PROJECT PORTFOLIO
SACHIN DAVANGERE
ELECTRICAL DESIGN & BIM
ENGINEER
+919945726970
PROJECT OVERVIEW
Building type : OFFICE
Location: BANGALURU
Area: 5009 sq ft.
Floors: STILT+GROUND FLOOR+4 FLOORS
Design occupancy: 200
Building operating schedule:12×5
Air distribution system: VAV SINGLE DUCT
ELECTRICAL SYSTEM
TOTAL AREA : 2115m²
CONSIDERING AS PER NBC LIGHTING POWER : 10.8W/m²
DIVERSITY FACTOR : 0.7
TOTAL LIGHTING LOAD: 15.98KW
LIGHT RENDERING IMAGE
ELECTRICAL LAYOUT
cable
Lighting fixture
Dis
trib
uti
on
bo
x
Wires are selected based on the load using standard catalogues.
Ladder type cable trays are used.
PLUMBING
Floor plan view
Section view
Y bends for sanitary pipes.
1% slope maintained for zero pressure flow.
INTERFERENCE/CLASH REPORT
Clashes between the MEP systems .
Clashes are indicated by ID in report.
Using ID clashes are solved.
CLASH FREE MODEL FOR CLASH FREE COORDINATE
HVAC ducts & air terminals Electrical cable trays
Plumbing sanitary and supply water pipes
BILL OF QUANTITIES BOQ are used for the estimation of cost.
Scheduling is used to get the details of equipment of whole project.
FAMILIES Designing Equipment with project specifications.
Designing labels with specified details.
Annotations