Page 1: 57086 05 controlling_a_stage

57086 Contract and Project Management5

David Sowden, The University of Hull

Page 2: 57086 05 controlling_a_stage

557086 Contract and Project Management

Introduction to Processes - Controlling a Stage

David Sowden, The University of Hull

Page 3: 57086 05 controlling_a_stage

Overview

–Controlling a Stage• Fundamental principles• Contexts• Process description• Work Packages• Assessing progress• Capturing Project Issues• Capturing Project Issues• Examining Project Issues• Reviewing Stage Status• Reporting Highlights• Taking Corrective Action• Escalating Project Issues• Receiving Completed Work Packages

Page 4: 57086 05 controlling_a_stage

4

Controlling a Stage THE BASICS

Report progress to

Project BoardEscalate

problems to Project Board

Take corrective action

Authorise work

Confirm work

completion

Capture progress

information

Review progress, quality work, issues

and risk status

Analyse the impact of

issues

Capture and log issues

Page 5: 57086 05 controlling_a_stage

Relationships of Processes

5

Starting a Project

Directing a Project

Initiating a Project

Managing a Stage

Boundary

Controlling a Stage

Managing ‘Product’ Delivery

End

Closing a Project

Page 6: 57086 05 controlling_a_stage

Icons

6

Guidelines - Rules, Policies,instructions that should be followed

Resources - tools, systemsor materials required to complete a task

Page 7: 57086 05 controlling_a_stage

New risk raised

New issue raised

Directing a Project

Controlling a Stage (1)

7

Stage authorisedDirecting a Project

Authorise a Work package

Update Configuration item RecordsUpdate Issue Register

PID

Update Quality RegisterUpdate Stage Plan (current)

Issue RegisterConfiguration Management Strategy

Update Risk Register

Exception Plan approved

Directing a Project

Project Board advised

Directing a Project

Completed Work Package

Managing ‘Product’ delivery

New issueraised

Managing ‘Product’ delivery

Managing ‘Product’ delivery

Project Controls

Quality Management Strategy

Page 8: 57086 05 controlling_a_stage

Controlling a Stage (2)

8

Review Work Package statusWork Package authorised

Update Configuration Item Record(s)Update Issue RegisterUpdate Risk Register

Checkpoint Record(s)

Update Stage PlanUpdate Work Package(s)

Quality RegisterRisk RegisterStage PlanTeam Plan(s)

Page 9: 57086 05 controlling_a_stage

Controlling a Stage (3)

9

Receive completed Work PackagesStatus reviewed

Update Configuration Item Record(s)

Configuration Item Records

Update Stage Plan

Quality Register

Stage Plan

Page 10: 57086 05 controlling_a_stage

Controlling a Stage (4)

10

Review the stage statusWork Packages received

Update Issue ReportUpdate Issue RegisterUpdate Lessons Log

Checkpoint Record(s)

Update Risk RegisterUpdate Stage Plan

Quality RegisterIssue RegisterPIDBenefits review Plan

Page 11: 57086 05 controlling_a_stage

Controlling a Stage (5)

11

Report StatusStage status reviewed

Create Highlight report (current Period)Checkpoint Record(s)Daily LogHighlight Report (previous period)Lessons LogQuality Register

Page 12: 57086 05 controlling_a_stage

Controlling a Stage (6)

12

Capture and examine issues and risksStatus reported

Update Daily LogUpdate Issue RegisterUpdate Issue Report

PIDUpdate Risk Register

Business CaseConfiguration Management StrategyCommunication Management StrategyProject plan

Page 13: 57086 05 controlling_a_stage

Controlling a Stage (7)

13

Escalate issues and risksissues and risk examined

Update Exception ReportUpdate Issue RegisterUpdate Risk Register

Issue RegisterUpdate Issue Report

Issue ReportPIDBusiness CaseRisk Register

Page 14: 57086 05 controlling_a_stage

Controlling a Stage (8)

14

Take corrective actionissues and risk escalated

Update Configuration Item Record(s)Update Daily LogUpdate Issue Register

Configuration Item Records

Update Issue ReportUpdate Risk Register

Daily LogIssue RegisterIssue ReportRisk Register

Page 15: 57086 05 controlling_a_stage

Controlling a Stage (9)

15

Take corrective action

Project end approaching

Work Package delivery authorised

Exception raised

Request for advise

Stage Boundary approaching Managing a Stage Boundary

Directing a Project

Directing a Project

Managing Project Delivery

Closing a Project

section 4

section 7

section 4

section 6

section 8

Page 16: 57086 05 controlling_a_stage

TASK

Review stage management within your project

Page 17: 57086 05 controlling_a_stage

Have Work Packages been created and issued?

Have all the Team Managers agreed their Work Packages?

Have completed product been produced in accordance with the Work Package and Product Description?

Have the relevant Configuration Items Records been created/updated?

Has the Quality Register been maintained?

Were any products handed over as part of a phased delivery?

Has the Risk Register been maintained?

Has the Issue Register been maintained?

Has the Stage Plan been updated with actuals and revised forecasts?

Has the Daily Log been maintained?

Have Checkpoint Report been received fro each issued Work Package at the frequency and in the format agreed?

Was progress (actual and forecast) checked against agreed tolerances?

If tolerances were forecast to be exceeded, were the escalated to the Project Boards?

If corrective actions were required, were they logged, implemented and tracked?

Was the Business Case periodically checked for ongoing viability?

Were Highlight Reports created and issued in accordance with agreed reporting format and frequency?

Do Issue Reports exist for all issues being handled formally?

Do Exception Reports exist for all exceptions raised to the Project Board?

Has the Lessons Log been updated with any new lessons?

CHECK