Page 1: PART III: CERTIFICATES OF COMPLETION - Stafford County

Stafford County Fire Marshal’s Office Handbook for Building/Fire Code Policies and Guidelines

PART III: CERTIFICATES OF COMPLETION

Office of the Fire Marshal Phone: 540-658-8648

Fax: 540-658-9128 www.staffordfirerescue.com/fm

2012 Edition

Page 2: PART III: CERTIFICATES OF COMPLETION - Stafford County

Stafford County Fire and Rescue Department Office of the Fire Marshal

1225 Courthouse Road, PO BOX 339, Stafford, VA 22555 (540) 658-8648 ∙ FAX (540) 658-9128 ∙ www.staffordfirerescue.com/fm

Table of Contents

NFPA 13 Certificate of Completion – Commercial Sprinklers

NFPA 13R, 13D Certificate of Completion – Residential Sprinklers

NFPA 17 Certificate of Completion – Dry Chemical Fire Protection System

NFPA 17A Certificate of Completion – Wet Chemical Fire Protection System (Hood)

NFPA 20 Acceptance Test Form – Fire Pump Test

NFPA 24 Certificate of Completion – Underground Fire Line

NFPA 72 Certificate of Completion – Fire Alarm

NFPA 2001 Acceptance Test Form – Clean Agent Fire Protection System

Page 3: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 4: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 5: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 6: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 7: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 8: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 9: PART III: CERTIFICATES OF COMPLETION - Stafford County

Copyright by National Fire Protection Association (NFPA). NFPA 17 is licensed, by agreement for individual use. No other reproduction or transmission in any form permitted without written permission of NFPA. For inquiries or to report unauthorized use, contact [email protected].

FIGURE A.10.4.6Sample Acceptance Test Report.

Page 10: PART III: CERTIFICATES OF COMPLETION - Stafford County

Copyright by National Fire Protection Association (NFPA). NFPA 17A is licensed, by agreement for individual use. No other reproduction or transmission in any form permitted without written permission of NFPA. For inquiries or to report unauthorized use, contact [email protected].

FIGURE A.6.4.10.3Sample Wet Chemical System Acceptance Test Report.

Page 11: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 12: PART III: CERTIFICATES OF COMPLETION - Stafford County
Page 13: PART III: CERTIFICATES OF COMPLETION - Stafford County

Print

Page 14: PART III: CERTIFICATES OF COMPLETION - Stafford County

Copyright by National Fire Protection Association (NFPA). NFPA 13 HBK is licensed, by agreement for individual use. No other reproduction or transmission in any form permitted without written permission of NFPA. For inquiries or to report unauthorized use, contact [email protected].

Page 15: PART III: CERTIFICATES OF COMPLETION - Stafford County

Copyright by National Fire Protection Association (NFPA). NFPA 72 is licensed, by agreement for individual use. No other reproduction or transmission in any form permitted without written permission of NFPA. For inquiries or to report unauthorized use, contact [email protected].

FIGURE 7.8.2(a)System Record of Completion. (SIG-FUN)

Page 16: PART III: CERTIFICATES OF COMPLETION - Stafford County

Copyright by National Fire Protection Association (NFPA). NFPA 72 is licensed, by agreement for individual use. No other reproduction or transmission in any form permitted without written permission of NFPA. For inquiries or to report unauthorized use, contact [email protected].

FIGURE 7.8.2(a)Continued

Page 17: PART III: CERTIFICATES OF COMPLETION - Stafford County

Copyright by National Fire Protection Association (NFPA). NFPA 72 is licensed, by agreement for individual use. No other reproduction or transmission in any form permitted without written permission of NFPA. For inquiries or to report unauthorized use, contact [email protected].

FIGURE 7.8.2(a)Continued

Page 18: PART III: CERTIFICATES OF COMPLETION - Stafford County

Fire Plan Review and Inspection Guidelines

200

Clean Agent System Acceptance Inspection IFC 904.10, 2008 NFPA 2001, and 2007 NFPA 72

Date of Inspection: _____________________________ Permit Number: ______________________________

Business/Building Name: ________________________ Address of Project: ____________________________

Contractor: ____________________________________ Contractor’s Phone: ___________________________

Reference numbers following worksheet statements represent an NFPA code section unless otherwise specified.

