WEEKLY PROGRESS REPORT Property: St. Andrew Today's Date: Friday, May 28, 2021 This report is for the week ending on: Friday, May 28, 2021 Projected Turnover date TBD Construction WK Preconstruction Inspection Issues n/a Utility Issues n/a Permit Issues n/a Hot Items Executed contracts Change Orders Sent None Change Orders Approved None RFIs Sent #1 RFIs Pending None Submittals Sent Concrete Package, Steel Package, Roof Package Submittals Open Roof Package Scope Completed To Date: 1 Site fencing installed 2 Portable restrooms placed 3 Storage container placed 4 Temp construction power installed 5 Building surveyed for excavation 6 Existing utilities marked 7 Excavator delivered Scope to be Completed Next Week: 1 Building excavation 2 Soil testing started 3 Building survey for building/foundation Inspections This Week: 1 None Inspections Scheduled for Next Week: 1 3rd Party Inspections