Top Banner
Environmental Monitoring Report ________________________________________ Project Number: 47021-002 Loan Number: 3239-PAK(COL) Semi-Annual: July- December 2021 Document Date: March 2022 PAKISTAN: Federally Administered Tribal Areas Water Resources Development Project Prepared by Project Management Unit, SDU, Government of Khyber Pakhtunkhwa, Pakistan for the Asian Development Bank
166

Environmental Monitoring Report (July-December 2021)

May 09, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Environmental Monitoring Report (July-December 2021)

Environmental Monitoring Report ________________________________________

Project Number: 47021-002

Loan Number: 3239-PAK(COL)

Semi-Annual: July- December 2021 Document Date: March 2022

PAKISTAN: Federally Administered Tribal Areas

Water Resources Development Project

Prepared by Project Management Unit, SDU, Government of Khyber Pakhtunkhwa, Pakistan

for the Asian Development Bank

Page 2: Environmental Monitoring Report (July-December 2021)

NOTES

(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its

agencies ends on 30 June.

(ii) In this report “$” refer to US dollars.

This environmental monitoring report is a document of the borrower. The views expressed herein

do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may

be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation

of or reference to a particular territory or geographic area in this document, the Asian

Development Bank does not intend to make any judgments as to the legal or other status of any

territory or area.

Page 3: Environmental Monitoring Report (July-December 2021)

a

Semi-Annual Environmental Monitoring

Report (SAEMR)

Project Number: (47021-002)

Loan Number: 3239-PAK

Islamic Republic of Pakistan: Federally Administered

Tribal Areas Water Resources Development Project

(FWRDP)

(Financed by the Asian Development Bank)

(Period: July – December 2021)

Client: Project Management Unit (PMU), Sustainable Development

Unit (SDU), Planning and Development Department (P&DD),

Government of Khyber Pakhtunkhwa.

Consultants: Joint Venture of BAK Consulting Engineers (PAK), AGES

Consultants and Rehman Habib Consultants (RHC) (Pvt) Ltd.

(PAK

Page 4: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | ii

Contents 1 INTRODUCTION ..................................................................................................... 1

1.1 Preamble ................................................................................................................. 1

1.2 Headline Information ............................................................................................. 1

2 PROJECT DESCRIPTION AND CURRENT ACTIVITIES........................................ 2

2.1 Project Description ................................................................................................ 2

2.1.1 Construction of Saro Shah Weir ........................................................................... 7

2.1.2 Construction of Kharkai Weir .............................................................................. 10

2.1.3 Construction of Khar Canal Sub Surface Infiltration Gallery ............................ 12

2.1.4 Construction of CAD of Raghagan Dam ............................................................. 14

2.1.5 Construction of Bar Kas Dam ............................................................................. 17

2.1.6 Construction of Magoo Dand Dam ..................................................................... 19

2.1.7 CAD of Khurshid Dam ......................................................................................... 21

2.1.8 Construction of Bada Khel Weir ......................................................................... 24

2.1.9 Construction of Neeli Tangi Weir ........................................................................ 26

2.1.10 Construction of Tarkho Kas Weir ....................................................................... 28

2.1.11 Construction of Tor Dara Weir ............................................................................ 30

2.2 Substantially Completed Subprojects ................................................................ 32

2.2.1 Construction of Haji Lawang Kas ....................................................................... 32

2.2.2 Construction of CAD of Warsak Left Bank Canal .............................................. 35

2.2.3 Construction of Tabai Dam ................................................................................. 38

2.3 Project Contracts and Management ................................................................... 41

2.3.1 Coordination amongst Contractor, Owner, Lender ........................................... 42

2.4 Project Activities during Current Reporting Period ........................................... 44

2.4.1 Bajaur District ...................................................................................................... 45

2.4.2 Mohmand District ................................................................................................. 47

2.4.3 Khyber District ..................................................................................................... 48

2.5 Description of Any Changes to Project Design ................................................. 49

2.6 Description of Any Changes to Agreed Construction Methods ....................... 49

3 ENVIRONMENTAL SAFEGUARDS ACTIVITIES .................................................. 50

3.1 General Description of Environmental Safeguards Activities .......................... 50

3.2 Site Audits ............................................................................................................ 50

3.3 Issues Tracking (Based on Non-Conformance Notices) ................................... 52

3.4 Trends ................................................................................................................... 54

3.5 Unanticipated Environmental Impacts or Risks ................................................ 56

3.5.1 COVID-19 Pandemic ............................................................................................. 56

4 RESULTS OF ENVIRONMENTAL MONITORING ................................................ 58

Page 5: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | iii

4.1 Overview of Monitoring Conducted during Current Period .............................. 58

4.2 Trends ................................................................................................................... 58

4.3 Summary of Monitoring Outcomes ..................................................................... 58

4.3.1 Instrumental Monitoring ...................................................................................... 58

4.3.2 Noise Monitoring .................................................................................................. 58

4.3.3 Air Quality Monitoring ......................................................................................... 59

4.3.4 Water Quality Monitoring..................................................................................... 62

4.3.5 Soil Erosion .......................................................................................................... 64

4.3.6 Natural Habitat Protection ................................................................................... 64

4.4 Material Resources Utilisation ............................................................................ 65

4.4.1 Current Period ...................................................................................................... 65

4.4.2 Cumulative Fuel Utilisation ................................................................................. 66

4.5 Waste Management.............................................................................................. 68

4.5.1 Current Period ...................................................................................................... 68

4.5.2 Cumulative Waste Generation ............................................................................ 68

4.6 Health and Safety ................................................................................................. 69

4.6.1 Community Health and Safety ............................................................................ 69

4.6.2 Workers` Safety and Health ................................................................................. 70

4.7 Training................................................................................................................. 71

5 FUNCTIONING OF THE SSEMP ........................................................................... 74

5.1 SSEMP Review ..................................................................................................... 74

6 GOOD PRACTICE AND OPPORTUNITY FOR IMPROVEMENT .......................... 75

6.1 Good Practice....................................................................................................... 75

6.1.1 Awareness ............................................................................................................ 75

6.1.2 Training................................................................................................................. 75

6.1.3 Communication .................................................................................................... 75

6.1.4 Supervision .......................................................................................................... 76

6.2 Opportunities for Improvement........................................................................... 76

6.2.1 Documentation ..................................................................................................... 76

6.2.2 Innovation ............................................................................................................. 76

6.2.3 Transparency ....................................................................................................... 76

7 SUMMARY AND RECOMMENDATIONS .............................................................. 77

ANNEX-1: ENVIRONMENTAL SAFEGUARDS COMPLETION REPORT ......................... 79

ANNEX-2 (A) ENVIRONMENTAL COMPLIANCE STATUS BAJAUR DISTRICT .............. 83

ANNEX-2 (B) ENVIRONMENTAL COMPLIANCE STATUS MOHMAND DISTRICT .......... 85

ANNEX-2 (C) ENVIRONMENTAL COMPLIANCE STATUS KHYBER DISTRICT.............. 87

ANNEX-3 MAJOR NON-COMPLIANCE NOTICES ............................................................ 89

ANNEX-4 CORRECTIVE ACTION PLAN ........................................................................... 91

ANNEX-5 INSTRUMENTAL MONITORING RESULTS ...................................................... 92

ANNEX-6: ENVIRONMENTAL MANAGEMENT PLAN .................................................... 113

ANNEX-7 A: WEEKLY MONITORING CHECKLIST ........................................................ 135

ANNEX-7 B: URDU BROCHURES FOR ENVIRONMENTAL AWARENESS FOR

CONTRACTOR STAFF .................................................................................................... 137

ANNEX-8: GUIDELINES FOR CAMP SITE SELECTION ................................................ 145

ANNEX-9: PHOTO LOG ................................................................................................... 147

Page 6: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | iv

List of Exhibits

Project Location .................................................................................................................. 3

SSEMP Submission Details of Sub Projects ......................................................................... 5

Saro Shah Weir Location Map ............................................................................................. 9

Kharkai Weir Location Map ............................................................................................... 11

Khar Canal Sub Project Location Map ............................................................................... 13

CAD Raghagan Dam Location Map ................................................................................... 16

Location Map of Bar Kas Dam ........................................................................................... 18

Location Map of Magoo Dand Dam .................................................................................. 20

Location Map of CAD of Khurshid Dam ............................................................................ 23

Location Map of Bada Khel Weir .................................................................................. 25

Location Map of Neeli Tangi Weir................................................................................. 27

Location Map of Tarkho Kas Weir ................................................................................. 29

Location Map of Tor Dara Weir ..................................................................................... 31

Haji Lawang Kas Location Map ...................................................................................... 34

CAD of Warsak LBC Location Map................................................................................. 37

Map showing location of Tabai Dam ............................................................................ 39

Substantially Completed Sub Projects .......................................................................... 40

Details of Contractors ................................................................................................... 43

Physical Progress of Sub Projects in Bajaur District ...................................................... 46

Physical Progress of Sub Projects in Mohmand District ............................................... 47

Physical Progress of Sub Project in Khyber District ...................................................... 48

Overall conformance Level of All Sub-Projects at District Mohmand .......................... 52

Overall conformance Level of All Sub-Projects at District Bajaur ................................. 52

Overall conformance Level of All Sub-Projects at District Khyber ................................ 53

Project Major and Minor Non-Conformance Level....................................................... 53

Summary of Issues Tracking Activity for Current Period .............................................. 54

Percentage Conformance of each SAEMR .................................................................... 54

Environmental Compliance Trend ................................................................................ 55

Total No. of Issues in each Reporting Period ................................................................ 55

Issues Trending ............................................................................................................. 56

Noise Testing Results .................................................................................................... 59

Air Quality Test Results ................................................................................................. 61

Drinking Water Quality Results ..................................................................................... 63

Watershed Management Status ................................................................................... 64

Fuel Consumption in last 6 Months .............................................................................. 67

Cumulative Fuel Consumption Trend ........................................................................... 67

Solid Waste Generated at Sites ..................................................................................... 68

Health and Safety Statistics........................................................................................... 70

Details of Trainings ........................................................................................................ 71

Page 7: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | v

Abbreviations

ADB Asian Development Bank

CAP Corrective Action Plan

CBO Community Based Organization

DCSC Design and Construction Supervision Consultants

EARF Environment Assessment and Review Framework

EIA Environmental Impact Assessment

EoT Extension of Time

EMP Environmental Management Plan

EPA Environmental Protection Agency

ERP Emergency Response Plan

ESMU Environmental and Social Management Unit

FATA Federally Administrated Tribal Areas

FWRDP FATA Water Resources Development Project

GAP Gender Action Plan

GRC Grievance Redressl Committee

GRM Grievance Redressl Mechanism

HSE Health Safety and Environment

IA Implementing Agency

IEE Initial Environmental Examination

LPG Liquid Petroleum Gas

NEQS National Environmental Quality Standards

NCN Non-Compliance Notice

NGO Non-Governmental Organization

NSL Natural Surface Level

PIU Project Implementation Unit

PMU Project Management Unit

PPE Personal Protective Equipment

QPR Quarterly Progress Report

RD Reduced Distance

RE Resident Engineer

REA Rapid Environmental Assessment

SSEMP Site Specific Environmental Management Plan

SAEMR Semi-Annual Environmental Monitoring Report

SPS Safeguard Policy Statement 2009

VO Variation Order

WHO World Health Organization

WWF World Wide Fund for Nature

Page 8: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 1

1 INTRODUCTION

1.1 Preamble

1. This report represents the Semi-Annual Environmental Monitoring Report (SAEMR) for

FATA Water Resources Development Project (FWRDP).

2. Design and Construction Supervision Consultants (DCSC) have prepared this Semi-

Annual Environmental Monitoring Report (SAEMR) for Project Management Unit (PMU)

covering period from July 2021 to December 2021. This report fulfils the requirements

to monitor the effectiveness of ADB`s Safeguards Policy Statement 2009, its

implementation and to ensure sound environmental planning. During the environmental

monitoring the gaps/shortcomings in the implementation of environmental safeguards

as per Safeguard Policy Statement (SPS) 2009 were identified and corrective actions

proposed and recommendations for future course of action provided.

1.2 Headline Information

3. DCSC`s environment team has orientated all the contractors on environmental

compliances as per IEEs/EMPs. The team has observed that environmental

management has improved over the time on subprojects sites. Mutually agreed

Corrective Action Plan is also devised and communicated to the contractors.

Contractors have been advised to address non-compliances as per agreed Corrective

Action Plan. Environment Safeguard Team of consultants includes, an Environment

Specialist, three Environmental Inspectors for looking after the EMP implementation on

different sites in Khyber, Mohmand and Bajaur Districts. Beside this HSE Managers

have been hired by the contractors for dams’ subprojects while for diversion weirs and

infiltration galleries contractors have nominated an engineering staff for of SSEMP at

sites. Therefore, the progress in environmental compliance has been improved during

the reporting period.

Page 9: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 2

2 PROJECT DESCRIPTION AND CURRENT ACTIVITIES

2.1 Project Description

4. Federally Administered Tribal Areas (FATA) Water Resources Development Project

(FWRDP) is operational in the provincial territories of Khyber Pakhtunkhwa (KP) at the

western borders of Pakistan with Afghanistan. It focuses on increasing irrigation

supplies in three districts, namely Mohmand, Khyber and Bajaur to increase crop

production and harvest water sustainably. The project is being proposed as a result of

the Water Assessment Study executed under the completed ADB supported FATA

Rural Development Project of former FATA Secretariat. The study identified 40

watersheds where the groundwater aquifers are depleting at a high rate, even under

average weather conditions due to unplanned water extraction for irrigation and other

associated purposes. It recommends shifting from groundwater to surface water, which

remains totally unutilized, and identified potential sites for small reservoirs dams and

diversion weirs in the 40 watersheds of Mohmand, Khyber and Bajaur Districts of KP.

Page 10: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 3

Project Location

Page 11: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 4

5. Project Management Unit (PMU) of FATA Water Resources Development Project

(FWRDP) has screened out thirty-four (34) subprojects for irrigation of agricultural land

under FWRDP. These subprojects have been screened, classified, and assessed

according to ADB’s Safeguard Policy Statement (SPS) 2009 and Pakistan

Environmental Protection Agency Review of IEE/EIA Regulations 2000. Environmental

considerations were assessed for these subprojects. Initial Environmental Examination

(IEEs) and Environmental Management Plans (EMPs) for 34 subprojects were

prepared by Design and Construction Supervision Consultant (DCSC), covered in 24

Nos Initial Environmental Examination (IEE) reports. Out of total 24 IEEs, 20 IEEs were

prepared for individual sub project while one consolidated IEE covers 8 sub projects

and three IEES covers two sub projects, respectively. All IEEs were cleared and

disclosed by ADB. Environmental Approvals were received from Environmental

Protection Agency (EPA) for all IEEs.

6. Presently, 121 subprojects are under construction while twenty-two (22) are

substantially completed. The table below (Exhibit 2) is a representation of each

subproject`s description in terms of environmental safeguards implementation (IEEs

and SSEMPs) as per ADB Safeguard Policy Statement 2009. Contractors are required

to submit the SSEMP and get an approval from DCSC/PMU 10 days before

commencement of civil works. This was a challenge for DCSC and PMU to comply with

this requirement at the start of the project as the contractor’s capacity to understand

environmental safeguards were not up to the mark as they have worked in erstwhile

FATA and environmental compliance in erstwhile FATA was a hard task and they have

not seen this type of requirement in any contract before FWRDP, but still, we put every

effort to ensure this compliance. As reflected in exhibit 2 the SSEMPs submission and

approval process was improved as compared with the initial subprojects for which

SSEMPs were submitted late.

7. A training session is regularly arranged for newly awarded contracts at DCSC office and

PMU to build the capacity of the contractors and understand the importance of

environmental safeguards implementation during subproject`s execution. Every

contractor is briefed in PMU about the SSEMP and its importance and in the same

session templates and SSEMP guidance handbook is provided to them for their

understanding and convenience.

1 Kamar Ragha Dag subproject is being executed as VO of CAD of Raghagn Dam subproject

Page 12: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 5

SSEMP Submission Details of Sub Projects

S.

