Page 1: Internship Report on Bahria Grand Mosque

1

Department of Civil Technology

Internship report 2016

MAAZ AHMED NAQVI

SHAHRUKH AQIQ

BS CIVIL TECHNOLOGY

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 2: Internship Report on Bahria Grand Mosque

2

Department of Civil Technology

INTERNSHIP SUPERVISOR: Engr. Osama ZahidAUTHOR: Maaz A. Naqvi

Shahrukh Aqiq

Hosting Organization: Paragon Constructors (PVT) LTD.

Commencement Date: September 28, 2016

Completion Date: November 03, 2016

Approved By:

Name of DGM: Eng. Zahoor Shah

Signature:

Name of mentor: Engr.Osama Zahid

Signature:

Hosting company stamp

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 3: Internship Report on Bahria Grand Mosque

3

Department of Civil Technology

ACKNOWLEDGEMENT

I would like to thank Paragon Construcrtors (PVT) LTD for giving me the opportunity to undertake my five week internship in their working area. I would like to convey my heartiest thanks to site engineer Osama and the project manager Engr. Zahoor Shah for their immense support and cooperation which made this experience very learning and worthwhile.

Date: November 10, 2016

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 4: Internship Report on Bahria Grand Mosque

4

Department of Civil Technology

Contents

1. Chapter oneIntroduction of the company ………………04

2. Chapter two Over all internship experience …………………...05

3. Chapter threeMaterials and methods ………………………….08

4. Batching Plant Inspection.…………………………...…….10

5. Laboratory work………… 12

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 5: Internship Report on Bahria Grand Mosque

5

Department of Civil Technology

Chapter one

1. Introduction of the company

Paragon continually strives to be the premier provider of construction services in Pakistan. Our people are experts in fostering solutions that create value for our clients, employees and stakeholders by consistently exceeding expectations. Our management approach and team orientation enable Paragon to truly be the Owner’s advocate. Our success is measured by our client’s trust.

BANKERS

Habib Metropolitan Bank, Karachi Bank Islami Pakistan Limited Summit Bank Limited Askari Bank Limited UBL JS Bank Meezan Bank

AUDITORS

S. Shakeel-ur-Rehman & Co

INSURERS

Adamjee Insurance, Karachi Eastern Federal Union, Karachi New Jubilee Insurance, Karachi New Hampshire Insurance Co, Karachi

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 6: Internship Report on Bahria Grand Mosque

6

Department of Civil Technology Pak Qatar Takaful Limited, Karachi United Insurance Company of Pakistan Limited.

Chapter Two

Over all internship experience

Joining of the company

I joined Paragon Costructors PVT LTD Karachi Pakistan

on 28th September 2016. The GM Engr.Zahoor Shah

assigned me with the site engineer on their on-going project Bahria Grand .Mosque in Bahria Town Karachi

Section of the company I have been work

My hosting company is working on several projects in the country. I was appointed in Bahria Town site which is almost 35km away from Karachi city center.

Our hosting company was a contractor it has so many responsibilities. First the accountant compute bid for their drawing after they selected by client they supply a working drawing like structural drawing, sanitary drawing, electrical drawing in one copy based on the agreement and the total project cost(bill of quantity) for the client after they officially announced the

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 7: Internship Report on Bahria Grand Mosque

7

Department of Civil Technology

contractor. Then construction begins starting from mobilization and office building.

Planning, Scheduling:

Create WBSManaged ActivitiesDrawings StudyLabor & Machinery Deployment

Site Layout:

Foundation LayoutForm work LayoutSteel LayoutColumn LayoutBeam LayoutCentre Line Marking

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 8: Internship Report on Bahria Grand Mosque

8

Department of Civil Technology

Fig: Footing layout markings

Digging Excavation for Foundation:

Fig: Excavation in process with excavator

Compaction of Foundation:

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 9: Internship Report on Bahria Grand Mosque

9

Department of Civil Technology

Chapter threetask execution and Methods.

