Environmental Monitoring Report ________________________________________
Project Number: 47021-002
Loan Number: 3239-PAK(COL)
Semi-Annual: July- December 2021 Document Date: March 2022
PAKISTAN: Federally Administered Tribal Areas
Water Resources Development Project
Prepared by Project Management Unit, SDU, Government of Khyber Pakhtunkhwa, Pakistan
for the Asian Development Bank
NOTES
(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its
agencies ends on 30 June.
(ii) In this report “$” refer to US dollars.
This environmental monitoring report is a document of the borrower. The views expressed herein
do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may
be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area.
a
Semi-Annual Environmental Monitoring
Report (SAEMR)
Project Number: (47021-002)
Loan Number: 3239-PAK
Islamic Republic of Pakistan: Federally Administered
Tribal Areas Water Resources Development Project
(FWRDP)
(Financed by the Asian Development Bank)
(Period: July – December 2021)
Client: Project Management Unit (PMU), Sustainable Development
Unit (SDU), Planning and Development Department (P&DD),
Government of Khyber Pakhtunkhwa.
Consultants: Joint Venture of BAK Consulting Engineers (PAK), AGES
Consultants and Rehman Habib Consultants (RHC) (Pvt) Ltd.
(PAK
Semi-Annual Environmental Monitoring Report July-December 2021
Page | ii
Contents 1 INTRODUCTION ..................................................................................................... 1
1.1 Preamble ................................................................................................................. 1
1.2 Headline Information ............................................................................................. 1
2 PROJECT DESCRIPTION AND CURRENT ACTIVITIES........................................ 2
2.1 Project Description ................................................................................................ 2
2.1.1 Construction of Saro Shah Weir ........................................................................... 7
2.1.2 Construction of Kharkai Weir .............................................................................. 10
2.1.3 Construction of Khar Canal Sub Surface Infiltration Gallery ............................ 12
2.1.4 Construction of CAD of Raghagan Dam ............................................................. 14
2.1.5 Construction of Bar Kas Dam ............................................................................. 17
2.1.6 Construction of Magoo Dand Dam ..................................................................... 19
2.1.7 CAD of Khurshid Dam ......................................................................................... 21
2.1.8 Construction of Bada Khel Weir ......................................................................... 24
2.1.9 Construction of Neeli Tangi Weir ........................................................................ 26
2.1.10 Construction of Tarkho Kas Weir ....................................................................... 28
2.1.11 Construction of Tor Dara Weir ............................................................................ 30
2.2 Substantially Completed Subprojects ................................................................ 32
2.2.1 Construction of Haji Lawang Kas ....................................................................... 32
2.2.2 Construction of CAD of Warsak Left Bank Canal .............................................. 35
2.2.3 Construction of Tabai Dam ................................................................................. 38
2.3 Project Contracts and Management ................................................................... 41
2.3.1 Coordination amongst Contractor, Owner, Lender ........................................... 42
2.4 Project Activities during Current Reporting Period ........................................... 44
2.4.1 Bajaur District ...................................................................................................... 45
2.4.2 Mohmand District ................................................................................................. 47
2.4.3 Khyber District ..................................................................................................... 48
2.5 Description of Any Changes to Project Design ................................................. 49
2.6 Description of Any Changes to Agreed Construction Methods ....................... 49
3 ENVIRONMENTAL SAFEGUARDS ACTIVITIES .................................................. 50
3.1 General Description of Environmental Safeguards Activities .......................... 50
3.2 Site Audits ............................................................................................................ 50
3.3 Issues Tracking (Based on Non-Conformance Notices) ................................... 52
3.4 Trends ................................................................................................................... 54
3.5 Unanticipated Environmental Impacts or Risks ................................................ 56
3.5.1 COVID-19 Pandemic ............................................................................................. 56
4 RESULTS OF ENVIRONMENTAL MONITORING ................................................ 58
Semi-Annual Environmental Monitoring Report July-December 2021
Page | iii
4.1 Overview of Monitoring Conducted during Current Period .............................. 58
4.2 Trends ................................................................................................................... 58
4.3 Summary of Monitoring Outcomes ..................................................................... 58
4.3.1 Instrumental Monitoring ...................................................................................... 58
4.3.2 Noise Monitoring .................................................................................................. 58
4.3.3 Air Quality Monitoring ......................................................................................... 59
4.3.4 Water Quality Monitoring..................................................................................... 62
4.3.5 Soil Erosion .......................................................................................................... 64
4.3.6 Natural Habitat Protection ................................................................................... 64
4.4 Material Resources Utilisation ............................................................................ 65
4.4.1 Current Period ...................................................................................................... 65
4.4.2 Cumulative Fuel Utilisation ................................................................................. 66
4.5 Waste Management.............................................................................................. 68
4.5.1 Current Period ...................................................................................................... 68
4.5.2 Cumulative Waste Generation ............................................................................ 68
4.6 Health and Safety ................................................................................................. 69
4.6.1 Community Health and Safety ............................................................................ 69
4.6.2 Workers` Safety and Health ................................................................................. 70
4.7 Training................................................................................................................. 71
5 FUNCTIONING OF THE SSEMP ........................................................................... 74
5.1 SSEMP Review ..................................................................................................... 74
6 GOOD PRACTICE AND OPPORTUNITY FOR IMPROVEMENT .......................... 75
6.1 Good Practice....................................................................................................... 75
6.1.1 Awareness ............................................................................................................ 75
6.1.2 Training................................................................................................................. 75
6.1.3 Communication .................................................................................................... 75
6.1.4 Supervision .......................................................................................................... 76
6.2 Opportunities for Improvement........................................................................... 76
6.2.1 Documentation ..................................................................................................... 76
6.2.2 Innovation ............................................................................................................. 76
6.2.3 Transparency ....................................................................................................... 76
7 SUMMARY AND RECOMMENDATIONS .............................................................. 77
ANNEX-1: ENVIRONMENTAL SAFEGUARDS COMPLETION REPORT ......................... 79
ANNEX-2 (A) ENVIRONMENTAL COMPLIANCE STATUS BAJAUR DISTRICT .............. 83
ANNEX-2 (B) ENVIRONMENTAL COMPLIANCE STATUS MOHMAND DISTRICT .......... 85
ANNEX-2 (C) ENVIRONMENTAL COMPLIANCE STATUS KHYBER DISTRICT.............. 87
ANNEX-3 MAJOR NON-COMPLIANCE NOTICES ............................................................ 89
ANNEX-4 CORRECTIVE ACTION PLAN ........................................................................... 91
ANNEX-5 INSTRUMENTAL MONITORING RESULTS ...................................................... 92
ANNEX-6: ENVIRONMENTAL MANAGEMENT PLAN .................................................... 113
ANNEX-7 A: WEEKLY MONITORING CHECKLIST ........................................................ 135
ANNEX-7 B: URDU BROCHURES FOR ENVIRONMENTAL AWARENESS FOR
CONTRACTOR STAFF .................................................................................................... 137
ANNEX-8: GUIDELINES FOR CAMP SITE SELECTION ................................................ 145
ANNEX-9: PHOTO LOG ................................................................................................... 147
Semi-Annual Environmental Monitoring Report July-December 2021
Page | iv
List of Exhibits
Project Location .................................................................................................................. 3
SSEMP Submission Details of Sub Projects ......................................................................... 5
Saro Shah Weir Location Map ............................................................................................. 9
Kharkai Weir Location Map ............................................................................................... 11
Khar Canal Sub Project Location Map ............................................................................... 13
CAD Raghagan Dam Location Map ................................................................................... 16
Location Map of Bar Kas Dam ........................................................................................... 18
Location Map of Magoo Dand Dam .................................................................................. 20
Location Map of CAD of Khurshid Dam ............................................................................ 23
Location Map of Bada Khel Weir .................................................................................. 25
Location Map of Neeli Tangi Weir................................................................................. 27
Location Map of Tarkho Kas Weir ................................................................................. 29
Location Map of Tor Dara Weir ..................................................................................... 31
Haji Lawang Kas Location Map ...................................................................................... 34
CAD of Warsak LBC Location Map................................................................................. 37
Map showing location of Tabai Dam ............................................................................ 39
Substantially Completed Sub Projects .......................................................................... 40
Details of Contractors ................................................................................................... 43
Physical Progress of Sub Projects in Bajaur District ...................................................... 46
Physical Progress of Sub Projects in Mohmand District ............................................... 47
Physical Progress of Sub Project in Khyber District ...................................................... 48
Overall conformance Level of All Sub-Projects at District Mohmand .......................... 52
Overall conformance Level of All Sub-Projects at District Bajaur ................................. 52
Overall conformance Level of All Sub-Projects at District Khyber ................................ 53
Project Major and Minor Non-Conformance Level....................................................... 53
Summary of Issues Tracking Activity for Current Period .............................................. 54
Percentage Conformance of each SAEMR .................................................................... 54
Environmental Compliance Trend ................................................................................ 55
Total No. of Issues in each Reporting Period ................................................................ 55
Issues Trending ............................................................................................................. 56
Noise Testing Results .................................................................................................... 59
Air Quality Test Results ................................................................................................. 61
Drinking Water Quality Results ..................................................................................... 63
Watershed Management Status ................................................................................... 64
Fuel Consumption in last 6 Months .............................................................................. 67
Cumulative Fuel Consumption Trend ........................................................................... 67
Solid Waste Generated at Sites ..................................................................................... 68
Health and Safety Statistics........................................................................................... 70
Details of Trainings ........................................................................................................ 71
Semi-Annual Environmental Monitoring Report July-December 2021
Page | v
Abbreviations
ADB Asian Development Bank
CAP Corrective Action Plan
CBO Community Based Organization
DCSC Design and Construction Supervision Consultants
EARF Environment Assessment and Review Framework
EIA Environmental Impact Assessment
EoT Extension of Time
EMP Environmental Management Plan
EPA Environmental Protection Agency
ERP Emergency Response Plan
ESMU Environmental and Social Management Unit
FATA Federally Administrated Tribal Areas
FWRDP FATA Water Resources Development Project
GAP Gender Action Plan
GRC Grievance Redressl Committee
GRM Grievance Redressl Mechanism
HSE Health Safety and Environment
IA Implementing Agency
IEE Initial Environmental Examination
LPG Liquid Petroleum Gas
NEQS National Environmental Quality Standards
NCN Non-Compliance Notice
NGO Non-Governmental Organization
NSL Natural Surface Level
PIU Project Implementation Unit
PMU Project Management Unit
PPE Personal Protective Equipment
QPR Quarterly Progress Report
RD Reduced Distance
RE Resident Engineer
REA Rapid Environmental Assessment
SSEMP Site Specific Environmental Management Plan
SAEMR Semi-Annual Environmental Monitoring Report
SPS Safeguard Policy Statement 2009
VO Variation Order
WHO World Health Organization
WWF World Wide Fund for Nature
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 1
1 INTRODUCTION
1.1 Preamble
1. This report represents the Semi-Annual Environmental Monitoring Report (SAEMR) for
FATA Water Resources Development Project (FWRDP).
2. Design and Construction Supervision Consultants (DCSC) have prepared this Semi-
Annual Environmental Monitoring Report (SAEMR) for Project Management Unit (PMU)
covering period from July 2021 to December 2021. This report fulfils the requirements
to monitor the effectiveness of ADB`s Safeguards Policy Statement 2009, its
implementation and to ensure sound environmental planning. During the environmental
monitoring the gaps/shortcomings in the implementation of environmental safeguards
as per Safeguard Policy Statement (SPS) 2009 were identified and corrective actions
proposed and recommendations for future course of action provided.
1.2 Headline Information
3. DCSC`s environment team has orientated all the contractors on environmental
compliances as per IEEs/EMPs. The team has observed that environmental
management has improved over the time on subprojects sites. Mutually agreed
Corrective Action Plan is also devised and communicated to the contractors.
Contractors have been advised to address non-compliances as per agreed Corrective
Action Plan. Environment Safeguard Team of consultants includes, an Environment
Specialist, three Environmental Inspectors for looking after the EMP implementation on
different sites in Khyber, Mohmand and Bajaur Districts. Beside this HSE Managers
have been hired by the contractors for dams’ subprojects while for diversion weirs and
infiltration galleries contractors have nominated an engineering staff for of SSEMP at
sites. Therefore, the progress in environmental compliance has been improved during
the reporting period.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 2
2 PROJECT DESCRIPTION AND CURRENT ACTIVITIES
2.1 Project Description
4. Federally Administered Tribal Areas (FATA) Water Resources Development Project
(FWRDP) is operational in the provincial territories of Khyber Pakhtunkhwa (KP) at the
western borders of Pakistan with Afghanistan. It focuses on increasing irrigation
supplies in three districts, namely Mohmand, Khyber and Bajaur to increase crop
production and harvest water sustainably. The project is being proposed as a result of
the Water Assessment Study executed under the completed ADB supported FATA
Rural Development Project of former FATA Secretariat. The study identified 40
watersheds where the groundwater aquifers are depleting at a high rate, even under
average weather conditions due to unplanned water extraction for irrigation and other
associated purposes. It recommends shifting from groundwater to surface water, which
remains totally unutilized, and identified potential sites for small reservoirs dams and
diversion weirs in the 40 watersheds of Mohmand, Khyber and Bajaur Districts of KP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 4
5. Project Management Unit (PMU) of FATA Water Resources Development Project
(FWRDP) has screened out thirty-four (34) subprojects for irrigation of agricultural land
under FWRDP. These subprojects have been screened, classified, and assessed
according to ADB’s Safeguard Policy Statement (SPS) 2009 and Pakistan
Environmental Protection Agency Review of IEE/EIA Regulations 2000. Environmental
considerations were assessed for these subprojects. Initial Environmental Examination
(IEEs) and Environmental Management Plans (EMPs) for 34 subprojects were
prepared by Design and Construction Supervision Consultant (DCSC), covered in 24
Nos Initial Environmental Examination (IEE) reports. Out of total 24 IEEs, 20 IEEs were
prepared for individual sub project while one consolidated IEE covers 8 sub projects
and three IEES covers two sub projects, respectively. All IEEs were cleared and
disclosed by ADB. Environmental Approvals were received from Environmental
Protection Agency (EPA) for all IEEs.
6. Presently, 121 subprojects are under construction while twenty-two (22) are
substantially completed. The table below (Exhibit 2) is a representation of each
subproject`s description in terms of environmental safeguards implementation (IEEs
and SSEMPs) as per ADB Safeguard Policy Statement 2009. Contractors are required
to submit the SSEMP and get an approval from DCSC/PMU 10 days before
commencement of civil works. This was a challenge for DCSC and PMU to comply with
this requirement at the start of the project as the contractor’s capacity to understand
environmental safeguards were not up to the mark as they have worked in erstwhile
FATA and environmental compliance in erstwhile FATA was a hard task and they have
not seen this type of requirement in any contract before FWRDP, but still, we put every
effort to ensure this compliance. As reflected in exhibit 2 the SSEMPs submission and
approval process was improved as compared with the initial subprojects for which
SSEMPs were submitted late.
7. A training session is regularly arranged for newly awarded contracts at DCSC office and
PMU to build the capacity of the contractors and understand the importance of
environmental safeguards implementation during subproject`s execution. Every
contractor is briefed in PMU about the SSEMP and its importance and in the same
session templates and SSEMP guidance handbook is provided to them for their
understanding and convenience.
1 Kamar Ragha Dag subproject is being executed as VO of CAD of Raghagn Dam subproject
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 5
SSEMP Submission Details of Sub Projects
S.
No
Name of Sub-
Project
Contractor
Name
Date of
Physical
Work Started
Status of
IEEs
Approval
Date of
SSEMPs
COVID-19
Updation
District Bajaur
1 Kharkai Weir
(Remaining
Works)
M/s MBCC 15-April-
2021
Approved 08-April-
2021
08-April-
2021
2 Daman Lift
Irrigation
M/s Haji Lal
Bad shah&
Sons
10-Aug-2018 Approved 18-Oct-
2018
30-Nov-
2020
3 Badi Samoor
Weir
M/s Haji Lal
Bad shah&
Sons
10-Aug-2018 Approved 18-Oct-
2018
26-Nov-
2020
4 Lardand Weir M/s Haji Lal
Bad shah&
Sons
16-Aug-2018 Approved 18-Oct-
2018
02-Dec-
2020
5 Damano Weir M/s National
RCC Works
Pvt Ltd
05-May-
2018
Approved 18-Oct-
2018
08-Dec-
2020
6 Nalai Kas Weir M/s National
RCC Works
Pvt Ltd
05-May-
2018
Approved 04-Sep-
2018
08-Dec-
2020
7 Shunga Weir M/s National
RCC Works
Pvt Ltd
10-May-
2018
Approved 04-Sep-
2018
08-Dec-
2020
8 Khar Canal Sub
Surface Infiltration
Gallery
M/s PMC-JHK
(JV)
10-Oct-2019 Approved 27-Sep-
2019
01-Dec-
2020
9 Lara Dandokai
Weir
M/s PMC-JHK
(JV)
28-Oct-19 Approved 27-Sep-
2019
02-Dec-
2020
10 Haji Lawang Kas
Lift Irrigation
M/s PMC-JHK
(JV)
25-Oct-19 Approved 27-Sep-
2019
01-Dec-
2020
11 Chepatra Weir M/s Zeraki
Enterprises
04-Nov-2019 Approved 02-Nov-
2019
27-Nov-
2020
12 Hayatai Sub
Surface Infiltration
Gallery
M/s Zeraki
Enterprises
06-Dec-2019 Approved 05-Nov-
2019
01-Dec-
2020
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 6
13 Shukrata Sub
Surface Infiltration
Gallery
M/s Zeraki
Enterprises
10-Dec-2019 Approved 05-Nov-
2019
07-Dec-
2020
14 Kat Gala
Extension of
Irrigation Chanel
M/s Zeraki
Enterprises
25-Nov-2019 Approved 15-Nov-
2019
02-Dec-
2020
15 Derakai Weir M/s MBCC-
PMC(JV)
11-Mar-20 Approved 10-Mar-
2020
09-Dec-
2020
16 CAD Raghagan
Dam
M/s National
RCC Works
Pvt Ltd
16-Apr-20 Approved 16-Mar-
2020
25-Nov-
2020
17 Dawawo Weir M/s National
RCC Works
Pvt Ltd
18-Aug-20 Approved 27-Jul-2020 30-Nov-
2020
District Mohmand
18 Jay Dam M/s Ali & Co 10-Oct-17 Approved 02-May-
2018
26-Nov-
2020
19 Ganjyano Danish
Kool Lift Irrigation
M/s Sher
Ghazan Khan
Construction
Company
08-June-
2018
Approved 04-Sep-
2018
01-Dec-
2020
20 Mundara Weir M/s Sher
Ghazan Khan
Construction
Company
15-Jul-2018 Approved 29-Oct-
2018
04-Dec-
2020
21 Saro Shah Weir
M/s PMC-JHK
(JV)
04-Dec-2019 Approved 27-Sep-
2019
07-Dec-
2020
22 Serai Bazar Shah
Lift Irrigation
M/s PMC-JHK
(JV)
23-Dec-2019 Approved 27-Sep-
2019
07-Dec-
2020
23 Madar Irrigation
Scheme
M/s Zeraki
Enterprises
11-Oct-2019 Approved 01-Oct-
2019
04-Dec-
2020
24 CAD of Warsak
Left Bank Canal
M/s Ali & Co 29-Dec-2020 Approved 11-Dec-
2020
11-Dec-
2020
25 CAD of Khurshid
Dam
M/s MBCC
Builders & M/s
PMC JV
29-Dec-2020 Approved 17-Dec-
2020
11-Dec-
2020
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 7
2.1.1 Construction of Saro Shah Weir
8. The Saro Shah subproject is proposed at Ambahar Khwar. The distance from Ekka
Ghund through District Mohmand Road is 55.5 km to reach weir site. As per site
observation perennial flow of 255 lit/sec (9 cusecs) exist in the khwar. The Saro Shah
subproject is proposed at coordinates of 34.5484° N &71.4502°E.