No

Name of Sub-

Project

Contractor

Name

Date of

Physical

Work Started

Status of

IEEs

Approval

Date of

SSEMPs

COVID-19

Updation

District Bajaur

1 Kharkai Weir

(Remaining

Works)

M/s MBCC 15-April-

2021

Approved 08-April-

2021

08-April-

2021

2 Daman Lift

Irrigation

M/s Haji Lal

Bad shah&

Sons

10-Aug-2018 Approved 18-Oct-

2018

30-Nov-

2020

3 Badi Samoor

Weir

M/s Haji Lal

Bad shah&

Sons

10-Aug-2018 Approved 18-Oct-

2018

26-Nov-

2020

4 Lardand Weir M/s Haji Lal

Bad shah&

Sons

16-Aug-2018 Approved 18-Oct-

2018

02-Dec-

2020

5 Damano Weir M/s National

RCC Works

Pvt Ltd

05-May-

2018

Approved 18-Oct-

2018

08-Dec-

2020

6 Nalai Kas Weir M/s National

RCC Works

Pvt Ltd

05-May-

2018

Approved 04-Sep-

2018

08-Dec-

2020

7 Shunga Weir M/s National

RCC Works

Pvt Ltd

10-May-

2018

Approved 04-Sep-

2018

08-Dec-

2020

8 Khar Canal Sub

Surface Infiltration

Gallery

M/s PMC-JHK

(JV)

10-Oct-2019 Approved 27-Sep-

2019

01-Dec-

2020

9 Lara Dandokai

Weir

M/s PMC-JHK

(JV)

28-Oct-19 Approved 27-Sep-

2019

02-Dec-

2020

10 Haji Lawang Kas

Lift Irrigation

M/s PMC-JHK

(JV)

25-Oct-19 Approved 27-Sep-

2019

01-Dec-

2020

11 Chepatra Weir M/s Zeraki

Enterprises

04-Nov-2019 Approved 02-Nov-

2019

27-Nov-

2020

12 Hayatai Sub

Surface Infiltration

Gallery

M/s Zeraki

Enterprises

06-Dec-2019 Approved 05-Nov-

2019

01-Dec-

2020

Page 13: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 6

13 Shukrata Sub

Surface Infiltration

Gallery

M/s Zeraki

Enterprises

10-Dec-2019 Approved 05-Nov-

2019

07-Dec-

2020

14 Kat Gala

Extension of

Irrigation Chanel

M/s Zeraki

Enterprises

25-Nov-2019 Approved 15-Nov-

2019

02-Dec-

2020

15 Derakai Weir M/s MBCC-

PMC(JV)

11-Mar-20 Approved 10-Mar-

2020

09-Dec-

2020

16 CAD Raghagan

Dam

M/s National

RCC Works

Pvt Ltd

16-Apr-20 Approved 16-Mar-

2020

25-Nov-

2020

17 Dawawo Weir M/s National

RCC Works

Pvt Ltd

18-Aug-20 Approved 27-Jul-2020 30-Nov-

2020

District Mohmand

18 Jay Dam M/s Ali & Co 10-Oct-17 Approved 02-May-

2018

26-Nov-

2020

19 Ganjyano Danish

Kool Lift Irrigation

M/s Sher

Ghazan Khan

Construction

Company

08-June-

2018

Approved 04-Sep-

2018

01-Dec-

2020

20 Mundara Weir M/s Sher

Ghazan Khan

Construction

Company

15-Jul-2018 Approved 29-Oct-

2018

04-Dec-

2020

21 Saro Shah Weir

M/s PMC-JHK

(JV)

04-Dec-2019 Approved 27-Sep-

2019

07-Dec-

2020

22 Serai Bazar Shah

Lift Irrigation

M/s PMC-JHK

(JV)

23-Dec-2019 Approved 27-Sep-

2019

07-Dec-

2020

23 Madar Irrigation

Scheme

M/s Zeraki

Enterprises

11-Oct-2019 Approved 01-Oct-

2019

04-Dec-

2020

24 CAD of Warsak

Left Bank Canal

M/s Ali & Co 29-Dec-2020 Approved 11-Dec-

2020

11-Dec-

2020

25 CAD of Khurshid

Dam

M/s MBCC

Builders & M/s

PMC JV

29-Dec-2020 Approved 17-Dec-

2020

11-Dec-

2020

Page 14: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 7

2.1.1 Construction of Saro Shah Weir

8. The Saro Shah subproject is proposed at Ambahar Khwar. The distance from Ekka

Ghund through District Mohmand Road is 55.5 km to reach weir site. As per site

observation perennial flow of 255 lit/sec (9 cusecs) exist in the khwar. The Saro Shah

subproject is proposed at coordinates of 34.5484° N &71.4502°E.

9. Weir is proposed at Saro Shah to collect water from the khwar and convey it to the

sump. Solar pumps are proposed to lift water from the sump and deliver it to the

command area. It is anticipated that from the scheme, culturable command area of 100

ha will be irrigated at cropping intensity of 126 % and design discharge of 134.1 lit/sec.

Total length of irrigation network is 2.90 km.

10. The project cost is estimated at Rs. 92.530 million and anticipated to take 12 months to

complete. The results of the economic analysis show that the project is economically

District Khyber

26 Shangade Weir M/s New Malik

Afridi & Co

25-Nov-2017 Approved Late

Submitted

Project

Completed

before

COVID

27 Tabai Dam M/s Tribal

Global

Construction

(Pvt) Ltd.

14-Jul-2020 Approved 16-June-

2020

26-Nov-

2020

28 Bar Kas Dam M/s Tribal

Global

Construction

(Pvt) Ltd.

14-Jul-2020 Approved 16-June-

2020

13-Oct-

2020

29 Magoo Dand Dam M/s National

RCC Works

Pvt Ltd.

01-Oct-2020 Approved 27-Jul-2020 13-Oct-

2020

30 Bada Khel Weir M/s New Malik

Afridi & Co

16-Feb-2021 Approved 01-Feb-

2021

01-Feb-

2021

31 Neeli Tangi Weir M/s Habib

Khan Builders

22-Sep-2021 Approved 10-Jul-2021 10-Jul-2021

32 Tarkho Kas Weir M/s Habib

Khan Builders

22-Sep-2021 Approved 18-Jul-2021 18-Jul-2021

33 Tor Dara Weir M/s Habib

Khan Builders

22-Sep-2021 Approved 26-Jul-2021 26-Jul-2021

Page 15: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 8

viable (EIRR 10.84 %). The financial analysis also indicates the safe investment with

FIRR as 9.43 %.

11. The subproject activities may cause some disturbances to the environment due to

material dumping, machinery work, taking borrow material, setting up of camp areas,

transportation on link roads and necessary facilities for the staff / labour to be engaged

for the subproject. These impacts are mitigated through measures envisaged in EMP.

12. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature.

13. Subproject does not involve any permanent or temporary land acquisition. No

indigenous people and women headed households have been identified in the

subproject area. The other social issues like safety of public and workers, security

problems, risk of communicable diseases, vector borne diseases etc. are of temporary

in nature. Subproject leads to creation of job opportunities particularly for the local

population and socioeconomic uplift through irrigated agriculture.

Page 16: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 9

Saro Shah Weir Location Map

Page 17: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 10

2.1.2 Construction of Kharkai Weir

14. The Kharkai Weir subproject envisages construction of weir at coordinates

34°53'43.00"N & 71°24'24.40"E on Wara Kharkai Stream. The Wara Kharkai weir site

is located about 21.4 Km North West of District Head Quarter Khar of Bajaur District.

15. It is envisaged to construct a low height weir and crest length 11 m for design flood of

50-year return period of 57 cumec. A Tyrolean part of 3 m in length is provided for

conveying of design discharge for canal/irrigation conduit. It is anticipated that from the

scheme, gross command area of about 164 ha and culturable command area of 126 ha

will be irrigated at cropping intensity of 133 % and design discharge of 53 lit/sec. The

irrigation network consists of main conduit (2350 m) and minor (850 m).

16. The project cost is estimated PRs. 47.70 million and anticipated to take 12 months to

complete. The results of the economic analysis show that the project is economically

viable (EIRR 57.93 %). The financial analysis also indicates the safe investment with

FIRR as 52.74 %.

17. The contractor M/s Rustam Khan & Co. was terminated due to slow progress and now

the contract has been awarded to M/s MBCC & Builders for the scope of remaining

woks of the subproject and SSEMP has been updated accordingly.

18. The subproject activities may cause some disturbances to the environment due to

material dumping, machinery work, taking borrow material, setting up of camp areas,

transportation on link roads and necessary facilities for the staff / labor to be engaged

for the subproject, in the RoW of Kharkai weir site and the allied sites. These impacts

are mitigated through measures envisaged in EMP.

19. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature.

20. Subproject does not involve any permanent or temporary land acquisition. No

indigenous people and women headed households have been identified in the

subproject area. The other social issues like safety of public and workers, security

problems, risk of communicable diseases, vector borne diseases etc. are of temporary

in nature. Subproject leads to creation of job opportunities particularly for the local

population and socioeconomic uplift through irrigated agriculture.

Page 18: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 11

Kharkai Weir Location Map

Page 19: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 12

2.1.3 Construction of Khar Canal Sub Surface Infiltration Gallery

21. The Khar Canal Project is located on Charmang Khwar Khar Canal site is located at a

distance of 1.2 km from Khar through paved road. As per site observation perennial

flow of 0.95 cumec exists in the khwar.

22. A network of subsurface pipe is proposed in the active flow channel of the khwar to

collect the flow. It is anticipated that from the scheme, culturable command area of 154

ha will be irrigated at cropping intensity of 133 % and design discharge of 116.5 lit/sec.

Total length of irrigation network is 7 km.

23. The project cost is estimated PRs. 49.179 million and anticipated to take 12 months to

complete. The results of the economic analysis show that the project is economically

viable (EIRR 31.76 %). The financial analysis also indicates the safe investment with

FIRR as 27.36 %.

24. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas and necessary facilities for the staff /

labour to be engaged for the subproject. All the anticipated adverse environmental

impacts of the subproject are mitigatable, temporary in nature and localized which can

be mitigated through implementation of EMP.

Page 20: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 13

Khar Canal Sub Project Location Map

Page 21: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 14

2.1.4 Construction of CAD of Raghagan Dam

25. Raghagan Dam Project is located across Babukara Khwar, a left bank tributary of

Bajaur Khwar, which ultimately falls into Panjkora River. The dam is located in Salarzai

area of Bajaur District. The villages located in the vicinity of dam are Raghagan,

Charghurai Marusa, Mullah Killi and Qazi Dheri.

26. The coordinates of Raghagan Dam Command Area sites are

S. No. Longitude (m) Latitude (m)

1. 734060.005 3851812.240

2. 736034.496 3848332.633

3. 745827.699 3853889.752

4. 743867.430 3857377.429

27. The project is divided into seven (07) number of chunks totaling gross command area

of 1,113 ha and cultivable command area of 929 ha. This Project includes development

of command area by providing irrigation network from the Raghagan main right and left

irrigation channels though outlets either by lift or through gravity. After the successful

completion of the Raghagan Dam Project, the proposed system under study will be able

to irrigate 929 ha. This project involves construction of secondary distributary system

which is inclusive of primary and secondary water courses/channels having a length of

31.50 km and tertiary distribution system which comprises tertiary water courses having

length of 41.20 km. It is to mention here that due to topography of the command area;

these water courses/channels have allied structures such as stepped fall structures,

aqueducts, syphon’s, road culverts, drainage culverts, sumps for lifting, lifting pipes, solar panels, accessories, naccas and washing pads etc.

28. The project cost is estimated to be PRs. 430.672 million and is anticipated to take 18

months period to complete. The results of the economic analysis show that the project

is economically viable (EIRR 12.24 %). The financial analysis also indicates the safe

investment with FIRR as 10.21 %.

29. The Kamar Ragha Dag diversion arrangement was proposed on Bajaur Khwar.

Kamar Ragha Dag subproject site is located at a distance of 7 km from Khar

through paved road. As per site observation perennial flow of 1.48 cumec exist

in the khwar.

30. Sub-surface Infiltration Gallery was proposed to collect water from the khwar

and convey it to the sump. Solar pumps are proposed to lift water from the sump

and deliver it to the command area. It is anticipated that from the scheme,

culturable command area of 137.6 ha will be irrigated at cropping intensity of

Page 22: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 15

130 % and design discharge of 86.9 lit/sec. Total length of irrigation network is

4.63 km.

31. The subproject cost is estimated Rs. 47.884 million and anticipated to take 12

months to complete. The results of the economic analysis show that the

subproject is economically viable (EIRR 27.37 %). The financial analysis also

indicates the safe investment with FIRR as 23.75 %.

32. At the time of feasibility and detail design of CAD of Raghagan Dam it was learned the

command area of Kamar Ragha Daag falls within the command area of Raghgan Dam

so it was decided that it will be irrigated from the right bank channel of Raghgan dam

which is more feasible option.

33. Kamar Ragha Dag subproject is being executed as Variation Order (VO) of CAD of

Raghagn Dam subproject which is already under construction.

34. The CAD of Raghagan Dam subproject based on Rapid Environmental Assessment

(REA) is categorized as “B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature

and will cause some disturbances to the local environment during execution like

material dumping, machinery work; borrow material, camp areas and necessary

facilities for the staff/ labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporary in nature and

localized which can be mitigated through implementation of EMP.

Page 23: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 16

CAD Raghagan Dam Location Map

Page 24: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 17

2.1.5 Construction of Bar Kas Dam

35. The Bar Kas Dam is proposed on Brag Khwar in Tehsil Landi Kotal of Khyber District.

Bar Kas Dam subproject site is located at a distance of about 50 Km from District

headquarter Jamrud. The proposed Bar Kas Dam is located at coordinates 71.1483 E

& 33.9915N.

36. A 15 m high and 131.00 m long Bar Kas RCC Slab/Box Local Material Filled Dam with

reservoir capacity of 0.267 Mm3 and spillway flood capacity of 230 m3/sec is proposed

at Barkas area of Khyber District to collect water from the Brag khwar and convey it to

the barani (rain-fed) command area. Cultivable command area of 75 ha will be irrigated

at cropping intensity of 120 % and design discharge of 21.95 lit/sec. Total length of

irrigation network is 3.15 km.

37. The project cost is estimated Rs. 324.557 million and anticipated to take 18 months

period to complete. The results of the economic analysis show that the project is

economically viable (EIRR 7.51 %). The financial analysis also indicates the safe

investment with FIRR as 6.29 %.

38. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

Page 25: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 18

Location Map of Bar Kas Dam

Page 26: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 19

2.1.6 Construction of Magoo Dand Dam

39. The Magoo Dand Dam is proposed on Aziz Khwar in Tehsil Bara of Khyber District.

Magoo Dand Dam subproject site is located at a distance of about 37 Km from district

headquarter Jamrud. The proposed Magoo Dand Dam is located at coordinates

71.4756° E and 33.7649°N.

40. A 15 m high and 60 m long Magoo Dand Concrete Gravity Dam with reservoir capacity

of 0.3094 Mm3 and design flood capacity of 97 cumecs is proposed at Magoo Dand

area of Khyber District to collect water from the Aziz khwar and convey it to the barrani

(rain-fed) command area. Cultivable command area of 76 ha will be irrigated at cropping

intensity of 125 % and design discharge of 0.02473 m3/sec (24.73 liter/sec). Total

length of delivery pipe irrigation network is 316 m and 3.195 km respectively.

41. The subproject cost is estimated Rs. 252.427 million and anticipated to take 18 months

period to complete. The results of the economic analysis show that the project is

economically viable (EIRR 10.15 %). The financial analysis also indicates the safe

investment with FIRR as 8.58%.

42. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

Page 27: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 20

Location Map of Magoo Dand Dam

Page 28: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 21

2.1.7 CAD of Khurshid Dam

43. Khurshid Dam is located at coordinates 34°22'28.9"N 71°35'54.1"E across Nawey Dand

nullah/ khwar, a tributary of Swat River. The subproject is located in Prang Ghar area

about 40 km North East of Ghalani (District Headquarter) of Mohmand District.

