Kirkby Main Composting Facility Parameters
Test Feature being
tested
Any specific conditions for
the facility to ensure that the
feature being tested is
subject of a valid test
Test Process and parameters measured Pass Criteria
1.1 Throughput of
the South
Kirkby Main
Composting
Facility
Throughout the period of the
Acceptance Test the South
Kirkby Main Composting
Facility shall be operated in
accordance with the relevant
Operating Manuals.
The South Kirkby Main
Composting Facility will be
staffed with the number of Staff
as set out in the relevant
Operating Manuals. Staff will
have completed the appropriate
induction and training process
prior to the commencement of
the Acceptance Test.
The time taken to reach maturity will depend on a number
of parameters and it is the role of the Contractor’s
composting operator to determine when the composting
process has finished. When the Contractor’s composting
operator deems that, after maturation, the material has
reached a suitable condition, the composted material for
each of the four batches shall be sampled using the
guidance in BS EN 12579 and the samples shall be tested
to demonstrate that the South Kirkby Main Composting
Facility can produce Composted Material to achieve:
a Composted Material compliant for agricultural or horticultural use in accordance with the standards defined in Table 1 of the Materials and Energy Marketing Plan.
and after further maturation and screening a Composted Material that meets the product quality aspects of PAS 100:2005 standard and is in accordance with Quality Protocol - Compost (the Quality protocol for the production and use of quality compost from source-segregated biodegradable waste” published by WRAP and the Environment Agency, July 2010).
1.2 Contribution of
the facility to
Contract
Targets
Throughout the period of the
Acceptance Test the South
Kirkby Main Composting
Facility shall be operated in
accordance with the relevant
Tonnage of Composting Input will be recorded and a mass
balance will be compiled detailing the input and output
streams across the South Kirkby Main Composting Facility.
Although there is no specific figure for the South Kirkby
Main Composting Facility the mass balance will be used to
determine the contribution of the South Kirkby Main
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 5 of 21
Operating Manuals.
The South Kirkby Main
Composting Facility will be
staffed with the number of Staff
as set out in the relevant
Operating Manuals. Staff will
have completed the appropriate
induction and training process
prior to the commencement of
the Acceptance Test.
Composting Facility towards:
the Household Waste Recycling Target; and
the BMW to Landfill Target
1.3 Noise levels The peak noise levels will be
recorded at the test points
identified in the South Kirkby
Acceptance Testing
Measurements Points SK-EXT-
9201 during normal operating
conditions whilst the following
activities are being conducted:
while Composting Input is being delivered;
while the waste shredder is operating at near operating capacity; and
while the loading shovel is filling a tunnel
The level of noise generated by the South Kirkby Main
Composting Facility will be measured in accordance with
the detailed procedure set out in the Acceptance Test
Programme.
The level of generated noise will be measured on one
occasion at each of the test points on the boundary of the
South Kirkby Main Site. The measurements taken at these
points, as may be determined by the Environmental Permit,
are to ensure that noise levels comply with the
requirements of the Environmental Permit.
1.4 Odour Levels This test will be performed
towards the end of the test
period for the South Kirkby
Main Composting Facility.
The biofilter operation will be
adjusted to take into account
The odour shall be monitored at a number of points on the
boundary of the South Kirkby Main Site as may be
determined by the Environmental Permit and in accordance
with the detailed procedure set out in the Acceptance Test
Programme to ensure that odour levels comply with the
requirements of the Environmental Permit.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 6 of 21
the number of tunnels being
tested using suitable means,
such as temporary baffles, to
maintain the residence time at
the design levels. The
ventilation fans in the unused
tunnels shall be configured so
as to maintain the expected
efflux velocity at the discharge
point. If the efflux velocity varies
from the predicted velocity no
correction factor shall be
applied.
The odour output from the biofilters will be measured to
ensure compliance with the levels of odour set out in the
Environmental Permit.
Should the measured odour level from either biofilter be
more than above the defined level in the air quality
model (in OUe/m3); the potential impact on overall site
odour release will be evaluated using the air quality model
once all odour measurements required as part of the
Acceptance Tests have been completed.
1.5 Bioaerosol
Levels
The bioaerosol tests shall not
be undertaken before the
biofilters have been
acclimatised and optimised.