9. Weir is proposed at Saro Shah to collect water from the khwar and convey it to the
sump. Solar pumps are proposed to lift water from the sump and deliver it to the
command area. It is anticipated that from the scheme, culturable command area of 100
ha will be irrigated at cropping intensity of 126 % and design discharge of 134.1 lit/sec.
Total length of irrigation network is 2.90 km.
10. The project cost is estimated at Rs. 92.530 million and anticipated to take 12 months to
complete. The results of the economic analysis show that the project is economically
District Khyber
26 Shangade Weir M/s New Malik
Afridi & Co
25-Nov-2017 Approved Late
Submitted
Project
Completed
before
COVID
27 Tabai Dam M/s Tribal
Global
Construction
(Pvt) Ltd.
14-Jul-2020 Approved 16-June-
2020
26-Nov-
2020
28 Bar Kas Dam M/s Tribal
Global
Construction
(Pvt) Ltd.
14-Jul-2020 Approved 16-June-
2020
13-Oct-
2020
29 Magoo Dand Dam M/s National
RCC Works
Pvt Ltd.
01-Oct-2020 Approved 27-Jul-2020 13-Oct-
2020
30 Bada Khel Weir M/s New Malik
Afridi & Co
16-Feb-2021 Approved 01-Feb-
2021
01-Feb-
2021
31 Neeli Tangi Weir M/s Habib
Khan Builders
22-Sep-2021 Approved 10-Jul-2021 10-Jul-2021
32 Tarkho Kas Weir M/s Habib
Khan Builders
22-Sep-2021 Approved 18-Jul-2021 18-Jul-2021
33 Tor Dara Weir M/s Habib
Khan Builders
22-Sep-2021 Approved 26-Jul-2021 26-Jul-2021
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 8
viable (EIRR 10.84 %). The financial analysis also indicates the safe investment with
FIRR as 9.43 %.
11. The subproject activities may cause some disturbances to the environment due to
material dumping, machinery work, taking borrow material, setting up of camp areas,
transportation on link roads and necessary facilities for the staff / labour to be engaged
for the subproject. These impacts are mitigated through measures envisaged in EMP.
12. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature.
13. Subproject does not involve any permanent or temporary land acquisition. No
indigenous people and women headed households have been identified in the
subproject area. The other social issues like safety of public and workers, security
problems, risk of communicable diseases, vector borne diseases etc. are of temporary
in nature. Subproject leads to creation of job opportunities particularly for the local
population and socioeconomic uplift through irrigated agriculture.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 10
2.1.2 Construction of Kharkai Weir
14. The Kharkai Weir subproject envisages construction of weir at coordinates
34°53'43.00"N & 71°24'24.40"E on Wara Kharkai Stream. The Wara Kharkai weir site
is located about 21.4 Km North West of District Head Quarter Khar of Bajaur District.
15. It is envisaged to construct a low height weir and crest length 11 m for design flood of
50-year return period of 57 cumec. A Tyrolean part of 3 m in length is provided for
conveying of design discharge for canal/irrigation conduit. It is anticipated that from the
scheme, gross command area of about 164 ha and culturable command area of 126 ha
will be irrigated at cropping intensity of 133 % and design discharge of 53 lit/sec. The
irrigation network consists of main conduit (2350 m) and minor (850 m).
16. The project cost is estimated PRs. 47.70 million and anticipated to take 12 months to
complete. The results of the economic analysis show that the project is economically
viable (EIRR 57.93 %). The financial analysis also indicates the safe investment with
FIRR as 52.74 %.
17. The contractor M/s Rustam Khan & Co. was terminated due to slow progress and now
the contract has been awarded to M/s MBCC & Builders for the scope of remaining
woks of the subproject and SSEMP has been updated accordingly.
18. The subproject activities may cause some disturbances to the environment due to
material dumping, machinery work, taking borrow material, setting up of camp areas,
transportation on link roads and necessary facilities for the staff / labor to be engaged
for the subproject, in the RoW of Kharkai weir site and the allied sites. These impacts
are mitigated through measures envisaged in EMP.
19. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature.
20. Subproject does not involve any permanent or temporary land acquisition. No
indigenous people and women headed households have been identified in the
subproject area. The other social issues like safety of public and workers, security
problems, risk of communicable diseases, vector borne diseases etc. are of temporary
in nature. Subproject leads to creation of job opportunities particularly for the local
population and socioeconomic uplift through irrigated agriculture.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 12
2.1.3 Construction of Khar Canal Sub Surface Infiltration Gallery
21. The Khar Canal Project is located on Charmang Khwar Khar Canal site is located at a
distance of 1.2 km from Khar through paved road. As per site observation perennial
flow of 0.95 cumec exists in the khwar.
22. A network of subsurface pipe is proposed in the active flow channel of the khwar to
collect the flow. It is anticipated that from the scheme, culturable command area of 154
ha will be irrigated at cropping intensity of 133 % and design discharge of 116.5 lit/sec.
Total length of irrigation network is 7 km.
23. The project cost is estimated PRs. 49.179 million and anticipated to take 12 months to
complete. The results of the economic analysis show that the project is economically
viable (EIRR 31.76 %). The financial analysis also indicates the safe investment with
FIRR as 27.36 %.
24. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas and necessary facilities for the staff /
labour to be engaged for the subproject. All the anticipated adverse environmental
impacts of the subproject are mitigatable, temporary in nature and localized which can
be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 13
Khar Canal Sub Project Location Map
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 14
2.1.4 Construction of CAD of Raghagan Dam
25. Raghagan Dam Project is located across Babukara Khwar, a left bank tributary of
Bajaur Khwar, which ultimately falls into Panjkora River. The dam is located in Salarzai
area of Bajaur District. The villages located in the vicinity of dam are Raghagan,
Charghurai Marusa, Mullah Killi and Qazi Dheri.
26. The coordinates of Raghagan Dam Command Area sites are
S. No. Longitude (m) Latitude (m)
1. 734060.005 3851812.240
2. 736034.496 3848332.633
3. 745827.699 3853889.752
4. 743867.430 3857377.429
27. The project is divided into seven (07) number of chunks totaling gross command area
of 1,113 ha and cultivable command area of 929 ha. This Project includes development
of command area by providing irrigation network from the Raghagan main right and left
irrigation channels though outlets either by lift or through gravity. After the successful
completion of the Raghagan Dam Project, the proposed system under study will be able
to irrigate 929 ha. This project involves construction of secondary distributary system
which is inclusive of primary and secondary water courses/channels having a length of
31.50 km and tertiary distribution system which comprises tertiary water courses having
length of 41.20 km. It is to mention here that due to topography of the command area;
these water courses/channels have allied structures such as stepped fall structures,
aqueducts, syphon’s, road culverts, drainage culverts, sumps for lifting, lifting pipes, solar panels, accessories, naccas and washing pads etc.
28. The project cost is estimated to be PRs. 430.672 million and is anticipated to take 18
months period to complete. The results of the economic analysis show that the project
is economically viable (EIRR 12.24 %). The financial analysis also indicates the safe
investment with FIRR as 10.21 %.
29. The Kamar Ragha Dag diversion arrangement was proposed on Bajaur Khwar.
Kamar Ragha Dag subproject site is located at a distance of 7 km from Khar
through paved road. As per site observation perennial flow of 1.48 cumec exist
in the khwar.
30. Sub-surface Infiltration Gallery was proposed to collect water from the khwar
and convey it to the sump. Solar pumps are proposed to lift water from the sump
and deliver it to the command area. It is anticipated that from the scheme,
culturable command area of 137.6 ha will be irrigated at cropping intensity of
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 15
130 % and design discharge of 86.9 lit/sec. Total length of irrigation network is
4.63 km.
31. The subproject cost is estimated Rs. 47.884 million and anticipated to take 12
months to complete. The results of the economic analysis show that the
subproject is economically viable (EIRR 27.37 %). The financial analysis also
indicates the safe investment with FIRR as 23.75 %.
32. At the time of feasibility and detail design of CAD of Raghagan Dam it was learned the
command area of Kamar Ragha Daag falls within the command area of Raghgan Dam
so it was decided that it will be irrigated from the right bank channel of Raghgan dam
which is more feasible option.
33. Kamar Ragha Dag subproject is being executed as Variation Order (VO) of CAD of
Raghagn Dam subproject which is already under construction.
34. The CAD of Raghagan Dam subproject based on Rapid Environmental Assessment
(REA) is categorized as “B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature
and will cause some disturbances to the local environment during execution like
material dumping, machinery work; borrow material, camp areas and necessary
facilities for the staff/ labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporary in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 16
CAD Raghagan Dam Location Map
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 17
2.1.5 Construction of Bar Kas Dam
35. The Bar Kas Dam is proposed on Brag Khwar in Tehsil Landi Kotal of Khyber District.
Bar Kas Dam subproject site is located at a distance of about 50 Km from District
headquarter Jamrud. The proposed Bar Kas Dam is located at coordinates 71.1483 E
& 33.9915N.
36. A 15 m high and 131.00 m long Bar Kas RCC Slab/Box Local Material Filled Dam with
reservoir capacity of 0.267 Mm3 and spillway flood capacity of 230 m3/sec is proposed
at Barkas area of Khyber District to collect water from the Brag khwar and convey it to
the barani (rain-fed) command area. Cultivable command area of 75 ha will be irrigated
at cropping intensity of 120 % and design discharge of 21.95 lit/sec. Total length of
irrigation network is 3.15 km.
37. The project cost is estimated Rs. 324.557 million and anticipated to take 18 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 7.51 %). The financial analysis also indicates the safe
investment with FIRR as 6.29 %.
38. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 18
Location Map of Bar Kas Dam
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 19
2.1.6 Construction of Magoo Dand Dam
39. The Magoo Dand Dam is proposed on Aziz Khwar in Tehsil Bara of Khyber District.
Magoo Dand Dam subproject site is located at a distance of about 37 Km from district
headquarter Jamrud. The proposed Magoo Dand Dam is located at coordinates
71.4756° E and 33.7649°N.
40. A 15 m high and 60 m long Magoo Dand Concrete Gravity Dam with reservoir capacity
of 0.3094 Mm3 and design flood capacity of 97 cumecs is proposed at Magoo Dand
area of Khyber District to collect water from the Aziz khwar and convey it to the barrani
(rain-fed) command area. Cultivable command area of 76 ha will be irrigated at cropping
intensity of 125 % and design discharge of 0.02473 m3/sec (24.73 liter/sec). Total
length of delivery pipe irrigation network is 316 m and 3.195 km respectively.
41. The subproject cost is estimated Rs. 252.427 million and anticipated to take 18 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 10.15 %). The financial analysis also indicates the safe
investment with FIRR as 8.58%.
42. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 20
Location Map of Magoo Dand Dam
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 21
2.1.7 CAD of Khurshid Dam
43. Khurshid Dam is located at coordinates 34°22'28.9"N 71°35'54.1"E across Nawey Dand
nullah/ khwar, a tributary of Swat River. The subproject is located in Prang Ghar area
about 40 km North East of Ghalani (District Headquarter) of Mohmand District.
44. Irrigation canal on left bank offtake from main dam to irrigate the command area. The
entire canal length of 2.7 km from intake point to tail end is partially choked by eroded
material and damaged at different locations by the local community. Utilizing the water
through solar pumps, at both sides of Khwar, from main reservoir and channel for
irrigating lands at higher elevation is observed in command area. Water conveyance
from dam to the fields is the crux of the project.
45. The major issue with the construction of command area development of Khurshid dam
is blockage of main road when the reservoir rises to normal conservation level (El 434
m) whereas the bed level of stream at river crossing is 432m, in order to make the road
accessible the locals have to drawdown the reservoir which results in water loss of 13
ha-m out of 52 ha-m of reservoir capacity which is approx. 25% loss of water/ benefits.
In order to overcome this issue, the present study includes multi barrel causeway, with
the height of 4.0m, which will result in utilization of top 25% reservoir capacity for the
agricultural benefits.
46. The subproject is divided into five (05) number of chunks totaling command area of 104
ha. This project includes development of command area by providing irrigation network
from the Khurshid irrigation channel though outlet. The proposed system under study
will be able to irrigate 104 ha. This project involves primary (rectangular section),
secondary and tertiary watercourses (Parabolic Precast E types), fall structures,
syphon, road culvert, drainage culverts, sumps, minors through Parabolic Type E,
nacca and washing pads etc.
47. The existing cropping intensity is 70%. Future irrigation intensity of subproject is
proposed as 126%. Total length of main irrigation channel under this subproject is 6.08
km.
48. The subproject cost is estimated to be Rs. 119.772 million and is anticipated to take 12
months period to complete. The results of the economic analysis show that the project
is economically viable (EIRR 12.86 %). The financial analysis also indicates the FIRR
as 10.94 %.
49. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 22
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 23
Location Map of CAD of Khurshid Dam
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 24
2.1.8 Construction of Bada Khel Weir
50. The Bada Khel weir sub-project is proposed on Lashora khwar. The sub-project site is
located at a distance of 12 km from Jamrud, Khyber District Headquarter. As per site
observation there is perennial flow in the khwar.
51. With the development of irrigation scheme, the perennial flows of the Lashora khwar
will be utilized to irrigate, command area of adjacent locality. The design and layout
planning of the irrigation scheme have been done by considering, topography,
command area and geology of the weir axis.
52. Bada Khel weir is proposed to collect water from the khwar and convey it to the
command area of approximately 26.77 hectares lying downstream of the proposed weir
site. Cultivable command area of 26.77 ha will be irrigated at cropping intensity of 81.8
% and design discharge of 14.7 lit/sec will be required to serve the purpose. Total length
of irrigation network is approximately 2.77 km.
53. The project cost is estimated Rs. 22.477 million and anticipated to take 12 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 12.63 %). The financial analysis also indicates the safe
investment with FIRR as 11.16 %.
54. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 25
Location Map of Bada Khel Weir
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 26
2.1.9 Construction of Neeli Tangi Weir
55. The Neeli Tangi weir sub-project is proposed on Neeli Tangi khwar and is located at a
distance of 68 km from Jamrud Khyber District Head Quarter. As per site observation
there is perennial flow in the khwar.
56. With the development of irrigation scheme, the perennial flows of the Neeli Tangi khwar
will be utilized to irrigate, command area of adjacent locality. The design and layout
planning of the irrigation scheme have been done by considering, Topography,
Command area and geology of the weir axis.
57. Neeli Tangi weir is proposed to collect water from the khwar and convey it to the barrani
command area. Cultivable command area of 80.36 ha will be irrigated at cropping
intensity of 100 % and design discharge of 21.11 liter /sec (0.75 cfs). Total length of
irrigation network is 7.12 km.
58. The project cost is estimated Rs. 58.437 million and anticipated to take 12 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 12.02 %). The financial analysis also indicates the safe
investment with FIRR as 10.16 %.
59. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 27
Location Map of Neeli Tangi Weir
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 28
2.1.10 Construction of Tarkho Kas Weir
60. The Tarkho Kas Weir sub-project is proposed on Matu Nullah near village Naghara in
Tirah vallay in District Khyber and is located at a distance of 79 km from Jamrud Khyber
District head quarter. As per site observation there is perennial flow exist in the Nullah.
61. Tarkho Kas Weir is proposed to collect water from Matu Nullah and convey it to the
command area. Cultivable command area of 90 ha will be irrigated at cropping intensity
of 100 % and design discharge of 28.9 lit/sec. Total length of irrigation network is 5290
m.
62. The project cost is estimated Rs. 64.577 million and anticipated to take 12 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 12.23 %). The financial analysis also indicates the safe
investment with FIRR as 10.33 %.
63. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 29
Location Map of Tarkho Kas Weir
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 30
2.1.11 Construction of Tor Dara Weir
64. The Tor Dara weir sub project has two weirs one on the main Tor Dara Nullah and the
other on its small tributary near village Natu Khel in Tirah Valley, District Khyber and is
located at a distance of 100 km from Peshawar.
65. During various visits at site the hydrological observation was made and found the
perennial flow in a range of 5-8 cusecs. In the last site visit was made approximately 5
cusecs of flows was observed on Tor Dara nullah and 0.30 cusecs was observed in its
tributary.
66. Tor Dara Weir and Natu Khel Weirs are proposed to collect water from Tor Dara Nullah
and its tributary to convey the available flows to the command area laying at both right
and left side of Tor Dara Nullah. Gross command area is 96 hectares and cultivable
command area is 93 hectares which is proposed to be irrigated at cropping intensity of
100 % with the design discharge of 22.90 lit/sec and 6.45 lit/sec for Tor Dara and Natu
Khel Weir respectively.
67. The main features of the project include construction of weirs, irrigation channels,
retaining walls, fall structures, road culverts and drainage culverts, on-farm water
management works and improvement of ware sheds through forestation. The project
cost is estimated as Rs. 93.804 million and is anticipated to take 12 months period to
complete. The results of the economic analysis show that the sub project is
economically viable (EIRR 12.03%). The financial analysis also indicates the safe
investment with FIRR as 10.23%.
68. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 31
Location Map of Tor Dara Weir
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 32
2.2 Substantially Completed Subprojects
69. The substantial construction of the subprojects mentioned below have been
successfully completed without any major environmental issues and the project
environmental compliance was rated as satisfactory.
70. The six subprojects (Shangade Weir, Shunga Weir, Nailai Kas Weir, Damano Weir,
Maddar Infiltration Gallery and Kat Gala irrigation channel) were completed in all
respects and were reported in 7thSAEMR July-December 2020. Thirteen (13)
subprojects (Jay Dam, Ganjyano Danish Kool Infiltration Gallery, Mundara Weir, Badi
Samoor Weir, Lar Dand Weir, Daman Lift Irrigation, Shukrata Infiltration Gallery,
Chepatra Weir, Dawawo Weir, Derakai Weir, Lara Dandokai Weir, Hayatai Infiltration
Gallery and Serai Bazar Shah Infiltration Gallery) were completed in all respects and
were reported in 8thSAEMR January-June 2021. While in the current reporting period
three subprojects have been completed namely (CAD of Warsak Left Bank Kanal, Haji
Lawang Kas Weir and Tabai Small Dam). The subprojects completion report
(Environment Compliance part) for 19 subprojects were also submitted previously.
2.2.1 Construction of Haji Lawang Kas
71. The Haji Lawang Kas subproject is located downstream of confluence of Watalai and
Charmang Khwars. Haji Lawang site is located at a distance of 2.3 km from Khar
through paved road. As per site observation perennial flow of 2.16 cumec exists in the
khwar.
72. A network of subsurface pipe is proposed in the active flow channel of the khwar to
collect the flow. It is anticipated that from the scheme, culturable command area of 39
ha will be irrigated at cropping intensity of 133 % and design discharge of 78.3 lit/sec.
Total length of irrigation network is 1.95 km.
73. The project cost is estimated PRs. 23.207 million and anticipated to take 12 months to
complete. The results of the economic analysis show that the project is economically
viable (EIRR 15.14 %). The financial analysis also indicates the safe investment with
FIRR as 12.79 %.
74. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas and necessary facilities for the staff /
labour to be engaged for the subproject. All the anticipated adverse environmental
impacts of the subproject are mitigatable, temporary in nature and localized which can
be mitigated through implementation of EMP.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 33
75. Environmental impacts like soil erosion, soil contamination, water contamination, air
pollution, high noise level, etc. are of temporary nature and can be controlled and
mitigated through proper management of borrow material area, establishment and
proper management of camp and material and machinery yard, transportation on link
roads and necessary facilities for the staff and labour by using good engineering
practices. Soil erosion and contamination, water contamination, air pollution and high
noise levels needs to be controlled with the use of good engineering practices.