44. Irrigation canal on left bank offtake from main dam to irrigate the command area. The

entire canal length of 2.7 km from intake point to tail end is partially choked by eroded

material and damaged at different locations by the local community. Utilizing the water

through solar pumps, at both sides of Khwar, from main reservoir and channel for

irrigating lands at higher elevation is observed in command area. Water conveyance

from dam to the fields is the crux of the project.

45. The major issue with the construction of command area development of Khurshid dam

is blockage of main road when the reservoir rises to normal conservation level (El 434

m) whereas the bed level of stream at river crossing is 432m, in order to make the road

accessible the locals have to drawdown the reservoir which results in water loss of 13

ha-m out of 52 ha-m of reservoir capacity which is approx. 25% loss of water/ benefits.

In order to overcome this issue, the present study includes multi barrel causeway, with

the height of 4.0m, which will result in utilization of top 25% reservoir capacity for the

agricultural benefits.

46. The subproject is divided into five (05) number of chunks totaling command area of 104

ha. This project includes development of command area by providing irrigation network

from the Khurshid irrigation channel though outlet. The proposed system under study

will be able to irrigate 104 ha. This project involves primary (rectangular section),

secondary and tertiary watercourses (Parabolic Precast E types), fall structures,

syphon, road culvert, drainage culverts, sumps, minors through Parabolic Type E,

nacca and washing pads etc.

47. The existing cropping intensity is 70%. Future irrigation intensity of subproject is

proposed as 126%. Total length of main irrigation channel under this subproject is 6.08

km.

48. The subproject cost is estimated to be Rs. 119.772 million and is anticipated to take 12

months period to complete. The results of the economic analysis show that the project

is economically viable (EIRR 12.86 %). The financial analysis also indicates the FIRR

as 10.94 %.

49. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

Page 29: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 22

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

Page 30: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 23

Location Map of CAD of Khurshid Dam

Page 31: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 24

2.1.8 Construction of Bada Khel Weir

50. The Bada Khel weir sub-project is proposed on Lashora khwar. The sub-project site is

located at a distance of 12 km from Jamrud, Khyber District Headquarter. As per site

observation there is perennial flow in the khwar.

51. With the development of irrigation scheme, the perennial flows of the Lashora khwar

will be utilized to irrigate, command area of adjacent locality. The design and layout

planning of the irrigation scheme have been done by considering, topography,

command area and geology of the weir axis.

52. Bada Khel weir is proposed to collect water from the khwar and convey it to the

command area of approximately 26.77 hectares lying downstream of the proposed weir

site. Cultivable command area of 26.77 ha will be irrigated at cropping intensity of 81.8

% and design discharge of 14.7 lit/sec will be required to serve the purpose. Total length

of irrigation network is approximately 2.77 km.

53. The project cost is estimated Rs. 22.477 million and anticipated to take 12 months

period to complete. The results of the economic analysis show that the project is

economically viable (EIRR 12.63 %). The financial analysis also indicates the safe

investment with FIRR as 11.16 %.

54. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

Page 32: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 25

Location Map of Bada Khel Weir

Page 33: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 26

2.1.9 Construction of Neeli Tangi Weir

55. The Neeli Tangi weir sub-project is proposed on Neeli Tangi khwar and is located at a

distance of 68 km from Jamrud Khyber District Head Quarter. As per site observation

there is perennial flow in the khwar.

56. With the development of irrigation scheme, the perennial flows of the Neeli Tangi khwar

will be utilized to irrigate, command area of adjacent locality. The design and layout

planning of the irrigation scheme have been done by considering, Topography,

Command area and geology of the weir axis.

57. Neeli Tangi weir is proposed to collect water from the khwar and convey it to the barrani

command area. Cultivable command area of 80.36 ha will be irrigated at cropping

intensity of 100 % and design discharge of 21.11 liter /sec (0.75 cfs). Total length of

irrigation network is 7.12 km.

58. The project cost is estimated Rs. 58.437 million and anticipated to take 12 months

period to complete. The results of the economic analysis show that the project is

economically viable (EIRR 12.02 %). The financial analysis also indicates the safe

investment with FIRR as 10.16 %.

59. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

Page 34: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 27

Location Map of Neeli Tangi Weir

Page 35: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 28

2.1.10 Construction of Tarkho Kas Weir

60. The Tarkho Kas Weir sub-project is proposed on Matu Nullah near village Naghara in

Tirah vallay in District Khyber and is located at a distance of 79 km from Jamrud Khyber

District head quarter. As per site observation there is perennial flow exist in the Nullah.

61. Tarkho Kas Weir is proposed to collect water from Matu Nullah and convey it to the

command area. Cultivable command area of 90 ha will be irrigated at cropping intensity

of 100 % and design discharge of 28.9 lit/sec. Total length of irrigation network is 5290

m.

62. The project cost is estimated Rs. 64.577 million and anticipated to take 12 months

period to complete. The results of the economic analysis show that the project is

economically viable (EIRR 12.23 %). The financial analysis also indicates the safe

investment with FIRR as 10.33 %.

63. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

Page 36: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 29

Location Map of Tarkho Kas Weir

Page 37: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 30

2.1.11 Construction of Tor Dara Weir

64. The Tor Dara weir sub project has two weirs one on the main Tor Dara Nullah and the

other on its small tributary near village Natu Khel in Tirah Valley, District Khyber and is

located at a distance of 100 km from Peshawar.

65. During various visits at site the hydrological observation was made and found the

perennial flow in a range of 5-8 cusecs. In the last site visit was made approximately 5

cusecs of flows was observed on Tor Dara nullah and 0.30 cusecs was observed in its

tributary.

66. Tor Dara Weir and Natu Khel Weirs are proposed to collect water from Tor Dara Nullah

and its tributary to convey the available flows to the command area laying at both right

and left side of Tor Dara Nullah. Gross command area is 96 hectares and cultivable

command area is 93 hectares which is proposed to be irrigated at cropping intensity of

100 % with the design discharge of 22.90 lit/sec and 6.45 lit/sec for Tor Dara and Natu

Khel Weir respectively.

67. The main features of the project include construction of weirs, irrigation channels,

retaining walls, fall structures, road culverts and drainage culverts, on-farm water

management works and improvement of ware sheds through forestation. The project

cost is estimated as Rs. 93.804 million and is anticipated to take 12 months period to

complete. The results of the economic analysis show that the sub project is

economically viable (EIRR 12.03%). The financial analysis also indicates the safe

investment with FIRR as 10.23%.

68. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

Page 38: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 31

Location Map of Tor Dara Weir

Page 39: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 32

2.2 Substantially Completed Subprojects

69. The substantial construction of the subprojects mentioned below have been

successfully completed without any major environmental issues and the project

environmental compliance was rated as satisfactory.

70. The six subprojects (Shangade Weir, Shunga Weir, Nailai Kas Weir, Damano Weir,

Maddar Infiltration Gallery and Kat Gala irrigation channel) were completed in all

respects and were reported in 7thSAEMR July-December 2020. Thirteen (13)

subprojects (Jay Dam, Ganjyano Danish Kool Infiltration Gallery, Mundara Weir, Badi

Samoor Weir, Lar Dand Weir, Daman Lift Irrigation, Shukrata Infiltration Gallery,

Chepatra Weir, Dawawo Weir, Derakai Weir, Lara Dandokai Weir, Hayatai Infiltration

Gallery and Serai Bazar Shah Infiltration Gallery) were completed in all respects and

were reported in 8thSAEMR January-June 2021. While in the current reporting period

three subprojects have been completed namely (CAD of Warsak Left Bank Kanal, Haji

Lawang Kas Weir and Tabai Small Dam). The subprojects completion report

(Environment Compliance part) for 19 subprojects were also submitted previously.

2.2.1 Construction of Haji Lawang Kas

71. The Haji Lawang Kas subproject is located downstream of confluence of Watalai and

Charmang Khwars. Haji Lawang site is located at a distance of 2.3 km from Khar

through paved road. As per site observation perennial flow of 2.16 cumec exists in the

khwar.

72. A network of subsurface pipe is proposed in the active flow channel of the khwar to

collect the flow. It is anticipated that from the scheme, culturable command area of 39

ha will be irrigated at cropping intensity of 133 % and design discharge of 78.3 lit/sec.

Total length of irrigation network is 1.95 km.

73. The project cost is estimated PRs. 23.207 million and anticipated to take 12 months to

complete. The results of the economic analysis show that the project is economically

viable (EIRR 15.14 %). The financial analysis also indicates the safe investment with

FIRR as 12.79 %.

74. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas and necessary facilities for the staff /

labour to be engaged for the subproject. All the anticipated adverse environmental

impacts of the subproject are mitigatable, temporary in nature and localized which can

be mitigated through implementation of EMP.

Page 40: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 33

75. Environmental impacts like soil erosion, soil contamination, water contamination, air

pollution, high noise level, etc. are of temporary nature and can be controlled and

mitigated through proper management of borrow material area, establishment and

proper management of camp and material and machinery yard, transportation on link

roads and necessary facilities for the staff and labour by using good engineering

practices. Soil erosion and contamination, water contamination, air pollution and high

noise levels needs to be controlled with the use of good engineering practices.

76. Contractor is bound to develop Site Specific Environmental Management Plan

(SSEMP), Traffic Management Plan, Solid Waste Management and Material

Management Plan, Occupation Health and Safety Plan etc. before starting the

construction activities and to ensure that no damage is done to the wildlife, public

infrastructure and local culture, customs, and traditions.

77. This subproject has been completed for civil works and the overall environmental

safeguard performance of the said subproject was rated satisfactory while the details

are provided in Annex-1.

Page 41: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 34

Haji Lawang Kas Location Map

Page 42: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 35

2.2.2 Construction of CAD of Warsak Left Bank Canal

78. Warsak Dam is a mass concrete gravity dam located at coordinates 34°09′50″N & 71°21′29″E on the Kabul River, approximately 20 km northwest of the city of Peshawar

in the Khyber Pakhtunkhwa province of Pakistan.

79. Warsak Left Bank Canal offtakes from main Warsak dam through left bank irrigation

conduit 2 Km downstream of the main dam to irrigate the command area. The capacity

of left bank irrigation conduit is 45 cusecs. Total length of the canal is 18.4 miles.

80. Water conveyances from channel to the fields are unlined which causes excessive

seepage resulting in water shortages at the tail end. The present feasibility study

undertakes the on-farm water management by lining the watercourses and construction

of proper Nuccas. Irrigation Department KP has also executed a separate project for

lining of main channels. This was thoroughly discussed with the official of Irrigation

Department and it was mutually agreed that FWRDP will undertake the on-farm water

management while Irrigation Department will continue with the main irrigation channels.

81. As per Irrigation Department, water availability for the Warsak Left bank Canal System

is120 Acre/Cusecs which seems to be enough to feed the proposed command area.

Agriculture study including crop water requirement carried out under this subproject

reveals that the allowance kept by the Irrigation Department is sufficient and with

execution of this subproject the present irrigation intensity will increase from 108% to

150%.

82. The subproject is divided into two (02) numbers of chunks totaling command area of

926 ha. The subproject includes lining of watercourses by using parabolic type-D

segments, Type-E segments, and PCC channel at some locations including allied

structures (Nuccas, Culverts and Washing pads). Total length of watercourses network

in On-Farm Water Management Works under this subproject is estimated to be 64.647

Km.

83. The total project cost is estimated to be Rs. 238.749 million and is anticipated to take

15 months period to complete. The results of the economic analysis show that the

project is economically viable (EIRR 16.53 %). The financial analysis also indicates the

safe investment with FIRR as 14.27 %.

84. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it does not involve

permanent land acquisition. No indigenous people or women headed households are

found in the subproject area. Safety of public and workers, security problems, risk of

communicable diseases, vector borne diseases etc. are of temporary nature which can

be mitigated through well managed operations. Expected benefits of the subproject are

Page 43: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 36

development of land through irrigated agriculture and creation of job opportunities

particularly for the local population.

85. All the anticipated adverse environmental impacts of the project can be mitigated,

temporary in nature and localized. There is no environmentally sensitive or

archaeological site falling within project area of influence. The REA Checklist defines

this subproject in category “B” as per ADB guidelines categorization.

86. Contractor is bound to develop Site Specific Environmental Management Plan

(SSEMP), Traffic Management Plan, Solid Waste Management and Material

Management Plan, Occupation Health and Safety Plan etc. before starting the

construction activities and to ensure that no damage is done to the wildlife, public

infrastructure and local culture, customs, and traditions.

87. This subproject has been completed for civil works and the overall environmental

safeguard performance of the said subproject was rated satisfactory while the details

are provided in Annex-1.

Page 44: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 37

CAD of Warsak LBC Location Map

Page 45: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 38

2.2.3 Construction of Tabai Dam

88. The Tabai Dam is proposed on Tabai Khwar of Tehsil Landi Kotal of Khyber district.

Tabai Dam sub project site is located at a distance of 43 km from Ali Masjid through

paved road and about 60 Km from district headquarter Jamrud. The proposed Tabai

Dam is located at coordinates 70.9715 E & 33.9977 N.

89. A 15 m high and 49.50 m long Tabai concrete gravity Dam with reservoir capacity of

0.206 Mm3 and spillway flood capacity of 95 m3/sec is proposed at Tabai area of

Khyber district to collect water from the khwar and convey it to the barrani command

area. Culturable command area of 50 ha will be irrigated at cropping intensity of 120 %

and design discharge of 14.64 lit/sec. Total length of irrigation network is 2.75 km.

90. The project cost is estimated Rs. 153.44 million and anticipated to take 18 months

period to complete. The results of the economic analysis show that the project is

economically viable (EIRR 7.27 %). The financial analysis also indicates the safe

investment with FIRR as 5.64 %.

91. The subproject, based on Rapid Environmental Assessment (REA), is categorized as

“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some

disturbances to the local environment during execution like material dumping,

machinery work; borrow material, camp areas, link roads and necessary facilities for

the staff / labour to be engaged for the subproject. All the anticipated adverse

environmental impacts of the subproject are mitigatable, temporarily in nature and

localized which can be mitigated through implementation of EMP.

92. Contractor is bound to develop Site Specific Environmental Management Plan

(SSEMP), Traffic Management Plan, Solid Waste Management and Material

Management Plan, Occupation Health and Safety Plan etc. before starting the

construction activities and to ensure that no damage is done to the wildlife, public

infrastructure and local culture, customs, and traditions.

93. This subproject has been completed for civil works and the overall environmental

safeguard performance of the said subproject was rated satisfactory while the details

are provided in Annex-1.

Page 46: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 39

Map showing location of Tabai Dam

Page 47: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 40

Substantially Completed Sub Projects

Sr. No Sub Project District Completion

Period

1. Shangade Weir Khyber

Completed and

reported in 7th

SAEMR July-Dec

2020.

2. Shunga Weir Bajaur

3. Nailai Kas Bajaur

4. Damano Weir Bajaur

5. Kat Gala Irrigation Scheme Bajaur

6. Maddar Irrigation Scheme Mohmand

7. Jay Dam Mohmand

Completed and

reported in 8th

SAEMR Jan-June

2021.

8. Ganjyano Danish Kool Infiltration

Gallery

Mohmand

9. Mundara Weir Mohmand

10. Badi Samoor Weir Bajaur

11. Lar Dand Weir Bajaur

12. Daman Lift Irrigation Bajaur

13. Shukrata Infiltration Gallery Bajaur

14. Chepatra Weir Bajaur

15. Dawawo Weir Bajaur

16. Derakai Weir Bajaur

17. Lara Dandokai Weir Bajaur

18. Hayatai Weir Bajaur

19. Serai Bazar Shah Mohmand

Page 48: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 41

20. Haji Lawang Kas Bajaur Completed during

the reporting

period i.e., July-

December 2021

(9th SAEMR)

21. CAD of Warsak LBC Mohmand

22. Tabai Dam Khyber

2.3 Project Contracts and Management

94. Implementing Agency (IA) for FWRDP is responsible for the implementation of

environmental management and monitoring requirements and procedures for the

project to comply with ADB`s Safeguard Policy Statement (2009). Environmental

Assessment and Review Framework (EARF), prepared and approved for FWRDP,

provides guidelines for environmental management and monitoring of the project. The

objective of the EARF is to establish systems and functions that will ensure that

conditional ties are built into each initiative at its design stage such that through

reconstruction, improved and environmentally sustainable structures are built that have

better resistance to natural calamities, particularly floods. EARF also requires ensuring

that all the environmental mitigation measures proposed for the design phase are

incorporated in the design and included in the contract documents.

