David Sowden, The University of Hull 6 57086 Contract and Project Management
Jun 11, 2015
David Sowden, The University of Hull
657086 Contract and Project Management
657086 Contract and Project Management
Introduction to Processes - Managing Product Delivery
David Sowden, The University of Hull
Overview
• Managing Product Delivery– Fundamental principles– Contexts– Process description– Accepting/Executing/Delivering a Work Package
3
Get approval for the completed products
Managing Product Delivery
4
Report on quality and progress
Supervise the team’s work
Plan the team’s work
Agree the work with the Project Manager
THE BASICS
Relationships of Processes
5
Starting a Project
Directing a Project
Initiating a Project
Managing a Stage
Boundary
Controlling a Stage
Managing ‘Product’ Delivery
End
Closing a Project
Icons
6
Guidelines - Rules, Policies,instructions that should be followed
Resources - tools, systemsor materials required to complete a task
Managing Project Delivery (1)
7
Accepting a Work PackageControlling a Stage
Update Quality RegisterCreate Team Plan(s)Approve Work Package(s)PIDWork package(s)
Work Package delivery authorised
Managing Project Delivery (2)
8
Execute a Work Package
Obtain approval record(s)Create Checkpoint Report(s)Update Configuration Item records
PIDTeam Plan(s)
Work Package accepted
Create Specialist Product(s)Create Team Plan(s)
Work package(s)
Managing Project Delivery (3)
9
Deliver a Work Package
Update Team plan(s)Update Work Package(s)Quality Register
Work Package executed
Work package(s)
Managing Project Delivery (4)
10
Controlling a Stage
Controlling a Stage
Controlling a Stage
Deliver a Work Package
New issues raised
New risk raised
Completed Work Package
section 5
section 5
section 5
TASK
Review your product delivery
Did the Work Package and Product Description(s) contain sufficient information, including cross-references?
Has a Team Plan been created that demonstrates that the Work Package could be completed within agreed tolerances?
Has the Team Plan been updated with actuals and revised forecasts?
Was progress (actuals and forecast) checked against agreed tolerances?
If tolerances were forecast to be exceeded, were they escalated to the Project Manager?
Were Checkpoint Reports issued to the Project Manager at the frequency and in the format agreed?
Did the Team Manager notify the Project Manager of any issues and risks?
Do approval records exist for each completed product?
Did the Team Manager notify Project Support of any required updates to Configuration Item Records and the Quality Register?
Did the Team Manager notify the Project Manager that all the products in the Work Package had been delivered?
CHECK