17 David Sowden, The University of Hull 57086 Contract and Project Management
12

57086 17 change_control_01

Nov 22, 2014

Download

Business

 
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 57086 17 change_control_01

17David Sowden, The University of Hull

57086 Contract and Project Management

Page 2: 57086 17 change_control_01

1757086 Contract and Project Management

Change Control

David Sowden, The University of Hull

Page 3: 57086 17 change_control_01

Overview

• Change Control– Purpose

– Project Issue Management

– Issue and Change Control procedure

– Change Budget

– Integrity of change

– Management

3

Page 4: 57086 17 change_control_01

Change Control - Purpose

• Change in a project is highly likely• All project change should be managed - as a formal Project

Issue• Control of change means assessment of:

– impact of potential change– importance– cost

• Approved changes must be reflected in project documentation

4

Page 5: 57086 17 change_control_01

Project Issue Management

The objective is to capture, log and categorise all Project Issues, these may be raised at any time during the project, by anyone with an interest in the project or its outcome.

5

Page 6: 57086 17 change_control_01

What could a Project Issue be?

• A change of requirements, however minor

• A change in the environment applicable to the project

• A problem occurring or being identified that was not anticipated during risk analysis

• An anticipated but unavoidable risk occurring

• A problem or error occurring in work completed or currently under way

• Advice of a new risk

• A query about any aspect of the project

6

Page 7: 57086 17 change_control_01

Managing Project Issues will involve:

• Capturing and formally logging the Project Issue (in the Issue Log)

• Assessing the Project Issue to decide on the type and therefore what action is required

• Investigating the required actions

• Documenting the actions and confirming their completion

• Reviewing the Issue Log on a regular basis to monitor progress on outstanding Project Issues.

7

Page 8: 57086 17 change_control_01
Page 9: 57086 17 change_control_01

Change Budget

– As well as considering where authority lies, the Project Board must consider:

• How will changes be funded?

• Will the Project Board go back to corporate or programme management to vary funding, timetable or scope each time a change is desired?

9

Page 10: 57086 17 change_control_01

RisksCostTime

AdvantageSaving

Change

Integrity of Change• Project Issues should not be considered in isolation

– Benefit/Business Case driven

– The Risk Log

– Time/cost/risk function balance

– Where the project is part of a programme.10

Page 11: 57086 17 change_control_01

Management

Project Managers should constantly be looking for ways to take advantage of events to improve on project costs, schedule or performance.These should be recorded as Project Issues (and the final outcome should be recorded in the Lessons Learnt Log)

11

Page 12: 57086 17 change_control_01

TASK

Review Project Issues within your own project, are these

documented?