Pass | Fail | NA_ 1. ____ | ____ | ____ Received clean agent system certification from installer. 2. ____ | ____ | ____ Control panel and components match approved plans. 3. ____ | ____ | ____ Approved drawing on site, as-builts required when installation is not the same as the plans. 4. ____ | ____ | ____ Control panel, piping, nozzles, and other components location are the same as shown on

the plans. 5. ____ | ____ | ____ Zones are properly identified on panel(s). 6. ____ | ____ | ____ Verify dedicated 120 AC branch circuit and labeling, 7.7.2.4.3. 7. ____ | ____ | ____ Device location same as plans. 8. ____ | ____ | ____ Devices are located in all areas required by the code. 9. ____ | ____ | ____ Devices are properly wired and in raceways, 4.3.1.3. 10. ____ | ____ | ____ Type and gauge of wire or cable match plans. 11. ____ | ____ | ____ 24 hour monitoring service agency received signals and conveys the type signals received,

7.7.2.5.3 12. ____ | ____ | ____ Verify proper operation of magnetic door-releasing hardware and/or ventilation shutdown,

6.7.2.3. 13. ____ | ____ | ____ Battery load test: system switched to battery operation 24 hours earlier, then activate

audible circuit for 5 minutes, 7.7.2.5.4(2). 14. ____ | ____ | ____ Pull stations comply with NFPA 72, distinct appearance, and mounted at proper height and

location which is no more that 4 ft. above the floor, 4.3.3.7, 7.7.2.4.11 15. ____ | ____ | ____ Under primary and secondary power operational tests are performed including. 7.7.2.5: ____ | ____ | ____ A. power light on and in normal condition. ____ | ____ | ____ B. supervisory signals: pressure switches, valves, etc.. ____ | ____ | ____ C. silence switches.

____ | ____ | ____ D. trouble signals and panel light operate for each circuit tested, disconnect wires. from devices and end-of-line resistors.

____ | ____ | ____ E. trouble and alarm reset switches operate. ____ | ____ | ____ F. a second initiating zone overrides silence switch. ____ | ____ | ____ G. audible and visual operation. ____ | ____ | ____ H. panel lamp test switch operates. ____ | ____ | ____ I. field zone signals correspond with panel zones. ____ | ____ | ____ J. detection devices and manual pull stations operate.

____ | ____ | ____ K. abort switch is in protected area; requires manual pressure and initiates visual/audible devices, 4.3.5.3, 6.7.2.5.

16. ____ | ____ | ____ Piping and nozzles are restrained so no unacceptable movement occurs, prior to the pressure test, 7.7.2.2.4.

17. ____ | ____ | ____ Piping pneumatically tested for 10 minutes at 40 PSIG and the pressure drop shall not exceed 20 percent of the test pressure, 7.7.2.2.12.

18. ____ | ____ | ____ Nozzles shall not be installed at a location were injury can occur. 19. ____ | ____ | ____ Release circuit is tested at the storage container. 20. ____ | ____ | ____ Pull stations activate system and override abort switch, 7.7.2.4.13. 21. ____ | ____ | ____ Test connection to a monitoring company or a location receiving signal, 7.7.2.5.1. 22. ____ | ____ | ____ Protected area is properly sealed and tested using a fan and smoke pencil, 7.7.2.3. 23. ____ | ____ | ____ An enclosure or room integrity room leakage test (fan test) may be required, 6.7.2.3. A

quantitative method shall be used and results provided that confirm 85 percent of the concentration holds for 10 minutes, 5.6.

24. ____ | ____ | ____ Warning and instruction signage is properly posted.

Page 19: PART III: CERTIFICATES OF COMPLETION - Stafford County

Fire Plan Review and Inspection Guidelines

201

25. ____ | _____ | ____ Perform a flow test with compressed air or inert gas to verify unobstructed pipes and nozzles, 7.7.2.2.13.

Additional Comments: