National University Manila College of Engineering INDUSTRY INTERNSHIP TRAINING PROGRAM WEEKLY PROGRESS REPORT Name of Student: John Gerald S. Mallari Age: 20 Sex: Male Course: BS Civil Engineering Name of the Company: SM Engineering Design and Development Corporation Company Address: 9 th Floor Mall of Asia Arena Annex, Mall of Asia Complex, Pasay City Division/Plant/Site Assigned: Special Project/Mall of Asia Complex Field of Training Assigned: Construction Week No: 1 Inclusive Dates of Training: From April 12, 2016 To April 15, 2016 ISO 9001:2008 QUALITY MANAGEMENT SYSTEM CERTIFIED Write summary of all activities accomplished during the week During the first week of the internship program, I was designated to the Mall of Asia complex knowing that different constructions were on going. First task is to check or inspect the cracks along the South Parking of Mall Of Asia includes beams, columns and slabs. The next days we were assigned to estimate the SM Taytay Proposed Cyberzoned and presented our computed values to project engineers also Engr. Liongson explained briefly and discuss on MEFPS (Mechanical, Electrical, Fire Protection & Sanitary Works) of a certain plan, keywords were also elaborated. A tour on ongoing constructions at The Galleon Museum, architectural fit outs at Conrad Mall and Hotel and briefly elaborated the color coordinations of pipes and wirings at the Mall of Asia phase 2 expansion. Lastly, Architectural works were
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
National UniversityManila
College of Engineering
INDUSTRY INTERNSHIP TRAINING PROGRAM
WEEKLY PROGRESS REPORT
Name of Student: John Gerald S. Mallari Age: 20 Sex: Male
Course: BS Civil Engineering
Name of the Company: SM Engineering Design and Development Corporation
Company Address: 9th Floor Mall of Asia Arena Annex, Mall of Asia Complex, Pasay City
Division/Plant/Site Assigned: Special Project/Mall of Asia Complex
Field of Training Assigned: Construction
Week No: 1 Inclusive Dates of Training: From April 12, 2016 To April 15, 2016
Verified by:
______________________________ _________________ Signature over Printed Name of Date Technical Training Supervisor
ISO 9001:2008QUALITY MANAGEMENT SYSTEM
CERTIFIED
Write summary of all activities accomplished during the week
During the first week of the internship program, I was designated to the Mall
of Asia complex knowing that different constructions were on going. First task is to
check or inspect the cracks along the South Parking of Mall Of Asia includes
beams, columns and slabs. The next days we were assigned to estimate the SM
Taytay Proposed Cyberzoned and presented our computed values to project
engineers also Engr. Liongson explained briefly and discuss on MEFPS
(Mechanical, Electrical, Fire Protection & Sanitary Works) of a certain plan,
keywords were also elaborated. A tour on ongoing constructions at The Galleon
Museum, architectural fit outs at Conrad Mall and Hotel and briefly elaborated the
color coordinations of pipes and wirings at the Mall of Asia phase 2 expansion.
Lastly, Architectural works were monitored at the The Galleon Musuem.
DOCUMENTATION
The floor plan of SM Taytay Proposed Cyberzone
Estimation of SM TayTay Proposed Cyberzone
On going fit outs at Directors Club, Conrad Mall Construction of Cinema, The Galleon Mall
Electrical and Ductings for Airconditioned were place.
National UniversityManila
Estimation of Stairs for SM Muntinlupa
Inspection of Architectural Works at the The Galleon Mall.
Tenants Partition
ISO 9001:2008QUALITY MANAGEMENT SYSTEM
CERTIFIED
College of Engineering
INDUSTRY INTERNSHIP TRAINING PROGRAM
WEEKLY PROGRESS REPORT
Name of Student: John Gerald S. Mallari Age: 20 Sex: Male
Course: BS Civil Engineering
Name of the Company: SM Engineering Design and Development Corporation
Company Address: 9th Floor Mall of Asia Arena Annex, Mall of Asia Complex, Pasay City
Division/Plant/Site Assigned: Special Project/Mall of Asia Complex
Field of Training Assigned: Construction
Week No: 2 Inclusive Dates of Training: From April 18, 2016 To April 22, 2016
Verified by:
______________________________ _________________ Signature over Printed Name of Date Technical Training Supervisor
Write summary of all activities accomplished during the week
. On the second week of the internship program Billing process were
explained by Engr. Acosta including all the documents needed and the step by step
procedures that need to conduct. Electrical plan was elaborated by Engr. Cloyd and
done a quick tour to MAAX’s AHU and electrical rooms, wirings and other fixtures
were also familiarized. Moreover, Cracks along beams, columns and slabs on the
South Parking of Mall of Asia were inspected for the second time to ensure that all
the cracks were reported. LC Perlins were placed on the phase 2 expansion of Mall
of Asia and also dry walls, drop walls were placed. Demolition of the existing
skylights is on going and board ups around the demolition area were painted.
Lastly, Post construction procedures were explained and discuss which includes the