76. Contractor is bound to develop Site Specific Environmental Management Plan
(SSEMP), Traffic Management Plan, Solid Waste Management and Material
Management Plan, Occupation Health and Safety Plan etc. before starting the
construction activities and to ensure that no damage is done to the wildlife, public
infrastructure and local culture, customs, and traditions.
77. This subproject has been completed for civil works and the overall environmental
safeguard performance of the said subproject was rated satisfactory while the details
are provided in Annex-1.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 34
Haji Lawang Kas Location Map
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 35
2.2.2 Construction of CAD of Warsak Left Bank Canal
78. Warsak Dam is a mass concrete gravity dam located at coordinates 34°09′50″N & 71°21′29″E on the Kabul River, approximately 20 km northwest of the city of Peshawar
in the Khyber Pakhtunkhwa province of Pakistan.
79. Warsak Left Bank Canal offtakes from main Warsak dam through left bank irrigation
conduit 2 Km downstream of the main dam to irrigate the command area. The capacity
of left bank irrigation conduit is 45 cusecs. Total length of the canal is 18.4 miles.
80. Water conveyances from channel to the fields are unlined which causes excessive
seepage resulting in water shortages at the tail end. The present feasibility study
undertakes the on-farm water management by lining the watercourses and construction
of proper Nuccas. Irrigation Department KP has also executed a separate project for
lining of main channels. This was thoroughly discussed with the official of Irrigation
Department and it was mutually agreed that FWRDP will undertake the on-farm water
management while Irrigation Department will continue with the main irrigation channels.
81. As per Irrigation Department, water availability for the Warsak Left bank Canal System
is120 Acre/Cusecs which seems to be enough to feed the proposed command area.
Agriculture study including crop water requirement carried out under this subproject
reveals that the allowance kept by the Irrigation Department is sufficient and with
execution of this subproject the present irrigation intensity will increase from 108% to
150%.
82. The subproject is divided into two (02) numbers of chunks totaling command area of
926 ha. The subproject includes lining of watercourses by using parabolic type-D
segments, Type-E segments, and PCC channel at some locations including allied
structures (Nuccas, Culverts and Washing pads). Total length of watercourses network
in On-Farm Water Management Works under this subproject is estimated to be 64.647
Km.
83. The total project cost is estimated to be Rs. 238.749 million and is anticipated to take
15 months period to complete. The results of the economic analysis show that the
project is economically viable (EIRR 16.53 %). The financial analysis also indicates the
safe investment with FIRR as 14.27 %.
84. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it does not involve
permanent land acquisition. No indigenous people or women headed households are
found in the subproject area. Safety of public and workers, security problems, risk of
communicable diseases, vector borne diseases etc. are of temporary nature which can
be mitigated through well managed operations. Expected benefits of the subproject are
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 36
development of land through irrigated agriculture and creation of job opportunities
particularly for the local population.
85. All the anticipated adverse environmental impacts of the project can be mitigated,
temporary in nature and localized. There is no environmentally sensitive or
archaeological site falling within project area of influence. The REA Checklist defines
this subproject in category “B” as per ADB guidelines categorization.
86. Contractor is bound to develop Site Specific Environmental Management Plan
(SSEMP), Traffic Management Plan, Solid Waste Management and Material
Management Plan, Occupation Health and Safety Plan etc. before starting the
construction activities and to ensure that no damage is done to the wildlife, public
infrastructure and local culture, customs, and traditions.
87. This subproject has been completed for civil works and the overall environmental
safeguard performance of the said subproject was rated satisfactory while the details
are provided in Annex-1.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 37
CAD of Warsak LBC Location Map
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 38
2.2.3 Construction of Tabai Dam
88. The Tabai Dam is proposed on Tabai Khwar of Tehsil Landi Kotal of Khyber district.
Tabai Dam sub project site is located at a distance of 43 km from Ali Masjid through
paved road and about 60 Km from district headquarter Jamrud. The proposed Tabai
Dam is located at coordinates 70.9715 E & 33.9977 N.
89. A 15 m high and 49.50 m long Tabai concrete gravity Dam with reservoir capacity of
0.206 Mm3 and spillway flood capacity of 95 m3/sec is proposed at Tabai area of
Khyber district to collect water from the khwar and convey it to the barrani command
area. Culturable command area of 50 ha will be irrigated at cropping intensity of 120 %
and design discharge of 14.64 lit/sec. Total length of irrigation network is 2.75 km.
90. The project cost is estimated Rs. 153.44 million and anticipated to take 18 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 7.27 %). The financial analysis also indicates the safe
investment with FIRR as 5.64 %.
91. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
92. Contractor is bound to develop Site Specific Environmental Management Plan
(SSEMP), Traffic Management Plan, Solid Waste Management and Material
Management Plan, Occupation Health and Safety Plan etc. before starting the
construction activities and to ensure that no damage is done to the wildlife, public
infrastructure and local culture, customs, and traditions.
93. This subproject has been completed for civil works and the overall environmental
safeguard performance of the said subproject was rated satisfactory while the details
are provided in Annex-1.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 39
Map showing location of Tabai Dam
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 40
Substantially Completed Sub Projects
Sr. No Sub Project District Completion
Period
1. Shangade Weir Khyber
Completed and
reported in 7th
SAEMR July-Dec
2020.
2. Shunga Weir Bajaur
3. Nailai Kas Bajaur
4. Damano Weir Bajaur
5. Kat Gala Irrigation Scheme Bajaur
6. Maddar Irrigation Scheme Mohmand
7. Jay Dam Mohmand
Completed and
reported in 8th
SAEMR Jan-June
2021.
8. Ganjyano Danish Kool Infiltration
Gallery
Mohmand
9. Mundara Weir Mohmand
10. Badi Samoor Weir Bajaur
11. Lar Dand Weir Bajaur
12. Daman Lift Irrigation Bajaur
13. Shukrata Infiltration Gallery Bajaur
14. Chepatra Weir Bajaur
15. Dawawo Weir Bajaur
16. Derakai Weir Bajaur
17. Lara Dandokai Weir Bajaur
18. Hayatai Weir Bajaur
19. Serai Bazar Shah Mohmand
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 41
20. Haji Lawang Kas Bajaur Completed during
the reporting
period i.e., July-
December 2021
(9th SAEMR)
21. CAD of Warsak LBC Mohmand
22. Tabai Dam Khyber
2.3 Project Contracts and Management
94. Implementing Agency (IA) for FWRDP is responsible for the implementation of
environmental management and monitoring requirements and procedures for the
project to comply with ADB`s Safeguard Policy Statement (2009). Environmental
Assessment and Review Framework (EARF), prepared and approved for FWRDP,
provides guidelines for environmental management and monitoring of the project. The
objective of the EARF is to establish systems and functions that will ensure that
conditional ties are built into each initiative at its design stage such that through
reconstruction, improved and environmentally sustainable structures are built that have
better resistance to natural calamities, particularly floods. EARF also requires ensuring
that all the environmental mitigation measures proposed for the design phase are
incorporated in the design and included in the contract documents.
95. Khyber Pakhtunkhwa Planning and Development Department (P&DD) is the
Implementing Agency (IA) for FWRDP, which has established Project Management Unit
(PMU) particularly dedicated for this project. Under PMU an Environmental and Social
Management Unit (ESMU) is established to oversee environmental planning,
management, and monitoring of the subprojects under FWRDP. PMU has appointed
Design and Construction Supervision Consultants (DCSC) as “The Engineer” who are
responsible for the environmental planning, management, and monitoring of the
subprojects.
96. Environment and Social Management Unit (ESMU) under Project Management Unit
(PMU) is responsible for environmental and social safeguard planning, compliance, and
monitoring. ESMU consists of Environmental Officer, Social Development and
Resettlement Officer. The ESMU is responsible for ensuring that the provisions of
IEEs/EMPs are implemented. In addition, it is also responsible for coordination with
ADB, EPA, Agriculture, Forest and Wildlife departments, NGOs/CBOs and other
public/private sector organizations.
97. PMU has appointed Design and Construction Supervision Consultants (DCSC) for the
design and construction supervision of the subprojects. DCSC is responsible for the
preparation of environment and social safeguard plans and documents besides
undertaking environmental and social safeguards monitoring. DCSC kept positions of
an Environment Specialist to perform these activities. The specialist is assisted by three
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 42
Environment Inspectors to undertake environmental monitoring in the field and a Social
Inspector to oversee social and gender aspects of the subprojects. Environmental
Inspectors, under the guidance of Environment Specialist is responsible for
environmental compliance monitoring as per proposed mitigation measures.
98. ADB Safeguard Specialist is responsible for explaining policy requirements to DCSC,
helping them to meet those requirements, building capacity, and monitoring
implementation of agreed safeguards.
2.3.1 Coordination amongst Contractor, Owner, Lender
99. Project Management Unit (PMU) has made IEEs/EMPs of subproject as part of contract
agreement of contractor under general clauses. Contractor must abide these clauses
to ensure implementation of IEEs/EMPs in their entirety. DCSC must ensure
environment and social safeguard compliance and impact monitoring through the
contractor. ESMU orientated DCSC and contractors on environmental and social
safeguard compliances and monitoring in progress review meetings and during field
inspections. ESMU also delivered guidelines for environmental and social safeguards
monitoring of subprojects to DCSC and the contractors. Furthermore, ESMU undertook
monitoring visits of subprojects to assess the progress on environmental monitoring and
environmental management practices and advised contractor to ensure all
environmental compliances.
100. DCSC has reported progress on IEEs/EMPs implementation through its Monthly
Progress Reports. PMU prepares and submits Quarterly Progress Reports (QPRs) on
environment and social aspects to ADB. PMU holds progress review meetings
periodically wherein DCSC and contractor participate and give updates on
environmental compliance monitoring. PMU provides guidance to DCSC and
contractors to resolve environmental issues and to streamline environmental monitoring
and environmental management activities.
101. A good working relationship is being maintained between the contractors and DCSC
during the execution of the subprojects. Training workshops are arranged by the
Environment Inspectors on site for the capacity building of the contractors and their
relevant staff. They are briefed on updating the environment monitoring checklists by
following IEEs/EMPs. Contractor is bound to submit these checklists to DCSC on
weekly basis. Environmental Inspectors undertake site visits of contractor’s camps and subprojects sites and discuss measures for improvement in environmental safeguards
with contractors and their staff.
102. The contractor will be responsible for execution of construction activities and for
environmental protection through their field staff. The contractor is subject to
environmental protection liabilities under national environmental laws, ADB’s Environmental Safeguards, project IEE/EMP provisions and under their contract with
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 43
PMU P&DD Khyber Pakhtunkhwa. The contractor is also responsible for
communicating environmental & social information and training of staff in all aspects of
the SSEMP. The details of contractors are as follows:
Details of Contractors
District
Project Contractor Project Manager/
Focal Person
HSE Site Inspector/
Environmental Manager
B
aja
ur
Dis
tric
t
Kharkai Weir (Remaining Works)
M/s MBCC Builders & PMC JV.
Wazir Ali Cell
03018184462 03465903438
Email:[email protected]
Mr. Muhammad Imran
0300-5756717
imranhanibest@
gmail.com
Haji Lawang Kas Lift Irrigation
M/S PMC JHK JV Construction Company
Mr. Tahir Khan
0335-9284500
Email:jhkconstructi
Mr. M. Yasir 03445151887
Khar Canal Sub Surface Infiltration Gallery
M/S PMC JHK JV Construction Company
Mr. Tahir Khan
0335-9284500
Email:jhkconstructi
Mr. M. Yasir 03445151887
CAD of Raghagan Dam
M/s National RCC
Works (Pvt) Ltd.
Mr. Farooq
0333-5023345
national_rcc_works
@yahoo.com
Mr. Haseeb Khan
0342-8960575
Mo
hm
an
d D
istr
ict
Saro Shah Weir
M/S PMC JHK JV
Construction
Company
Mr. Zulfiqar Khan
0333-5946261
Email:jhkconstructi
Mr. Zareen Khan 03215620578 Email: [email protected]
CAD of Warsak Left Bank Canal
M/s Ali & Co. Mr. Abuzar Ali
Cell: 03329950432
Email:
abuzarali964@gma
il.com
Mr. Abuzar Ali
Cell:
03329950432
Email:
abuzarali964@
gmail
CAD of Khurshid
Dam
M/s MBCC Builders &
PMC JV
Wazir Ali Cell
03018184462 03465903438
Email:wazir338@g
mail.com
Mr. Niazat Khan Cell: 03028885656, 03455233018 [email protected]
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 44
K
hyb
er
Dis
tric
t
Tabai Dam M/s Tribal Global Construction (TGC) Pvt Ltd.
PM Abid Azeem Cell: 03102679610 Email:
m
Mr. M. Jawad 03319100621 Email:
jsm10928jawa
Bar Kas Dam
M/s Tribal Global Construction (TGC) Pvt Ltd.
PM Nawab Khan Cell: 03329898608
m
Mr. Gul Hayat 03426067561
tgcwazir@gma
il.com
Magoo Dand Dam
M/s National RCC Works (Pvt) Ltd.
PM Altaf Khan Cell: 03335756596 Email:
national_rcc_work
Mr. Akhtar Ali 03472813701
akhtaralikhan2
Bada Khel Weir
M/s New Malik Afridi &Co.
PM Syed Ameer Shah Cell: 0333 9042554
Mr. Syed Ameer Shah Cell: 0333 9042554
Neeli Tangi Weir
M/s Habib Khan Builders
PM Imad Khan Cell: 03339263663
masroorhabib6@g
mail.com
PM Imad Khan Cell: 03339263663 [email protected]
Tarkho Kas Weir
M/s Habib Khan Builders
PM Imad Khan Cell: 03339263663
masroorhabib6@g
mail.com
PM Imad Khan Cell: 03339263663 [email protected]
Tor Dara Weirs
M/s Habib Khan Builders
PM Imad Khan Cell: 03339263663
masroorhabib6@g
mail.com
PM Imad Khan Cell: 03339263663 [email protected]
2.4 Project Activities during Current Reporting Period
103. The SSEMPs of Neeli Tangi, Tarkho Kas and Tor Dara weirs were submitted by the
contractor and reviewed and approved by DCSC and PMU.
104. In total 45 meetings with contractors have been arranged and a total of 82 site
inspections and audits were paid by DCSC and PMU while 50 trainings were delivered
to contractors’ staff till December, 2021.
105. A total of 34 subprojects construction contract were awarded where twelve (12)
subprojects are under construction phase in three Districts namely Bajaur, Mohmand
and Khyber. While twenty-two (22) subprojects are completed for civil works as shown
in Exhibit 30. Details of physical activities are provided under next headings.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 45
2.4.1 Bajaur District
106. Four (04)2 subprojects are under construction in Bajaur District while 14 subprojects are
substantially completed as per site requirements. Their physical progress as of June
2021 is presented in Exhibit below:
2 Kamar Ragha Dag subproject is being executed as VO of CAD of Raghagan Dam subproject
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 46
Physical Progress of Sub Projects in Bajaur District
S.No
Name of Sub-Project
Contractor Name CCA
(Ha)
Commencement Date
Completion Date
Revised Completion Date
Physical Progress
(%)
Structural Progress
[Executed/Total Scope]
Weir/Gallery
(%)
Irri. Channel (KM/KM)
OFWM
(KM/KM)
Remarks
1 Kharkai Weir
M/s Rustam Khan & Co
126
11-Sep-17 16-Aug-18 23-Aug-19 39%
90%
0.73/2.028 (36%)
0/6.3 (0%)
M/S MBCC 15-April-21 15-Dec-21 67% 0% 2.62/2.92
(89%) 3.9/6.3 (62%)
Work is in progress
2 Khar canal M/S PMC-JHK (JV)
154
25-Jul-19 07-Aug-20 Jan 24,2021 Ld.’s already recommended
57.5% 99.5% 3.15/7.0 (45%)
2.2/6.846 (32%)
Dead-Slow Progress
3 CAD of Raghagan Dam M/s National RCC Works Pvt Ltd 1017 16-Apr-20 15-Oct-21 28th Feb 2020 45%/100% - 22.815/37.7 (60.40%)
26.49/43.6(61.80%)
Work is in Progress
* Kamar Ragha Dag subproject is being executed as VO of CAD of Raghagan Dam subproject
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 47
2.4.2 Mohmand District
107. Two (02) subprojects are under construction in Mohmand District while six (06) are substantially completed. Their physical progress as December 2021 is presented in the following Exhibit:
Physical Progress of Sub Projects in Mohmand District
S.No Name of Sub-
Project Contractor Name
CCA
(Ha)
Commencement
Date
Completion
Date
Revised
Completion Date
Physical
Progress
Structural Progress
[Executed/Total Scope]
Weir/ Gallery/ Dam
(m/m)
Irri. Channel
(KM/KM)
OFWM
(KM/KM)
1 Saro Shah M/S PMC-JHK (JV) 100 25th -Jul-19 24th -Jul-20 22nd February
2021 79%
30 m (Weir)
(100%).
2.2/2.9
(75%)
4.2/4.2
(100%)
126 No of panel
installed at site.
2 CAD of Khurshid
Dam
M/S MBCC & Builders-
M/s PMC (Joint Venture) 104 29th December 2020 29th December 2021 55%
Multi Cell Cause Way
Concrete Works
(RCC G-20)
655/825.96 m3
(79%)
PCC(G-10)
60/81.23 m3
(74%)
PCC(G-20)
200/309.54 m3
(64%)
Plum Concrete
0/897.71 m3
(0%)
0.700/3.740
(2.1 +1.640)
(19%)
Contractor is lagging
behind the actual
progress.
Type E
3.4/4.486
(75%)
(SWC1 0.150)
(SWC2 0.190)
SWC3 0.200)
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 48
2.4.3 Khyber District
108. Six (06) subprojects are under construction in Khyber District while two subproject (Shangade Weir and Tabai Dam) is completed. Their physical progress as of December 2021 is presented in the following Exhibit:
Physical Progress of Sub Project in Khyber District
S.No Name of Sub-Project Contractor Name Commencement
Date Completion
Date
Physical Progress
(%)
Structural Progress [Executed/Total Scope]
REMARKS
Dam (m/m)
Irri. Channel (KM/KM)
OFWM
(KM/KM)
Inspecti-on
Hut
1 Bar Kas Dam M/S Tribal Global Construction 14-July-2020 14-Jan-2022 64.4% 64.1% 98.6% 18%
89.6%
Expected to be completed in time.
2 Magoo Dand Dam M/s National RCC Works 1-october-2020 31-March-2022
48.65%
43.86% 45% 2%
25.5%
• Social issue at main irrigation channel was resolved during a joint (R.E +PIU + T/L Designer) visit to the site on Friday dated Dec 17, 2021.
• The progress is lagging
3 Bada Khel Weir M/s New Malik Afridi & Co 16 February, 2021 15 February,
2022
50%
95 44% 35% -
The works are partially resumed on 28
Dec 2021. Delivery Pipe encasement & Sumps are
remaining.
Water Pressure testing is conducted for HDPE Delivery pipe on 28 Dec 2021.
RD.0+509 – RD. 0+820
4 Neeli Tangi Weir
M/s Habib Khan Builders
22 September, 2021 22 June, 2022
11.5 %
- - - -
• Mix design Cylinder for G-10, G-15, G-20 and G-30 has been casted.
• Steel Sample submitted for testing.
• Jointly survey of Neeli tangi COMPLETED.
• Excavation of Neeli Tangi Weir COMPLETED.
• Tarkho kas, Tor Dara and Natu Khel in Progress.
• Neeli Tangi excavation of Channel 2 in Progress.
