IE 419 1 IE 419 Work Design: Productivity and Safety Dr. Andris Freivalds Class #2
Dec 17, 2015
IE 419 2
NEED FOR SAFETY – 5
• Myths, misconceptions– Safety doesn’t sell– Catastrophic failures main concern– Safety slows operations– Safety is human (operator, user) problem– Cheaper to pay insurance (McWane??)– Making product safer increases costs
IE 419 4
IE 419 – Work Design
• Productivity– Productivity tools: PERT, Worker-machine charts, line
balancing, plant layout
– Work measurement: MTM-2, MOST, Work sampling
• Safety– General safety principles: how to recognize & analyze
problem, select & apply remedy
– Quantitative analyses: JSA, fault-tree, cost-benefit
– Legal aspects: Workers Comp, OSHA
– Hazards: recognize & control specific hazards
IE 419 5
PRODUCTIVITY TOOLS
Methods Study = Systematic recording of existing and proposed ways of doing work in order to improve productivity (to improve the job for the operator)
1) Select project
2) Get and present data
3) Analyze data
4) Develop ideal method
IE 419 7
#1 – Select Project Pareto analysis
• aka: 80-20 rule• 80% of problems
from 20% of jobs• Focus on the 20%• Plot in descen-
ding order as cumulative proba-bility distribution
• DesignTools
IE 419 8
#1 – Select Project Gantt Chart
• Horizontal bar chart of activities, shaded if done• A snapshot of the status of all activities• Focus efforts on those that are behind schedule
IE 419 9
METHODS STUDY (Next?)
2) Get and present data
3) Analyze data
4) Develop ideal method• All of these overlap• Use special charts • Quicker, efficient, for IEs• Focus on productivity
improvement
IE 419 10
PERT and CPM (pp. 27-30)
• PERT = Program Evaluation and Review Technique (1950s)– Booz Allen for U.S. government & military– Time has uncertainty– Minimizing time is main goal
• CPM = Critical Path Method (1950s)– DuPont for large scale projects– Time is specified– Trade-off between cost and completion date
IE 419 11
BASICS
• Set of well defined jobs (activities)
• Totality of which defines a project
• Jobs start/stop independently of each other
• Jobs are ordered in specific (technological) sequence
• Forms a graphical network diagram
• Allows computational estimates
IE 419 12
GOALS/QUESTIONS
• How long if every job works out ideally? (optimistic estimate)
• How long if everything goes wrong? (pessimistic estimate)
• With average conditions → likely result
• How can project be shortened at least cost? (trade-offs)
IE 419 13
RULES/PROCEDURES #1
1) List jobs and estimated duration time
2) Draw network diagrama) Arcs or vectors to depict jobs
b) Arrows to indicate direction (progress)
c) Numbered nodes to indicate events
d) Events = start and end of jobs
IE 419 14
RULES/PROCEDURES #2
3) No two jobs can be identified by same nodes 3
a) 1 2 1 2
b) Dummy jobs take no time, no resources
c) Only to show dependency
1 3
2
Job A
Job BUse Dummy Job
Job A
Job B
Job C
Job D
Dummy Job
Job B
Job A
IE 419 15
RULES/PROCEDURES #3
4) Show precedence relationships (IP) clearlya) Jobs B & C both required for Job D
b) Job C not required for Job D (but needed further on)
AC
4
1 2
3 5
BD E
AC
4
1 2
3 5
BD E
IE 419 16
RULES/PROCEDURES #4
• Time = estimated duration of each job– Earliest start time (ES) = such that IP hold– Latest start time (LS) = without delaying project completion– Earliest finish (EF) = ES + time to complete job– Latest finish (LF) = LS + time complete job
• Critical jobs = jobs which delayed, delay project • Float (slack) = difference between ES and LS; time
that noncritical jobs can be ↑, without delaying project
• Critical path = longest path of critical jobs, determines duration of project; zero float
IE 419 17
Ex #1- CRITICAL PATH (Travel Times)
• Two PSU profs (Allen, Booz) drive to Washington DC for a meeting with their contract sponsor (U.S. Army)
• Prof. Allen leaves State College at 8 AM– drives to Philadelphia (KP, 3 hrs)– get materials from subcontractor Lockheed Martin (0.5 hr)– then onto Washington DC (2.5 hrs)
• Prof. Booz leaves State College 8 AM– drives to Pittsburgh (3 hrs)– meets 3rd prof (collaborator) for lunch (2 hrs)– then onto Washington DC (4.5 hrs)
• What is earliest they can meet for dinner?
IE 419 19
Ex. CRITICAL PATH – 3Network Table
Activity Nodes IP Time
A - drive (SC, Ph) - 3
B – pick up (Ph, LM) A 0.5
C - drive (LM, DC) B 2.5
D - drive (SC, Pi) - 3
E - lunch (Pi, Lu) D 2
F - drive (Lu, DC) E 4.5
IE 419 20
Ex. CRITICAL PATH – 4Network Diagram
Pi Lu3
2
SC
Ph LM
DC
3
0.5
2.5
4.5
Critical Path = 3 + 2 + 4.5 = 9.5
Earliest dinner: 8 + 9.5 = 5:30 PM
IE 419 21
Ex. CRITICAL PATH - 5
• Critical path = 9.5 hours
• Earliest dinner is 5:30 PM
• Allen can leave 3.5 hrs later (11:30 AM)– Or drive more slowly, sightsee– Flexibility or slack in time = float
• Practically: If Booz shortens lunch to 1 hr, then could meet a 4:30 PM
IE 419 22
Ex #2 – CPM and FLOAT (Building a House)
7 major steps in building a house (months):1) A - Design & obtain financing (3)
2) B - Lay foundation (2)
3) C - Order materials (1)
4) D – Build house (3)
5) E – Select paint (1)
6) F – Select carpet (1)
7) G – Finish work (1)
IE 419 27
Job LS ES LF EF Float
A (1,2)
B (2,3)
C(2,4)
Dum (3,4)
D (4,6) 5 5 8 8 0
E (4,5) 6 5 7 6 1
F (5,6) 7 6 8 7 1
G (6,7) 8 8 9 9 0
Float = LS – ES = LF – EF
1 2 4 6 7
3
5
A 3
C 1
B 2D 3
E 1 F 1
G 1
0,3 0,3
3,5 3,5
3,4 4,5
5,5 5,55,8 5,8
5,6 6,7
6,7 7,8
8,9 8,9
Critical path = all with 0 float =