The biofilter operation will be
adjusted to take into account
the number of tunnels being
tested using suitable means,
such as temporary baffles, to
maintain the residence time at
the design levels. The
ventilation fans in the unused
tunnels shall be configured so
as to maintain the expected
efflux velocity at the discharge
If required by the Environment Agency as part of the
Environmental Permit, bioaerosol levels will be measured
at a number of points on the boundary of the South Kirkby
Main Site in accordance with the detailed procedure set out
in the Acceptance Test Programme.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 7 of 21
point.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 8 of 21
2. South Kirkby Main MRF
2.1 The Acceptance Test
2.1.1 The period for the Acceptance Test for the South Kirkby Main MRF shall be two (2) weeks.
2.1.2 The Acceptance Test will demonstrate that the South Kirkby Main MRF can process the MRF Input without breaching the Environmental Permit and produce Reclaimed Materials and Waste Derived Products in accordance with test 2.2 of Table 2 below.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 9 of 21
Table 2 South Kirkby Main MRF Parameters
Test Feature being tested Any specific conditions for
the facility to ensure that the
feature being tested is subject
of a valid test
Test Process and parameters measured Pass Criteria
2.1 Average Throughput
of the South Kirkby
Main MRF
The South Kirkby Main MRF
shall be operated in accordance
with the relevant Operating
Manuals with adjustments to
take into account the quantity of
MRF Input delivered for the
purposes of the Acceptance
Test.
The South Kirkby Main MRF will
be staffed with the number of
Staff as set out in the relevant
Operating Manuals. Staff will
have completed the appropriate
induction and training prior to
the commencement of the
Acceptance Test.
Each week of the testing period shall comprise the following categories of time.
Planned Operating Time (POT) shall be 45 hours/week. This is the time when the plant would normally be expected to be in operation including: preparation, startups, shutdowns and daily maintenance and cleaning. The exact start and finish times which make up POT each week shall be set by the Sub Contractor and written into the detailed testing procedures prior to starting the test.
Planned Weekend Maintenance Time (PWMT) shall be 48 hours/week. The exact start and finish times for PWMT each week shall be set by the Sub Contractor and written into the detailed testing procedures prior to starting the test.
Planned Idle Time (PIT) shall be the remaining periods in the week which are not covered by POT or PWMT.
The throughput over the testing period shall be calculated as follows.
AT = TTP/(POT-UIT+EXT)
AT = Average Throughput (expressed in tonnes/hours input waste)
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 10 of 21
TTP = Total Tonnes Processed as measured using weighbridge data, with appropriate adjustments for inventory levels at the start and end of the testing period.
UIT = Unplanned Idle Time is any time within the specified POT periods when the plant cannot operate solely due to lack of waste in the reception area. For any time to count towards UIT, the plant shall not be cleaned, maintained, prepared, worked on in any manner or awaiting repairs.
EXT = Extra Time is any time within the PIT
periods when the plant is being operated
cleaned, maintained, prepared or worked on in
any manner
2.2 Contribution of the
South Kirkby Main
MRF to Contract
Targets
The South Kirkby Main MRF
shall be operated in accordance
with the relevant Operating
Manuals with adjustments to
take into account the quantity of
MRF Input delivered for the
purposes of Acceptance Test.
The South Kirkby Main MRF will
be staffed with the number of
Staff as set out in the relevant
Operating Manuals. Staff will
have completed the appropriate
induction and training prior to
the commencement of the
Acceptance Test.
The tonnage of MRF Input and both Waste
Derived Products and Reclaimed Materials
delivered to market will be recorded and a mass
balance will be compiled detailing the input and
output streams across the South Kirkby Main
MRF to determine the contribution of the South
Kirkby Main MRF towards:
the Household Waste Recycling Target; and
the BMW to Landfill Target
Reclaimed Materials and Waste Derived
Products shall be produced to a standard that
can be delivered to the markets identified in
Table 1 of the Materials and Energy Marketing
Plan.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 11 of 21
2.3 Noise levels The peak noise levels will be
recorded at the test points
identified in the South Kirkby
Acceptance Testing
Measurements Points SK-EXT-
9201 during the test operating
hours and under normal
operating conditions whilst the
following activities are being
conducted:
while MRF Input is being delivered;
while the loading shovel is in operation; and
while the trommel screen is handling MRF Input.