• Tarkho kas excavation of channel in progress
5 Tarkho Kas Weir 22 September, 2021 22 June, 2022
3.02%
- - - -
6 Tora Dara Weir 22 September, 2021 22 June, 2022
1.4 %
- - - -
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 49
2.5 Description of Any Changes to Project Design
109. So far, no major change has been made to the project design.
2.6 Description of Any Changes to Agreed Construction Methods
110. No changes have been made to agreed construction methods.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 50
3 ENVIRONMENTAL SAFEGUARDS ACTIVITIES
3.1 General Description of Environmental Safeguards Activities
111. Environment Specialist of DCSC developed weekly environmental monitoring
checklists (see Annex-7 A) for environmental compliance of the subprojects. This
checklist is based on the recommended mitigation measures given in the EMP for
environmental safeguard at different stages of the subprojects. Contractors were
orientated how to fill out the checklist. A checklist for the Semi-Annual Environmental
Monitoring Report has also been formed to analyse the follow up of the ongoing
subprojects (see Annex-2).
112. Environmental Inspector of DCSC conducted environmental safeguard trainings of
contractor’s staff and workers on each subproject with the purpose to build capacity of the staff in environmental compliance monitoring and in ensuring environmental
safeguards for the subprojects. These trainings focused on EMPs of the subproject,
environmental monitoring checklists, environmental monitoring activities and Health,
Environment and Safety (HSE) of staff and workers. Knowledge on potential hazards
on the site and procedures to avoid such hazards and actions in case of any
incident/accident were communicated to contractor’s staff and workers. Environment Specialist of DCSC has followed up these trainings by assessing the capacity of
contractors’ staff and workers during site visits.
3.2 Site Audits
113. Contractors are supposed to conduct internal audits and review by their own staff to
ensure a safe, healthy, and secure environment, both physically and behaviourally, for
workers, equipment, property, visitors, and the public. DCSC has undertaken site
inspections of all under execution subprojects. The findings of these inspections are
being updated regularly in monthly environmental monitoring reports. Contractors are
advised to submit weekly environmental monitoring checklists to DCSC and implement
the environmental compliance activities in accordance with the approved IEEs/EMPs.
Contractors are improving their environmental compliance, yet they slack in some
areas. To ensure implementation of EMP the contractors were asked to nominate their
focal persons/site inspectors who will be responsible for environmental safeguards
implementation for weir sites while for dams’ sub-projects the contractors have
dedicated HSE Managers in their staff. The nominated site inspectors were trained on
EMP/SSEMP implementation and directed to submit weekly checklist regularly to
DCSC as previously weekly checklists were not submitted on regular basis.
114. Environmental Inspectors of DCSC carried out field visits of all subprojects on regular
basis. During these field visits meetings are convened with the contractors' staff and
workers, visual observations and photographs are taken and key findings are discussed
with the concerned engineering staff and the contractors. Recommendations are
communicated to the contractor to address environmental issues and non-compliances
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 51
on all the subprojects. Corrective Action Plan (CAP) is revised for all the subprojects in
consultation with the contractor’s staff.
115. For the purpose of environmental audit, Mr. Ihsan Afridi, Mr. Lehaz Imran and Mr. Altaf
Hussain (Environmental Inspectors) from DCSC visited all the under-construction sub
projects in district Khyber, Mohmand and Bajaur. By strengthening the environment
team of DCSC the environmental compliance status has been improved during the
current reporting period.
116. As already reported during the previous eight SAEMRs, the environmental guidelines
were being followed. However, the contractors have willingness to follow the
environmental guidelines and the environmental team of DCSC is continuously working
on the capacity building. Some of the findings of the recent environmental audit are as
follows:
a) Proper drainage system has been constructed for water at Magoo Dand Dam.
b) Proper oil storage areas have been constructed for oil storage at sites and
additional cross drainage provided as per SSEMP.
c) The drivers and mechanical staff have been trained to change the mobile oil
safely and speed limit observation to minimize dust.
d) Trainings have been provided by the contractor with respect to prevention and
control of COVID-19 specifically on ADB suggested SOPs.
e) Workers were using personal protection equipment’s. The construction areas were fenced.
f) Weekly Checklist are submitted by the contractors of the diversion weirs on
regular basis.
g) All required documents e.g., IEE, SSEMP and GRM are available on sites.
h) HSE managers have been hired for all small dams’ sites.
i) Water sprinkling is done regularly on dust prone areas where the dry, loose
dirt picks up in the wind.
j) Collecting Kitchen waste at separate bins and disposing of in a pit at
designated area/s has been improved at all under construction sites.
k) Construction equipment and machinery is fitted with silencers and maintained
properly.
l) Surface water or ground water contamination, due to oil spillage or solid
waste, has not occurred at any sites.
m) No noise level exceeding the permissible NEQs limits was recorded at any
under construction site.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 52
n) During the reporting period, no major grievances were recorded. Contractors
are addressing the issues in consultation with PIU and DCSC. Other minor
onsite grievances are being addressed in consultation with local communities
and village chiefs.
o) There are no damages to houses or shops at any site.
p) No damage to Archaeological /Religious/Cultural or Historical sites.
q) First Aid Kits are available at construction sites.
117. The corrective action plan and trainings brought major change in the behavior of
contractors. As a result, environmental compliance is seriously considered in project
execution. Site inspectors has been trained and SSEMPs are being developed for each
subproject. The implementation of SSEMP and further trainings is bringing major
change in the behavior of the contractor’s staff towards environment friendly construction of all the sub projects. The contractors have assured they will not harm the
local environment and will take all the necessary steps for the protection and
conservation of natural environment and will make sure the health safety of workers
and local community.
3.3 Issues Tracking (Based on Non-Conformance Notices)
118. The overall environmental progress of almost all of the subprojects improved during this
reporting period. The total average compliance status was 91%, which is calculated on
the basis of observation checklist attached as Annex-2 and shown in Exhibits 32, 33
and 34 for District Mohmand, Bajaur and Khyber respectively.
Environmental Compliance %
Saro Shah CAD Warsak CAD Khurshid Avg
Conformance % 91 96 96 95
Minor Nonconformance %
9 4 4 5
Major Nonconformance %
0 0 0 0
Overall conformance Level of All Sub-Projects at District Mohmand
Environmental Compliance %
Kharkai Haji Lawang
Kas Khar Canal CAD Raghagan Avg
Conformance % 89 89 84 95 89
Minor Nonconformance %
11 11 16 5 11
Major Nonconformance %
0 0 0 0 0
Overall conformance Level of All Sub-Projects at District Bajaur
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 53
Environmental Compliance %
Magoo Dand Dam
Bar Kas Dam
Tabai Dam
Bada Khel
Neeli Tangi
Tarkho Kas
Tor Dara
Avg
Conformance % 96 96 96 88 84 86 86 90
Minor Nonconformance %
4 4 4 12 16 14 14 10
Major Nonconformance %
0 0 0 0 0 0 0 0
Overall conformance Level of All Sub-Projects at District Khyber
The overall average major non-conformance is 0% while minor non-conformances are
9%. The overall conformance level of the project and all subprojects is presented in Exhibits above.
Project Major and Minor Non-Conformance Level
119. The major issues opened during this reporting period were
i) Weekly Checklist report is not being submitted by contractors of diversion weirs on
regular basis.
ii) Barricading the construction sites
iii) Lack of PPE’s
iv) Scarcity of Safety/ caution sign boards at weir sites only.
v) No record of water consumption present at any site.
120. Issue no i. is closed as the contractors submit weekly checklist on regular basis. Site
fencing has been done by the contractors. Beside these contactors have provided the
appropriate PPEs to the labours as per agreed corrective action plan provided to them.
Contractors were directed to keep proper documentation of water consumption. The
contractors were also directed to place safety sign boards. The overall situation of sites
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 54
was satisfactory and the issues have been resolved to a greater extent and non-
compliances are converted into compliances.
Summary of Issues Tracking Activity for Current Period
3.4 Trends
The information from previous period reports and the current period information are
used to identify trends in conformance and issues. The percentage conformance status,
reference exhibits 32, 33 & 34, of the SAEMRs is being improved as shown in Exhibits
below:
SAEMR No. Environmental Compliance % Average
1st SAEMR 54%
2nd SAEMR 54%
3rd SAEMR 68%
4th SAEMR 73%
5th SAEMR 67%
6th SAEMR 75%
7th SAEMR 81%
8th SAEMR 86%
9th SAEMR 91%
Percentage Conformance of each SAEMR
Total Number of Issues for Project 5
Number of partially closed issues 1
Number of Closed Issues 4 Percentage Closed 91%
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 55
Environmental Compliance Trend
121. Overall improvement is observed in environmental conformance but still needs efforts
to make it up to the mark. The status of main issues in each SAEMR period are
presented in exhibits below.
SAEMR Report No Issues in SAEMR % Issues Closed % Issues closed
late/open
1 25 44% 56%
2 12 52% 48%
3 14 45% 55%
4 11 49% 51%
5 13 47% 53%
6 10 30% 70%
7 20 45% 55%
8 16 87% 12%
9 5 91% 9%
Total No. of Issues in each Reporting Period
122. The percentage of issues which are closed late, i.e., not within the same SAEMR
reporting period or are still open (open issue off this SAEMR) is being decreased with
the passage of time and with the overall conformance level of the project. (Overall
conformance is already discussed in previous section). The trending of issues
54% 54%
68%73%
67%75%
81%86%
91%
1stSAEMR
2ndSAEMR
3rdSAEMR
4thSEMAR
5thSEMAR
6thSEMAR
7thSEMAR
8thSEMAR
9thSEMAR
Co
mp
lia
nc
e P
erc
en
tag
e
Environmental Compliance Trending
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 56
presented in Exhibit below depicts that percentage of closed issued is being increased
and overall trends are positive.
Issues Trending
123. Copy of NCN’s for major Non-Conformances is provided in Annex-3.
3.5 Unanticipated Environmental Impacts or Risks
3.5.1 COVID-19 Pandemic
124. Coronavirus disease (COVID-19) is an infectious disease caused by a newly discovered
coronavirus. COVID-19 can affect your lungs and airways. Symptoms can be mild,
moderate, severe or fatal. Most people who fall sick with COVID-19 will experience mild
to moderate symptoms and recover without special treatment.
125. Construction processes are dynamic with significantly varying number of workers on a
construction project site from day to day. The workers coming from diverse
environments and working closely together increases the risk of exposure to COVID 19.
126. The COVID-19 outbreak represents significant health and safety risks that were not
anticipated at project appraisal stage and is thus not reflected in any of the project’s safeguards instruments, most importantly the environmental management plan (EMP).
127. In accordance with the Asian Development Bank (ADB) Safeguard Policy Statement
2009 (SPS) and the loan agreement between ADB and the borrower, the borrower is
required to assess implications of unanticipated risks and impacts under the project;
and to identify and implement necessary risk mitigation measures.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
5
10
15
20
25
30
1 2 3 4 5 7 8 9
Issues Trending
Issues in SAEMAR % issues Closed % issues closed late/open
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 57
128. In response to the requirements of the SPS, as incorporated into the loan agreement,
to provide workers with safe and healthy working conditions, as well as minimize
adverse impacts and risks to the health and safety of local communities living near or
affected by, ADB-financed project, a project-level COVID-19 risk assessment was
conducted and all the contractors were instructed to update (or prepare) their respective
Health and Safety Plans (HSP) and Emergency Response Plans (ERP) as necessary.
As a result, ADB`s Project Officer was notified through letter and all the SSEMPs were
updated. Moreover, for unawarded subprojects a contract clause has been added in the
bidding document for contractors to comply with SOPs and adopt measures for
prevention and control of the COVID-19. The SSEMP of Khrakai Weir was updated with
respect to COVID-19 after re-award of the subproject to the new contractor. The Project
Officer of ADB was notified through 2nd notification about the updating of SSEMPs.
129. In October, 2021 ADB’s suggested SOPs have been received for strict compliance on
under construction subprojects sites after which training sessions were arranged by the
Environmental Inspectors of DCSC on the implementation of these SOPs for
contractors’ staff and labour.
130. The workers and staff are fully aware of the risk of COVID-19 and adopted all the
possible prevention measures provided in the updated SSEMPs. None of the worker
have been reported with COVID-19 symptoms neither any worker with illness was
observed during the site visits.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 58
4 RESULTS OF ENVIRONMENTAL MONITORING
4.1 Overview of Monitoring Conducted during Current Period
131. Environmental monitoring consists of two types. The first type requires field sampling
and laboratory analysis for example water quality, air quality and noise levels. The
second type refers to visual inspections of such things as soil erosion, restoration of
vegetation, solid waste disposal and so on. The field sampling and laboratory analysis
has been conducted, including air, noise, and water quality during the current reporting
period. Environment Inspector of DCSC undertook field inspections on fortnightly basis.
Environmental Specialist of DCSC also inspected subprojects on periodical basis.
DCSC prepared Corrective Action Plans in consultation with contractors.
132. The environmental monitoring was carried out by DCSC to assess actual nature and
extent of key impacts and the effectiveness of mitigation and enhancement measures
outlined in the Initial Environmental Examination (IEEs) and Environmental
Management Plans (EMPs). The IEEs prepared for subprojects includes Environmental
management plan (EMP) that addresses the potential impacts. (Annex-6). Mitigation
measures are considered so that the projects are designed, constructed, and operated
in compliance with applicable national and provincial laws and regulations and meets
the requirements of ADB SPS, 2009. Contractors are provided with monitoring checklist
and Urdu brochures for the better understanding of the Environment. (ANNEX-7[A&B]).
The overall status of Environmental Compliance was monitored and presented as
Annex 2.
4.2 Trends
133. Keeping in mind the construction volume the impacts on water quality, air quality and
noise is negligible and no major change was noticed after analysing the test results.
The results of monitoring checklist indicate that EMP compliance is increasing as
already discussed above.
4.3 Summary of Monitoring Outcomes
134. The Impact monitoring of some environmental parameters are discussed hereunder:
4.3.1 Instrumental Monitoring
135. The instrumental monitoring of air quality and noise as well as water testing has been
conducted at sites.
4.3.2 Noise Monitoring
136. Noise monitoring on construction sites is being carried out to assess impacts of noise
level generated to curtail its adverse impacts on workers, nearby communities, and
fauna of the area. For this purpose, noise level monitoring is being carried out by using
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 59
digital noise level meter to know the noise value at subproject locations. The field
instrumental Monitoring results reveals that the noise results is within limits of NEQS
and WHO guidelines.
137. Contractors are advised to keep their machinery in good condition and provide
personal protective equipment’s (PPEs) like ear plugs to the working staff at noise generating sites. Speed of the trucks and other vehicles used for construction activities
were to be controlled and the construction activities were to be limited to daytime only.
138. The environmental monitoring conducted during December 2021 deduces that no noise
or vibration related complaints from public or workers were registered at any of the
subproject site. However, Environment team of DCSC has reinforced contractor staff to
adopt mitigation measures to reduce the impact of noise and vibration as delineated in
EMPs. DCSC environment team repeatedly advised the contractors to keep their
machinery in good condition and provide personal protective equipment (PPE) like ear
plugs to the working staff to worn at noise generating sites. DCSC advised the
contractor to provide PPEs to workers. Contractors of all subproject’s sites were
advised to control vehicle speed and restrict construction activities to daytime only.
DCSC advised the contractors to carry out noise monitoring by using noise meter on
regular basis. Noise testing was carried out at sub projects where construction activities
were in progress.
139. Results of instrumental monitoring of noise are given in the exhibit below:
Noise Testing Results
4.3.3 Air Quality Monitoring
140. The ambient air of an area may be polluted due to emissions of Carbon Oxides (COX),
Sulphur oxides (SOX), Nitrogen Oxides (NOx) and Particulate Matter (PM10). The
industry that may produce high emissions of gases and other toxic elements is not
present in the any of the subproject area so only dust and smoke emissions were to be
S. No Sub Project Result NEQS/WHO
(dB)
1 Magoo Dand Dam 46.19 75
2 Bar Kas Dam 50.07 75
3 Tabai Dam 48.09 75
4 CAD Raghagan Dam 49.27 75
5 Kharkai Weir 52.72 75
6 CAD Warsak LBC 50.37 75
7 CAD Khurshid Dam 48.78 75
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 60
monitored visually by the contractors during transportation or use of excavators etc.
Some pollution might be caused due to dust emission which was to be monitored.
141. Contractors of all subprojects were guided to adopt measures helpful in controlling air
quality deterioration in the subproject activity areas like regular water sprinkling to
reduce the air dust emissions and regular tuning of vehicles maintaining the equipment
properly to minimize the smoke and other gaseous emissions. The objective was to
minimize the airborne particulate matter, dust pollution and fumes of vehicular
emissions into the atmosphere to avoid negative impacts on the health of construction
workers, residents, and nearby vegetation.
142. Visual observations were made to monitor regular water sprinkling at dust prone areas
during the construction activities and to monitor the vehicular emissions to minimize the
smoke emissions. Contractors ensured water sprinkling at most of the sites. Contractors
are advised to regularly tune and check up their construction vehicles and machinery
to comply the vehicular exhaust emission levels. Contractors regularly tune their
vehicles at all the subproject sites. Contractors are advised to ensure use of masks and
helmets by workers. Also, they were advised to transport excavated material by using
covers on the dumpers to avoid spills.
143. Air quality testing was carried out at sub projects where construction activities were in
progress. The air quality results indicate under permissible limits. The results of
instrumental monitoring are presented in exhibit below;
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 61
Air Quality Test Results
S. No Parameters Unit Magoo Dand Dam Bar Kas Dam Tabai Dam CAD Warsak LBC CAD Khurshid Dam CAD Raghagan Dam Kharkai Weir NEQS WHO
1 PM 2.5 ɥg/m3
5.4 3.6 6.3 7.2 5.4 7.2 5.4
15 ɥg/m3 25
2 PM 10 ɥg/m3
3.6 4.5 4.5 5.4 7.8 6.3 7.2
150 ɥg/m3 125
3 CO2
mg/m3
581 474 387 389 587 482 466
- mg/m3 --
4 CO
mg/m3
0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 mg/m3
80 ɥg/m3
--
5 NO2 ug/m3
47.7 71.11 58.5 90.6 65.7 78.3 54
-- 40
6 SO2 ɥg/m3
0.00 0.00 0.00 0.00 0.00 0.00 0.00
120 ɥg/m3 125
7 NO
ɥg/m3
14.28 21.33 17.8 27.08 19.71 23.49 16.2
40 ɥg/m3 --
8 NOx ɥg/m3
61.98 92.46 75.6 118.4 85.41 101.79 70.2
ɥg/m3 --
9 O3
ɥg/m3
0.00 0.00 0.00 0.00 0.00 0.00 0.00
180 ɥg/m3
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 62
4.3.4 Water Quality Monitoring
144. Subproject construction activities should not lead to pollution or contamination of
surface and groundwater in the subproject area knowing that contamination bears direct
effects on human health. Therefore, preventive measures are required to be taken to
save water sources. Contractors are guided to take measures at camp site to prevent
water pollution in the adjoining stream, water channel and in groundwater: Construction
of sewage system with septic tank to dispose of sanitary wastewater and lined wash
areas are the other measures contractors were asked to take to prevent pollution of
water. Furthermore, contractors are asked to avoid oils spills in subproject areas.
145. Environment staff of DCSC has observed no surface or groundwater pollution caused
by construction activities. Contractors tested surface and drinking water from certified
labs for physical, chemical and biological parameters. No water borne disease (gastro,
diarrhoea, etc.) has been noticed. Sewerage system/septic tanks at camp sites were
constructed. Contractors are advised to ensure operation and maintenance of drainage
system to avoid contamination of ground and surface water sources. Contractors are
also advised to avoid oil spill to protect ground water and surface water channels.
146. The samples of drinking water from contractors’ camp and surface water quality were
tested in December 2021. Almost all the results are under permissible limits according
to National Environmental Quality Standard (NEQS) and WHO guidelines. The
contractor has been advised to regularly carryout chlorination and or provide clean
drinking water to labour and staff from any other source. The results are given in the
tables below:
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 63
*UO: Unobjectionable
Drinking Water Quality Results
S# Parameters WHO/NEQS Limits Magoo Dand Dam Bar Kas Dam Tabai Dam CAD Warsak LBC CAD Khurshid Dam CAD Raghagan
Dam Kharkai Weir
01 pH
6.5-8.5 7.89 7.91 7.71 7.96 8.01 7.79 8.01
02 Temp
- 08 C 08 C 08 C 08 C 08 C 07 C 07 C
03 Dissolve Oxygen
- 0 ppm 0 ppm 0 ppm 0 ppm 0 ppm 0 ppm 0 ppm
04 Turbidity ≤ 5NTU
2.21 3.21 4.21 1.51 2.53 3.31 2.03
05 E. Conductivity
NGVS 1498 1133 1678 1087 1056 947 1432
06 TDS
1000 mg/l 803 563 834 542 526 478 714
07 Color
< 15 TCU 0.0 0.0 0.0 0.0 0.0 0.0 0.0
08 Odor
Sensory evaluation Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable
09 Taste
Sensory evaluation Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable
10 Total Alkalinity
< 500 ppm 150.2 97.2 110.2 97.1 96.1 193 129
11 Total Hardness
< 500 ppm 220 84.67 150.6 90.78 83.78 130 117
12 Calcium ≤ 250 ppm
119.7 42.0 87.1 43.3 40.3 47.03 45.3
13 Magnesium ≤ 250 ppm
44.9 12.6 22.6 14.1 11.1 22.90 16.90
14 Sodium ≤ 200 ppm
27.1 19.7 23.7 19.3 17.3 37.3 21.3
15 Potassium
NGVS 34.1 17.1 29.1 17.1 13.1 12.34 22.37
16 Sulfate ≤ 250 ppm
187.4 87.5 119.0 87.5 79.5 111.2 101.2
17 Chloride ≤ 250 ppm
44.2 09.9 29.2 11.7 09.7 27.8 22.8
18 Nitrate ≤ 50 ppm
17.2 7.2 14.2 7.2 6.2 11.8 9.8
19 Nitrite ≤ 3 ppm
1.07 2.00 2.09 1.00 1.89 1.79 2.01
20 Fluoride ≤ 1.5 ppm
1.89 0.76 0.89 0.78 0.97 0.91 0.79
21 Arsenic ≤ 2 ppm
0.007 0.004 0.002 0.000 0.000 0.002 0.000
22 Iron ≤ 2 ppm
1.06 1.01 1.01 1.00 1.03 0.63 1.10
23 Copper ≤ 0.01 ppm
0.87 0.56 0.56 0.56 0.56 0.21 0.03
24 E. coli
NGVS 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU
25 Fecal Coliform
0 CFU/100 ml 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 64
4.3.5 Soil Erosion
147. No damages to the agricultural lands due to borrow pits or soil erosion is observed so
far as mostly soil is obtained from local uplands from their owners who in return get their
agricultural land levelled. Still the contractors have been advised to proceed after written
agreements. Contractors are also advised to make complete line plans for excavation
and transportation showing the distance of the borrow pits from the construction sites
and to get them approved from RE of DCSC.
4.3.6 Natural Habitat Protection
148. The contractors are advised to avoid damaging the natural habitats and to replant the
damaged plants, if unavoidable, after construction. Also, the native wildlife and habitats
should not be disturbed. However, no tree has been cut during construction processes
on any of the subproject. Similarly, no native species are being disturbed due to the
construction activities.
149. Tree plantation cost is kept for each subproject under watershed management
component of the project. Tree plantation is in the process with the help of District Forest
Officers (DFO) of the three districts. As of 31st December 2021, plantation on 4475 ha
area has been completed. The overall implementation progress is 77% (Bajaur 2533
ha, Mohmand 1,427 ha and Khyber 515 ha) of revised target of 5,829 ha. Remaining
plantation is in progress and will be completed as soon as possible. District wise
watershed targets vs achieved are shown in below table;
District
Target (ha)
Original PC-I
Designed (ha)
Revised PC-I
%
Bajaur 2,816 2281 79.68%
Khyber 1,079 517 47.91%
Mohmand 720 1405 211.66%
Total 4,615 4203 91.07%
Watershed Management Status
150. Neither flora nor fauna were disturbed by the contractors at any of the subproject area
since the subprojects involve only weir/ lift irrigation sump and channels construction
which locate farer to wildlife habitats. Wildlife sanctuary does exist near any subproject
site. No hunting of birds and animal is reported. Continuous monitoring is being carried
out by environmental inspectors of DCSC to check any hunting activity or activities
damaging vegetation or wildlife habitat.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 65
4.4 Material Resources Utilisation
4.4.1 Current Period
151. The use of water in construction sites for human needs, is basically related to the
essential demands of employees of the construction site and these are preserved in
accordance with the labour laws. In the construction site, the human water
consumption, is for the following facilities: sanitary, housing, dining place, laundry, and
kitchen, when preparing meals.
152. The other major use of water is for the sprinkling of water at project site for compaction
and around the project site for dust control. Oil has been also used for project
equipment, like generators, machinery and vehicles. Consumption of Oil in gallon for
the reporting period is given in exhibit below:
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 66
4.4.2 Cumulative Fuel Utilisation
153. Cumulative Fuel Utilization was also assessed, trends are uniform and do not show any exceptional changes.
Oil Consumption
Gallon Jay Dam Kharkai Shangade
Ganjyano Danish Kool
Shunga NailaiKas Mundara Badi
Samoor Lar
Dand Damano Daman
Lara Dandokai
Chepatra Hayatai Shukrata Kat
Gala Maddar
Serai Bazar Shah
Saro Shah
CAD Raghgan
Dawawo Bar Kas
Dam Tabai Dam
Magoo Dand Dam
CAD Warsak
CAD Khurshid
Bada Khel
Neeli Tangi
Tarkho Kas
Tor Dara
1st SAEMR 2522.843 607.5957 531.5142
2nd SAEMR 8949.0924 1452.946 2913.8177 396.2581 272.0972 248.322
3rd SAEMR 2169.272583 622.03 520.23 105.669 327.1 292.3 211.338 230.43 252.25 230
4th SAEMR 2050.314 200.05 600.5 100.2 312 290.25 400.25 250.98 300.6 500.5 200.5
5th SAEMR 2825.32 30.33 107.56 263.67 158.42 375.22 350.342 338.234 370.6 435.23 498.34 126.32 160.42 98.99 160.77 155.56 170 40.52 250
6th SAEMR 3532 0 45 165.8 114.8 168.23 265.88 481 247 415.43 512.22 198.86 120.33 60.55 178.67 215.48 168.78 215.65 350.66
7th SAEMR 2534.455 0 0 204.88 0 0 35 78 123 137 33.8 178,87 195,56 120.45 208.22 90.32 148.78 188.91 232.78 4825.32 540.22 6348.22 7578.45 2822.843
8th SAEMR 3870.487 0 243.76 20.66 67.89 250.34 23.54 263.44 270.89 233.5 219.17 260.67 270.33 5432.34 257.66 7843.23 8460.56 3400.45 570.87 461.98 20.34
9th SAEMR 563.76 183.34 7837 8426.56 8786.23 5160.88 4789.89 4576.23 170.33 6 3
Total 28,453.78 3,476.71 4,718.62 1,480.24 1,184.42 1,374.32 1,283.47 1,446.53 1,543.79 1,718.16 1,268.40 588.62 551.64 513.49 766.83 461.36 487.56 705.75 1,287.11 18,094.66 797.88 22,618.01 24,825.24 11,384.17 5,360.76 5,038.21 190.67 6.00 3.00 -
No physical Activity Started at site/ project completed
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 67
154. No water consumption record was present at any site. However, the contractors are not
putting pressure on ground water table as in almost all subprojects the contractors are
relying on surface water from stream and springs.
Fuel Consumption in last 6 Months
Cumulative Fuel Consumption Trend
- 1,000.00 2,000.00 3,000.00 4,000.00 5,000.00 6,000.00 7,000.00 8,000.00 9,000.00
10,000.00
Kh
ark
ai
Sa
ro S
ha
h
CA
D R
ag
hg
an
Ba
r K
as
Da
m
Ta
ba
i D
am
Ma
go
o D
an
d D
am
CA
D W
ars
ak
CA
D K
hu
rsh
id
Ba
da
Kh
el
Ne
eli
Ta
ng
i
Ta
rkh
o K
as
To
r D
ara
9th SAEMR
0
5000
10000
15000
20000
25000
30000
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Fuel Consumption
1st SAEMR 2nd SAEMR 3rd SAEMR 4th SAEMR 5th SAEMR
6th SAEMR 7th SAEMR 8th SAEMR 9th SAEMR Total
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 68
4.5 Waste Management
4.5.1 Current Period
155. Currently, there are two types of waste at all sub-project areas.
a. Domestic waste from camps, offices, labours, etc.
b. Construction waste including hazardous waste from construction sites.
4.5.2 Cumulative Waste Generation
156. The waste generated from the cutting of earth is reused for back filling. The unused
excavated material is disposed of at designated sites. Negligible construction waste
including wire cutters, plastic and paper, etc. is generated at the site which is recycled
and reused in second market. Currently, all such waste is segregated disposed of
temporarily on designated sites, identified and demarked before construction for
disposal during construction activities. The Dumping sites/Disposal sites are identified
and approved by Environment Specialist of FWRDPC. The dumping site for each
subproject is shown on the maps attached as Annexure 10. Such waste is then removed
to be reused in second market on regular interval with the help of specified
subcontractors, assigned by each contractor.
157. Domestic waste is disposed of in low lying areas or depression on other side of sites,
where water becomes stagnant and becomes a breeding place for disease vectors like
malarial mosquitoes. This method is identified in IEE reports and also the general
practice of local municipality. Dumping waste material in these ponds achieve two
purposes: disposing off waste material and filling the pond to make the sites more health
friendly.
Solid Waste Generated at Sites
S.N# Sub-Project Solid Waste Generated in Kilogram per
day
Types of Waste Remarks
1 Kharkai Weir 1.9 Packaging bags, wood ply and food items etc.
Solid waste is
preferably reused
and disposed-off
at designated site.
2 Khar Canal Infiltration Gallery
4.5 Packaging bags, wood ply and food items etc.
-do-
3 CAD Raghagan Dam 13 Cement bags, wood ply and food items etc.
-do-
4 CAD of Khurshid Dam 05 Cement bags, wood ply and General Waste (plastics,
-do-
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 69
polythene, packaging and kitchen scraps)
5 CAD of Warsak LBC 07 Cement bags, wood ply and General Waste (plastics, polythene, packaging and kitchen scraps)
-do-
6 Saro Shah 00 No activity
7 Bar Kas Dam 03 General Waste (plastics, polythene, packaging and kitchen scraps)
-do-
8 Magoo Dand dam 04 General Waste (plastics, polythene, packaging and kitchen scraps)
-do-
9 Bada Khel Weir 01 Cement bags, wood ply and food items etc.
-do-
10 Neeli Tangi Weir 01 General Waste (plastics, polythene, packaging and kitchen scraps)
-do-
11 TarKho Kas Weir 01 General Waste (plastics, polythene, packaging and kitchen scraps)
-do-
12 Tor Dara Weir 0.5 General Waste (plastics, polythene, packaging and kitchen scraps)
-do-
4.6 Health and Safety
4.6.1 Community Health and Safety
158. The safety of the local people is a major concern, due to which all the contractors were
advised to place safety signs (safety cautions, safety cones, safety tapes etc.) on site.
Campsite is established 500 meters away from the human settlements at all the
subprojects. Subproject signs are not properly placed at any site. Contractors have
ensured water sprinkling at all subproject sites. All Contractors are advised to ensure
proper water sprinkling and maintain the record. The contractors are also advised to
place safety signs for the protection of community from any incident. Traffic operations
are well on all subprojects since no complaint is received from the community in this
regard. Furthermore, no complaints have been received of damage to public/community
assets and infrastructure.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 70
4.6.2 Workers` Safety and Health
159. The awareness of contractors needed to be created for instituting safety procedures
during construction. Provision of proper safety equipment for the workers such as
helmets, goggles, masks, shoes and gloves etc needed to be provided to the workers
during construction activities. Other safety measures to avoid exposure to accidents
due to operation of construction, vehicle movements and machinery operations were to
be ensured.
160. The findings of monitoring activities reveal that contractor have provided Personal
Protective Equipment (PPEs) to the workers on all subproject sites. Contractors are
advised to ensure provision and utilization of PPEs on all the subprojects. First Aid kits
are available at most of the subprojects while ambulance is not available at any
subproject’s sites. However, the contractors have 4WD vehicles to deal with any kind
of emergency. Furthermore, Govt. hospitals as well as private clinics are available in
close vicinity to deal with any major injuries and health issues No accident/incident of
major nature is reported during July-December 2021.
Health and Safety Statistics
S.No. Sub Project Type of problem No of persons Remarks
1 Kharkai Weir Minor Injury (hand) 3 First aid provided
2 Khar Canal Infiltration Gallery
Minor Injury (Finger) 1 First aid provided
3 CAD Raghagan Dam
Fever and Minor injury of hand
6 First aid provided
4 CAD of Khurshid Dam
Minor Injury Finger 4 First aid provided
5 CAD of Warsak LBC
Minor cut in finger 5 First aid provided
6 Saro Shah 0
7 Bar Kas Dam Minor Injury hand 8 First aid provided
8 Magoo Dand dam Fever with symptoms of COVID-19
15 Opted for Self-quarantine at home. No test reports available
9 Bada Khel Weir Minor Injury leg 2 First aid provided
10 Neeli Tangi Weir Minor injury Finger 1 First aid provided
11 TarKho Kas Weir 0
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 71
4.7 Grievances Redressal
161. Construction sites and labour camps are away from local community. There are no
houses in 500-meter vicinity of construction sites or labour camp. The contractor HSE
Managers are sensitizing the labours from time to time to take care of local norms and
culture. Beside this they placed grievances register at camp site to register local
communities’ complaints but till date no complaint has been received from the local
community. The contractor guided the drivers to keep speed limits of 30km/h to avoid
any unfair situations. In case if any unfair situation occurring at sites, the issues are
resolved on priority basis and will involve local Jirga according to the complexity of the
situation. Most of the complaints of communities is of social nature and dealt by PIU
and Sociologist of CSC jointly and reported in six monthly social monitoring report
submitted to ADB.
4.8 Training
162. The environmental and social unit of DCSC is comprising only one environmental expert
(intermittent basis) and one environmental and one social inspector. There is no HS
(Health and Safety) expert or trainer among the DCSC. Currently the DCSC provide
information and guidelines on all environmental safeguard related training activities to
the Contractor`s Environmentalist/HSE Officers, staff and labours. These include
trainings of nominated site inspectors, Contractors, HSE inductions for site workers,
guidelines on HSE training, risk assessment requirements before start of each activity,
etc. The site inspectors then provide the training on these issues to the staff and labour.
163. The site inspectors were nominated by the contractors who were trained by the
environment specialist of DCSC. These inspectors were specifically trained on
construction site inspections and weekly checklist monitoring, this will ensure
compliance of EMP/SSEMP in true letter and spirit.
164. The following exhibit shows the trainings provided during the reported period.
Details of Trainings
S. No Sub
Project Date
No. of Participants
Topic
Target Group
1 CAD of Warsak
LBC 01.07.2021 06 Work hazards and
heat stroke
Contractor’s Staff
2 Serai Bazar Shah 14.07.2021 05 Heat stroke
Contractor’s Staff
3 Bada Khel
Weir 21.07.2021 04 PPEs Contractor’s Staff
4 Magoo
Dand Dam 28.07.2021 05 Good House
Keeping Contractor’s Staff
5 Tabai Dam 07.07.2021 8 Fall from Height Contractor’s staff
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 72
S. No Sub
Project Date
No. of Participants
Topic
Target Group
6 Bar Kas
Dam 13.07.2021 9
Solid Waste Management
Contractor’s staff
7 CAD
Raghagan 24.07.2021 8 PPEs Contractor’s staff
8 Kharkai
Weir 27.07.2021 5
COVID-19 Precautions and
Preventions Contractor’s staff
9 CAD
Raghagan Dam
12.8.2021 10 Waste material Contractor’s staff
10 kharkai 23.8.2021 06 PPE’s Contractor’s staff
11 Bada Khel
Weir 05.08.2021 07 Solid Waste Management
Contractor’s Staff
12 Magoo
Dand Dam 07.08.2021 05 PPEs Contractor’s Staff
13 Tabai Dam 24.08.2021 04 Excavated Material
Contractor’s staff
14 Bar Kas
Dam 27.08.2021 9 Fall from Height Contractor’s staff
15 CAD of
warsak left bank canal 09.08.2021 04
Work hazards and use of PPEs
Contractor’s Staff
16 CAD of khurshid
Dam 17.08.2021 05
Safety sign boards and use of safety
warning tape
Contractor’s Staff
17 CAD
Raghagan Dam
12.09.2021 12 PPEs Contractor’s staff
18 kharkai 18.09.2021 05 Housekeeping Contractor’s staff
19 Bada Khel
Weir 25.09.2021 06 PPEs Contractor’s Staff
20 Magoo
Dand Dam 17.09.2021 12 COVID-19 control
and Prevention Contractor’s Staff
21 Tabai Dam 28.09.2021 07 COVID-19 control
and Prevention Contractor’s staff
22 Bar Kas
Dam 28.09.2021 10
COVID-19 control and Prevention
Contractor’s staff
23 CAD of
warsak left bank canal 07.09.2021 06 House keeping
Contractor’s Staff
24 CAD of khurshid
Dam 16.09.2021 03 Work hazards
Contractor’s Staff
25 CAD
Raghagan Dam
28.10.2021 15 COVID-19 control
and Prevention Contractor’s staff
26 Kharkai
Weir 27.10.2021 05
COVID-19 control and Prevention
Contractor’s staff
27 Bada Khel
Weir 21.10.2021 06 Manual Handling Contractor’s Staff
28 Magoo
Dand Dam 14.10.2021 10 Work at height Contractor’s Staff
29 Tabai Dam 18.10.2021 07 Work at Height Contractor’s staff
30 Bar Kas
Dam 19.10.2021 10 House keeping Contractor’s staff
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 73
S. No Sub
Project Date
No. of Participants
Topic
Target Group
31 CAD of Warsak
LBC 08.10.2021 07 COVID-19 control
and Prevention
Contractor’s Staff
32 CAD of
Khurshid Dam 21.10.2021 05
COVID-19 control and Prevention
Contractor’s Staff
33 CAD
Raghagan Dam
11.11.2021 13 Waste
Management, PPEs
Contractor’s staff
34 Kharkai 15.11.2021 9 PPE’s Contractor’s staff
35 Bada Khel
Weir 4.11.2021 06 PPEs Contractor’s Staff
36 Magoo
Dand Dam 24.11.2021 10 Solid Waste Management
Contractor’s Staff
37 Tabai Dam 28.11.2021 07 COVID-19 Prevention
Contractor’s staff
38 Bar Kas
Dam 28.10.2021 10
COVID-19 Prevention
Contractor’s staff
39
CAD of Warsak
Left Bank Canal 05.11.2021 05
COVID-19 Prevention
Contractor’s Staff
40 CAD of
Khurshid Dam 18.11.2021 06
COVID-19 Prevention
Contractor’s Staff
41 Neeli Tangi
13.12.2021 05 Excavation
Hazards Contractor’s Staff
42 Tarkho
Kas 14.12.2021 04 Excavation
Hazards Contractor’s Staff
43 Magoo
Dand Dam 20.12.2021 07 Solid Waste Management
Contractor’s Staff
44 Bar Kas
Dam 21.12.2021 10 Work at Height Contractor’s Staff
45 Tabai Dam 22.12.2021 4 Site Restoration Contractor’s Staff
46 Khar Canal
05.12.2021 5 PPE’s Contractor’s staff
47 CAD
Raghagan Dam
09.12.2021 17 Work at Height,
PPEs Contractor’s staff
48 Kharkai 06.12.2021 4 PPE’s Contractor’s staff
49
CAD of Warsak left bank
canal 09.12.2021 07 Covid 19
precautions
Contractor’s Staff
50 CAD of
Khurshid Dam 15.12.2021 04
Covid 19 precautions
Contractor’s Staff
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 74
5 FUNCTIONING OF THE SSEMP
5.1 SSEMP Review
165. Contractors are required to prepare Site Specific Environmental Monitoring Plan
(SSEMP), including environmental management measures, risk assessment,
Environmental Management Plan (EMP), Emergency Response Plan (ERP), Borrow
Area Management Plan, Traffic Management Plan, Health Environment and Safety
Plan.
166. The contractors of the awarded subprojects were directed through letters to submit the
SSEMP reports 10 days prior to the commencement of physical work. In response to
the letter the SSEMPs of the subprojects mentioned in exhibit 2 have been submitted
by the contractors and approved by DCSC and ESMU.
167. It was observed that all the subprojects are implementing the measures proposed in the
EMP and SSEMP. This was mainly due to the fact that the contractor`s nominated staff
were trained on Environment, Health & Safety which in turn helped a lot in
implementation of mitigation measures proposed.
168. As these subprojects mainly involve soil/earthworks, dust suppression measures were
stressed upon by the DCSC staff. The contractors` staff was persuaded to maintain
good house-keeping and waste management.
169. The contractors were directed to revise their SSEMPs and include COVID-19 Health
and Safety Plan (HSP) and Emergency Response Plan (ERP) in accordance with
guidelines for construction site issued by the Ministry of Health, Govt. of Pakistan and
international good practices. All the SSEMPs were revised and submitted to ESMU
against which approval have been granted by ESMU and they were strictly directed to
implement it with true letter and spirit.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 75
6 GOOD PRACTICE AND OPPORTUNITY FOR IMPROVEMENT
6.1 Good Practice
170. In most workplaces, accidents are a nuisance for the worker and a headache for Project
Management Team. However, at construction sites, accidents have the potential to be
life threatening. With every new story about environmental disasters and trapped
labourers, construction sites become less and less appealing — even as the population
grows and demands new, updated structures increases. Regarded as one of the most
dangerous professions, construction work on the job site can be considered anything
but entirely safe. Obviously, the employers do need to mitigate safety hazards to
construction workers, but the workers need to keep in mind a lot of precautions
themselves when working in such hazardous conditions.
171. Thus, construction sites must be strived to safeguard their employees if not for the
ethical reasons, then for the economic ones. Here are eight ways construction
businesses can reduce workplace accidents. The following Good Practices at project
sites
6.1.1 Awareness
172. Before any worker — no matter his or her role or experience level — can set foot on a
construction site, he or she must be fully cognizant of the possible hazards. Ignorant
workers are perhaps the biggest dangers at any construction sight, as their unknowing
mistakes put everyone else at risk. Understanding of perils at hand and sustaining a
perpetual state of alertness is perhaps the number-one best way to prevent accidents
for which awareness campaign and risk assessment of each activity is done before start
of the new activity for the staff.
6.1.2 Training
173. Though most of a construction worker’s skills can be gained on the job, safety is one skill set that is best learned before works enter the construction site. Occasional
trainings are held on all sites for the labourers on standard safety and security practices.
Experienced workers were also provided with same trainings to refresh their knowledge
of standard safety by attending regular training sessions throughout the project cycle.
6.1.3 Communication
174. Accidents are more likely to occur when workers are unsure what to expect. Direct
communication regarding the day’s goals and activities resulted in cut down on
surprises that could cause bodily harm. Construction workers and supervisors are
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 76
equipped with devices, like smartphones or headsets, which allow fast and efficient
communication among team members.
6.1.4 Supervision
175. Ideally, construction workers would fully understand the ramifications of inadequate
safety precautions and thus act in a manner to ensure site-wide well-being — but this
is not a perfect world. So, every site must have a strong supervisor who is willing and
capable of enforcing safety standards with no exceptions. Such supervision is provided
in almost all the sites (giving the best conformance level of +90%).
6.2 Opportunities for Improvement
6.2.1 Documentation
176. It is noticed almost all of the subproject sites, although the most of the environmental
issues are being catered but their documentation and record keeping is poor.
Documenting all work in the field will make issues easier than ever before to mitigate.
6.2.2 Innovation
177. The development of new practices that will enhance safety and security should always
be encouraged, and workers should avoid speaking against legislation aimed at
improving safety protocols. Perhaps with enough innovation, all construction sites can
give 100 percent conformance.
6.2.3 Transparency
178. The worst thing any construction contractor can do for its reputation is attempting a
cover-up. Hiding accidents not only lowers the opinion of a single endeavour — it paints
the construction sites as a whole in a negative light. Ultimately, people understand that
accidents happen, and as long as contractors are doing their best to foster a safe
environment for their workers, any accidents that do occur will only contribute to the
growing need to augment modern safety techniques. Transparency, along with the
other practices on this list, will help construction as a whole become a safer industry in
which to work.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 77
7 SUMMARY AND RECOMMENDATIONS
179. Twelve (12) subprojects are under construction. The contractors have been directed to
ensure implementation of EMP and SSEMP to make sure environment friendly
construction. DCSC environment team had orientated contractors and their staff on how
to carry out environmental monitoring.
180. DCSC environment team has orientated all the contractors on environmental
compliances as per IEEs/EMPs. DCSC has issued notices to the contractors on non-
compliance of environmental safeguard measures related to environmental
management and health and safety of workers and public. Mutually agreed Corrective
Action Plan is also devised and communicated to the contractors. DCSC has advised
the contractor to address non-compliance as per agreed Corrective Action Plan.
181. The subprojects under construction are mostly weirs and infiltration galleries for
irrigation purposes which requires no chemical storage, while for dam subprojects the
contractors have stored the chemical material in camps at separate room, mostly at a
corner of the camp, and properly labelled with safety precautions. Also, they are advised
to use MSDS for chemicals stored at camps as currently at all the sites they have no
MSDS.
Semi-Annual Environmental Monitoring Report July-December 2021
________________________________________________________________________
Page | 78
ANNEX
Semi-Annual Environmental Monitoring Report July-December 2021
________________________________________________________________________
Page | 79
ANNEX-1: ENVIRONMENTAL SAFEGUARDS COMPLETION REPORT
A. Introduction
1. The approach to Environmental Management Recommended in the project`s
Environmental Management Plan (EMP) took into account the institutional capacity in
environmental management in three districts namely Khyber, Mohmand and Bajaur of
Khyber Pakhtunkhwa and aimed to use the flexibility inherent in the project to
recognize and avoid any potential environmental hazards through a step-wise process
as below:
i. Selection criteria for subprojects were designed to avoid any really obvious
environmental concerns. (Thus, no subproject was undertaken within the Protected
area or any wildlife sanctuaries or forest reserves.
ii. Every subproject was screened through Rapid Environmental Assessment (REA) and
subjected to an initial environmental examination (IEE). This step would allow any
potential environmental hazard to be identified and mitigation measures drawn
up. (If it appeared that mitigation measures could not be satisfactorily designed to
ensure a minimal environmental impact, the subproject would be dropped).
iii. The detailed design of every subproject was checked before construction to ensure
that mitigation measures had been incorporated and appropriate safeguards and
required practices written into civil works contracts.
iv. Construction and operation of subprojects was monitored to ensure compliance with
environmental safeguards and that no serious environmental problem would arise.
2. The second step was undertaken during project implementation, where experts were
present in the project management Unit (PMU), Design and Construction Supervision
Consultants (DCSC) and Asian Development Bank`s (ADB) Environmental Safeguards
Team to help ensure compliance with the plan.
3. The third Step was initiated during implementation but was expected to continue into
the operational phase.
4. In summary, the approach to environmental management was to avoid major negative
impacts in the first place through:
• the subproject selection process;
• recognition and mitigation of lesser hazards identified by the IEEs;
• Ensuring of environmentally sound construction and operation, and monitoring of
subprojects to ensure sound operational practices were being followed and mitigation
measures were working as expected.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 80
5. The under-construction FATA Water Resources Development Project (FWRDP), out of
34 subprojects, 03 subprojects are substantially completed, in addition to 6 sub projects
that were already completed and reported in the 7th SAEMR, and 13 in 8th SAEMR. The
remaining 12 subprojects are still under construction. This completion Report is the
summary of completed subprojects and the lesson learned (Environmental Practical
Experience) for under construction subprojects. The list of completed subprojects are
given below.
1) CAD of Warsak Left Bank Canal
2) Haji Lawang Kas
3) Tabai Dam
B. Project Performance during Implementation
6. The EMP contained in the report and recommendation of the ADB and EPA-KP,
specified various activities to be undertaken during subproject identification, design, and
implementation.
7. These were inevitably affected by the revisions to expected processes, as outlined in
the safeguard documents, and in fact the selection of subprojects applied broadly
involved the process of identification, catchment area and water use studies, feasibility
study, and detailed design. This complied with the original design, and environmental
aspects (especially of water resources management & EHS) remained integral to the
entire process.
8. Monitoring of the environmental aspects of project implementation was the
responsibility of the Design and Construction Supervision Consultants and
Environmental and Social Management Unit (ESMU), and of the project Management
unit (PMU) assisted by Environment Officer (PMU), Environmental specialist with
assistance of Environmentalists (DCSC). Implementing Agency performance was
generally adequate, and institutional and technical requirements of the loan covenants
were complied. Specific activities undertaken included:
• (Rapid Environmental Assessment (REA) for each subproject and Detailed
designs followed the environmental assessment or IEE as captured in the Water
assessment studies and/or feasibility studies;
• (Detailed designs were approved by relevant agencies (i.e., Department
of Irrigation with the coordination of Department of Agriculture, Forestry and
Environment);
• The Environmental safeguards Documentation i.e., IEEs, EMPs and SSEMPs
are also approved by the relevant Agencies i.e., Environmental Protection
Agency and ADB.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 81
C. Overall Assessment
9. The subprojects completed are rated successful based on the earlier assessments of
relevance, effectiveness, efficiency, and likely sustainability.
10. These subprojects are an appropriate response to the recognized problems of rural
poverty, Low agriculture production and water scarcity in Erstwhile FATA of the 21st
century. Its technical composition was adequate, although if detailed formulation had
been somewhat more rigorous, the implementation delays (arising from the difficult
conditions on some subproject land, lack of contractor`s capacity.
11. The subprojects are implemented in circumstances that have continued to evolve
rapidly, yet retained its fundamental relevance. While some economic, social, and
institutional successes are now obvious at the subproject level. This is the most
fundamental shortcoming of the project to work in an area where environment and
climate-related pressures are growing.
12. The overall progress with respect to Environment Compliance is satisfactory. At the
start it was assessed somewhat very difficult, because of the tribal nature of the people
and ADB/country Environmental compliance requirements but with the passage of time,
it was improved and currently projected to 86% in the 8th Semi-Annual Environmental
Monitoring Report.
D. Lessons Learned
13. Probably the most obvious lesson is that the capacity needed to implement a project
with fully adopted Environment Compliance Procedures must be met at all levels i.e.,
PMU, DCSC and Contractors. According to ADB and Country Safeguards guidelines in
a particular area of the country, where the under-discussion compliance at this
particular tribal nature seemed difficult, particularly the contractors were also unaware
of the Environment Compliance Procedures. But the environment team and
management of the project were quite successful to achieve the goal up to the mark.
14. At all levels of involvement executing agency, consultants and contractors, all are
effective in the project performance and they must be on a single page to work for a
same cause to make sure the project is implemented smoothly.
15. It was also learned that appropriate and necessary interventions to support capacity
development and training must be included in the project scope. The most important
requirement is to focus on safety and health issues.
16. The most valuable lesson learned is the project implementors must aware the
contractors of the Environmental Safeguards requirements at an early stage to fulfil the
compliance.
Semi-Annual Environmental Monitoring Report July-December 2021
Page | 82
17. At the end we can say that achievement is possible, when all the stakeholders involved
in Environmental Planning and Compliance work heartily and fully follow the prescribed
Guidelines.
18. Therefore, during the construction period of afore-mentioned subprojects, no accidents
were reported.
19. It is first project in the Tribal belt of Pakistan, where we achieved fully up to some extent
the Environment Compliance according to the Guidelines of Donor Agency.
E. Recommendations
20. The project’s design and implementation experience has yielded significant technical and institutional lessons on the nature of conditions in the water sector; as it is likely
that development of small and medium-sized irrigation schemes will continue to feature
in the sector development agenda, it is essential that these experiences are reflected
in ADB’s future analytical work, specifically in the assessment, strategy, and roadmaps
prepared as part of the country partnership strategy process.
21. An enabling environment is needed to allow farmers to supply the demand for their
production. Examples include
(i) a policy and institutional framework that promotes sound water resource
management;
(ii) a legal framework for water user associations that promotes cost recovery at least
sufficient to finance sustainable operation and maintenance (O&M);
(iii) rural infrastructure (e.g., roads that allow farmers to market their products, and farm
inputs to be delivered when they are needed);
(iv) efficient markets that are free of price distortions and barriers to competition for
both farm products and agricultural inputs; and
(v) access to information on demand, prices, and technology.
22. To successfully capture the opportunities created by growing markets, supportive
alliances must be created among upstream and downstream business partners (i.e.,
suppliers and service providers of agricultural inputs and implements such as farm
machines, agricultural processing entities and others related to markets). Extension
services must be provided; there must be access to improved seeds, fertilizers,
pesticides, and technologies; and private sector merchants must be involved in
marketing the incremental products.
23. In addition to the Environment Documentation, the Environment Compliance
Supervision at all level i.e., Client, Supervision Consultants and Contractor must be fully
technically sound and adequate in number to fulfil the requirements of the project.
