PAGE 1 OF 4 WEEKLY CONSTRUCTION PROGRESS AND INSPECTION REPORT Period Ending 06.28.2020 T-O Engineers Project AIP Number: 502 33 rd Street Cody, WY 82414 03-56-0030-010-2018, 03- 56-0030-011-2018 State Project Numbers: AEAN10A, AEAN10B, AEAN10C Airport Name Phifer Airfield, Wheatland, Wyoming Project Description Contractor’s Name Runway Reconstruction Project Paul Reed Construction & Supply, Inc. 1. Rough Estimate of Percent Completion to Date of Construction Phases (Include items such as clearing, grading, drainage, base, surface, lighting, etc.) Overall project percent complete – 95%. See attached sheet for additional information. 2. Work Completed or in Progress this Period. Monday 06.22.20 – Contractor performed patching operations on damaged P-401 material on bottom lift from “Lot #1”, “Lot #2”, “Lot #8”, and “Lot #9” that were damaged from coring operations by Contractor on 6/19/2020. Contractor performed grinding operations on P-401 bottom lift material placed on Connector. Contractor installed Edge Drain Pipe Daylights. Contractor continued installation of Edge Drain Cleanouts. Contractor placed P-603 and P-401 material for “Lot #21” on top mat, where “Lot 14 – Test Strip #3” and “Lot #15 -Test Strip #4” had been removed by mill. Contractor installed Counterpoise Wire and Grounding Rods as well as began the replacement of Guidance Sign on east side of Connector that was damaged during paving operations in 2019. Contractor performed initial profilograph testing on P-401 material on Runway and diamond grinding on bottom mat of Connector. Tuesday 06.23.20 – Contractor installed Edge Drain Pipe Daylights. Contractor continued installation of Edge Drain Cleanouts. Contractor graded north Runway shoulder and placed material for east end drainage berm. Contractor placed P-603 and P-401 material for “Lot #22” on top mat of Connector. Contractor installed Counterpoise Wire and Grounding Rods as well as began cutting through asphalt for Runway Threshold Lights. Contractor concluded initial profilograph testing on top lift of P-401 on Runway. Wednesday 06.24.20 – Contractor continued installation of Edge Drain Cleanouts. Contractor finished placement of P-401 material for “Lot #22 – Partial Lot” on top mat of Connector. Contractor installed Runway Edge Lights and prepared for the placement of Concrete for Runway Threshold Light Cans. Thursday 06.25.20 – Contractor completed installation of Edge Drain Cleanouts. Contractor installed Runway Edge Lights, Counterpoise Wire, and Grounding Rods. Contractor continued P-401 waste cleanup, Topsoil placement, Runway shoulder grading, and HMA plant demobilization. Contractor placed P-610 material for Runway Threshold Light Cans. Friday 06.26.20 – Contractor continued P-401 waste cleanup, Topsoil placement, Runway shoulder grading, and HMA plant demobilization. Contractor installed Earthen Irrigation Ditch for Irrigation System “A”. Saturday 06.27.20 – No work was performed on site. Sunday 06.28.20 – Contractor installed Runway Edge Lights, Runway Threshold Lights, Counterpoise Wire, and Grounding Rods.
4
Embed
WEEKLY CONSTRUCTION PROGRESS AND INSPECTION REPORT
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
PAGE 1 OF 4
WEEKLY CONSTRUCTION PROGRESS AND
INSPECTION REPORT
Period Ending
06.28.2020
T-O Engineers Project AIP Number:
502 33rd Street
Cody, WY 82414
03-56-0030-010-2018, 03-
56-0030-011-2018
State Project Numbers:
AEAN10A, AEAN10B,
AEAN10C
Airport Name
Phifer Airfield, Wheatland, Wyoming
Project Description Contractor’s Name
Runway Reconstruction Project Paul Reed Construction & Supply, Inc.
1. Rough Estimate of Percent Completion to Date of Construction Phases (Include items such as clearing, grading, drainage, base, surface, lighting,
etc.)
Overall project percent complete – 95%. See attached sheet for additional information.
2. Work Completed or in Progress this Period.
Monday 06.22.20 – Contractor performed patching operations on damaged P-401 material on bottom lift from “Lot #1”, “Lot #2”,
“Lot #8”, and “Lot #9” that were damaged from coring operations by Contractor on 6/19/2020. Contractor performed grinding
operations on P-401 bottom lift material placed on Connector. Contractor installed Edge Drain Pipe Daylights. Contractor
continued installation of Edge Drain Cleanouts. Contractor placed P-603 and P-401 material for “Lot #21” on top mat, where “Lot 14
– Test Strip #3” and “Lot #15 -Test Strip #4” had been removed by mill. Contractor installed Counterpoise Wire and Grounding Rods
as well as began the replacement of Guidance Sign on east side of Connector that was damaged during paving operations in 2019.
Contractor performed initial profilograph testing on P-401 material on Runway and diamond grinding on bottom mat of Connector.
Tuesday 06.23.20 – Contractor installed Edge Drain Pipe Daylights. Contractor continued installation of Edge Drain Cleanouts.
Contractor graded north Runway shoulder and placed material for east end drainage berm. Contractor placed P-603 and P-401
material for “Lot #22” on top mat of Connector. Contractor installed Counterpoise Wire and Grounding Rods as well as began
cutting through asphalt for Runway Threshold Lights. Contractor concluded initial profilograph testing on top lift of P-401 on
Runway.
Wednesday 06.24.20 – Contractor continued installation of Edge Drain Cleanouts. Contractor finished placement of P-401 material
for “Lot #22 – Partial Lot” on top mat of Connector. Contractor installed Runway Edge Lights and prepared for the placement of