The level of noise generated by the South Kirkby
Main MRF will be measured and in accordance
with the detailed procedure set out in the
Acceptance Test Programme.
The level of generated noise will be measured on
one occasion at each of the test points on the
boundary of the South Kirkby Main Site. The
measurements taken at these points, as may be
determined by the Environmental Permit, are to
ensure that noise levels comply with the
requirements of the Environmental Permit.
2.4 Odour Levels The odour test shall not be
undertaken unless the South
Kirkby Main MRF ventilation
fans are operating.
The odour shall be monitored at a number of
points on the boundary of the South Kirkby Main
Site as may be determined by the Environmental
Permit and in accordance with the detailed
procedure set out in the Acceptance Test
Programme to ensure that odour levels comply
with the requirements of the Environmental
Permit.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 12 of 21
2.5 Dust Levels The dust test shall not be
undertaken unless the South
Kirkby Main MRF ventilation
fans are operating.
A test shall be conducted to monitor dust levels
emitted from the facility if required by the
Environmental Permit.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 13 of 21
3. South Kirkby Main Residual Waste Treatment Facility
3.1 The Acceptance Test
3.1.1 For the purpose of this Section 3 reference to the South Kirkby Main Residual Waste Treatment Facility includes all stages in the process from reception hall up to and including the pasteurisation process and shall exclude the anaerobic digestion system which includes; the intermediate storage tanks, anaerobic digestion tanks, digestate dewatering system, gas handling systems, effluent treatment system and combined heat and power facilities.
3.1.2 The period for the Acceptance Test for the South Kirkby Main Residual Waste Treatment Facility shall be four (4) weeks
3.1.3 The Acceptance Test will demonstrate that the South Kirkby Main Residual Waste Treatment Facility can process the Residual Waste Treatment Input without breaching the Environmental Permit and produce Reclaimed Materials and Waste Derived Products and AD feedstock/cooked organic fraction in accordance with test 3.1 of Table 3 below.
3.1.4 The South Kirkby Main Residual Waste Treatment Facility shall be tested to demonstrate its compliance with the overall design capacity requirements as set out in section 2.2 of the Works Delivery Plan by operating the facility for a period of time required to process the tonnage of Residual Waste Treatment Input available.
3.1.5 The average hourly throughput rate is calculated in accordance with the following formula:
Average hourly throughput rate =
∑(daily tonnage of Residual
Waste Treatment Input)
∑(daily operating hours)
Where
Daily operating hours The daily operating period (hours) taken as the period from the recorded start time until the recorded end time as defined in test 3.1 of Table 3.
3.1.6 Unless agreed with the Independent Certifier, during the period of the Acceptance Test planned maintenance and defect rectification can only be carried out during:
the daily operating hours;
during the planned daily maintenance and cleaning period (4.5 hours);
the weekend non operating periods.
3.1.7 Plant preparation activities such as the preparation of the boiler can be completed outside of the daily operating hours.
3.1.8 The criteria being monitored or measured are defined in Table 3 below.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 14 of 21
3.1.9 The Acceptance Test of the South Kirkby Main Residual Waste Treatment Facility shall be deemed passed provided the pass criteria defined in Table 3 below are achieved.
3.1.10 Should the pass criteria in test 3.1 of Table 3 below not be achieved then following modification to the South Kirkby Main Residual Waste Treatment Facility, test 3.1 of the Acceptance Test shall be repeated with a duration that shall be agreed with the Independent Certifier.
3.1.11 Should the pass criteria in tests 3.2, 3.3, 3.5, or 3.6 of Table 3 below not be achieved then following modification to the South Kirkby Main Residual Waste Treatment Facility that test shall be repeated within the remaining period of the Acceptance Test or the period of the Acceptance Test shall be increased to accommodate the retest as agreed with the Independent Certifier.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 15 of 21
Table 3 South Kirkby Main Residual Waste Treatment Facility Parameters
Test Feature being
tested
Any specific conditions for
the facility to ensure that the
feature being tested is
subject of a valid test
Test process and parameters measured Pass Criteria
3.1 Throughput of
the South
Kirkby Main
Residual
Waste
Treatment
Facility
The South Kirkby Main
Residual Waste Treatment
Facility shall be operated in
accordance with the relevant
Operating Manuals.