95. Khyber Pakhtunkhwa Planning and Development Department (P&DD) is the

Implementing Agency (IA) for FWRDP, which has established Project Management Unit

(PMU) particularly dedicated for this project. Under PMU an Environmental and Social

Management Unit (ESMU) is established to oversee environmental planning,

management, and monitoring of the subprojects under FWRDP. PMU has appointed

Design and Construction Supervision Consultants (DCSC) as “The Engineer” who are

responsible for the environmental planning, management, and monitoring of the

subprojects.

96. Environment and Social Management Unit (ESMU) under Project Management Unit

(PMU) is responsible for environmental and social safeguard planning, compliance, and

monitoring. ESMU consists of Environmental Officer, Social Development and

Resettlement Officer. The ESMU is responsible for ensuring that the provisions of

IEEs/EMPs are implemented. In addition, it is also responsible for coordination with

ADB, EPA, Agriculture, Forest and Wildlife departments, NGOs/CBOs and other

public/private sector organizations.

97. PMU has appointed Design and Construction Supervision Consultants (DCSC) for the

design and construction supervision of the subprojects. DCSC is responsible for the

preparation of environment and social safeguard plans and documents besides

undertaking environmental and social safeguards monitoring. DCSC kept positions of

an Environment Specialist to perform these activities. The specialist is assisted by three

Page 49: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 42

Environment Inspectors to undertake environmental monitoring in the field and a Social

Inspector to oversee social and gender aspects of the subprojects. Environmental

Inspectors, under the guidance of Environment Specialist is responsible for

environmental compliance monitoring as per proposed mitigation measures.

98. ADB Safeguard Specialist is responsible for explaining policy requirements to DCSC,

helping them to meet those requirements, building capacity, and monitoring

implementation of agreed safeguards.

2.3.1 Coordination amongst Contractor, Owner, Lender

99. Project Management Unit (PMU) has made IEEs/EMPs of subproject as part of contract

agreement of contractor under general clauses. Contractor must abide these clauses

to ensure implementation of IEEs/EMPs in their entirety. DCSC must ensure

environment and social safeguard compliance and impact monitoring through the

contractor. ESMU orientated DCSC and contractors on environmental and social

safeguard compliances and monitoring in progress review meetings and during field

inspections. ESMU also delivered guidelines for environmental and social safeguards

monitoring of subprojects to DCSC and the contractors. Furthermore, ESMU undertook

monitoring visits of subprojects to assess the progress on environmental monitoring and

environmental management practices and advised contractor to ensure all

environmental compliances.

100. DCSC has reported progress on IEEs/EMPs implementation through its Monthly

Progress Reports. PMU prepares and submits Quarterly Progress Reports (QPRs) on

environment and social aspects to ADB. PMU holds progress review meetings

periodically wherein DCSC and contractor participate and give updates on

environmental compliance monitoring. PMU provides guidance to DCSC and

contractors to resolve environmental issues and to streamline environmental monitoring

and environmental management activities.

101. A good working relationship is being maintained between the contractors and DCSC

during the execution of the subprojects. Training workshops are arranged by the

Environment Inspectors on site for the capacity building of the contractors and their

relevant staff. They are briefed on updating the environment monitoring checklists by

following IEEs/EMPs. Contractor is bound to submit these checklists to DCSC on

weekly basis. Environmental Inspectors undertake site visits of contractor’s camps and subprojects sites and discuss measures for improvement in environmental safeguards

with contractors and their staff.

102. The contractor will be responsible for execution of construction activities and for

environmental protection through their field staff. The contractor is subject to

environmental protection liabilities under national environmental laws, ADB’s Environmental Safeguards, project IEE/EMP provisions and under their contract with

Page 50: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 43

PMU P&DD Khyber Pakhtunkhwa. The contractor is also responsible for

communicating environmental & social information and training of staff in all aspects of

the SSEMP. The details of contractors are as follows:

Details of Contractors

District

Project Contractor Project Manager/

Focal Person

HSE Site Inspector/

Environmental Manager

B

aja

ur

Dis

tric

t

Kharkai Weir (Remaining Works)

M/s MBCC Builders & PMC JV.

Wazir Ali Cell

03018184462 03465903438

Email:[email protected]

Mr. Muhammad Imran

0300-5756717

imranhanibest@

gmail.com

Haji Lawang Kas Lift Irrigation

M/S PMC JHK JV Construction Company

Mr. Tahir Khan

0335-9284500

Email:jhkconstructi

[email protected]

Mr. M. Yasir 03445151887

[email protected]

Khar Canal Sub Surface Infiltration Gallery

M/S PMC JHK JV Construction Company

Mr. Tahir Khan

0335-9284500

Email:jhkconstructi

[email protected]

Mr. M. Yasir 03445151887

[email protected]

CAD of Raghagan Dam

M/s National RCC

Works (Pvt) Ltd.

Mr. Farooq

0333-5023345

national_rcc_works

@yahoo.com

Mr. Haseeb Khan

0342-8960575

[email protected]

Mo

hm

an

d D

istr

ict

Saro Shah Weir

M/S PMC JHK JV

Construction

Company

Mr. Zulfiqar Khan

0333-5946261

Email:jhkconstructi

[email protected]

Mr. Zareen Khan 03215620578 Email: [email protected]

CAD of Warsak Left Bank Canal

M/s Ali & Co. Mr. Abuzar Ali

Cell: 03329950432

Email:

abuzarali964@gma

il.com

Mr. Abuzar Ali

Cell:

03329950432

Email:

abuzarali964@

gmail

CAD of Khurshid

Dam

M/s MBCC Builders &

PMC JV

Wazir Ali Cell

03018184462 03465903438

Email:wazir338@g

mail.com

Mr. Niazat Khan Cell: 03028885656, 03455233018 [email protected]

Page 51: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 44

K

hyb

er

Dis

tric

t

Tabai Dam M/s Tribal Global Construction (TGC) Pvt Ltd.

PM Abid Azeem Cell: 03102679610 Email:

[email protected]

m

Mr. M. Jawad 03319100621 Email:

jsm10928jawa

[email protected]

Bar Kas Dam

M/s Tribal Global Construction (TGC) Pvt Ltd.

PM Nawab Khan Cell: 03329898608

[email protected]

m

Mr. Gul Hayat 03426067561

tgcwazir@gma

il.com

Magoo Dand Dam

M/s National RCC Works (Pvt) Ltd.

PM Altaf Khan Cell: 03335756596 Email:

national_rcc_work

[email protected]

Mr. Akhtar Ali 03472813701

akhtaralikhan2

[email protected]

Bada Khel Weir

M/s New Malik Afridi &Co.

PM Syed Ameer Shah Cell: 0333 9042554

Mr. Syed Ameer Shah Cell: 0333 9042554

Neeli Tangi Weir

M/s Habib Khan Builders

PM Imad Khan Cell: 03339263663

masroorhabib6@g

mail.com

PM Imad Khan Cell: 03339263663 [email protected]

Tarkho Kas Weir

M/s Habib Khan Builders

PM Imad Khan Cell: 03339263663

masroorhabib6@g

mail.com

PM Imad Khan Cell: 03339263663 [email protected]

Tor Dara Weirs

M/s Habib Khan Builders

PM Imad Khan Cell: 03339263663

masroorhabib6@g

mail.com

PM Imad Khan Cell: 03339263663 [email protected]

2.4 Project Activities during Current Reporting Period

103. The SSEMPs of Neeli Tangi, Tarkho Kas and Tor Dara weirs were submitted by the

contractor and reviewed and approved by DCSC and PMU.

104. In total 45 meetings with contractors have been arranged and a total of 82 site

inspections and audits were paid by DCSC and PMU while 50 trainings were delivered

to contractors’ staff till December, 2021.

105. A total of 34 subprojects construction contract were awarded where twelve (12)

subprojects are under construction phase in three Districts namely Bajaur, Mohmand

and Khyber. While twenty-two (22) subprojects are completed for civil works as shown

in Exhibit 30. Details of physical activities are provided under next headings.

Page 52: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 45

2.4.1 Bajaur District

106. Four (04)2 subprojects are under construction in Bajaur District while 14 subprojects are

substantially completed as per site requirements. Their physical progress as of June

2021 is presented in Exhibit below:

2 Kamar Ragha Dag subproject is being executed as VO of CAD of Raghagan Dam subproject

Page 53: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 46

Physical Progress of Sub Projects in Bajaur District

S.No

Name of Sub-Project

Contractor Name CCA

(Ha)

Commencement Date

Completion Date

Revised Completion Date

Physical Progress

(%)

Structural Progress

[Executed/Total Scope]

Weir/Gallery

(%)

Irri. Channel (KM/KM)

OFWM

(KM/KM)

Remarks

1 Kharkai Weir

M/s Rustam Khan & Co

126

11-Sep-17 16-Aug-18 23-Aug-19 39%

90%

0.73/2.028 (36%)

0/6.3 (0%)

M/S MBCC 15-April-21 15-Dec-21 67% 0% 2.62/2.92

(89%) 3.9/6.3 (62%)

Work is in progress

2 Khar canal M/S PMC-JHK (JV)

154

25-Jul-19 07-Aug-20 Jan 24,2021 Ld.’s already recommended

57.5% 99.5% 3.15/7.0 (45%)

2.2/6.846 (32%)

Dead-Slow Progress

3 CAD of Raghagan Dam M/s National RCC Works Pvt Ltd 1017 16-Apr-20 15-Oct-21 28th Feb 2020 45%/100% - 22.815/37.7 (60.40%)

26.49/43.6(61.80%)

Work is in Progress

* Kamar Ragha Dag subproject is being executed as VO of CAD of Raghagan Dam subproject

Page 54: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 47

2.4.2 Mohmand District

107. Two (02) subprojects are under construction in Mohmand District while six (06) are substantially completed. Their physical progress as December 2021 is presented in the following Exhibit:

Physical Progress of Sub Projects in Mohmand District

S.No Name of Sub-

Project Contractor Name

CCA

(Ha)

Commencement

Date

Completion

Date

Revised

Completion Date

Physical

Progress

Structural Progress

[Executed/Total Scope]

Weir/ Gallery/ Dam

(m/m)

Irri. Channel

(KM/KM)

OFWM

(KM/KM)

1 Saro Shah M/S PMC-JHK (JV) 100 25th -Jul-19 24th -Jul-20 22nd February

2021 79%

30 m (Weir)

(100%).

2.2/2.9

(75%)

4.2/4.2

(100%)

126 No of panel

installed at site.

2 CAD of Khurshid

Dam

M/S MBCC & Builders-

M/s PMC (Joint Venture) 104 29th December 2020 29th December 2021 55%

Multi Cell Cause Way

Concrete Works

(RCC G-20)

655/825.96 m3

(79%)

PCC(G-10)

60/81.23 m3

(74%)

PCC(G-20)

200/309.54 m3

(64%)

Plum Concrete

0/897.71 m3

(0%)

0.700/3.740

(2.1 +1.640)

(19%)

Contractor is lagging

behind the actual

progress.

Type E

3.4/4.486

(75%)

(SWC1 0.150)

(SWC2 0.190)

SWC3 0.200)

Page 55: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 48

2.4.3 Khyber District

108. Six (06) subprojects are under construction in Khyber District while two subproject (Shangade Weir and Tabai Dam) is completed. Their physical progress as of December 2021 is presented in the following Exhibit:

Physical Progress of Sub Project in Khyber District

S.No Name of Sub-Project Contractor Name Commencement

Date Completion

Date

Physical Progress

(%)

Structural Progress [Executed/Total Scope]

REMARKS

Dam (m/m)

Irri. Channel (KM/KM)

OFWM

(KM/KM)

Inspecti-on

Hut

1 Bar Kas Dam M/S Tribal Global Construction 14-July-2020 14-Jan-2022 64.4% 64.1% 98.6% 18%

89.6%

Expected to be completed in time.

2 Magoo Dand Dam M/s National RCC Works 1-october-2020 31-March-2022

48.65%

43.86% 45% 2%

25.5%

• Social issue at main irrigation channel was resolved during a joint (R.E +PIU + T/L Designer) visit to the site on Friday dated Dec 17, 2021.

• The progress is lagging

3 Bada Khel Weir M/s New Malik Afridi & Co 16 February, 2021 15 February,

2022

50%

95 44% 35% -

The works are partially resumed on 28

Dec 2021. Delivery Pipe encasement & Sumps are

remaining.

Water Pressure testing is conducted for HDPE Delivery pipe on 28 Dec 2021.

RD.0+509 – RD. 0+820

4 Neeli Tangi Weir

M/s Habib Khan Builders

22 September, 2021 22 June, 2022

11.5 %

- - - -

• Mix design Cylinder for G-10, G-15, G-20 and G-30 has been casted.

• Steel Sample submitted for testing.

• Jointly survey of Neeli tangi COMPLETED.

• Excavation of Neeli Tangi Weir COMPLETED.

• Tarkho kas, Tor Dara and Natu Khel in Progress.

• Neeli Tangi excavation of Channel 2 in Progress.

• Tarkho kas excavation of channel in progress

5 Tarkho Kas Weir 22 September, 2021 22 June, 2022

3.02%

- - - -

6 Tora Dara Weir 22 September, 2021 22 June, 2022

1.4 %

- - - -

Page 56: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 49

2.5 Description of Any Changes to Project Design

109. So far, no major change has been made to the project design.

2.6 Description of Any Changes to Agreed Construction Methods

110. No changes have been made to agreed construction methods.

Page 57: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 50

3 ENVIRONMENTAL SAFEGUARDS ACTIVITIES

3.1 General Description of Environmental Safeguards Activities

111. Environment Specialist of DCSC developed weekly environmental monitoring

checklists (see Annex-7 A) for environmental compliance of the subprojects. This

checklist is based on the recommended mitigation measures given in the EMP for

environmental safeguard at different stages of the subprojects. Contractors were

orientated how to fill out the checklist. A checklist for the Semi-Annual Environmental

Monitoring Report has also been formed to analyse the follow up of the ongoing

subprojects (see Annex-2).

112. Environmental Inspector of DCSC conducted environmental safeguard trainings of

contractor’s staff and workers on each subproject with the purpose to build capacity of the staff in environmental compliance monitoring and in ensuring environmental

safeguards for the subprojects. These trainings focused on EMPs of the subproject,

environmental monitoring checklists, environmental monitoring activities and Health,

Environment and Safety (HSE) of staff and workers. Knowledge on potential hazards

on the site and procedures to avoid such hazards and actions in case of any

incident/accident were communicated to contractor’s staff and workers. Environment Specialist of DCSC has followed up these trainings by assessing the capacity of

contractors’ staff and workers during site visits.

3.2 Site Audits

113. Contractors are supposed to conduct internal audits and review by their own staff to

ensure a safe, healthy, and secure environment, both physically and behaviourally, for

workers, equipment, property, visitors, and the public. DCSC has undertaken site

inspections of all under execution subprojects. The findings of these inspections are

being updated regularly in monthly environmental monitoring reports. Contractors are

advised to submit weekly environmental monitoring checklists to DCSC and implement

the environmental compliance activities in accordance with the approved IEEs/EMPs.

Contractors are improving their environmental compliance, yet they slack in some

areas. To ensure implementation of EMP the contractors were asked to nominate their

focal persons/site inspectors who will be responsible for environmental safeguards

implementation for weir sites while for dams’ sub-projects the contractors have

dedicated HSE Managers in their staff. The nominated site inspectors were trained on

EMP/SSEMP implementation and directed to submit weekly checklist regularly to

DCSC as previously weekly checklists were not submitted on regular basis.

