ID WBS Task Name DurationStart Finish
1 1 Literature revew ofPlastic Recycling Plant
13 days Mon 1/5/15 Wed 1/21/15
2 1.1 Literature Plastic 1 day Mon 1/5/15 Mon 1/5/15
3 1.2 Literature Extruder 6 days Tue 1/6/15 Tue 1/13/15
4 1.3 Literature Crusher 6 days Wed 1/14/15 Wed 1/21/15
5 2 Material Selection 6 days Thu 1/22/15 Wed 1/28/15
6 2.1 Plastic recyclingmaterial
2 days Thu 1/22/15 Fri 1/23/15
7 2.2 Machine componentmaterial
4 days Sat 1/24/15 Wed 1/28/15
8 3 Plant Layout 2 days Thu 1/29/15 Fri 1/30/15
9 4 Die Design 20 days Sat 1/31/15 Thu 2/26/15
10 4.1 literature review 12 days Sat 1/31/15 Mon 2/16/15
11 4.2 Extrusion areacalculation
1 day Tue 2/17/15 Tue 2/17/15
12 4.3 Modeling 7 days Wed 2/18/15 Thu 2/26/15
13 5 Cooling Bath design 15 days Sun 2/15/15 Thu 3/5/15
14 5.1 Literature review 10 days Sun 2/15/15 Thu 2/26/15
15 5.2 Calculation 5 days Wed 2/25/15 Tue 3/3/15
16 5.3 Modeling 2 days Wed 3/4/15 Thu 3/5/15
17 6 Air knife design 15 days Fri 3/6/15 Thu 3/26/15
18 6.1 Literature review 12 days Fri 3/6/15 Mon 3/23/15
19 6.2 Modeling 4 days Mon 3/23/15 Thu 3/26/15
20 7 Pelletizer design 16 days Fri 3/27/15 Fri 4/17/15
21 7.1 Literature review 8 days Fri 3/27/15 Tue 4/7/15
22 7.2 Calculation 2 days Wed 4/8/15 Thu 4/9/15
23 7.3 Modeling 6 days Fri 4/10/15 Fri 4/17/15
24 8 Design Improvement (ifnecessary)
2 days Mon 2/2/15 Tue 2/3/15
25 9 Exam Leave 28 days Wed 4/22/15 Fri 5/29/15
26 10 Market Survey 5 days Mon 6/1/15 Fri 6/5/15
27 11 Fabrication 30 days Mon 6/8/15 Fri 7/17/15
28 11.1 Die 6 days Thu 1/29/15 Thu 2/5/15
29 11.2 Water Bath 6 days Sat 1/24/15 Fri 1/30/15
30 11.3 Air knife 3 days Thu 1/29/15 Mon 2/2/15
31 11.4 Pelletizer 12 days Mon 2/2/15 Tue 2/17/15
32 11.5 Assembly 3 days Wed 7/15/15 Fri 7/17/15
33 12 Testing 4 days Fri 2/27/15 Wed 3/4/15
34 13 Modification 6 days Fri 3/6/15 Fri 3/13/15
35 14 Documentation 10 days Fri 2/27/15 Thu 3/12/15
36 15 Report Submission 1 day Wed 3/4/15 Wed 3/4/15
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S MJan Feb Mar Apr May Jun Jul
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
PLASTIC RECYCLING PLANT - GANTT CHART
Page 1
Project: Plastic Recycling PlantDate: Fri 3/6/15