WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016 Page 1 of 4 Prepared For: Atlanta Public Schools Prepared By: Austin Nichols Aerial Photo Aerial Photo Aerial Photo Auditorium Stairs/Sidewalk
4

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

Jun 30, 2018

Download

Documents

trinhkhue
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 1 of 4

Prepared For: Atlanta Public Schools

Prepared By: Austin Nichols

Aerial Photo Aerial Photo

Aerial Photo Auditorium Stairs/Sidewalk

Page 2: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 2 of 4

Chiller Walls Striped Track

‘ New Basketball Goals Gym/Auditorium Demo

Last Week’s Activities:

• Classroom Addition

o Finished installing door hardware

o Finished painting

o Began VCT install

• Auditorium

o Installed restroom fixtures

o Installed stage lights

• Administration Addition

o Installed Sunshade support

o Installed ACT grid

Page 3: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 3 of 4

o MEP grid rough-in

• Administration Renovation

o Finished framing

o Hung ceiling

o Startup HVAC

• Gym Renovation

o Continued MEP rough-in

o Began installing rails

This Week’s Activities:

• Classroom Addition

o Began installing rubber base

o Finished installing VCT

o Finished installing shelves

o Began final cleaning

• Auditorium

o Began prep for sidewalk and steps

o Poured steps and sidewalk

o Demoed wall between auditorium and gym

• Administration Addition

o Finished MEP rough in

• Administration Renovation

o Began hanging drywall

o Finished MEP install

• Gym Renovation

o Continue MEP rough-in

o Continued framing

Next Week’s Activities:

• Classroom Addition

o Begin installing lockers

o Begin installing marker boards

o Begin cleaning

o Continue final cleaning

• Auditorium

o Continue finish paint

o Begin backstage VCT

• Administration Addition

o Begin installing epoxy flooring

Page 4: WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long … · WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School ... WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle

WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 1st, 2016

Page 4 of 4

o Begin installing restroom tile

o Finish priming walls

o Overhead ceiling inspection

• Administration Renovation

o Finish prime paint on walls

o Begin wall tile

o Begin epoxy flooring installation

• Gym Renovation

o Finish hanging new basketball goal

o Continue installing waste and vent installation

o Begin MEP overhead rough in new classrooms

Schedule:

• Status: Weather dependent

• Substantial Completion Dates:

o Classroom Addition: July 15, 2016

o Renovations: July 20, 2016

o Administration Addition: July 25, 2016

o Track and Field: September 1, 2016

o Auditorium Addition: September 1, 2016

o Gym Renovation: October 1, 2016

• Final Completion: December 31, 2016

Budget:

• Construction Budget: $15,920,000

• Budget Status: On Budget

• Gross Billed To Date: $10,118,024