Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Jul 17, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding
Page 2: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Bethel Park High Schoolet e a g Sc ooBethel Park, PA

Weekly Progress SlideshowWeekly Progress SlideshowDecember 24, 2010,

Page 3: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Metal Siding DeliveredMetal Siding Delivered

Page 4: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Site Grading Around AuditoriumSite Grading Around Auditorium

Page 5: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Building Tented for Temporary HHeat

Page 6: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Roofing Materials StagedRoofing Materials Staged

Page 7: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Academic Wing West WindowsAcademic Wing West Windows

Page 8: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Electrical WorkElectrical Work

Page 9: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Duct Staged and InstalledDuct Staged and Installed

Page 10: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Masonry AuditoriumMasonry Auditorium

Page 11: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Brick Academic WingBrick Academic Wing

Page 12: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Topping Walls Admin WingTopping Walls Admin Wing

Page 13: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Gas Line Piped & Heaters StagedGas Line Piped & Heaters Staged

Page 14: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Cleaning Up In All AreasCleaning Up In All Areas

Page 15: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Academic Wing Carpentry C iContinues

Page 16: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

CHILI COOK-OFF!CHILI COOK OFF!

Massaro CM will be challenging the other primes on the Bethelthe other primes on the Bethel

Park Job to a chili cook off January 12th. For details contact y

Chuck [email protected]@

412-831-1024

Page 17: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Scheduled Work for Next Few Weeks:Scheduled Work for Next Few Weeks:• Roof Curbs (Areas D, E, F, & G)• Installing Interior and Exterior Metal Studs• Window & Door Framing• Masonry Block Walls• Punch Windows (Area B)

B i k V E t i W ll (A A B & C)• Brick Veneer Exterior Walls (Areas A, B & C)• Ext. Sheathing & Spray Foam Insulation (Area H)

Fireproofing Str ct ral Steel• Fireproofing Structural Steel• Aluminum Roofing Panels (Area E)• MEP Rough in’s across the site• MEP Rough-in s across the site.

Page 18: Betet e a g Sc oohel Park High School Weekly Progress ... · 24/12/2010  · Weekly Progress SlideshowWeekly Progress Slideshow December 24, 2010. Metal Siding DeliveredMetal Siding

Thank YouThank YouThe EndThe EndJeremy Beiter

Intern Massaro CMS LLCIntern, Massaro CMS, LLC