Steel Fixing In Picked-Up Wall:

Picked-Up walls are vertical load distribution wall. It is a RCC structure.

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 10: Internship Report on Bahria Grand Mosque

10

Department of Civil Technology

Fig: Steel formation can be seen in picked up wall

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 11: Internship Report on Bahria Grand Mosque

11

Department of Civil Technology

Steel Form work on Dome:

Steel Structure Fixing:

Fixing of steel structure inside minar.Steel Structure has used inside the minar.Steel ramp are constructed for future maintenance work.Centre space will be used for lift.

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 12: Internship Report on Bahria Grand Mosque

12

Department of Civil Technology

Batching Plant Inspection:Batching Plant produces Ready mix concrete.It is operated by a technician in control room located near plant.Crush stone, sand and cement added in plant with proper weight through conveyor belt.Water is then added.

Fig: Control room inside view

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 13: Internship Report on Bahria Grand Mosque

13

Department of Civil Technology

o Fig: Conveyor belt at Batching Plant and silo mixer with, 108Ton capacity eacho Shovel in process of foiling belt

Fig: Ready-mix concrete is transferring into Transit Mixer to sent to Site.

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 14: Internship Report on Bahria Grand Mosque

14

Department of Civil Technology

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 15: Internship Report on Bahria Grand Mosque

15

Department of Civil Technology

Laboratory work.

I. Concrete Mix DesignII. Compression Test

III. Field Density Test

Concrete Mix DesignNo of Cement Bags for Concrete:

Total Quantity = 100 Cft/sftDry Volume = 100x1.54

Dry = 154

No. of Cement Bags

Vol of cement Bag = 154

1+2+4∗1

Volume of Cement = 22Cft

No of Cement Bag = vol of cement quantity

Vol of 1bag

No of Cement bag = 22

1.25

No of cement bag = 17.6 qty.

Volume of Fine Aggregate:=

1541+2+4 x2

44 Cft.

Volume of Coarse Aggregate:154

1+2+4∗4

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 16: Internship Report on Bahria Grand Mosque

16

Department of Civil Technology

88 Cft.Plaster quantity for 100 Sqft

Wet Volume = 100 x1/2 x ½= 25

Dry Volume = 25 x 1.2 = 30Sq/ft

Cement Ratio: = DryVolume∑ of ratio

∗Ratio of cement

= 301+4

∗1

Cement Bag for Plaster = 6 bags

Compression Test:

Compression Test is done to find out the bearing capacity of concrete mix designCylinders or Cubical design of concrete are use in testing.It is performed before concrete start on site.Several tests are conducted after 7, 14 and 28 days respectively.

Compression Test after 7 days @ 4000 PSI:

420 KN/M x 7.953340 PSI

33404000

∗100 = 83.5%

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 17: Internship Report on Bahria Grand Mosque

17

Department of Civil Technology

Field Density Test

Sand = 16# sieve Pass , 30# sieve RetainSand Weight = Cone + Sand

=7728gms

Executed Soil Weight = 4915gmResidual Sand = 2674 gm

Moisture Content = Oven Baked Weight of Waste/ Dry Soil = %

Conclusion:We were appointed on Bahria grand mosque. We were asked to perform different task. The staff of Paragon Constructors were so friendly and helpful and do listen to new generation ideas.We did enjoy our work with learning experience, and we thanked all engineers’ staff and workers who helped me.This report is helpful for students of Civil Engineering upto 3rd year.

Refernce:

http://paragon.com.pk/new/ http://www.slideshare.net/zakkisbest/surveying-internship-

report

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company:

Page 18: Internship Report on Bahria Grand Mosque

18

Department of Civil Technology

This report is compiled and edited by Ahmed Zakaria on client request.

Written By: Maaz A. Naqvi & Shahrukh. Aqiq Hosting Company: