HOSPITAL PENGAJAR UNIVERSITI
SULTAN ZAINAL ABIDIN
(HPUniSZA)
LAPORAN KEMAJUAN PROJEK
Ogos 2020
Disediakan Oleh:
Pusat Pembangunan Hospital Universiti
KEMAJUAN KESELURUHAN
2
Ogos 2020
Physical Schedule
Actual
Ahead/Delay
71.62% 71.60%
-0.02% /-2 Days
Financial Schedule
Actual
Ahead/Delay
55.04% 50.31%
-4.73%
M&E WORK PHOTO;
AT LEVEL 7
PRESSURIZATION FAN INSTALLATION MOTORISED FIRE DAMPER AT
STAIRCASE
PIPING WORKS AT FRP TANK ROOFTOP PRESSURIZATION FAN C/W DUCT
INSTALLATION
M&E WORK PHOTO;
AT LEVEL 6
SUBMAIN TRUNKING & CHILLED WATER
PIPING WORKS TRUNKING WORKS IN ELV RISER ROOM
HR DRUM & BREAKGLASS/BELL
INSTALLATION HIGH LEVEL TRUNKING & PIPING WORKS
M&E WORK PHOTO;
AT LEVEL 5
DUCTWORKS SUBMAIN TRUNKING & CHILLED WATER
PIPING WORKS
HOSEREEL DRUM, BREAKGLASS & BELL
INSTALLATION FCU UNIT C/W DUCT INSTALLATION
M&E WORK PHOTO;
AT LEVEL 4
FCU UNIT C/W DUCT & CHILLED WATER PIPE
CONNECTION DUCTWORKS & FINAL SUB CABLING
DUCT INSTALLATION FOR AHU OT FINAL SUB CABLING
M&E WORK PHOTO;
AT LEVEL 3
DUCT INSULATION & FINAL SUB CABLING DUCT INSULATION & PENDANT BRACKET
INSTALLATION
CHILLED WATER PIPING CONNECTION TO
AHU UNIT DUCTWORKS FOR HEPA FILTER AT OT ROOM
M&E WORK PHOTO;
AT LEVEL 2
27
DUCT & CHILLED WATER PIPING
CONNECTION TO AHU UNIT
DUCT & CHILLED WATER PIPING
CONNECTION TO AHU UNIT
LIGHT FITTINGS ,SPRINKLER
HEAD,SPEAKER, SUPPLY & RETURN GRILLE
LIGHT FITTINGS ,SPRINKLER HEAD & AC
DIFFUSER
M&E WORK PHOTO;
AT LEVEL 1
28
• AVSU PANEL FOR MEDICAL GASES EM LOCK FOR CARD ACCESS SYSTEM
DUCTWORKS FOR KITCHEN HOOD
DB INSTALLATION
M&E WORK PHOTO;
AT ENGINEERING BLOCK
29
MAIN CABLING WORKS AT MSB ELECTRICAL MAIN CABLING WORKS AT MSB ELECTRICAL
GANTRY MAIN CABLING WORKS FROM ENGINEERING
BLOCK TO GANTRY