114. Environmental Inspectors of DCSC carried out field visits of all subprojects on regular

basis. During these field visits meetings are convened with the contractors' staff and

workers, visual observations and photographs are taken and key findings are discussed

with the concerned engineering staff and the contractors. Recommendations are

communicated to the contractor to address environmental issues and non-compliances

Page 58: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 51

on all the subprojects. Corrective Action Plan (CAP) is revised for all the subprojects in

consultation with the contractor’s staff.

115. For the purpose of environmental audit, Mr. Ihsan Afridi, Mr. Lehaz Imran and Mr. Altaf

Hussain (Environmental Inspectors) from DCSC visited all the under-construction sub

projects in district Khyber, Mohmand and Bajaur. By strengthening the environment

team of DCSC the environmental compliance status has been improved during the

current reporting period.

116. As already reported during the previous eight SAEMRs, the environmental guidelines

were being followed. However, the contractors have willingness to follow the

environmental guidelines and the environmental team of DCSC is continuously working

on the capacity building. Some of the findings of the recent environmental audit are as

follows:

a) Proper drainage system has been constructed for water at Magoo Dand Dam.

b) Proper oil storage areas have been constructed for oil storage at sites and

additional cross drainage provided as per SSEMP.

c) The drivers and mechanical staff have been trained to change the mobile oil

safely and speed limit observation to minimize dust.

d) Trainings have been provided by the contractor with respect to prevention and

control of COVID-19 specifically on ADB suggested SOPs.

e) Workers were using personal protection equipment’s. The construction areas were fenced.

f) Weekly Checklist are submitted by the contractors of the diversion weirs on

regular basis.

g) All required documents e.g., IEE, SSEMP and GRM are available on sites.

h) HSE managers have been hired for all small dams’ sites.

i) Water sprinkling is done regularly on dust prone areas where the dry, loose

dirt picks up in the wind.

j) Collecting Kitchen waste at separate bins and disposing of in a pit at

designated area/s has been improved at all under construction sites.

k) Construction equipment and machinery is fitted with silencers and maintained

properly.

l) Surface water or ground water contamination, due to oil spillage or solid

waste, has not occurred at any sites.

m) No noise level exceeding the permissible NEQs limits was recorded at any

under construction site.

Page 59: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 52

n) During the reporting period, no major grievances were recorded. Contractors

are addressing the issues in consultation with PIU and DCSC. Other minor

onsite grievances are being addressed in consultation with local communities

and village chiefs.

o) There are no damages to houses or shops at any site.

p) No damage to Archaeological /Religious/Cultural or Historical sites.

q) First Aid Kits are available at construction sites.

117. The corrective action plan and trainings brought major change in the behavior of

contractors. As a result, environmental compliance is seriously considered in project

execution. Site inspectors has been trained and SSEMPs are being developed for each

subproject. The implementation of SSEMP and further trainings is bringing major

change in the behavior of the contractor’s staff towards environment friendly construction of all the sub projects. The contractors have assured they will not harm the

local environment and will take all the necessary steps for the protection and

conservation of natural environment and will make sure the health safety of workers

and local community.

3.3 Issues Tracking (Based on Non-Conformance Notices)

118. The overall environmental progress of almost all of the subprojects improved during this

reporting period. The total average compliance status was 91%, which is calculated on

the basis of observation checklist attached as Annex-2 and shown in Exhibits 32, 33

and 34 for District Mohmand, Bajaur and Khyber respectively.

Environmental Compliance %

Saro Shah CAD Warsak CAD Khurshid Avg

Conformance % 91 96 96 95

Minor Nonconformance %

9 4 4 5

Major Nonconformance %

0 0 0 0

Overall conformance Level of All Sub-Projects at District Mohmand

Environmental Compliance %

Kharkai Haji Lawang

Kas Khar Canal CAD Raghagan Avg

Conformance % 89 89 84 95 89

Minor Nonconformance %

11 11 16 5 11

Major Nonconformance %

0 0 0 0 0

Overall conformance Level of All Sub-Projects at District Bajaur

Page 60: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 53

Environmental Compliance %

Magoo Dand Dam

Bar Kas Dam

Tabai Dam

Bada Khel

Neeli Tangi

Tarkho Kas

Tor Dara

Avg

Conformance % 96 96 96 88 84 86 86 90

Minor Nonconformance %

4 4 4 12 16 14 14 10

Major Nonconformance %

0 0 0 0 0 0 0 0

Overall conformance Level of All Sub-Projects at District Khyber

The overall average major non-conformance is 0% while minor non-conformances are

9%. The overall conformance level of the project and all subprojects is presented in Exhibits above.

Project Major and Minor Non-Conformance Level

119. The major issues opened during this reporting period were

i) Weekly Checklist report is not being submitted by contractors of diversion weirs on

regular basis.

ii) Barricading the construction sites

iii) Lack of PPE’s

iv) Scarcity of Safety/ caution sign boards at weir sites only.

v) No record of water consumption present at any site.

120. Issue no i. is closed as the contractors submit weekly checklist on regular basis. Site

fencing has been done by the contractors. Beside these contactors have provided the

appropriate PPEs to the labours as per agreed corrective action plan provided to them.

Contractors were directed to keep proper documentation of water consumption. The

contractors were also directed to place safety sign boards. The overall situation of sites

Page 61: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 54

was satisfactory and the issues have been resolved to a greater extent and non-

compliances are converted into compliances.

Summary of Issues Tracking Activity for Current Period

3.4 Trends

The information from previous period reports and the current period information are

used to identify trends in conformance and issues. The percentage conformance status,

reference exhibits 32, 33 & 34, of the SAEMRs is being improved as shown in Exhibits

below:

SAEMR No. Environmental Compliance % Average

1st SAEMR 54%

2nd SAEMR 54%

3rd SAEMR 68%

4th SAEMR 73%

5th SAEMR 67%

6th SAEMR 75%

7th SAEMR 81%

8th SAEMR 86%

9th SAEMR 91%

Percentage Conformance of each SAEMR

Total Number of Issues for Project 5

Number of partially closed issues 1

Number of Closed Issues 4 Percentage Closed 91%

Page 62: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 55

Environmental Compliance Trend

121. Overall improvement is observed in environmental conformance but still needs efforts

to make it up to the mark. The status of main issues in each SAEMR period are

presented in exhibits below.

SAEMR Report No Issues in SAEMR % Issues Closed % Issues closed

late/open

1 25 44% 56%

2 12 52% 48%

3 14 45% 55%

4 11 49% 51%

5 13 47% 53%

6 10 30% 70%

7 20 45% 55%

8 16 87% 12%

9 5 91% 9%

Total No. of Issues in each Reporting Period

122. The percentage of issues which are closed late, i.e., not within the same SAEMR

reporting period or are still open (open issue off this SAEMR) is being decreased with

the passage of time and with the overall conformance level of the project. (Overall

conformance is already discussed in previous section). The trending of issues

54% 54%

68%73%

67%75%

81%86%

91%

1stSAEMR

2ndSAEMR

3rdSAEMR

4thSEMAR

5thSEMAR

6thSEMAR

7thSEMAR

8thSEMAR

9thSEMAR

Co

mp

lia

nc

e P

erc

en

tag

e

Environmental Compliance Trending

Page 63: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 56

presented in Exhibit below depicts that percentage of closed issued is being increased

and overall trends are positive.

Issues Trending

123. Copy of NCN’s for major Non-Conformances is provided in Annex-3.

3.5 Unanticipated Environmental Impacts or Risks

3.5.1 COVID-19 Pandemic

124. Coronavirus disease (COVID-19) is an infectious disease caused by a newly discovered

coronavirus. COVID-19 can affect your lungs and airways. Symptoms can be mild,

moderate, severe or fatal. Most people who fall sick with COVID-19 will experience mild

to moderate symptoms and recover without special treatment.

125. Construction processes are dynamic with significantly varying number of workers on a

construction project site from day to day. The workers coming from diverse

environments and working closely together increases the risk of exposure to COVID 19.

126. The COVID-19 outbreak represents significant health and safety risks that were not

anticipated at project appraisal stage and is thus not reflected in any of the project’s safeguards instruments, most importantly the environmental management plan (EMP).

127. In accordance with the Asian Development Bank (ADB) Safeguard Policy Statement

2009 (SPS) and the loan agreement between ADB and the borrower, the borrower is

required to assess implications of unanticipated risks and impacts under the project;

and to identify and implement necessary risk mitigation measures.

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0

5

10

15

20

25

30

1 2 3 4 5 7 8 9

Issues Trending

Issues in SAEMAR % issues Closed % issues closed late/open

Page 64: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 57

128. In response to the requirements of the SPS, as incorporated into the loan agreement,

to provide workers with safe and healthy working conditions, as well as minimize

adverse impacts and risks to the health and safety of local communities living near or

affected by, ADB-financed project, a project-level COVID-19 risk assessment was

conducted and all the contractors were instructed to update (or prepare) their respective

Health and Safety Plans (HSP) and Emergency Response Plans (ERP) as necessary.

As a result, ADB`s Project Officer was notified through letter and all the SSEMPs were

updated. Moreover, for unawarded subprojects a contract clause has been added in the

bidding document for contractors to comply with SOPs and adopt measures for

prevention and control of the COVID-19. The SSEMP of Khrakai Weir was updated with

respect to COVID-19 after re-award of the subproject to the new contractor. The Project

Officer of ADB was notified through 2nd notification about the updating of SSEMPs.

129. In October, 2021 ADB’s suggested SOPs have been received for strict compliance on

under construction subprojects sites after which training sessions were arranged by the

Environmental Inspectors of DCSC on the implementation of these SOPs for

contractors’ staff and labour.

130. The workers and staff are fully aware of the risk of COVID-19 and adopted all the

possible prevention measures provided in the updated SSEMPs. None of the worker

have been reported with COVID-19 symptoms neither any worker with illness was

observed during the site visits.

Page 65: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 58

4 RESULTS OF ENVIRONMENTAL MONITORING

4.1 Overview of Monitoring Conducted during Current Period

131. Environmental monitoring consists of two types. The first type requires field sampling

and laboratory analysis for example water quality, air quality and noise levels. The

second type refers to visual inspections of such things as soil erosion, restoration of

vegetation, solid waste disposal and so on. The field sampling and laboratory analysis

has been conducted, including air, noise, and water quality during the current reporting

period. Environment Inspector of DCSC undertook field inspections on fortnightly basis.

Environmental Specialist of DCSC also inspected subprojects on periodical basis.

DCSC prepared Corrective Action Plans in consultation with contractors.

132. The environmental monitoring was carried out by DCSC to assess actual nature and

extent of key impacts and the effectiveness of mitigation and enhancement measures

outlined in the Initial Environmental Examination (IEEs) and Environmental

Management Plans (EMPs). The IEEs prepared for subprojects includes Environmental

management plan (EMP) that addresses the potential impacts. (Annex-6). Mitigation

measures are considered so that the projects are designed, constructed, and operated

in compliance with applicable national and provincial laws and regulations and meets

the requirements of ADB SPS, 2009. Contractors are provided with monitoring checklist

and Urdu brochures for the better understanding of the Environment. (ANNEX-7[A&B]).

The overall status of Environmental Compliance was monitored and presented as

Annex 2.

4.2 Trends

133. Keeping in mind the construction volume the impacts on water quality, air quality and

noise is negligible and no major change was noticed after analysing the test results.

The results of monitoring checklist indicate that EMP compliance is increasing as

already discussed above.

4.3 Summary of Monitoring Outcomes

134. The Impact monitoring of some environmental parameters are discussed hereunder:

4.3.1 Instrumental Monitoring

135. The instrumental monitoring of air quality and noise as well as water testing has been

conducted at sites.

4.3.2 Noise Monitoring

136. Noise monitoring on construction sites is being carried out to assess impacts of noise

level generated to curtail its adverse impacts on workers, nearby communities, and

fauna of the area. For this purpose, noise level monitoring is being carried out by using

Page 66: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 59

digital noise level meter to know the noise value at subproject locations. The field

instrumental Monitoring results reveals that the noise results is within limits of NEQS

and WHO guidelines.

137. Contractors are advised to keep their machinery in good condition and provide

personal protective equipment’s (PPEs) like ear plugs to the working staff at noise generating sites. Speed of the trucks and other vehicles used for construction activities

were to be controlled and the construction activities were to be limited to daytime only.

138. The environmental monitoring conducted during December 2021 deduces that no noise

or vibration related complaints from public or workers were registered at any of the

subproject site. However, Environment team of DCSC has reinforced contractor staff to

adopt mitigation measures to reduce the impact of noise and vibration as delineated in

EMPs. DCSC environment team repeatedly advised the contractors to keep their

machinery in good condition and provide personal protective equipment (PPE) like ear

plugs to the working staff to worn at noise generating sites. DCSC advised the

contractor to provide PPEs to workers. Contractors of all subproject’s sites were

advised to control vehicle speed and restrict construction activities to daytime only.

DCSC advised the contractors to carry out noise monitoring by using noise meter on

regular basis. Noise testing was carried out at sub projects where construction activities

were in progress.

139. Results of instrumental monitoring of noise are given in the exhibit below:

Noise Testing Results

4.3.3 Air Quality Monitoring

140. The ambient air of an area may be polluted due to emissions of Carbon Oxides (COX),

Sulphur oxides (SOX), Nitrogen Oxides (NOx) and Particulate Matter (PM10). The

industry that may produce high emissions of gases and other toxic elements is not

present in the any of the subproject area so only dust and smoke emissions were to be

S. No Sub Project Result NEQS/WHO

(dB)

1 Magoo Dand Dam 46.19 75

2 Bar Kas Dam 50.07 75

3 Tabai Dam 48.09 75

4 CAD Raghagan Dam 49.27 75

5 Kharkai Weir 52.72 75

6 CAD Warsak LBC 50.37 75

7 CAD Khurshid Dam 48.78 75

Page 67: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 60

monitored visually by the contractors during transportation or use of excavators etc.

Some pollution might be caused due to dust emission which was to be monitored.

141. Contractors of all subprojects were guided to adopt measures helpful in controlling air

quality deterioration in the subproject activity areas like regular water sprinkling to

reduce the air dust emissions and regular tuning of vehicles maintaining the equipment

properly to minimize the smoke and other gaseous emissions. The objective was to

minimize the airborne particulate matter, dust pollution and fumes of vehicular

emissions into the atmosphere to avoid negative impacts on the health of construction

workers, residents, and nearby vegetation.

142. Visual observations were made to monitor regular water sprinkling at dust prone areas

during the construction activities and to monitor the vehicular emissions to minimize the

smoke emissions. Contractors ensured water sprinkling at most of the sites. Contractors

are advised to regularly tune and check up their construction vehicles and machinery

to comply the vehicular exhaust emission levels. Contractors regularly tune their

vehicles at all the subproject sites. Contractors are advised to ensure use of masks and

helmets by workers. Also, they were advised to transport excavated material by using

covers on the dumpers to avoid spills.

