61T01411 – Project Execution Plan for Valeo Foshan New Facility Project
Valeo
Tebodin
Jul 22, 2014
Agenda
page 2
Agenda:•PEP project Execution Plan•Procurement Plan•Master Schedule•Engineering Status
page 3
Index
Project Execution Plan
Project Organization Project Schedule (milestone) Communication and Interface Management Engineering Management Construction Management HSSE Quality Management Project Control
page 4
Project Team Organization Chart (Sample)
Project Schedule (milestones) Vs Progress
▪ Time Schedule ▪ Engineering Phase: 23 weeks ▪ Conceptual Design: 7 weeks; (4.29~6.20) ▪ Conceptual Design Review/Approval/optimizing: 2 weeks; (6.10~7.3) ▪ Detail Design Phase 1: (for exiting building refurbishment) 7 weeks; (6.19~7.24) ▪ Detail Design Phase 2: 5 weeks; (7.24~8.28) ▪ Detail Design Review/Approval/Audit: 2 weeks; (8.28 ~9.18)
▪ Procurement Phase: ▪ Phase 1: (for exiting building refurbishment) 4 weeks; (7.3~7.23) ▪ Phase 2: (for new buildings and utilities) 4 weeks; (9.1~9.25)
▪ Construction Phase: 5 months. (7.31~12.31)
page 5
page 6
Key Activities- Interface Management
• Interface with Authorities and third parts
• Interface with GC Contractor/suppliers
• Interface with operation Team
• Interface with Project Management Team
• Interface with Land Lord
Communication Management
page 7
2 Project Management for EPC phase Communication Management
Tools - Interface Management :▪ Role and Responsibility Matrix▪ Action List ▪ Master Schedule▪ Permitting matrix▪ Technical Interface Schedule▪ Turnaround Plan
page 8
Meeting and Reporting
1. Tebodin to Borouge
• Weekly Report • Weekly Contract and Manning report • Monthly Status report
2. GC Contractor to PM team
• Project Kick off Meetings• Weekly Coordination Meeting and Report • Monthly Progress Report –
Communication Management
page 9
Data Transfer Systems
Implement Borouge Document System
1. Numbering/Naming of Documents2. Filling of Documents3. Distribution of Documents4. Documents templates
Audit Document System of GC
Review JianLi Technical Document System
Communication Management
page 10
1. The design manager and team will transfer the Conceptual phase design and requirements to the detailed design through gate review of EPC’s design.
2. Supervise the detail design at progress of 30%, 60% & 90% and final. Including activities:
• Review of Vendor Design• Review of Documents and Records• Safety Engineering• Local Laws and Regulations• Design Continuity Management • Technical Interface Management
3. All information and data shall be documented amount interface boundaries through design, procurement, construction and commissioning phase of project
Engineering Management
page 11
1. Construction Planning • Temporary facilities plan• Site logistic and access control plan• Shut down and turnaround plan• Staff personnel and security force• Construction Schedule• Construction Execution Plan
2. Construction Execution• Implement quality control program • Interface with Jian Li • Implement design change and variation order approval procedure • Co-ordinate daily construction activities • Site quality inspection and testing• Organize meetings and report a regular basis • Ensure good housekeeping• Conduct Health, Safety and Environmental Protection inspections and audits on site • Manage EPC contractors work to be acceptance by authority. • Plan and execute Project handover
Construction Management
page 12
HSSE Management HSSE Management
Manage and monitor EPC execution, including:
• Organize Health Security & Safety Policy• Action and Resources• Compliance with Laws and Regulations• Training• Control of HSSE Document• HSSE audit and Management Review
Key Safety Risks – listed but not limited• Material and warehousing is narrow on site • Tie-in impact to the existing production• Separation fence (for both external and internal work)• Pipe-line protection• Underground pipeline protection• Crane Work• Fire Protection on construction site• Fall down Protection on construction site• Edge Protection• Rubbish and Pollution control• Dust protection• Site Security and Access control• Plant fire Loop blocked and lost function
page 13
HSSE Management
page 14
Quality Management
The Quality Control Manager will implement quality procedures and will conduct regular inspect and audit, including activities:
QA (Quality Assurance)• Tebodin TQS as Guideline (Tebodin Quality System)• Project Quality Plan• Manage Jianli (Local Quality Supervision Company)
QC( Quality Control):• Design quality control• Procurement quality control• Construction quality control• Document quality control
page 15
Project Progress Control Progress Control
Milestone Summary Schedule (Level 1) EPC Level Schedule (Level 2)
• Permitting schedule• Procurement Schedule • Construction Schedule• Long Lead items• T&C schedules• Start-up schedules
Detailed Construction Schedule (Level 3)Weekly Working Plan
page 16
Project Cost Control Cost Control
EPC Cost BaselineLog changes Change Order ControlMonitor DeviationAction and Forecast
Area of Concerns
1. Permitting
2. Interface of Landlord
page 17
Questions
▪ Any questions?
page 18
always close
page 20
2.3 Information and Document ContentMeeting Management
Meeting Schedule
frequency for each meeting is described as below:
Project and program control meeting – once a week Design coordination meeting – once a week Site construction meeting – once a week Site safety meeting – once a week Procurement meeting – once a month Change control meeting - once bi-week
page 21
2.1 Information and Document ContentMeeting Management
General
o Agendao Requesto Meeting scheduleo Meeting minuteso Distribution matrix
Pre-construction Meetings
Construction stage meetings
page 22
2.1 Information and Document ContentTechnical Report
Internal review Client for approval
Project Weekly Report
EHS, Engineering Quality, Procurement Cost control Schedule and Progress Risk Site photos
Note:Submission date on each Monday for last week
page 23
2.1 Information and Document ContentProject Monthly Report
EHS, Engineering Quality, Procurement Cost control Schedule and Progress Risk Site photos
Note:Submission date within 1st week of next month.Cut date is end of current.
page 24
3. Procurement Management Bidder Long List PreparationPre-qualification Bidder short listPreparation of inquiryBiddingBid Clarifications Evaluation Team Set UpBid EvaluationAuthorization to Order ExpeditingCritical Equipment / Critical Delivery TimeVendor DocumentsInspectionProject Procurement ReportPayment Control
1.Bidding