7901 EAST RIVERSIDE, BUILDING 2, SUITE 100 ∙ (512) 326-4223 WWW.BARTLETTCOCKE.COM HAYS CISD TRANSPORTATION (PROJECT 162090) WEEKLY PROGRESS REPORT: FEBRUARY 22, 2019 ANTICIPATED DATE OF SUBSTANTIAL COMPLETION: APRIL 23, 2019 Fuel Depot Canopies Bus Wash area graded. This Week’s Activities: • Area B canopy erection • Fuel Depot canopy erection • Ceiling grid dropped throughout Area A • PEMB trim, ridge cap, wall panels. • Area B Mechanical and Electrical overhead. • Overhead MEP devices in progress Area A • Forming and reinforcement for 2 nd to last paving pour, grading in bus wash. Forming and reinforcing 2 nd to last paving pour. Area B canopy erection Upcoming Activities: • Final 2 paving pours • Flatwork • Perimeter fencing • Complete PEMB • Area B mechanical and electrical • Aluminum canopy installation • Lighting and AV installation.