143. Air quality testing was carried out at sub projects where construction activities were in

progress. The air quality results indicate under permissible limits. The results of

instrumental monitoring are presented in exhibit below;

Page 68: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 61

Air Quality Test Results

S. No Parameters Unit Magoo Dand Dam Bar Kas Dam Tabai Dam CAD Warsak LBC CAD Khurshid Dam CAD Raghagan Dam Kharkai Weir NEQS WHO

1 PM 2.5 ɥg/m3

5.4 3.6 6.3 7.2 5.4 7.2 5.4

15 ɥg/m3 25

2 PM 10 ɥg/m3

3.6 4.5 4.5 5.4 7.8 6.3 7.2

150 ɥg/m3 125

3 CO2

mg/m3

581 474 387 389 587 482 466

- mg/m3 --

4 CO

mg/m3

0.00 0.00 0.00 0.00 0.00 0.00 0.00

10 mg/m3

80 ɥg/m3

--

5 NO2 ug/m3

47.7 71.11 58.5 90.6 65.7 78.3 54

-- 40

6 SO2 ɥg/m3

0.00 0.00 0.00 0.00 0.00 0.00 0.00

120 ɥg/m3 125

7 NO

ɥg/m3

14.28 21.33 17.8 27.08 19.71 23.49 16.2

40 ɥg/m3 --

8 NOx ɥg/m3

61.98 92.46 75.6 118.4 85.41 101.79 70.2

ɥg/m3 --

9 O3

ɥg/m3

0.00 0.00 0.00 0.00 0.00 0.00 0.00

180 ɥg/m3

Page 69: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 62

4.3.4 Water Quality Monitoring

144. Subproject construction activities should not lead to pollution or contamination of

surface and groundwater in the subproject area knowing that contamination bears direct

effects on human health. Therefore, preventive measures are required to be taken to

save water sources. Contractors are guided to take measures at camp site to prevent

water pollution in the adjoining stream, water channel and in groundwater: Construction

of sewage system with septic tank to dispose of sanitary wastewater and lined wash

areas are the other measures contractors were asked to take to prevent pollution of

water. Furthermore, contractors are asked to avoid oils spills in subproject areas.

145. Environment staff of DCSC has observed no surface or groundwater pollution caused

by construction activities. Contractors tested surface and drinking water from certified

labs for physical, chemical and biological parameters. No water borne disease (gastro,

diarrhoea, etc.) has been noticed. Sewerage system/septic tanks at camp sites were

constructed. Contractors are advised to ensure operation and maintenance of drainage

system to avoid contamination of ground and surface water sources. Contractors are

also advised to avoid oil spill to protect ground water and surface water channels.

146. The samples of drinking water from contractors’ camp and surface water quality were

tested in December 2021. Almost all the results are under permissible limits according

to National Environmental Quality Standard (NEQS) and WHO guidelines. The

contractor has been advised to regularly carryout chlorination and or provide clean

drinking water to labour and staff from any other source. The results are given in the

tables below:

Page 70: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 63

*UO: Unobjectionable

Drinking Water Quality Results

S# Parameters WHO/NEQS Limits Magoo Dand Dam Bar Kas Dam Tabai Dam CAD Warsak LBC CAD Khurshid Dam CAD Raghagan

Dam Kharkai Weir

01 pH

6.5-8.5 7.89 7.91 7.71 7.96 8.01 7.79 8.01

02 Temp

- 08 C 08 C 08 C 08 C 08 C 07 C 07 C

03 Dissolve Oxygen

- 0 ppm 0 ppm 0 ppm 0 ppm 0 ppm 0 ppm 0 ppm

04 Turbidity ≤ 5NTU

2.21 3.21 4.21 1.51 2.53 3.31 2.03

05 E. Conductivity

NGVS 1498 1133 1678 1087 1056 947 1432

06 TDS

1000 mg/l 803 563 834 542 526 478 714

07 Color

< 15 TCU 0.0 0.0 0.0 0.0 0.0 0.0 0.0

08 Odor

Sensory evaluation Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable

09 Taste

Sensory evaluation Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable Unobjectionable

10 Total Alkalinity

< 500 ppm 150.2 97.2 110.2 97.1 96.1 193 129

11 Total Hardness

< 500 ppm 220 84.67 150.6 90.78 83.78 130 117

12 Calcium ≤ 250 ppm

119.7 42.0 87.1 43.3 40.3 47.03 45.3

13 Magnesium ≤ 250 ppm

44.9 12.6 22.6 14.1 11.1 22.90 16.90

14 Sodium ≤ 200 ppm

27.1 19.7 23.7 19.3 17.3 37.3 21.3

15 Potassium

NGVS 34.1 17.1 29.1 17.1 13.1 12.34 22.37

16 Sulfate ≤ 250 ppm

187.4 87.5 119.0 87.5 79.5 111.2 101.2

17 Chloride ≤ 250 ppm

44.2 09.9 29.2 11.7 09.7 27.8 22.8

18 Nitrate ≤ 50 ppm

17.2 7.2 14.2 7.2 6.2 11.8 9.8

19 Nitrite ≤ 3 ppm

1.07 2.00 2.09 1.00 1.89 1.79 2.01

20 Fluoride ≤ 1.5 ppm

1.89 0.76 0.89 0.78 0.97 0.91 0.79

21 Arsenic ≤ 2 ppm

0.007 0.004 0.002 0.000 0.000 0.002 0.000

22 Iron ≤ 2 ppm

1.06 1.01 1.01 1.00 1.03 0.63 1.10

23 Copper ≤ 0.01 ppm

0.87 0.56 0.56 0.56 0.56 0.21 0.03

24 E. coli

NGVS 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU

25 Fecal Coliform

0 CFU/100 ml 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU 00 CFU

Page 71: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 64

4.3.5 Soil Erosion

147. No damages to the agricultural lands due to borrow pits or soil erosion is observed so

far as mostly soil is obtained from local uplands from their owners who in return get their

agricultural land levelled. Still the contractors have been advised to proceed after written

agreements. Contractors are also advised to make complete line plans for excavation

and transportation showing the distance of the borrow pits from the construction sites

and to get them approved from RE of DCSC.

4.3.6 Natural Habitat Protection

148. The contractors are advised to avoid damaging the natural habitats and to replant the

damaged plants, if unavoidable, after construction. Also, the native wildlife and habitats

should not be disturbed. However, no tree has been cut during construction processes

on any of the subproject. Similarly, no native species are being disturbed due to the

construction activities.

149. Tree plantation cost is kept for each subproject under watershed management

component of the project. Tree plantation is in the process with the help of District Forest

Officers (DFO) of the three districts. As of 31st December 2021, plantation on 4475 ha

area has been completed. The overall implementation progress is 77% (Bajaur 2533

ha, Mohmand 1,427 ha and Khyber 515 ha) of revised target of 5,829 ha. Remaining

plantation is in progress and will be completed as soon as possible. District wise

watershed targets vs achieved are shown in below table;

District

Target (ha)

Original PC-I

Designed (ha)

Revised PC-I

%

Bajaur 2,816 2281 79.68%

Khyber 1,079 517 47.91%

Mohmand 720 1405 211.66%

Total 4,615 4203 91.07%

Watershed Management Status

150. Neither flora nor fauna were disturbed by the contractors at any of the subproject area

since the subprojects involve only weir/ lift irrigation sump and channels construction

which locate farer to wildlife habitats. Wildlife sanctuary does exist near any subproject

site. No hunting of birds and animal is reported. Continuous monitoring is being carried

out by environmental inspectors of DCSC to check any hunting activity or activities

damaging vegetation or wildlife habitat.

Page 72: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 65

4.4 Material Resources Utilisation

4.4.1 Current Period

151. The use of water in construction sites for human needs, is basically related to the

essential demands of employees of the construction site and these are preserved in

accordance with the labour laws. In the construction site, the human water

consumption, is for the following facilities: sanitary, housing, dining place, laundry, and

kitchen, when preparing meals.

152. The other major use of water is for the sprinkling of water at project site for compaction

and around the project site for dust control. Oil has been also used for project

equipment, like generators, machinery and vehicles. Consumption of Oil in gallon for

the reporting period is given in exhibit below:

Page 73: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 66

4.4.2 Cumulative Fuel Utilisation

153. Cumulative Fuel Utilization was also assessed, trends are uniform and do not show any exceptional changes.

Oil Consumption

Gallon Jay Dam Kharkai Shangade

Ganjyano Danish Kool

Shunga NailaiKas Mundara Badi

Samoor Lar

Dand Damano Daman

Lara Dandokai

Chepatra Hayatai Shukrata Kat

Gala Maddar

Serai Bazar Shah

Saro Shah

CAD Raghgan

Dawawo Bar Kas

Dam Tabai Dam

Magoo Dand Dam

CAD Warsak

CAD Khurshid

Bada Khel

Neeli Tangi

Tarkho Kas

Tor Dara

1st SAEMR 2522.843 607.5957 531.5142

2nd SAEMR 8949.0924 1452.946 2913.8177 396.2581 272.0972 248.322

3rd SAEMR 2169.272583 622.03 520.23 105.669 327.1 292.3 211.338 230.43 252.25 230

4th SAEMR 2050.314 200.05 600.5 100.2 312 290.25 400.25 250.98 300.6 500.5 200.5

5th SAEMR 2825.32 30.33 107.56 263.67 158.42 375.22 350.342 338.234 370.6 435.23 498.34 126.32 160.42 98.99 160.77 155.56 170 40.52 250

6th SAEMR 3532 0 45 165.8 114.8 168.23 265.88 481 247 415.43 512.22 198.86 120.33 60.55 178.67 215.48 168.78 215.65 350.66

7th SAEMR 2534.455 0 0 204.88 0 0 35 78 123 137 33.8 178,87 195,56 120.45 208.22 90.32 148.78 188.91 232.78 4825.32 540.22 6348.22 7578.45 2822.843

8th SAEMR 3870.487 0 243.76 20.66 67.89 250.34 23.54 263.44 270.89 233.5 219.17 260.67 270.33 5432.34 257.66 7843.23 8460.56 3400.45 570.87 461.98 20.34

9th SAEMR 563.76 183.34 7837 8426.56 8786.23 5160.88 4789.89 4576.23 170.33 6 3

Total 28,453.78 3,476.71 4,718.62 1,480.24 1,184.42 1,374.32 1,283.47 1,446.53 1,543.79 1,718.16 1,268.40 588.62 551.64 513.49 766.83 461.36 487.56 705.75 1,287.11 18,094.66 797.88 22,618.01 24,825.24 11,384.17 5,360.76 5,038.21 190.67 6.00 3.00 -

No physical Activity Started at site/ project completed

Page 74: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 67

154. No water consumption record was present at any site. However, the contractors are not

putting pressure on ground water table as in almost all subprojects the contractors are

relying on surface water from stream and springs.

Fuel Consumption in last 6 Months

Cumulative Fuel Consumption Trend

- 1,000.00 2,000.00 3,000.00 4,000.00 5,000.00 6,000.00 7,000.00 8,000.00 9,000.00

10,000.00

Kh

ark

ai

Sa

ro S

ha

h

CA

D R

ag

hg

an

Ba

r K

as

Da

m

Ta

ba

i D

am

Ma

go

o D

an

d D

am

CA

D W

ars

ak

CA

D K

hu

rsh

id

Ba

da

Kh

el

Ne

eli

Ta

ng

i

Ta

rkh

o K

as

To

r D

ara

9th SAEMR

0

5000

10000

15000

20000

25000

30000

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

Fuel Consumption

1st SAEMR 2nd SAEMR 3rd SAEMR 4th SAEMR 5th SAEMR

6th SAEMR 7th SAEMR 8th SAEMR 9th SAEMR Total

Page 75: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 68

4.5 Waste Management

4.5.1 Current Period

155. Currently, there are two types of waste at all sub-project areas.

a. Domestic waste from camps, offices, labours, etc.

b. Construction waste including hazardous waste from construction sites.

4.5.2 Cumulative Waste Generation

156. The waste generated from the cutting of earth is reused for back filling. The unused

excavated material is disposed of at designated sites. Negligible construction waste

including wire cutters, plastic and paper, etc. is generated at the site which is recycled

and reused in second market. Currently, all such waste is segregated disposed of

temporarily on designated sites, identified and demarked before construction for

disposal during construction activities. The Dumping sites/Disposal sites are identified

and approved by Environment Specialist of FWRDPC. The dumping site for each

subproject is shown on the maps attached as Annexure 10. Such waste is then removed

to be reused in second market on regular interval with the help of specified

subcontractors, assigned by each contractor.

157. Domestic waste is disposed of in low lying areas or depression on other side of sites,

where water becomes stagnant and becomes a breeding place for disease vectors like

malarial mosquitoes. This method is identified in IEE reports and also the general

practice of local municipality. Dumping waste material in these ponds achieve two

purposes: disposing off waste material and filling the pond to make the sites more health

friendly.

Solid Waste Generated at Sites

S.N# Sub-Project Solid Waste Generated in Kilogram per

day

Types of Waste Remarks

1 Kharkai Weir 1.9 Packaging bags, wood ply and food items etc.

Solid waste is

preferably reused

and disposed-off

at designated site.

2 Khar Canal Infiltration Gallery

4.5 Packaging bags, wood ply and food items etc.

-do-

3 CAD Raghagan Dam 13 Cement bags, wood ply and food items etc.

-do-

4 CAD of Khurshid Dam 05 Cement bags, wood ply and General Waste (plastics,

-do-

Page 76: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 69

polythene, packaging and kitchen scraps)

5 CAD of Warsak LBC 07 Cement bags, wood ply and General Waste (plastics, polythene, packaging and kitchen scraps)

-do-

6 Saro Shah 00 No activity

7 Bar Kas Dam 03 General Waste (plastics, polythene, packaging and kitchen scraps)

-do-

8 Magoo Dand dam 04 General Waste (plastics, polythene, packaging and kitchen scraps)

-do-

9 Bada Khel Weir 01 Cement bags, wood ply and food items etc.

-do-

10 Neeli Tangi Weir 01 General Waste (plastics, polythene, packaging and kitchen scraps)

-do-

11 TarKho Kas Weir 01 General Waste (plastics, polythene, packaging and kitchen scraps)

-do-

12 Tor Dara Weir 0.5 General Waste (plastics, polythene, packaging and kitchen scraps)

-do-

4.6 Health and Safety

4.6.1 Community Health and Safety

158. The safety of the local people is a major concern, due to which all the contractors were

advised to place safety signs (safety cautions, safety cones, safety tapes etc.) on site.

Campsite is established 500 meters away from the human settlements at all the

subprojects. Subproject signs are not properly placed at any site. Contractors have

ensured water sprinkling at all subproject sites. All Contractors are advised to ensure

proper water sprinkling and maintain the record. The contractors are also advised to

place safety signs for the protection of community from any incident. Traffic operations

are well on all subprojects since no complaint is received from the community in this

regard. Furthermore, no complaints have been received of damage to public/community

assets and infrastructure.

Page 77: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 70

4.6.2 Workers` Safety and Health

159. The awareness of contractors needed to be created for instituting safety procedures

during construction. Provision of proper safety equipment for the workers such as

helmets, goggles, masks, shoes and gloves etc needed to be provided to the workers

during construction activities. Other safety measures to avoid exposure to accidents

due to operation of construction, vehicle movements and machinery operations were to

be ensured.

160. The findings of monitoring activities reveal that contractor have provided Personal

Protective Equipment (PPEs) to the workers on all subproject sites. Contractors are

advised to ensure provision and utilization of PPEs on all the subprojects. First Aid kits

are available at most of the subprojects while ambulance is not available at any

subproject’s sites. However, the contractors have 4WD vehicles to deal with any kind

of emergency. Furthermore, Govt. hospitals as well as private clinics are available in

close vicinity to deal with any major injuries and health issues No accident/incident of

major nature is reported during July-December 2021.

Health and Safety Statistics

S.No. Sub Project Type of problem No of persons Remarks

1 Kharkai Weir Minor Injury (hand) 3 First aid provided

2 Khar Canal Infiltration Gallery

Minor Injury (Finger) 1 First aid provided

3 CAD Raghagan Dam

Fever and Minor injury of hand

6 First aid provided

4 CAD of Khurshid Dam

Minor Injury Finger 4 First aid provided

5 CAD of Warsak LBC

Minor cut in finger 5 First aid provided

6 Saro Shah 0

7 Bar Kas Dam Minor Injury hand 8 First aid provided

8 Magoo Dand dam Fever with symptoms of COVID-19

15 Opted for Self-quarantine at home. No test reports available

9 Bada Khel Weir Minor Injury leg 2 First aid provided

10 Neeli Tangi Weir Minor injury Finger 1 First aid provided

11 TarKho Kas Weir 0

Page 78: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 71

4.7 Grievances Redressal

161. Construction sites and labour camps are away from local community. There are no

houses in 500-meter vicinity of construction sites or labour camp. The contractor HSE

Managers are sensitizing the labours from time to time to take care of local norms and

culture. Beside this they placed grievances register at camp site to register local

communities’ complaints but till date no complaint has been received from the local

community. The contractor guided the drivers to keep speed limits of 30km/h to avoid

any unfair situations. In case if any unfair situation occurring at sites, the issues are

resolved on priority basis and will involve local Jirga according to the complexity of the

situation. Most of the complaints of communities is of social nature and dealt by PIU

and Sociologist of CSC jointly and reported in six monthly social monitoring report

submitted to ADB.

4.8 Training

162. The environmental and social unit of DCSC is comprising only one environmental expert

(intermittent basis) and one environmental and one social inspector. There is no HS

(Health and Safety) expert or trainer among the DCSC. Currently the DCSC provide

information and guidelines on all environmental safeguard related training activities to

the Contractor`s Environmentalist/HSE Officers, staff and labours. These include

trainings of nominated site inspectors, Contractors, HSE inductions for site workers,

guidelines on HSE training, risk assessment requirements before start of each activity,

etc. The site inspectors then provide the training on these issues to the staff and labour.

163. The site inspectors were nominated by the contractors who were trained by the

environment specialist of DCSC. These inspectors were specifically trained on

construction site inspections and weekly checklist monitoring, this will ensure

compliance of EMP/SSEMP in true letter and spirit.

164. The following exhibit shows the trainings provided during the reported period.

Details of Trainings

S. No Sub

Project Date

No. of Participants

Topic

Target Group

1 CAD of Warsak

LBC 01.07.2021 06 Work hazards and

heat stroke

Contractor’s Staff

2 Serai Bazar Shah 14.07.2021 05 Heat stroke

Contractor’s Staff

3 Bada Khel

Weir 21.07.2021 04 PPEs Contractor’s Staff

4 Magoo

Dand Dam 28.07.2021 05 Good House

Keeping Contractor’s Staff

5 Tabai Dam 07.07.2021 8 Fall from Height Contractor’s staff

Page 79: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 72

S. No Sub

Project Date

No. of Participants

Topic

Target Group

6 Bar Kas

Dam 13.07.2021 9

Solid Waste Management

Contractor’s staff

7 CAD

Raghagan 24.07.2021 8 PPEs Contractor’s staff

8 Kharkai

Weir 27.07.2021 5

COVID-19 Precautions and

Preventions Contractor’s staff

9 CAD

Raghagan Dam

12.8.2021 10 Waste material Contractor’s staff

10 kharkai 23.8.2021 06 PPE’s Contractor’s staff

11 Bada Khel

Weir 05.08.2021 07 Solid Waste Management

Contractor’s Staff

12 Magoo

Dand Dam 07.08.2021 05 PPEs Contractor’s Staff

13 Tabai Dam 24.08.2021 04 Excavated Material

Contractor’s staff

14 Bar Kas

Dam 27.08.2021 9 Fall from Height Contractor’s staff

15 CAD of

warsak left bank canal 09.08.2021 04

Work hazards and use of PPEs

Contractor’s Staff

16 CAD of khurshid

Dam 17.08.2021 05

Safety sign boards and use of safety

warning tape

Contractor’s Staff

17 CAD

Raghagan Dam

12.09.2021 12 PPEs Contractor’s staff

18 kharkai 18.09.2021 05 Housekeeping Contractor’s staff

19 Bada Khel

Weir 25.09.2021 06 PPEs Contractor’s Staff

20 Magoo

Dand Dam 17.09.2021 12 COVID-19 control

and Prevention Contractor’s Staff

21 Tabai Dam 28.09.2021 07 COVID-19 control

and Prevention Contractor’s staff

22 Bar Kas

Dam 28.09.2021 10

COVID-19 control and Prevention

Contractor’s staff

23 CAD of

warsak left bank canal 07.09.2021 06 House keeping

Contractor’s Staff

24 CAD of khurshid

Dam 16.09.2021 03 Work hazards

Contractor’s Staff

25 CAD

Raghagan Dam

28.10.2021 15 COVID-19 control

and Prevention Contractor’s staff

26 Kharkai

Weir 27.10.2021 05

COVID-19 control and Prevention

Contractor’s staff

27 Bada Khel

Weir 21.10.2021 06 Manual Handling Contractor’s Staff

28 Magoo

Dand Dam 14.10.2021 10 Work at height Contractor’s Staff

29 Tabai Dam 18.10.2021 07 Work at Height Contractor’s staff

30 Bar Kas

Dam 19.10.2021 10 House keeping Contractor’s staff

Page 80: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 73

S. No Sub

Project Date

No. of Participants

Topic

Target Group

31 CAD of Warsak

LBC 08.10.2021 07 COVID-19 control

and Prevention

Contractor’s Staff

32 CAD of

Khurshid Dam 21.10.2021 05

COVID-19 control and Prevention

Contractor’s Staff

33 CAD

Raghagan Dam

11.11.2021 13 Waste

Management, PPEs

Contractor’s staff

34 Kharkai 15.11.2021 9 PPE’s Contractor’s staff

35 Bada Khel

Weir 4.11.2021 06 PPEs Contractor’s Staff

36 Magoo

Dand Dam 24.11.2021 10 Solid Waste Management

Contractor’s Staff

37 Tabai Dam 28.11.2021 07 COVID-19 Prevention

Contractor’s staff

38 Bar Kas

Dam 28.10.2021 10

COVID-19 Prevention

Contractor’s staff

39

CAD of Warsak

Left Bank Canal 05.11.2021 05

COVID-19 Prevention

Contractor’s Staff

40 CAD of

Khurshid Dam 18.11.2021 06

COVID-19 Prevention

Contractor’s Staff

41 Neeli Tangi

13.12.2021 05 Excavation

Hazards Contractor’s Staff

42 Tarkho

Kas 14.12.2021 04 Excavation

Hazards Contractor’s Staff

43 Magoo

Dand Dam 20.12.2021 07 Solid Waste Management

Contractor’s Staff

44 Bar Kas

Dam 21.12.2021 10 Work at Height Contractor’s Staff

45 Tabai Dam 22.12.2021 4 Site Restoration Contractor’s Staff

46 Khar Canal

05.12.2021 5 PPE’s Contractor’s staff

47 CAD

Raghagan Dam

09.12.2021 17 Work at Height,

PPEs Contractor’s staff

48 Kharkai 06.12.2021 4 PPE’s Contractor’s staff

49

CAD of Warsak left bank

canal 09.12.2021 07 Covid 19

precautions

Contractor’s Staff

50 CAD of

Khurshid Dam 15.12.2021 04

Covid 19 precautions

Contractor’s Staff

Page 81: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 74

5 FUNCTIONING OF THE SSEMP

5.1 SSEMP Review

165. Contractors are required to prepare Site Specific Environmental Monitoring Plan

(SSEMP), including environmental management measures, risk assessment,

Environmental Management Plan (EMP), Emergency Response Plan (ERP), Borrow

Area Management Plan, Traffic Management Plan, Health Environment and Safety

Plan.

166. The contractors of the awarded subprojects were directed through letters to submit the

SSEMP reports 10 days prior to the commencement of physical work. In response to

the letter the SSEMPs of the subprojects mentioned in exhibit 2 have been submitted

by the contractors and approved by DCSC and ESMU.

167. It was observed that all the subprojects are implementing the measures proposed in the

EMP and SSEMP. This was mainly due to the fact that the contractor`s nominated staff

were trained on Environment, Health & Safety which in turn helped a lot in

implementation of mitigation measures proposed.

168. As these subprojects mainly involve soil/earthworks, dust suppression measures were

stressed upon by the DCSC staff. The contractors` staff was persuaded to maintain

good house-keeping and waste management.

169. The contractors were directed to revise their SSEMPs and include COVID-19 Health

and Safety Plan (HSP) and Emergency Response Plan (ERP) in accordance with

guidelines for construction site issued by the Ministry of Health, Govt. of Pakistan and

international good practices. All the SSEMPs were revised and submitted to ESMU

against which approval have been granted by ESMU and they were strictly directed to

implement it with true letter and spirit.

Page 82: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 75

6 GOOD PRACTICE AND OPPORTUNITY FOR IMPROVEMENT

6.1 Good Practice

170. In most workplaces, accidents are a nuisance for the worker and a headache for Project

Management Team. However, at construction sites, accidents have the potential to be

life threatening. With every new story about environmental disasters and trapped

labourers, construction sites become less and less appealing — even as the population

grows and demands new, updated structures increases. Regarded as one of the most

dangerous professions, construction work on the job site can be considered anything

but entirely safe. Obviously, the employers do need to mitigate safety hazards to

construction workers, but the workers need to keep in mind a lot of precautions

themselves when working in such hazardous conditions.

171. Thus, construction sites must be strived to safeguard their employees if not for the

ethical reasons, then for the economic ones. Here are eight ways construction

businesses can reduce workplace accidents. The following Good Practices at project

sites

6.1.1 Awareness

172. Before any worker — no matter his or her role or experience level — can set foot on a

construction site, he or she must be fully cognizant of the possible hazards. Ignorant

workers are perhaps the biggest dangers at any construction sight, as their unknowing

mistakes put everyone else at risk. Understanding of perils at hand and sustaining a

perpetual state of alertness is perhaps the number-one best way to prevent accidents

for which awareness campaign and risk assessment of each activity is done before start

of the new activity for the staff.

6.1.2 Training

173. Though most of a construction worker’s skills can be gained on the job, safety is one skill set that is best learned before works enter the construction site. Occasional

trainings are held on all sites for the labourers on standard safety and security practices.

Experienced workers were also provided with same trainings to refresh their knowledge

of standard safety by attending regular training sessions throughout the project cycle.

6.1.3 Communication

174. Accidents are more likely to occur when workers are unsure what to expect. Direct

communication regarding the day’s goals and activities resulted in cut down on

surprises that could cause bodily harm. Construction workers and supervisors are

Page 83: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 76

equipped with devices, like smartphones or headsets, which allow fast and efficient

communication among team members.

6.1.4 Supervision

175. Ideally, construction workers would fully understand the ramifications of inadequate

safety precautions and thus act in a manner to ensure site-wide well-being — but this

is not a perfect world. So, every site must have a strong supervisor who is willing and

capable of enforcing safety standards with no exceptions. Such supervision is provided

in almost all the sites (giving the best conformance level of +90%).

6.2 Opportunities for Improvement

6.2.1 Documentation

176. It is noticed almost all of the subproject sites, although the most of the environmental

issues are being catered but their documentation and record keeping is poor.

Documenting all work in the field will make issues easier than ever before to mitigate.

6.2.2 Innovation

177. The development of new practices that will enhance safety and security should always

be encouraged, and workers should avoid speaking against legislation aimed at

improving safety protocols. Perhaps with enough innovation, all construction sites can

give 100 percent conformance.

6.2.3 Transparency

178. The worst thing any construction contractor can do for its reputation is attempting a

cover-up. Hiding accidents not only lowers the opinion of a single endeavour — it paints

the construction sites as a whole in a negative light. Ultimately, people understand that

accidents happen, and as long as contractors are doing their best to foster a safe

environment for their workers, any accidents that do occur will only contribute to the

growing need to augment modern safety techniques. Transparency, along with the

other practices on this list, will help construction as a whole become a safer industry in

which to work.

Page 84: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 77

7 SUMMARY AND RECOMMENDATIONS

179. Twelve (12) subprojects are under construction. The contractors have been directed to

ensure implementation of EMP and SSEMP to make sure environment friendly

construction. DCSC environment team had orientated contractors and their staff on how

to carry out environmental monitoring.

180. DCSC environment team has orientated all the contractors on environmental

compliances as per IEEs/EMPs. DCSC has issued notices to the contractors on non-

compliance of environmental safeguard measures related to environmental

management and health and safety of workers and public. Mutually agreed Corrective

Action Plan is also devised and communicated to the contractors. DCSC has advised

the contractor to address non-compliance as per agreed Corrective Action Plan.

181. The subprojects under construction are mostly weirs and infiltration galleries for

irrigation purposes which requires no chemical storage, while for dam subprojects the

contractors have stored the chemical material in camps at separate room, mostly at a

corner of the camp, and properly labelled with safety precautions. Also, they are advised

to use MSDS for chemicals stored at camps as currently at all the sites they have no

MSDS.

Page 85: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

________________________________________________________________________

Page | 78

ANNEX

Page 86: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

________________________________________________________________________

Page | 79

ANNEX-1: ENVIRONMENTAL SAFEGUARDS COMPLETION REPORT

A. Introduction

1. The approach to Environmental Management Recommended in the project`s

Environmental Management Plan (EMP) took into account the institutional capacity in

environmental management in three districts namely Khyber, Mohmand and Bajaur of

Khyber Pakhtunkhwa and aimed to use the flexibility inherent in the project to

recognize and avoid any potential environmental hazards through a step-wise process

as below:

i. Selection criteria for subprojects were designed to avoid any really obvious

environmental concerns. (Thus, no subproject was undertaken within the Protected

area or any wildlife sanctuaries or forest reserves.

ii. Every subproject was screened through Rapid Environmental Assessment (REA) and

subjected to an initial environmental examination (IEE). This step would allow any

potential environmental hazard to be identified and mitigation measures drawn

up. (If it appeared that mitigation measures could not be satisfactorily designed to

ensure a minimal environmental impact, the subproject would be dropped).

iii. The detailed design of every subproject was checked before construction to ensure

that mitigation measures had been incorporated and appropriate safeguards and

required practices written into civil works contracts.

iv. Construction and operation of subprojects was monitored to ensure compliance with

environmental safeguards and that no serious environmental problem would arise.

2. The second step was undertaken during project implementation, where experts were

present in the project management Unit (PMU), Design and Construction Supervision

Consultants (DCSC) and Asian Development Bank`s (ADB) Environmental Safeguards

Team to help ensure compliance with the plan.

3. The third Step was initiated during implementation but was expected to continue into

the operational phase.

4. In summary, the approach to environmental management was to avoid major negative

impacts in the first place through:

• the subproject selection process;

• recognition and mitigation of lesser hazards identified by the IEEs;

• Ensuring of environmentally sound construction and operation, and monitoring of

subprojects to ensure sound operational practices were being followed and mitigation

measures were working as expected.

Page 87: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 80

5. The under-construction FATA Water Resources Development Project (FWRDP), out of

34 subprojects, 03 subprojects are substantially completed, in addition to 6 sub projects

that were already completed and reported in the 7th SAEMR, and 13 in 8th SAEMR. The

remaining 12 subprojects are still under construction. This completion Report is the

summary of completed subprojects and the lesson learned (Environmental Practical

Experience) for under construction subprojects. The list of completed subprojects are

given below.

1) CAD of Warsak Left Bank Canal

2) Haji Lawang Kas

3) Tabai Dam

B. Project Performance during Implementation

6. The EMP contained in the report and recommendation of the ADB and EPA-KP,

specified various activities to be undertaken during subproject identification, design, and

implementation.

7. These were inevitably affected by the revisions to expected processes, as outlined in

the safeguard documents, and in fact the selection of subprojects applied broadly

involved the process of identification, catchment area and water use studies, feasibility

study, and detailed design. This complied with the original design, and environmental

aspects (especially of water resources management & EHS) remained integral to the

entire process.

8. Monitoring of the environmental aspects of project implementation was the

responsibility of the Design and Construction Supervision Consultants and

Environmental and Social Management Unit (ESMU), and of the project Management

unit (PMU) assisted by Environment Officer (PMU), Environmental specialist with

assistance of Environmentalists (DCSC). Implementing Agency performance was

generally adequate, and institutional and technical requirements of the loan covenants

were complied. Specific activities undertaken included:

• (Rapid Environmental Assessment (REA) for each subproject and Detailed

designs followed the environmental assessment or IEE as captured in the Water

assessment studies and/or feasibility studies;

• (Detailed designs were approved by relevant agencies (i.e., Department

of Irrigation with the coordination of Department of Agriculture, Forestry and

Environment);

• The Environmental safeguards Documentation i.e., IEEs, EMPs and SSEMPs

are also approved by the relevant Agencies i.e., Environmental Protection

Agency and ADB.

Page 88: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 81

C. Overall Assessment

9. The subprojects completed are rated successful based on the earlier assessments of

relevance, effectiveness, efficiency, and likely sustainability.