The South Kirkby Main
Residual Waste Treatment
Facility will be staffed with the
number of Staff as set out in
the relevant Operating
Manuals. Staff will have
completed the appropriate
induction and training process
prior to the commencement of
the Acceptance Test.
The tonnage of Residual Waste Treatment Input to the
South Kirkby Main Residual Waste Treatment Facility
will be taken from weighbridge records with appropriate
adjustments for waste inventory levels at the start and
end of the test period.
The start time for processing of waste on each day shall
be recorded as the time the first load of waste is
collected by the front end loading shovel for depositing in
the waste loading hopper.
The end time for processing of waste on each day shall
be recorded as the time the last load of waste is
collected by the front end loading shovel for depositing in
the waste loading hopper.
3.2 AD feedstock
preparation
using the
autoclave
The entire South Kirkby Main
Residual Waste Treatment
Facility including the autoclave
shall be operational
At some stage during the Acceptance Test the AD
feedstock produced by the autoclave process will be
tested in accordance with the detailed procedure set out
in the Acceptance Test Programme to ensure that it is a
suitable feedstock for Anaerobic Digestion. The following
criteria will be measured:
The level of pathogens as defined by the Animal By- Products Regulations.
Plastics content is within the specification for Digestate defined in Table 1 of the Materials and Energy
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 16 of 21
Marketing Plan
Glass content is within the specification for Digestate defined in Table 1 of the Materials and Energy Marketing Plan
3.3 AD feedstock
preparation
using the
autoclave
bypass line
The entire South Kirkby Main
Residual Waste Treatment
Facility shall be operational
excluding the autoclave which
shall be bypassed and the
autoclave bypass line shall be
operational
At some stage during the Acceptance Test the autoclave
bypass line shall be operated and the suitability of the
AD feedstock for Anaerobic Digestion established in
accordance with the detailed procedure set out in the
Acceptance Test Programme. The following criteria will
be measured:
The level of pathogens as defined by the Animal By- Products Regulations.
Plastics content is within the specification for Digestate defined in Table 1 of the Materials and Energy Marketing Plan
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 17 of 21
Glass content is within the specification for Digestate defined in Table 1 of the Materials and Energy Marketing Plan
3.4 RDF quality The South Kirkby Main
Residual Waste Treatment
Facility shall be operated in
accordance with the relevant
Operating Manuals.
The RDF output shall be sampled and tested in
accordance with Schedule 2 of the Ferrybridge Off-Take
Contract.
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 18 of 21
3.5 Contribution of
the South
Kirkby Main
Residual
Waste
Treatment
Facility to
Contract
Targets
The South Kirkby Main
Residual Waste Treatment
Facility shall be operated in
accordance with the relevant
Operating Manuals.
The South Kirkby Main
Residual Waste Treatment
Facility will be staffed with
the number of Staff as set
out in the relevant Operating
Manuals. Staff will have
completed the appropriate
induction and training
process prior to the
commencement of the
Acceptance Test.
The tonnage of Residual Waste Treatment Input and
both Waste Derived Products and Reclaimed Materials
delivered to market will be recorded and a mass
balance will be compiled detailing the input and output
streams across the South Kirkby Main Residual Waste
Treatment Facility to determine the contribution of the
South Kirkby Main Residual Waste Treatment Facility
towards.
the Household Waste Recycling Target; and
the BMW to Landfill Target
Reclaimed Materials and Waste Derived Products shall
be produced to a standard that can be delivered to the
markets identified in Table 1 of the Materials and
Energy Marketing Plan.
The quantity of AD feedstock sent to Anaerobic
Digestion shall be estimated.
There is no requirement to measure the water vapour
and exhaust gases given off as a by-product of the
autoclave process
3.6 Noise levels The peak noise levels will be
recorded at the test points
identified in the South Kirkby
Acceptance Testing
Measurements Points SK-
EXT-9201 during normal
operating conditions whilst the
following activities are being
conducted
while Residual Waste Treatment Input is being
The level of noise generated by the South Kirkby Main
Residual Waste Treatment Facility will be measured
and in accordance with the detailed procedure set out
in the Acceptance Test Programme.
