Roadway Resurfacing / Reconstruction of Eastern Avenue, N.E. from Sargent Road N.E. to Cul-De-Sac (Section A) and from Michigan Avenue N.E. to Randolph Street N.E. (Section B). DC Contract: DCKA-2012-C-0036 Federal Aid Project No: STP-3210(006) Project Engineer: Edmond Sheffield/Muhammed Ilyas Inspector: Morgan Prince WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014
12

WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:

Jun 21, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:

Roadway Resurfacing / Reconstruction of Eastern Avenue, N.E.

from Sargent Road N.E. to Cul-De-Sac (Section A) and

from Michigan Avenue N.E. to Randolph Street N.E. (Section B).

DC Contract: DCKA-2012-C-0036

Federal Aid Project No: STP-3210(006)

Project Engineer: Edmond Sheffield/Muhammed Ilyas

Inspector: Morgan Prince

WEEKLY PROGRESS REPORT

1/27/2014 to 1/31/2014

Page 2: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:

1. Project Description: The work under this project includes but not limited to the following:

Maintenance of vehicular and pedestrian traffic and maintenance of access to residential and commercial establishments as approved, removal of all existing curbs and gutters within the project and replacement with new granite curbs and concrete gutters, removal of all existing sidewalks and reconstruction with new PCC sidewalks, Building wheel chair ramps and upgrading existing wheel chair ramps to meet ADA requirements.

Upgrading street lighting, modifying traffic signals at intersections of Sargent Road and Varnum Street, planting new trees and removing selected trees, removing selected Fire Hydrants and installing new Fire Hydrants, building Water Quality basins, manholes, and storm water system, milling existing asphalt surface course and paving with new super-pave surface course.

Repairing existing PCC pavements and overlaying with asphalt for section, removing and reconstructing existing bus pads, Installing permanent signs and pavement markings, reconstructing existing PCC pavement at intersection of Eastern Avenue with Varnum Street. Constructing new retaining wall and Coping along Eastern Ave at locations shown on plans, reconstructing 8” water line and service pipe on south side of Eastern Ave from Sargent Road N.E. to Cul-De-Sac.

Project Start Date: Nov. 19, 2012 Project Completion Date: Feb. 28, 2014

Page 3: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:

Progress Summary: Sargent Road to Cul-De-Sac (Section A) 90% of the work has been completed Michigan Ave to Randolph Street (Section B) 70% of the work has been completed January 27, 2014 Monday No field work January 28, 2014 Tuesday No construction work January 29, 2014 Wednesday Mc Dean to install ground rod in manhole#13- manhole#14 January 30, 2014 Thursday Metro Paving to install 5’-0’’ feet of 4’’ conduit to service wood pole#L85 Mc Dean to install ground rod in manhole15, 20, 47; rack the cable, install jet line. DDOT technician to install cable to Traffic Signal controller TC-1 January 31, 2014 Friday

Metro Paving (no field work) DDOT technician to continue to pull cable to the traffic signal controller to make Connection to the traffic signal cabinet. Mc Dean to ground manhole at the intersection of Eastern Avenue & Varnum Splice and rack electrical manhole in-prep.for inspection manhole 46, 48, 17, 18, 19. To ground splice, rack, electrical manhole at the intersection Eastern & Sargeant Mo1, 2, 39, 40, 41, 42, 43.

Page 4: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:

1. Project Completion Status: Project Funding:

Original Contract amount: $ 5,215,676 .15 Approved Change Orders: CO #1 (3/12/2013) -$194,820.00 CO #2 (11/6/2013) $351,311.06 CO #3 (11/18/13) w/103 days, time extension $ 5,101.23 Total Contract Amount: $ 5,377,268.44

Project Expenditures:

Previous Payment Invoice #13: $ 738,803.02 Current Payment Request Invoice #14: $ 51,503.78 Total Payment to Date: $ 4,763,085.63 Balance remaining $ 609,081.59 % of Dollars: 88.66 % Project Time Project Completion Time: (365+103) 468 Days Project Time Used: 439 Days

% of Time: 93 %

2. Change Orders: No new Change Orders.

3. Materials Testing: None

4. RFI’s: RFI No. 11 On October 22, 2013, Metro Paving requested information concerning the Color Scheme, Font Size, and Picture Size for the Neighborhood Watch Sign, Tree City USA Sign, and the Welcome to Washington Sign. DDOT provided color photos of existing signs, as response to RFI no.11.

5. Schedules and Delays: Updated schedule is to be submitted by the contractor.

Page 5: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:

6. Issues/Delays: None

7. Public Relations: None

8. Accidents: None 9.

Page 6: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:
Page 7: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:
Page 8: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:
Page 9: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:
Page 10: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:
Page 11: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description:
Page 12: WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014dashboard.ddot.dc.gov/DTAPDOC/document/150_54790_Weekly Rep… · WEEKLY PROGRESS REPORT 1/27/2014 to 1/31/2014 . 1. Project Description: