Internship report 2016
MAAZ AHMED NAQVI
SHAHRUKH AQIQ
BS CIVIL TECHNOLOGY
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
2
Department of Civil Technology
INTERNSHIP SUPERVISOR: Engr. Osama ZahidAUTHOR: Maaz A. Naqvi
Shahrukh Aqiq
Hosting Organization: Paragon Constructors (PVT) LTD.
Commencement Date: September 28, 2016
Completion Date: November 03, 2016
Approved By:
Name of DGM: Eng. Zahoor Shah
Signature:
Name of mentor: Engr.Osama Zahid
Signature:
Hosting company stamp
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
3
Department of Civil Technology
ACKNOWLEDGEMENT
I would like to thank Paragon Construcrtors (PVT) LTD for giving me the opportunity to undertake my five week internship in their working area. I would like to convey my heartiest thanks to site engineer Osama and the project manager Engr. Zahoor Shah for their immense support and cooperation which made this experience very learning and worthwhile.
Date: November 10, 2016
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
4
Department of Civil Technology
Contents
1. Chapter oneIntroduction of the company ………………04
2. Chapter two Over all internship experience …………………...05
3. Chapter threeMaterials and methods ………………………….08
4. Batching Plant Inspection.…………………………...…….10
5. Laboratory work………… 12
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
5
Department of Civil Technology
Chapter one
1. Introduction of the company
Paragon continually strives to be the premier provider of construction services in Pakistan. Our people are experts in fostering solutions that create value for our clients, employees and stakeholders by consistently exceeding expectations. Our management approach and team orientation enable Paragon to truly be the Owner’s advocate. Our success is measured by our client’s trust.
BANKERS
Habib Metropolitan Bank, Karachi Bank Islami Pakistan Limited Summit Bank Limited Askari Bank Limited UBL JS Bank Meezan Bank
AUDITORS
S. Shakeel-ur-Rehman & Co
INSURERS
Adamjee Insurance, Karachi Eastern Federal Union, Karachi New Jubilee Insurance, Karachi New Hampshire Insurance Co, Karachi
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
6
Department of Civil Technology Pak Qatar Takaful Limited, Karachi United Insurance Company of Pakistan Limited.
Chapter Two
Over all internship experience
Joining of the company
I joined Paragon Costructors PVT LTD Karachi Pakistan
on 28th September 2016. The GM Engr.Zahoor Shah
assigned me with the site engineer on their on-going project Bahria Grand .Mosque in Bahria Town Karachi
Section of the company I have been work
My hosting company is working on several projects in the country. I was appointed in Bahria Town site which is almost 35km away from Karachi city center.
Our hosting company was a contractor it has so many responsibilities. First the accountant compute bid for their drawing after they selected by client they supply a working drawing like structural drawing, sanitary drawing, electrical drawing in one copy based on the agreement and the total project cost(bill of quantity) for the client after they officially announced the
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
7
Department of Civil Technology
contractor. Then construction begins starting from mobilization and office building.
Planning, Scheduling:
Create WBSManaged ActivitiesDrawings StudyLabor & Machinery Deployment
Site Layout:
Foundation LayoutForm work LayoutSteel LayoutColumn LayoutBeam LayoutCentre Line Marking
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
8
Department of Civil Technology
Fig: Footing layout markings
Digging Excavation for Foundation:
Fig: Excavation in process with excavator
Compaction of Foundation:
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
9
Department of Civil Technology
Chapter threetask execution and Methods.
Steel Fixing In Picked-Up Wall:
Picked-Up walls are vertical load distribution wall. It is a RCC structure.
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
10
Department of Civil Technology
Fig: Steel formation can be seen in picked up wall
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
11
Department of Civil Technology
Steel Form work on Dome:
Steel Structure Fixing:
Fixing of steel structure inside minar.Steel Structure has used inside the minar.Steel ramp are constructed for future maintenance work.Centre space will be used for lift.
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
12
Department of Civil Technology
Batching Plant Inspection:Batching Plant produces Ready mix concrete.It is operated by a technician in control room located near plant.Crush stone, sand and cement added in plant with proper weight through conveyor belt.Water is then added.
Fig: Control room inside view
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
13
Department of Civil Technology
o Fig: Conveyor belt at Batching Plant and silo mixer with, 108Ton capacity eacho Shovel in process of foiling belt
Fig: Ready-mix concrete is transferring into Transit Mixer to sent to Site.
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
14
Department of Civil Technology
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
15
Department of Civil Technology
Laboratory work.
I. Concrete Mix DesignII. Compression Test
III. Field Density Test
Concrete Mix DesignNo of Cement Bags for Concrete:
Total Quantity = 100 Cft/sftDry Volume = 100x1.54
Dry = 154
No. of Cement Bags
Vol of cement Bag = 154
1+2+4∗1
Volume of Cement = 22Cft
No of Cement Bag = vol of cement quantity
Vol of 1bag
No of Cement bag = 22
1.25
No of cement bag = 17.6 qty.
Volume of Fine Aggregate:=
1541+2+4 x2
44 Cft.
Volume of Coarse Aggregate:154
1+2+4∗4
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
16
Department of Civil Technology
88 Cft.Plaster quantity for 100 Sqft
Wet Volume = 100 x1/2 x ½= 25
Dry Volume = 25 x 1.2 = 30Sq/ft
Cement Ratio: = DryVolume∑ of ratio
∗Ratio of cement
= 301+4
∗1
Cement Bag for Plaster = 6 bags
Compression Test:
Compression Test is done to find out the bearing capacity of concrete mix designCylinders or Cubical design of concrete are use in testing.It is performed before concrete start on site.Several tests are conducted after 7, 14 and 28 days respectively.
Compression Test after 7 days @ 4000 PSI:
420 KN/M x 7.953340 PSI
33404000
∗100 = 83.5%
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
17
Department of Civil Technology
Field Density Test
Sand = 16# sieve Pass , 30# sieve RetainSand Weight = Cone + Sand
=7728gms
Executed Soil Weight = 4915gmResidual Sand = 2674 gm
Moisture Content = Oven Baked Weight of Waste/ Dry Soil = %
Conclusion:We were appointed on Bahria grand mosque. We were asked to perform different task. The staff of Paragon Constructors were so friendly and helpful and do listen to new generation ideas.We did enjoy our work with learning experience, and we thanked all engineers’ staff and workers who helped me.This report is helpful for students of Civil Engineering upto 3rd year.
Refernce:
http://paragon.com.pk/new/ http://www.slideshare.net/zakkisbest/surveying-internship-
report
Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:
18
Department of Civil Technology
This report is compiled and edited by Ahmed Zakaria on client request.