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 83
ANNEX-2 (a) Environmental Compliance Status Bajaur District
Sr. No Environmental Compliance Kharkai Haji Lawang Kas Khar Canal CAD Raghgan
1 Copy of the Site-Specific Environmental Management Plan (SSEMP) is provided at the camp site/contractors office 1 1 1 1
2 Contractor has provided Health Environment and Safety (HSE) plan and Emergency Response Procedures (ERP) to Resident Engineers (REs) 1 1 1 1
3 The EMP instructions are understood by the contractor 1 1 1 1
4 HSE officer hired/nominated for implementation of EMP 1 1 1 1
5 Contractors provided training to its staff and workers to effectively implement project specific EMP 1 1 1 1
6 Contractor is following the safety precautions as per ILO convention no.62 1 1 1 1
7 Contractors prohibited child labour or forced labour 1 1 1 1
8 Contractors hired local labour 1 1 1 1
9 Contractors provided PPEs to their workforce 1 1 1 1
10 PPEs are used by workforce 1 1 1 1
11 First Aid Kit is provided at camp and individual nominated for addressing emergency. 1 1 1 1
12 Ambulance is available at camp site 0 0 0 0
13 Campsite is fenced to prevent trespassing 1 1 1 1
14 Camp area has adequate drainage arrangements for disposal of waste water 1 1 1 1
15 Arrangement for proper storage and disposal for solid waste is ensured 1 1 1 1
16 No contamination of surface or ground water by oil spillage or solid waste dumping 1 1 1 1
17 Fuel/oil storage areas are at least 200 meters away from watercourses 1 1 1 1
18 Additional cross drainage is provided for spoil 1 1 1 1
19 Potable clean and safe drinking is available to labour 1 1 1 1
20 No wood being used as fuel 1 1 1 1
21 LPG cylinders are provided for cooking or heating purposes 1 1 1 1
22 Subproject construction site is fenced to curtail trespassing 1 1 1 1
23 No vegetation cover aside from that required as part of construction and inside the RoW removed 1 1 1 1
24 No tree cutting in the RoW and shoulder areas 1 1 1 1
25 Subproject activities are displayed at proper locations 0 0 0 1
26 Dust generation during construction well managed and record exists 0 0 0 1
27 Proper water sprinkling is done on regular basis 1 1 1 1
28 Water sprinkling record is available 0 0 0 0
29 Site selected for camp is 100 meters away from the human settlements and wildlife habitats 1 1 1 1
30 Safety signs are properly displayed 0 0 0 1
31 Construction machinery parked at designated areas 1 1 1 1
32 Traffic issues managed well, no complaints on record 1 1 1 1
33 No complaints were made due to noise and vibration 1 1 1 1
34 Construction activities carried out in daylight to reduce the impact of noise 1 1 1 1
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 84
35 No loss of forests and intrusion into wetlands 1 1 1 1
36 No damage to the Archaeological /Religious/Cultural or Historical sites 1 1 1 1
37 No damage reported to public services like electric, water, gas, sewer, or telephone lines 1 1 1 1
38 Contractors maintained Environmental Monitoring Record and submit Weekly Monitoring Checklist reports 1 1 1 1
39 Contractors maintained Grievances Log to register complaints from community 1 1 1 1
40 No complaint registered in the Grievance Log 1 1 1 1
41 Borrow areas identified, having suitable material, and approved by design team 1 1 1 1
42 Borrow Pits not established in RoW 1 1 1 1
43 No damage to the agriculture land due to borrow pits on agriculture land 1 1 1 1
44 Top 15 cm are stripped and stockpiled for redressing 1 1 1 1
45 Top 0.5 m is stripped of and stockpiled when deep ditching is carried out 1 1 1 1
46 Community consultation has been carried out for subproject activities/concerns 1 1 1 1
47 No complaint filed regarding transmission of Communicable diseases (such as STI’s and HIV/AIDS) 1 1 1 1
48 No shops or houses inside ROW 1 1 1 1
49 No negative impact on the means of livelihood of the community because of the construction work 1 1 1 1
50 Ambient air testing is carried out on quarterly basis at site 1 1 0 1
51 Ambient Noise testing is carried out on quarterly basis at site 1 1 0 1
52 Drinking water quality testing is conducted on quarterly basis at site 1 1 0 1
53 Environmental Complaint Register (ECR) is placed at site? 1 1 1 1
54 Solid waste is properly handled and disposed of properly at site 1 1 1 1
55 Record of solid waste generated per day is available at site 0 0 0 0
56 No damage to flora and fauna been reported at site 1 1 1 1
57 No injury/Fatality reported at site 1 1 1 1
Compliance Score 51 51 48 54
Compliance Percentage % 89.47 89.47 84.21 94.74
Minor Compliance Percentage % 10.53 10.53 15.79 5.26
Major Compliance Percentage % 0.00 0.00 0.00 0.00
1 Compliance
-1 Major Non-Compliance
0 Minor Non-Compliance
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 85
ANNEX-2 (b) Environmental Compliance Status Mohmand District
Sr. No Environmental Compliance Saro Shah CAD Warsak LBC CAD Khurshid Dam
1 Copy of the Site-Specific Environmental Management Plan (SSEMP) is provided at the camp site/contractors office 1 1 1
2 Contractor has provided Health Environment and Safety (HSE) plan and Emergency Response Procedures (ERP) to Resident Engineers (REs) 1 1 1
3 The EMP instructions are understood by the contractor 1 1 1
4 HSE officer hired/nominated for implementation of EMP 1 1 1
5 Contractors provided training to its staff and workers to effectively implement project specific EMP 1 1 1
6 Contractor is following the safety precautions as per ILO convention no.62 1 1 1
7 Contractors prohibited child labour or forced labour 1 1 1
8 Contractors hired local labour 1 1 1
9 Contractors provided PPEs to their workforce 1 1 1
10 PPEs are used by workforce 1 1 1
11 First Aid Kit is provided at camp and individual nominated for addressing emergency. 1 1 1
12 Ambulance is available at camp site 0 0 0
13 Campsite is fenced to prevent trespassing 1 1 1
14 Camp area has adequate drainage arrangements for disposal of waste water 1 1 1
15 Arrangement for proper storage and disposal for solid waste is ensured 1 1 1
16 No contamination of surface or ground water by oil spillage or solid waste dumping 1 1 1
17 Fuel/oil storage areas are at least 200 meters away from watercourses 1 1 1
18 Additional cross drainage is provided for spoil 1 1 1
19 Potable clean and safe drinking is available to labour 1 1 1
20 No wood being used as fuel 1 1 1
21 LPG cylinders are provided for cooking or heating purposes 1 1 1
22 Subproject construction site is fenced to curtail trespassing 1 1 1
23 No vegetation cover aside from that required as part of construction and inside the RoW removed 1 1 1
24 No tree cutting in the RoW and shoulder areas 1 1 1
25 Subproject activities are displayed at proper locations 0 1 1
26 Dust generation during construction well managed and record exists 0 1 1
27 Proper water sprinkling is done on regular basis 1 1 1
28 Water sprinkling record is available 0 0 0
29 Site selected for camp is 100 meters away from the human settlements and wildlife habitats 1 1 1
30 Safety signs are properly displayed 1 1 1
31 Construction machinery parked at designated areas 1 1 1
32 Traffic issues managed well, no complaints on record 1 1 1
33 No complaints were made due to noise and vibration 1 1 1
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 86
34 Construction activities carried out in daylight to reduce the impact of noise 1 1 1
35 No loss of forests and intrusion into wetlands 1 1 1
36 No damage to the Archaeological /Religious/Cultural or Historical sites 1 1 1
37 No damage reported to public services like electric, water, gas, sewer, or telephone lines 1 1 1
38 Contractors maintained Environmental Monitoring Record and submit Weekly Monitoring Checklist reports 1 1 1
39 Contractors maintained Grievances Log to register complaints from community 1 1 1
40 No complaint registered in the Grievance Log 1 1 1
41 Borrow areas identified, having suitable material, and approved by design team 1 1 1
42 Borrow Pits not established in RoW 1 1 1
43 No damage to the agriculture land due to borrow pits on agriculture land 1 1 1
44 Top 15 cm are stripped and stockpiled for redressing 1 1 1
45 Top 0.5 m is stripped of and stockpiled when deep ditching is carried out 1 1 1
46 Community consultation has been carried out for subproject activities/concerns 1 1 1
47 No complaint filed regarding transmission of Communicable diseases (such as STI’s and HIV/AIDS) 1 1 1
48 No shops or houses inside ROW 1 1 1
49 No negative impact on the means of livelihood of the community because of the construction work 1 1 1
50 Ambient air testing is carried out on quarterly basis at site 1 1 1
51 Ambient Noise testing is carried out on quarterly basis at site 1 1 1
52 Drinking water quality testing is conducted on quarterly basis at site 1 1 1
53 Environmental Complaint Register (ECR) is placed at site? 1 1 1
54 Solid waste is properly handled and disposed of properly at site 1 1 1
55 Record of solid waste generated per day is available at site 0 1 1
56 No damage to flora and fauna been reported at site 1 1 1
57 No injury/Fatality reported at site 1 1 1
Compliance Score 52 55 55
Compliance Percentage % 91.23 96.49 96.49
Minor Compliance Percentage % 8.77 3.51 3.51
Major Compliance Percentage % 0.00 0.00 0.00
1 Compliance
-1 Major Non-Compliance
0 Minor Non-Compliance
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 87
ANNEX-2 (c) Environmental Compliance Status Khyber District
Sr. No Environmental Compliance Magoo Dand
Dam Bar Kas Dam Tabai Dam Bada Khel Weir Neeli Tangi Tarkho Kas Tor Dara
1 Copy of the Site-Specific Environmental Management Plan (SSEMP) is provided at the camp site/contractors office
1 1 1 1 1 1 1
2 Contractor has provided Health Environment and Safety (HSE) plan and Emergency Response Procedures (ERP) to Resident Engineers (REs)
1 1 1 1 1 1 1
3 The EMP instructions are understood by the contractor 1 1 1 1 1 1 1
4 HSE officer hired/nominated for implementation of EMP 1 1 1 1 1 1 1
5 Contractors provided training to its staff and workers to effectively implement project specific EMP 1 1 1 1 1 1 1
6 Contractor is following the safety precautions as per ILO convention no.62 1 1 1 1 1 1 1
7 Contractors prohibited child labour or forced labour 1 1 1 1 1 1 1
8 Contractors hired local labour 1 1 1 1 1 1 1
9 Contractors provided PPEs to their workforce 1 1 1 1 1 1 1
10 PPEs are used by workforce 1 1 1 1 1 1 1
11 First Aid Kit is provided at camp and individual nominated for addressing emergency. 1 1 1 1 1 1 1
12 Ambulance is available at camp site 0 0 0 0 0 0 0
13 Campsite is fenced to prevent trespassing 1 1 1 1 1 1 1
14 Camp area has adequate drainage arrangements for disposal of waste water 1 1 1 1 1 1 1
15 Arrangement for proper storage and disposal for solid waste is ensured 1 1 1 1 1 1 1
16 No contamination of surface or ground water by oil spillage or solid waste dumping 1 1 1 1 1 1 1
17 Fuel/oil storage areas are at least 200 meters away from watercourses 1 1 1 1 1 1 1
18 Additional cross drainage is provided for spoil 1 1 1 1 1 1 1
19 Potable clean and safe drinking is available to labour 1 1 1 1 1 1 1
20 No wood being used as fuel 1 1 1 1 1 1 1
21 LPG cylinders are provided for cooking or heating purposes 1 1 1 1 1 1 1
22 Subproject construction site is fenced to curtail trespassing 1 1 1 1 1 1 1
23 No vegetation cover aside from that required as part of construction and inside the RoW removed 1 1 1 1 1 1 1
24 No tree cutting in the RoW and shoulder areas 1 1 1 1 1 1 1
25 Subproject activities are displayed at proper locations 1 1 1 0 0 0 0
26 Dust generation during construction well managed and record exists 1 1 1 1 1 1 1
27 Proper water sprinkling is done on regular basis 1 1 1 1 1 1 1
28 Water sprinkling record is available 0 0 0 0 0 0 0
29 Site selected for camp is 100 meters away from the human settlements and wildlife habitats 1 1 1 1 1 1 1
30 Safety signs are properly displayed 1 1 1 0 0 1 1
31 Construction machinery parked at designated areas 1 1 1 1 1 1 1
32 Traffic issues managed well, no complaints on record 1 1 1 1 1 1 1
33 No complaints were made due to noise and vibration 1 1 1 1 1 1 1
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 88
34 Construction activities carried out in daylight to reduce the impact of noise 1 1 1 1 1 1 1
35 No loss of forests and intrusion into wetlands 1 1 1 1 1 1 1
36 No damage to the Archaeological /Religious/Cultural or Historical sites 1 1 1 1 1 1 1
37 No damage reported to public services like electric, water, gas, sewer, or telephone lines 1 1 1 1 1 1 1
38 Contractors maintained Environmental Monitoring Record and submit Weekly Monitoring Checklist reports
1 1 1 1 0 0 0
39 Contractors maintained Grievances Log to register complaints from community 1 1 1 1 1 1 1
40 No complaint registered in the Grievance Log 1 1 1 1 1 1 1
41 Borrow areas identified, having suitable material, and approved by design team 1 1 1 1 1 1 1
42 Borrow Pits not established in RoW 1 1 1 1 1 1 1
43 No damage to the agriculture land due to borrow pits on agriculture land 1 1 1 1 1 1 1
44 Top 15 cm are stripped and stockpiled for redressing 1 1 1 1 1 1 1
45 Top 0.5 m is stripped of and stockpiled when deep ditching is carried out 1 1 1 1 1 1 1
46 Community consultation has been carried out for subproject activities/concerns 1 1 1 1 1 1 1
47 No complaint filed regarding transmission of Communicable diseases (such as STI’s and HIV/AIDS) 1 1 1 1 1 1 1
48 No shops or houses inside ROW 1 1 1 1 1 1 1
49 No negative impact on the means of livelihood of the community because of the construction work 1 1 1 1 1 1 1
50 Ambient air testing is carried out on quarterly basis at site 1 1 1 0 0 0 0
51 Ambient Noise testing is carried out on quarterly basis at site 1 1 1 0 0 0 0
52 Drinking water quality testing is conducted on quarterly basis at site 1 1 1 0 0 0 0
53 Environmental Complaint Register (ECR) is placed at site? 1 1 1 1 1 1 1
54 Solid waste is properly handled and disposed of properly at site 1 1 1 1 1 1 1
55 Record of solid waste generated per day is available at site 1 1 1 1 0 0 0
56 No damage to flora and fauna been reported at site 1 1 1 1 1 1 1
57 No injury/Fatality reported at site 1 1 1 1 1 1 1
Compliance Score 55 55 55 50 48 49 49
Compliance Percentage % 96.49 96.49 96.49 87.72 84.21 85.96 85.96
Minor Compliance Percentage % 3.51 3.51 3.51 12.28 15.79 14.04 14.04
Major Compliance Percentage % 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1 Compliance
-1 Major Non-Compliance
0 Minor Non-Compliance
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 89
ANNEX-3 Major Non-Compliance Notices
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Page | 91
ANNEX-4 Corrective Action Plan Sr. No
Date Raised
By Location Issues Category* Corrective Action
Responsibility
Original Target Date
Status
1 December
2021 CSC
All diversion Weirs sites
Barricading the construction sites
Moderate All under construction sites have to
be properly barricaded Contractor Immediate
Closed
2 December
2021 CSC
All Under Construction
sites Lack of PPE’s Major
Provide adequate PPEs to all workers
Contractor 15 Dec,
2021 Closed
3 December
2021 CSC
All under construction
sites
Covid SOP’s and guidelines
Major Ensure to follow and implement Covid-19 SOPs and guidelines.
Contractor 15 Dec,
2021 Closed
4 December
2021 CSC
All Under Construction
sites
Displaying Safety signages
Moderate Proper safety signs should be installed by the Contractors
Contractor 15 Dec,
2021 Partially Closed
*Category of Non-Compliance
1. Minor: Within fifteen days: Draw attention through copy of daily check list 2. Moderate: Beyond 15 days and up to 30 days: Issue warning recorded on check list as well as separate letter 3. Major: Beyond one month: Do not verify the contractor’s invoice.
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 92
ANNEX-5 Instrumental Monitoring Results
Water Quality Testing Results
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 93
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 94
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 95
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 96
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 97
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 98
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 99
Air Quality Results
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 100
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 101
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 102
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 103
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 104
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 105
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 106
Noise Level Results
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 107
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 108
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 109
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 110
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 111
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 112
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 113
ANNEX-6: Environmental Management Plan
Activity Problem / Impact Mitigation Measures Timing to
Implement MM Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
Pre-Construction Stage Assure compliance with relevant construction field legislation.
Legal complications and delay in project
• Acquire construction permit/ Environmental NOC from local authorities.
• Preparation of SSEMPs for each site and get them approved by the Consultant, before the construction works start.
• Provide Water management guidelines if subprojects are executed near surface watercourse.
Before the construction of the project activities.
Number of reported non-compliances
Minimization and continued improvement in number of reported non-compliances
EPC Contractor
ESMU/ Consultant
Development of Strategies.
Problems arising due to non-compliance
• An ‘Operation Environmental Action Plan’ (OEAP) needs to be prepared demonstrating the manner in which the Contractor/Operator will comply with the requirements of management plans proposed in EMP/SSEMP.
• The following strategies and procedures will be developed prior to the commencement of Project operations:
• Project specific security and public access control strategy;
• Project specific waste management strategy
Pre-Operations Implementation Operation Environmental Action Plan’ (OEAP)
Beneficial in long terms with the implementation of Operation Environmental Action Plan’ (OEAP)
ESMU PMU & ADB
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 114
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Project specific air and noise control strategy;
• Project specific traffic control strategy;
Construction Stage Impacts Impacts on Land Resources Excavation • Noise &
Vibration
• HSE issues
• Vegetation loss will be avoided as much as possible and limited to demarcated construction area.
• Slope stabilization measures will be adopted such as adequate vertical and horizontal drains, cross drainage etc.
• Slope movements will be monitored around excavation work areas.
• Top six inches soil should be protected before excavation and should be placed back after completion of construction work.
• Excavated material shall preferably be reused after approval of quality control engineer of CSC.
• Non-reusable excavated material shall be safely dumped and leveled in barren land with approval from Environment specialist of CSC and
During Construction
• Implementation of SSEMP before start of works
• Annual reports and documentation of safety inspection
• Workforce /Community complaints
Not Significant (Minimal) Target = zero Threshold 1, with agreed mitigation
EPC Contractor
ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 115
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
dumping location should be provided in SSEMP.
Waste Management
• Waste Pollution
• To minimize environmental impacts and avoid any need for disposal of earthwork materials or the importation and unnecessary storage of earth, the project will maximize the reuse of excavated materials.
• All of the construction activity will be contained inside construction area.
• Solid waste generation should be reduced and should be reused and recycled.
• Any residual spoil will have to be disposed in environment friendly manner, where it will be leveled and landscaped. The dumping sites must be approved by CSC environment specialist.
• To be made contractor’s obligation through contract document, as an SSEMP will be prepared by the contractor and waste management plan will be a part of it.
During construction stage
• EPC’s Site officer and EHS officer in place
• SSEMP including Waste Management Plan
• Zero Complaints from Community & Workers
• Internal auditing and reporting by EPC
Not Significant (Minimal)
EPC Contractor
ESMU/CSC
Labor camps and material storage
• Cultural & Social issues
• The contractor will, in consultation with RE, resolve the exact location of all these facilities within
During construction
• Monthly Reports (EPC)
Not Significant (Minimal)
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 116
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Water & Sanitation issues
the barren land owned by the local community that will be provided by the community temporarily and free of cost.
• The location of these facilities will be at least 500 m away from the settlements.
• The contractor will not locate and construct any facilities without the written approval of the CSC.
• Supervision by Consultant
• EHS officer implementing SSEMP Information Events for work force
Soil pollution due to oils and lubricants / equipment poor maintenance and repairs / refueling at the construction site.
• Soil pollution
• Water pollution
• Strict rules will be imposed on workers and labors to ensure that no such spills are caused.
• If the spills take place, it must be followed by treatment prescribed above as per the degree of spill.
• An Oil Spill Management Plan containing specific mitigation measures to be part of contractor site specific environmental management plan are:
• Spill prevention trays will be provided and used at refueling locations
• On-site maintenance of construction vehicles and equipment will be avoided, a vehicle maintenance area with impermeable floor will be designated.
Because the area can be subject to un seasonal heavy rain plan before and during construction (cut and fill, land reclamation etc.) while considering the climatic conditions.
Spill contingency plan is available at site Properly paved/cemented mechanical workshop No water bodies near the working area Staff Training over oil spillage All the vehicles and machinery seals are intact Containers are available for used oil
Not Significant (Minimal)
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 117
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Regular inspections will be carried out to detect leakages in construction vehicles and equipment.
• Fuels and lubricants will be stored in covered and dyked areas, underlain with impervious lining.
• Spill control kit (shovels, plastic bags and absorbent materials) will be available near fuel and oil storage areas.
• Contaminated soil will be removed from the site and disposed in a manner to ensure protection of water sources
• Emergency plan for spill management will be prepared and inducted to the staff for any incident of spill.
• The bottom of any soak pit or septic tank will be constructed at least 100 meters away from springs and water bores
• Record of spills and Volume of removed contaminated soil will be maintained.
• Record of remedial measures taken will be maintained.
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 118
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
Heavy Machinery near agricultural land
• Agriculture Land Damage
• It is contractor’s obligation not to cause such damage and strictly follow the design.
• Top six inches soil will be protected and land will be restored to its previous condition after completion of construction works.
Construction and post construction
• Monthly Reports (EPC)
• Supervision by Consultant
• EHS officer implementing SSEMP
Information Events for work force
Not Significant (Minimal)
Contractor ESMU/CSC
Earth borrow • Land owner problems
• Levelling of land after borrowing
• Issues to the local community
• Compensation difficulties
• No private land will be acquired for the borrow areas.
• The Contractor will ensure that selected borrow areas on irrigation land are clearly demarcated and approved by the engineer including the allowed depth of the excavation before starting excavation.
• The borrow areas will be leveled. The Contractor will not leave the borrow pits in such a condition that they are unsuitably filled with rain water and cause the problem for the community.
• If the borrow area is near to the settlements, then it should be fenced completely.
• If agriculture land needs to be used as borrowing area, then the Contractor will adopt the following
Construction and post construction
Top soil management Government approved site Approval for any other site by RE and Government Borrow area management generated and implemented Agreement in case of private land owner Grievance redress Mechanism Leveling of Borrow Area
Minor \Reduced
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 119
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
methods during the digging process.
• Fix the location of excavation.
• Remove thirty centimeters of the top soil and keep it on reserved site for re-spreading in the field.
• Excavate up to one-meter depth.
• Maintain the slope as far as possible.
• Place the top soil back during the restoration
• Pay compensation for any damages/ crop losses.
Movement and Operation of heavy machinery & vehicles
• Change in Soil characteristics e.g. soil erosion, contamination and compaction
• Avoid use of heavy machinery where possible.
• Contractors before handing the site back will apply such measures as to mitigate the impact of compaction and leave the site almost in the same state in which it was occupied.
• Pictures of the area should be taken before handing it over to contactor which will help the RE to ensure an acceptable state of soil while getting the area back from the contractor.
During construction
• Monthly Reports (EPC)
• Supervision by Consultant
• EHS officer implementing SSEMP
• Information Events for work force
Not Significant (Minimal)
Contractor ESMU/CSC
Construction material
Waste generation due to closure of site
• All shivers and material that remain after the closure of temporary
Completion of Construction
• Site Inspection
• Implementation of Environmental
Not Significant (Minimal) Short term during construction phase
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 120
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
leftovers and site restoration
Occupation of usable land.
construction sites are to be removed from the location and re-used/re-cycled where possible.
• All remains are to be disposed of in a manner that will not be harmful to environment.
Enhancement Program
Beneficial in long terms with the implementation of Environmental Enhancement Program
Impacts on Hydrology and Water Resources Washing of Vehicle and equipment in the stream
• Contamination of Surface water
• Contractor will demarcate a washing area for all sorts of washing activities, with running water facility connected to a dedicated drain flowing into the septic tanks. There would be restriction on servicing/ washing of vehicles and equipment at site.
During Construction
• Documentation of audit and remedial actions where necessary
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal) Short term during construction phase
Contractor ESMU/CSC
Drinking Water supply
• Water borne diseases & other water related issues
• Contractor, under the guidance of Environment Specialist of CSC, will get spring water tested for chemical and biological contaminants, and assist in providing filtration to make water drinkable.
• There are numerous cost-effective water treatment models available in order to mitigate chemical and/or biological contamination. Sand filtration, Chlorination, UV treatment and oxidation are a few such methods.
Before construction and during the project activities.
• Documentation of audit and remedial actions where necessary
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal)
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 121
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
Municipal solid and liquid Waste Generation
• Nuisance and Soil Pollution, diseases due to dumping
• Solid waste bins will be placed at labor eating and resting areas.
