Top Banner
Free PMP® Exam Sample Question pm-exam-simulator.com
19

PMP Sample Questions

Apr 10, 2017

Download

Education

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 2: PMP Sample Questions

PMP® Exam Sample Question

Presented by Cornelius Fichtner, PMP

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Page 3: PMP Sample Questions

Provided by

www.pm-exam-simulator.com

This presentation showcases a free sample

questions to help you study for the PMP exam

Page 4: PMP Sample Questions

You are managing an insurance project. An

executive steering committee meeting is

scheduled for tomorrow and you are required to

make a presentation about project progress.

Which of the following presentation formats is

best used in this type of meeting?

Page 5: PMP Sample Questions

A. Hammock Diagram

B. Network Diagram

C. Milestone Chart

D. Gantt Chart

Page 6: PMP Sample Questions

In management meetings you are looking

for a chart that gives a high-level overview.

Page 7: PMP Sample Questions

C. Milestone Chart

Page 8: PMP Sample Questions

As a general project management best

practice, milestone charts are regarded as

an effective way to communicate project

progress to senior executives in a meeting

environment.

Page 9: PMP Sample Questions

You are currently managing a team of five

auditors and conducting an IT audit project for a

customer on their premises. Due to technical

reasons you and your team cannot use your

business email accounts during the project. You

decide to use Blahoo web mail in order to

communicate with each other. The use of the

Blahoo web mail is an example of?

Page 10: PMP Sample Questions

A. Formal Communication

B. Interactive Communication

C. Push Communication

D. Pull Communication

Page 11: PMP Sample Questions

Emails are not considered formal

communication.

Page 12: PMP Sample Questions

D. Pull Communication

Page 13: PMP Sample Questions

Emails are neither formal communication nor

interactive communication, and when used in a

normal office environment are considered push

communication. This is because the messages

are pushed into the email program. However, in

the case of web mail, project team members

must log in to the web mail server in order to

retrieve their emails, which is an example of pull

communication.

Page 14: PMP Sample Questions

Management decided to introduce a quality

management program which required the

employees to learn statistical process control

techniques. The employees responded

negatively to this change. What can be the

probable reason for this?

Page 15: PMP Sample Questions

A. They fear they will lose their job

B. Threat of safety

C. Change will lower their income

D. Fear of the unknown

Page 16: PMP Sample Questions

This fear results in resistance to

change.

Page 17: PMP Sample Questions

D. Fear of the unknown

Page 18: PMP Sample Questions

The employees are resisting because they

are not familiar with the new technique.

Fear of the unknown is a very common

human characteristic. They fear that they

will not be able to perform on the job. The

PM should use his/her interpersonal skills

to manage this resistance to change.