PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the PMP PMP ® Sample Sample Questions Questions
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
PMPPMP® Sample Sample
QuestionsQuestions
This presentation will showcase free sample PMP® questions that
will help and guide you in studying for your PMP® exam
Find more free sample questions when you visit
www.free-pm-exam-questions.com and free.pm-
exam-simulator.com
Which of the following elements constitute the scope baseline?
a.Scope Statement, WBS, and Project Scheduleb.Scope Statement, Project Schedule, and WBS Dictionaryc.WBS Dictionary, Resource Calendars, and Project Scheduled.Scope Statement, WBS, and WBS Dictionary
Sample PMP® Exam Question
HINT: The Scope Baseline should contain the scope and related work information.
The correct answer is D
The Scope Baseline contains the Scope Statement, the WBS, and the WBS Dictionary.
Answer and Explanation
Which of the following buffers are placed at the end of the critical chain to protect the target finish date from slippage?
HINT: This buffer protects the target finish date from moving and is intended to protect the project end date.
The correct answer is B
A Project Buffer is placed at the end of the critical chain to protect the target finish from slippage along the critical chain. On the other hand, Feeding Buffers are placed at those points in the chain where tasks that are not on the critical path feed into the critical path. Free buffers and Activity buffers are not used in critical chain.
Answer and Explanation
According to the PMBOK® Guide, which of the following is not a valid activity dependency?
HINT: This question references the Sequence Activities process.
The correct answer is B
The PMBOK Guide recognizes three types of dependencies; Mandatory, Discretionary and External. The PMBOK Guide doesn't recognize "Internal Dependencies" as a type of dependency. Did it confuse you that one of the answers used the term "Discretional Dependencies" instead of "Discretionary Dependencies"? Expect that even on the actual PMP exam you will come across questions where terminology does not exactly match the PMBOK Guide. Even considering that "Discretional Dependencies" is not the exact same term as “Discretionary Dependencies”, "Internal Dependencies" is even less correct and therefore the correct answer.
Answer and Explanation
According to the PMBOK Guide, a WBS is not directly involved in which of the following processes?
HINT: Develop Project Management Plan process creates the Scope Management Plan.
The correct answer is D
The Develop Project Management Plan process carries out scope planning, which documents how the WBS will be created and defined. Define Activities takes the WBS as an input and decomposes it to define activities. Create WBS creates the WBS itself. The Define Scope process must be completed before the Create WBS process can be started.
Answer and Explanation
Information in the WBS dictionary does not include?
HINT: WBS dictionary contains a lot of items and explains each work package in great detail.
The correct answer is D
The WBS Dictionary contains a lot of items and explains each work package in great detail. This information includes Contract Information regarding the work packages, Quality Requirements, and the Responsible Organization. However, the WBS Dictionary does not included the specific project activities.