• Latrines and washing areas with septic tanks will be erected by the contractor at the construction site.
• Waste from the project construction area and office area shall be segregated and collected by the Tehsil Municipal corporation for dumping at approved land fill site or if small amount then a natural gully or uncultivable land for dumping will be arranged with approval from CSC Environment Specialist.
• All these provisions will be incorporated in site Contractor Site Specific EMP for construction. Prior utilization, all the landfill sites or disposal sites will be approved by CSC Environment Specialist
During construction
• Implementation of SSEMP
• Site auditing
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal)
Contractor ESMU/CSC
Water Quality and Sedimentation Load
• Health issues to labour from water borne diseases
• Surface water quality deterioration
• Quarterly water sampling and testing will be conducted in order to ascertain water quality during different seasons.
• Two samples each from the labour camp and 10 m
During Construction and Post Construction
• Plan to be developed before completion of construction
Not Significant (Minimal)
Contractor
ESMU/ CSC PMU Merged Area Secretariat
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 122
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
due to construction and operation of the project
downstream location of the weir and will be drawn for testing to make comparison of water quality with the baseline data to determine its suitability for labour consumption or any change in water quality due to construction of weir.
• Quarterly Water Monitoring Reports by EPA certified Laboratory
Impacts on Air Quality and Noise Pollution Dust/smoke Emission from plants and equipment
• Air pollution
• Lung Diseases
• Contractor’s contractual obligation will include keeping the dust and smoke within permissible level by using machinery, which is well maintained and with low noise.
• Land, all katcha roads and paths will be sprinkled with water after regular intervals.
• The contractor must avoid/ control the dust and smoke by carefully storing and distributing the construction material so as to cause minimum dust which again should be within the acceptable limits.
During Construction. Water sprinkling to be done on regular/daily basis.
• Water sprinkling Records
• Monthly reports EPC
• Site Inspection and Audits
• Monthly Monitoring Reports by EPA certified Laboratory
Not Significant (Minimal)
Contractor ESMU/CSC
Smoke from burning of waste or firewood
• Cutting of trees and shrubs
• Smoke pollution
• Contractor shall strictly prohibit burning of waste or of wood, especially extracted from nearby shrubs and bushes.
During construction
• EPC’s Site officer and EHS officer in place
• SSEMP Implementation
Not Significant (Minimal)
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 123
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Diseases • Contractor must provide clean fuel like LPG cylinders to the labor to use for their daily purposes.
• Internal auditing and reporting by EPC
Operation of heavy mechanization and generators.
Noise pollution
and vibration
• Contractor’s contractual obligation is to use new, well maintained and low noise machinery preferably during day time.
• The drivers, operators and workers working on or near the heavy machinery must be provided with ear plugs. The contractor will ensure use of newer, well maintained machinery that creates minimum noise and emissions, as per National Environmental Quality Standards (NEQS 2000)
• Environment Specialist of CSC will ensure that this clause is added to the bidding and contract document.
• Night time construction activities will be strictly discouraged, and may only be carried out in exceptional cases, with prior permission of Resident Engineer.
• Noise monitoring will be carried out near sensitive
During Construction stage
• EPC Site Manager and EHS Officer in Place
• Audit and Inspection record of heavy mechanization and generators.
• Monthly Noise level Monitoring Reports by EPA certified Laboratory
• No. of Grievance’s (Target=0)
Not Significant (Minimal)
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 124
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
receptors on a quarterly basis.
• The NEQS for noise in residential areas is 55 dB (A) in the day-time and 45 dB (A) at night. It is recommended that noise levels close to sensitive receptors do not exceed 55 dB (A) during the day time as required by the NEQS.
Stone quarrying and Transportation of material
• Dust Emission and lungs diseases.
• Contractor shall use the road network carefully and repair any damages immediately.
• During transportation, covering of vehicle with sheet will be done.
• Unloading of vehicles will be done on designated sites.
During construction.
• Recording of violations and corrective measures
• Performance of Regular Driver Training (target 100% participation of drivers)
• Instruction and Information Events for workforce
• No. of accidents (Target=0)
Not Significant (Minimal)
Contractor ESMU/CSC
Impacts on Biological Resources Multiple project activities
• Damage to Flora and Fauna
• Impact on aquatic life
• Environment Specialist together with FATA line departments will ascertain the status of the site area in terms of occurrence of wildlife species, flora and
Rerouting and site identification during design stage and other matters during
• EPC internal monitoring and monthly reports
• Site auditing
Not Significant (Minimal) during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 125
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
fisheries. And in accordance, recommend a watch and ward system that will be based on partnership between communities, wildlife, forest & fisheries departments and political administration. Each partner’s roles will be specified at the onset, and responsibilities assigned.
• Till the completion of the survey, contractor will ensure no extraction takes place from the surrounding vegetation for fuel wood or hunting of any birds by the labor employed.
• If such a case is witnessed, it will be brought to the notice of the project management as well as the concerned Assistant Political Agent (APA).
• Contractor’s obligation is to strictly respect the limits of construction site.
• Cutting of trees will be strictly prohibited and if no alternate is available plantation of trees will be done in case any tree is cut for project activities.
construction of relevant activities
• Photographic record of pre and post project
• Implementation of Environmental Enhancement Program
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 126
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Tree cutting will be restored by planting four trees against each tree cut.
• Borrow areas with least vegetation cover will be selected.
• The project will have a soft start for allowing time to reptiles to move away from the project site.
• There will be restriction and prohibition on hunting, shooting, trapping, and poaching of wild species.
• No night time activity will be carried out.
• Photographs of the project area will be taken at pre and post project stage.
• Continuous inspection of the area will be carried jointly with other agencies involved in maintenance of protected areas.
Impacts on Socioeconomic and Cultural Issues Project Activities
• Tribal tensions and rivalries
• For matters pertaining to social obligation and benefits of the communities, if needed, a social Framework Agreement shall be signed by the RE with communities to ensure their participation and full satisfaction in matters pertaining to them. All
Before and During construction
• Continued Community Consultation Records
• Implementation of Community Liaison Plan by EPC
• No. Of Grievance’s (Target=0)
Not Significant (Minimal)
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 127
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
matters where contractor is involved, these should be made as his contractual obligations.
• Project Team along with the Social Development Specialist will ensure continuous liaison with the communities throughout the construction phase of the project, so as to identify any such incident in time. Relevant political authorities will be kept abreast of the progress, as well as any such issue if in making.
• If, during the execution of the activities or excavation, any material is discovered onsite, which may be considered of historical or cultural interest, such as evidence of prior settlements, native or historical activities, evidence of any existence on a site, which may be of cultural significance, all work shall stop and the supervising contracting officer shall be notified immediately. The area in which the material was discovered shall be marked and the evidence preserved for examination.
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 128
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• The contractor is required to develop Chance Find Procedure as part of the SSEMP.
Excavation activities
Impact on the existing civil infrastructure and facilities, especially underground installations (water supply and sewerage pipeline etc.) which cause obstacles in the provision of services to consumers
• Precisely situate the position of infrastructure and underground installations at the local works in cooperation with the relevant institutions at all levels of authority.
• Close liaison with local relevant authorities
• Should the damage take place, the contractor must contractually be bound to carry out repair immediately.
Before the construction of the dam and all other structures, the APs should be given sufficient time and compensation to satisfy them.
• Continued Community Consultation Records
• No. Of Grievance’s (Target=0)
• Monthly Reports on Information activities and response from community
• Liaison Records with local relevant authorities
Not Significant (Minimal)
Contractor CS Consultant / EMU in cooperation with concerned Department. I-e, Public Health etc.
Multiple project activities related to HSE
• Risk of injuries at work
• Spread of COVID-19
• The contractor will ensure that proper HSE protocols are in place, including protective gear, drinking water, sanitation, energy supply and overall safety for the labor.
• Evacuation plans in case of fire or any other accidents will also be prepared, and drills carried out to ensure the labor is aware of responding to such a situation.
Prior to commencement and during construction
• Site Inspection
• Monthly EPC Reports
• PPEs issuance records
• Health and safety Plans in Place and Implemented
• Implementation of Construction Site Organization Plan
Not Significant (Minimal)
Contractor ESMU/CSC
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 129
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• A detailed HSE Plan will be formulated in SSEMP.
• The Construction processes are dynamic with significantly varying number of workers on a construction project site from day to day. The workers coming from diverse environments and working closely together increases the risk of exposure to COVID 19. The
project will follow both GOP
SOPs and ADB guidelines on
COVID-19.
• Without prejudice to the following, all possible and prescribed actions shall be taken at the project site, as should facilitate the health of all life present at the site.
• Every construction project shall make proper arrangements for uninterrupted building services including but not restricted to, electricity, fuel, water supply, water disposal and sanitation, communication links, washrooms with hand hygiene and shower facility and with proper and
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 130
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
adequate supply of soaps and disinfectants.
• All incidences of appearance of the symptoms of COVID-19 shall be immediately documented and maintained at the site and information regarding which shall be immediately communicated through e-mail or else, to the designated health facility, and the sick worker shall be transported to the health facility for further advice and action. The site manager must establish a link with a nearby healthcare facility with arrangements for quick transportation of workers in case of an emergency.
• Persuade the workers to inform the authorities for their safety and of other if they observe any signs and symptoms in a colleague.
• Do not allow any worker at the construction site who has the symptoms.
• Display the awareness banners about hand hygiene and physical distancing, where you can, around the work site.
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 131
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• The lunch breaks and stretch breaks of the workers must be staggered to avoid the clustering of workers. Workers must not sit at less than 2 meters distance while having meals and while any other activity requiring interpersonal communications.
• In case of workers sleeping in at the site of construction, a safe distance of 2 meters must be ensured in the sleeping rooms •
• A supply of safe drinking water must be made available at the project site and maintained.
• Every individual must use face mask. Face mask shall be replaced as and when soiled or otherwise removed. Outer surface of face mask must not be touched with hands. Workers should wash their hands as frequently as practicable and shall not to touch their face with their hands during work.
• Workers must maintain no less than two arm lengths between them before, during after work at all the
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 132
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
times. They shall not make physical contact and shall be required to maintain separate personal gears and assets which must be clearly labelled and stored without intermix.
• Use safe transport arrangements which should not be crowded and should have social distancing in place during the entire process from pickups till drops at destination.
Operation Stage Impacts and Maintenance (O&M) Earth and Borrowing activities, fertilization for crops
• Change in visual character and soil erosion
• Restoration and Environmental enhancement plan to be prepared.
• Use of borrow areas with Engineer’s approval at specified depth.
• Limited movement of machinery.
• Documentation of area.
• Ensuring areas under crops are not used as borrow areas.
• Leveling and dressing of borrow areas; Water sprinkling.
• Rescue of any encountered species.
Pre-Operations • Implementation of Environmental enhancement plan
• EPC Construction Completion Report
• Site Inspection
Not Significant (Minimal) Short term during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program
Contractor ESMU/CSC EPA ADB
• Soil pollution due to
• Agriculture Directorate shall introduce Agriculture
Post Construction
• Agriculture extension
Minor Agriculture Directorate
PMU
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 133
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
excessive application of fertilizers and pesticides
extension programs targeting use of Integrated Pest Management (IPM), green manure, and limiting use of pesticides/ fertilizers to required levels only will target farmer communities to inform and train them. In general, in erstwhile FATA area the farmer uses mostly the Farm yard manure or green manure. The pesticide use is also rare, because of less vegetables and fruit production.
program developed before completion of construction
• Use of irrigation water for cultivating high delta crops
• Cultivation of high delta crops will be strictly discouraged.
• Cropping pattern in accordance with the water balance model will be suggested and promoted.
Post construction
Agriculture extension program developed before completion of construction
Not Significant (Minimal)
Agriculture Directorate
PMU
Monitoring programmes
Mitigation plan implementation cannot be gauged
The following monitoring programmes will be developed prior to the commencement of Project operations:
• Landslide monitoring;
• Water quality monitoring
• Watershed and flood telemetry monitoring
Operational stage
Site Inspection Monitoring Reports
Beneficial in long terms with the implementation of Operation Environmental Action Plan’ (OEAP)
Irrigation Department
PMU
Training/ educational programmes.
Effect on employees` efficiency during project
The following educational programmes will be developed prior to the commencement of Project operations:
Operational stage
Implementation of Training Events and Programs
Highly Beneficial Irrigation Department
PMU
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Semi-annual Environmental Monitoring Report Page 134
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Employee induction programme on environmental awareness;
• Employee code of conduct;
• Health and Safety training programme
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 135
ANNEX-7 A: Weekly Monitoring Checklist
Description Status Additional Comments
A-Physical Conditions 1-Ambient air quality Are dust emissions being regulated through sprinkling water on the routes being used by the Contractor? □Yes □No
Are vehicle speeds being monitored to avoid excessive dust emissions at dust prone areas? □Yes □No
Are vehicle properly tuned/maintained to reduce air emissions? □Yes □No
2. Noise Control
Are noise levels remained within safe limits (<75dB)? □Yes □No
In case excessive noise levels are detected have appropriate mitigation measures been taken? □Yes □No
Is restriction on playing tape records and blowing pressure horns etc. is being observed? □Yes □No
2-Waste Material
Has any natural drainage been disturbed or altered? □Yes □No
Are the waste bins emptied regularly in the burn pit? □Yes □No
Is food waste disposed in the open? □Yes □No
Is the combustible waste burnt regularly in the burn pit? □Yes □No
Is any medical waste generated and handled properly? □Yes □No
3-Fuel/Lubricant
Are the fuel tanks properly marked with their contents? □Yes □No
Are the fuels and oils handled in a safe manner, ensuring no leakage or spillage? □Yes □No
Any spillage of liquid waste occurred? □Yes □No
If spillage occurred, managed properly? □Yes □No
4-Traffic management
Is vehicle speed limit of 30 km/hr. being followed? □Yes □No
Is the movement of all project vehicles and personnel been restricted to within the work areas? □Yes □No
Do all vehicles and equipment have muffles to reduce noise levels whilst working close to communities? □Yes □No
Movement of machinery restricted to designated routes? □Yes □No
Construction vehicles, machinery and equipment stated in designated places within RoW? □Yes □No
B-Biological Conditions 1-Flora
Has any tree cut/uprooted? □Yes □No
Have trees and branches been used as fuel wood? □Yes □No
2-Fauna
Are the drivers careful and watchful about wild and domestic animals? □Yes □No
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 136
Any damage to animals? □Yes □No
C-Socio-economic
1-Community
During construction have good management practices been adopted by avoiding disturbance to areas adjacent to work area? □Yes □No
Are complaints from local communities being registered and responded to? □Yes □No
Have the local communities been formally notified about methods for registering complaints? □Yes □No
Is un-necessary interference to adjoining private agriculture land avoided? □Yes □No
Are damages (if any) to private property repaired and/or compensated by the Contractor? □Yes □No
Are metaled roads properly maintained? □Yes □No
2-Work Force
Are proper hygienic facilities being provided? □Yes □No
Are sufficient guards for security deployed? □Yes □No
Name _______________________________ Signature ___________________
Additional Comments:
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 137
ANNEX-7 B: Urdu Brochures for Environmental Awareness for Contractor staff
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 138
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 139
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 140
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 141
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 142
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 143
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 144
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 145
ANNEX-8: Guidelines for Camp Site Selection
• Contractor should locate camp facilities preferably at distance of 500 m or with the approval of DCSC at a minimum distance of 100 m from existing settlements, built up areas or wildlife habitats.
• The construction camp will be established in areas where vegetation cover removal
and tree cutting can be avoided.
• The camp areas should have adequate natural drainage to facilitate the flow of treated effluents preferably within the works and services land.
• The camp site should not be at blind spots, sharp turns to avoid any accidents due to
movement of machinery from the camp area. Properly designed warning signs and speed humps should be provided at inlet and outlet of the camp site.
• If camp land is on lease, the land owners should be compensated as per lease agreements.
Camp Site Management
• Contractor shall provide copy of the Environmental management Plan (EMP) at the concerned sites. Copy of the EMP should be available at camp site all the times.
• Contractor will nominate and authorize the individual(s) with role and responsibility to
implement EMP measures.
• EMP recommendations should be clearly understood by the concerned implementing individual(s).
• Contractor shall comply with the safety precautions for constructions as per ILO
convention 62.
• Contractor shall provide PPE to construction workforce and monitor if they are appropriately used.
• The labour shall be provided with the adequate potable water at site.
• Wood shall not be used as fuel or for any other activity.
• Contractor shall provide LPF cylinders for cooking and heating purposes.
• Contractor shall provide first aid kit at camp site and nominate/train individuals to
address any emergency.
• Camp site will be fenced to prevent trespassing.
• Maintain good liaison with local communities.
• Contractor shall maintain grievances log, where all community complaints are registered and follow up actions should be recorded.
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 146
Worker’s Training
• Contractor shall provide trainings to effectively implement project specific EMP. It may involve special trainings of workers on specific jobs.
• Training of construction workforce on health and safety and use of PPE (safety
shoes, helmets, gloves, masks).
• Construction workforce training in the storage and handling of material and chemicals that can potentially cause soil contamination and/or explosion.
• Contractor shall prohibit hiring of child labour and forced labour.
• Contractor shall encourage hiring of local labour.
Plans and Procedures
• Contractor shall prepare and submit health and safety plan.
• Contractor shall prepare and submit emergency response procedures for a) Spills and leakages b) Accident c) Fire fighting d) Electric
• Contractor shall prepare and submit worker’s training plan.
Waste Management
• Contractor will be responsible for treatment of wastewater from camp toilets. Wastewater will primarily pass through septic tank and later be discharge into soak pit.
• Solid waste generated during construction at campsite will be properly collected at source, treated, and safely disposed of only in selected waste disposal sites.
• Fuel and oil storage areas should be located away from any watercourses. They should be properly paved with contaminated ditch to control any spillage.
• Contractor will be responsible to contain, collect, clean-up and properly dispose-off the wastes in case of any emergency spill.
• Drinking water sources shall be at least 50 m away from soak pit to avoid contamination.
• Contractor will be responsible to implement proper dust and noise abatement procedures at camp site.
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 147
ANNEX-9: Photo Log
Pictorial View: Onsite Trainings
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 148
Pictorial View: Environmental Monitoring
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 149
Pictorial View: Construction Sites
A view of entrance at Camp Office
Vehicle Parking at Camp
Warning in Local Language about GRM Site Fencing with Warning Tape
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 150
Warning Sign Board at Site A View of Bar Kas Dam
A view of Tabai Dam A View of Labour Camp
A view of Magoo Dand Dam
Warning Sign Board at Site
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 151
A view of Labour Camp at Magoo Dand Dam
Hygiene Facilities at Site
A view of Katcha Road with precautionary board Warning and precautionary board at construction
yard
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 152
Warning Sign Board at subproject access Project Sign Board Displayed at Site
Warning Sign Board at subproject access Steel Fixing Workers at Site
Workers Wearing PPEs
Improved Drainage at Subproject
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 153
Treatment of Kitchen Waste
Kitchen Waste Land Fill
Site Fencing with Warning Tape
Excavated Areas Barricaded
Use of Wheelbarrow to avoid agricultural land
damage
A View of Jay Dam Reservoir
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 154
ANNEX-10 Maps Showing Dumping Sites of the Contractors for Each Subproject
Kharkai Weir Subproject
Khar Canal Subproject
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 155
CAD of Raghagan Dam Subproject
Saro Shah Subproject
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 156
CAD of Khurshid Dam Subproject
CAD of Warsak Left Bank Canal Subproject
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 157
Barkas Dam Subproject
Badakhel Weir Subproject
Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX
Annex: Semi-annual Environmental Monitoring Report Page 158
Neeli Tangi Weir Subproject
Tarkho kas Weir Subproject