The level of generated noise will be measured on one
occasion at each of the test points on the boundary of
the South Kirkby Main Site. The measurements taken
at these points, as may be determined by the
Environmental Permit, are to ensure that noise levels
comply with the requirements of the Environmental
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 19 of 21
delivered,
while the pre-sort MRF and autoclave are in operation,
while the loading shovel is in operation.
Permit.
3.7 Odour Levels -
Residual
Waste
Treatment
Facility
In order to ensure that the bio-
scrubbers have achieved
stable operation this test shall
not be commenced until after
the first week of the
throughput test has been
completed.
The ventilation fans shall be
operating normally during the
conduct of the odour test.
whilst Residual Waste Treatment input is being stored on the floor of the reception hall
the bag opener shall be operating normally.
The level of odour shall be assessed whilst the autoclave
is venting into the condenser with the remainder of the
South Kirkby Main Residual Waste Treatment Facility
processing Residual Waste Treatment Input.
The odour shall be monitored at a number of points on
the boundary of the South Kirkby Main Site as may be
determined by the Environmental Permit and in
accordance with the detailed procedure set out in the
Acceptance Test Programme to ensure that odour levels
comply with the requirements of the Environmental
Permit.
Should the monitoring at all points not be completed on a
single autoclave vent cycle then the test shall cover
additional autoclave cycles as necessary.
Odour Levels -
Autoclave
Building
The ventilation fans shall be
operating normally during the
conduct of the odour test.
In order to ensure that the bio-
scrubbers have achieved
stable operation this test shall
not be commenced until after
the first week of the
The level of odour release shall be measured at two
stages of the autoclave cycle:
1. Whilst the autoclave is venting into the condenser
with the remainder of the South Kirkby Main
Residual Waste Treatment Facility processing
Residual Waste Treatment Input.
2. During the autoclave cook phase with the
remainder of the South Kirkby Main Residual
Schedule 9 – Part 2 Acceptance Tests
07/01/2013 Part 2
Page 20 of 21
throughput test has been
completed.
Waste Treatment Facility processing waste
The odour output from the AD and autoclave
bioscrubbers and the pre-sort MRF carbon filter will be
measured individually to ensure compliance with the
levels of odour set out in the Environmental Permit.
Should the measured odour level from any of the
bioscrubbers/carbon filters be more than above the
defined level in the air quality model (in OUe/m3); the
potential impact on overall site odour release will be
evaluated using the air quality model once all odour
measurements required as part of the Acceptance Tests
have been completed.
Odour Levels
– Reception
Hall
The ventilation fans shall be
operating normally during the
conduct of the odour test. The
measurements will be taken
whilst at least 50% of the
Residual Waste Treatment
Input expected during that day
is on the floor in the Reception
Hall.
the bag opener shall be
operating normally.
The odour output from the carbon filter will be measured
to ensure compliance with the levels of odour set out in
the Environmental Permit.
Should the measured odour level from any of the carbon
filters be more than above the defined level in the
air quality model (in OUe/m3); the potential impact on
overall site odour release will be evaluated using the air
quality model once all odour measurements required as
part of the Acceptance Tests have been completed.
Schedule 9 – Part 3 Post Anaerobic Test
07/01/2013 Part 3
Page 21 of 21
Part 3 - Post Anaerobic Digestion Test
1. Introduction
1.1 The Anaerobic Digestion system will take several months to commission and establish
steady state operations. The Parties agree and acknowledge that this test does not
form part of the Acceptance Tests required for the South Kirkby Main Residual Waste
Treatment Facility to receive a Completion Certificate (and this test does not need to
be undertaken for the Contractor to achieve the Full Service Commencement Date and
the step up to the Unitary Charge). The Contractor shall undertake this test at an
appropriate time during the Full Service Period and the results passed to the Council.
1.2 This test will be conducted to demonstrate that the Anaerobic Digestion system is
performing as expected by generating Digestate that meets the market requirement
defined in the Materials and Energy Marketing Plan.
1.3 Once the Anaerobic Digestion system has achieved a steady state, the Digestate
produced over a 24 hour period will be sampled and tested. The test results will be
compared with the market requirements defined in the Materials and Energy Marketing
Plan. The sampling methodology and the detailed tests to be carried out will be