10. These subprojects are an appropriate response to the recognized problems of rural

poverty, Low agriculture production and water scarcity in Erstwhile FATA of the 21st

century. Its technical composition was adequate, although if detailed formulation had

been somewhat more rigorous, the implementation delays (arising from the difficult

conditions on some subproject land, lack of contractor`s capacity.

11. The subprojects are implemented in circumstances that have continued to evolve

rapidly, yet retained its fundamental relevance. While some economic, social, and

institutional successes are now obvious at the subproject level. This is the most

fundamental shortcoming of the project to work in an area where environment and

climate-related pressures are growing.

12. The overall progress with respect to Environment Compliance is satisfactory. At the

start it was assessed somewhat very difficult, because of the tribal nature of the people

and ADB/country Environmental compliance requirements but with the passage of time,

it was improved and currently projected to 86% in the 8th Semi-Annual Environmental

Monitoring Report.

D. Lessons Learned

13. Probably the most obvious lesson is that the capacity needed to implement a project

with fully adopted Environment Compliance Procedures must be met at all levels i.e.,

PMU, DCSC and Contractors. According to ADB and Country Safeguards guidelines in

a particular area of the country, where the under-discussion compliance at this

particular tribal nature seemed difficult, particularly the contractors were also unaware

of the Environment Compliance Procedures. But the environment team and

management of the project were quite successful to achieve the goal up to the mark.

14. At all levels of involvement executing agency, consultants and contractors, all are

effective in the project performance and they must be on a single page to work for a

same cause to make sure the project is implemented smoothly.

15. It was also learned that appropriate and necessary interventions to support capacity

development and training must be included in the project scope. The most important

requirement is to focus on safety and health issues.

16. The most valuable lesson learned is the project implementors must aware the

contractors of the Environmental Safeguards requirements at an early stage to fulfil the

compliance.

Page 89: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021

Page | 82

17. At the end we can say that achievement is possible, when all the stakeholders involved

in Environmental Planning and Compliance work heartily and fully follow the prescribed

Guidelines.

18. Therefore, during the construction period of afore-mentioned subprojects, no accidents

were reported.

19. It is first project in the Tribal belt of Pakistan, where we achieved fully up to some extent

the Environment Compliance according to the Guidelines of Donor Agency.

E. Recommendations

20. The project’s design and implementation experience has yielded significant technical and institutional lessons on the nature of conditions in the water sector; as it is likely

that development of small and medium-sized irrigation schemes will continue to feature

in the sector development agenda, it is essential that these experiences are reflected

in ADB’s future analytical work, specifically in the assessment, strategy, and roadmaps

prepared as part of the country partnership strategy process.

21. An enabling environment is needed to allow farmers to supply the demand for their

production. Examples include

(i) a policy and institutional framework that promotes sound water resource

management;

(ii) a legal framework for water user associations that promotes cost recovery at least

sufficient to finance sustainable operation and maintenance (O&M);

(iii) rural infrastructure (e.g., roads that allow farmers to market their products, and farm

inputs to be delivered when they are needed);

(iv) efficient markets that are free of price distortions and barriers to competition for

both farm products and agricultural inputs; and

(v) access to information on demand, prices, and technology.

22. To successfully capture the opportunities created by growing markets, supportive

alliances must be created among upstream and downstream business partners (i.e.,

suppliers and service providers of agricultural inputs and implements such as farm

machines, agricultural processing entities and others related to markets). Extension

services must be provided; there must be access to improved seeds, fertilizers,

pesticides, and technologies; and private sector merchants must be involved in

marketing the incremental products.

23. In addition to the Environment Documentation, the Environment Compliance

Supervision at all level i.e., Client, Supervision Consultants and Contractor must be fully

technically sound and adequate in number to fulfil the requirements of the project.

Page 90: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 83

ANNEX-2 (a) Environmental Compliance Status Bajaur District

Sr. No Environmental Compliance Kharkai Haji Lawang Kas Khar Canal CAD Raghgan

1 Copy of the Site-Specific Environmental Management Plan (SSEMP) is provided at the camp site/contractors office 1 1 1 1

2 Contractor has provided Health Environment and Safety (HSE) plan and Emergency Response Procedures (ERP) to Resident Engineers (REs) 1 1 1 1

3 The EMP instructions are understood by the contractor 1 1 1 1

4 HSE officer hired/nominated for implementation of EMP 1 1 1 1

5 Contractors provided training to its staff and workers to effectively implement project specific EMP 1 1 1 1

6 Contractor is following the safety precautions as per ILO convention no.62 1 1 1 1

7 Contractors prohibited child labour or forced labour 1 1 1 1

8 Contractors hired local labour 1 1 1 1

9 Contractors provided PPEs to their workforce 1 1 1 1

10 PPEs are used by workforce 1 1 1 1

11 First Aid Kit is provided at camp and individual nominated for addressing emergency. 1 1 1 1

12 Ambulance is available at camp site 0 0 0 0

13 Campsite is fenced to prevent trespassing 1 1 1 1

14 Camp area has adequate drainage arrangements for disposal of waste water 1 1 1 1

15 Arrangement for proper storage and disposal for solid waste is ensured 1 1 1 1

16 No contamination of surface or ground water by oil spillage or solid waste dumping 1 1 1 1

17 Fuel/oil storage areas are at least 200 meters away from watercourses 1 1 1 1

18 Additional cross drainage is provided for spoil 1 1 1 1

19 Potable clean and safe drinking is available to labour 1 1 1 1

20 No wood being used as fuel 1 1 1 1

21 LPG cylinders are provided for cooking or heating purposes 1 1 1 1

22 Subproject construction site is fenced to curtail trespassing 1 1 1 1

23 No vegetation cover aside from that required as part of construction and inside the RoW removed 1 1 1 1

24 No tree cutting in the RoW and shoulder areas 1 1 1 1

25 Subproject activities are displayed at proper locations 0 0 0 1

26 Dust generation during construction well managed and record exists 0 0 0 1

27 Proper water sprinkling is done on regular basis 1 1 1 1

28 Water sprinkling record is available 0 0 0 0

29 Site selected for camp is 100 meters away from the human settlements and wildlife habitats 1 1 1 1

30 Safety signs are properly displayed 0 0 0 1

31 Construction machinery parked at designated areas 1 1 1 1

32 Traffic issues managed well, no complaints on record 1 1 1 1

33 No complaints were made due to noise and vibration 1 1 1 1

34 Construction activities carried out in daylight to reduce the impact of noise 1 1 1 1

Page 91: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 84

35 No loss of forests and intrusion into wetlands 1 1 1 1

36 No damage to the Archaeological /Religious/Cultural or Historical sites 1 1 1 1

37 No damage reported to public services like electric, water, gas, sewer, or telephone lines 1 1 1 1

38 Contractors maintained Environmental Monitoring Record and submit Weekly Monitoring Checklist reports 1 1 1 1

39 Contractors maintained Grievances Log to register complaints from community 1 1 1 1

40 No complaint registered in the Grievance Log 1 1 1 1

41 Borrow areas identified, having suitable material, and approved by design team 1 1 1 1

42 Borrow Pits not established in RoW 1 1 1 1

43 No damage to the agriculture land due to borrow pits on agriculture land 1 1 1 1

44 Top 15 cm are stripped and stockpiled for redressing 1 1 1 1

45 Top 0.5 m is stripped of and stockpiled when deep ditching is carried out 1 1 1 1

46 Community consultation has been carried out for subproject activities/concerns 1 1 1 1

47 No complaint filed regarding transmission of Communicable diseases (such as STI’s and HIV/AIDS) 1 1 1 1

48 No shops or houses inside ROW 1 1 1 1

49 No negative impact on the means of livelihood of the community because of the construction work 1 1 1 1

50 Ambient air testing is carried out on quarterly basis at site 1 1 0 1

51 Ambient Noise testing is carried out on quarterly basis at site 1 1 0 1

52 Drinking water quality testing is conducted on quarterly basis at site 1 1 0 1

53 Environmental Complaint Register (ECR) is placed at site? 1 1 1 1

54 Solid waste is properly handled and disposed of properly at site 1 1 1 1

55 Record of solid waste generated per day is available at site 0 0 0 0

56 No damage to flora and fauna been reported at site 1 1 1 1

57 No injury/Fatality reported at site 1 1 1 1

Compliance Score 51 51 48 54

Compliance Percentage % 89.47 89.47 84.21 94.74

Minor Compliance Percentage % 10.53 10.53 15.79 5.26

Major Compliance Percentage % 0.00 0.00 0.00 0.00

1 Compliance

-1 Major Non-Compliance

0 Minor Non-Compliance

Page 92: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 85

ANNEX-2 (b) Environmental Compliance Status Mohmand District

Sr. No Environmental Compliance Saro Shah CAD Warsak LBC CAD Khurshid Dam

1 Copy of the Site-Specific Environmental Management Plan (SSEMP) is provided at the camp site/contractors office 1 1 1

2 Contractor has provided Health Environment and Safety (HSE) plan and Emergency Response Procedures (ERP) to Resident Engineers (REs) 1 1 1

3 The EMP instructions are understood by the contractor 1 1 1

4 HSE officer hired/nominated for implementation of EMP 1 1 1

5 Contractors provided training to its staff and workers to effectively implement project specific EMP 1 1 1

6 Contractor is following the safety precautions as per ILO convention no.62 1 1 1

7 Contractors prohibited child labour or forced labour 1 1 1

8 Contractors hired local labour 1 1 1

9 Contractors provided PPEs to their workforce 1 1 1

10 PPEs are used by workforce 1 1 1

11 First Aid Kit is provided at camp and individual nominated for addressing emergency. 1 1 1

12 Ambulance is available at camp site 0 0 0

13 Campsite is fenced to prevent trespassing 1 1 1

14 Camp area has adequate drainage arrangements for disposal of waste water 1 1 1

15 Arrangement for proper storage and disposal for solid waste is ensured 1 1 1

16 No contamination of surface or ground water by oil spillage or solid waste dumping 1 1 1

17 Fuel/oil storage areas are at least 200 meters away from watercourses 1 1 1

18 Additional cross drainage is provided for spoil 1 1 1

19 Potable clean and safe drinking is available to labour 1 1 1

20 No wood being used as fuel 1 1 1

21 LPG cylinders are provided for cooking or heating purposes 1 1 1

22 Subproject construction site is fenced to curtail trespassing 1 1 1

23 No vegetation cover aside from that required as part of construction and inside the RoW removed 1 1 1

24 No tree cutting in the RoW and shoulder areas 1 1 1

25 Subproject activities are displayed at proper locations 0 1 1

26 Dust generation during construction well managed and record exists 0 1 1

27 Proper water sprinkling is done on regular basis 1 1 1

28 Water sprinkling record is available 0 0 0

29 Site selected for camp is 100 meters away from the human settlements and wildlife habitats 1 1 1

30 Safety signs are properly displayed 1 1 1

31 Construction machinery parked at designated areas 1 1 1

32 Traffic issues managed well, no complaints on record 1 1 1

33 No complaints were made due to noise and vibration 1 1 1

Page 93: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 86

34 Construction activities carried out in daylight to reduce the impact of noise 1 1 1

35 No loss of forests and intrusion into wetlands 1 1 1

36 No damage to the Archaeological /Religious/Cultural or Historical sites 1 1 1

37 No damage reported to public services like electric, water, gas, sewer, or telephone lines 1 1 1

38 Contractors maintained Environmental Monitoring Record and submit Weekly Monitoring Checklist reports 1 1 1

39 Contractors maintained Grievances Log to register complaints from community 1 1 1

40 No complaint registered in the Grievance Log 1 1 1

41 Borrow areas identified, having suitable material, and approved by design team 1 1 1

42 Borrow Pits not established in RoW 1 1 1

43 No damage to the agriculture land due to borrow pits on agriculture land 1 1 1

44 Top 15 cm are stripped and stockpiled for redressing 1 1 1

45 Top 0.5 m is stripped of and stockpiled when deep ditching is carried out 1 1 1

46 Community consultation has been carried out for subproject activities/concerns 1 1 1

47 No complaint filed regarding transmission of Communicable diseases (such as STI’s and HIV/AIDS) 1 1 1

48 No shops or houses inside ROW 1 1 1

49 No negative impact on the means of livelihood of the community because of the construction work 1 1 1

50 Ambient air testing is carried out on quarterly basis at site 1 1 1

51 Ambient Noise testing is carried out on quarterly basis at site 1 1 1

52 Drinking water quality testing is conducted on quarterly basis at site 1 1 1

53 Environmental Complaint Register (ECR) is placed at site? 1 1 1

54 Solid waste is properly handled and disposed of properly at site 1 1 1

55 Record of solid waste generated per day is available at site 0 1 1

56 No damage to flora and fauna been reported at site 1 1 1

57 No injury/Fatality reported at site 1 1 1

Compliance Score 52 55 55

Compliance Percentage % 91.23 96.49 96.49

Minor Compliance Percentage % 8.77 3.51 3.51

Major Compliance Percentage % 0.00 0.00 0.00

1 Compliance

-1 Major Non-Compliance

0 Minor Non-Compliance

Page 94: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 87

ANNEX-2 (c) Environmental Compliance Status Khyber District

Sr. No Environmental Compliance Magoo Dand

Dam Bar Kas Dam Tabai Dam Bada Khel Weir Neeli Tangi Tarkho Kas Tor Dara

1 Copy of the Site-Specific Environmental Management Plan (SSEMP) is provided at the camp site/contractors office

1 1 1 1 1 1 1

2 Contractor has provided Health Environment and Safety (HSE) plan and Emergency Response Procedures (ERP) to Resident Engineers (REs)

1 1 1 1 1 1 1

3 The EMP instructions are understood by the contractor 1 1 1 1 1 1 1

4 HSE officer hired/nominated for implementation of EMP 1 1 1 1 1 1 1

5 Contractors provided training to its staff and workers to effectively implement project specific EMP 1 1 1 1 1 1 1

6 Contractor is following the safety precautions as per ILO convention no.62 1 1 1 1 1 1 1

7 Contractors prohibited child labour or forced labour 1 1 1 1 1 1 1

8 Contractors hired local labour 1 1 1 1 1 1 1

9 Contractors provided PPEs to their workforce 1 1 1 1 1 1 1

10 PPEs are used by workforce 1 1 1 1 1 1 1

11 First Aid Kit is provided at camp and individual nominated for addressing emergency. 1 1 1 1 1 1 1

12 Ambulance is available at camp site 0 0 0 0 0 0 0

13 Campsite is fenced to prevent trespassing 1 1 1 1 1 1 1

14 Camp area has adequate drainage arrangements for disposal of waste water 1 1 1 1 1 1 1

15 Arrangement for proper storage and disposal for solid waste is ensured 1 1 1 1 1 1 1

16 No contamination of surface or ground water by oil spillage or solid waste dumping 1 1 1 1 1 1 1

17 Fuel/oil storage areas are at least 200 meters away from watercourses 1 1 1 1 1 1 1

18 Additional cross drainage is provided for spoil 1 1 1 1 1 1 1

19 Potable clean and safe drinking is available to labour 1 1 1 1 1 1 1

20 No wood being used as fuel 1 1 1 1 1 1 1

21 LPG cylinders are provided for cooking or heating purposes 1 1 1 1 1 1 1

22 Subproject construction site is fenced to curtail trespassing 1 1 1 1 1 1 1

23 No vegetation cover aside from that required as part of construction and inside the RoW removed 1 1 1 1 1 1 1

24 No tree cutting in the RoW and shoulder areas 1 1 1 1 1 1 1

25 Subproject activities are displayed at proper locations 1 1 1 0 0 0 0

26 Dust generation during construction well managed and record exists 1 1 1 1 1 1 1

27 Proper water sprinkling is done on regular basis 1 1 1 1 1 1 1

28 Water sprinkling record is available 0 0 0 0 0 0 0

29 Site selected for camp is 100 meters away from the human settlements and wildlife habitats 1 1 1 1 1 1 1

30 Safety signs are properly displayed 1 1 1 0 0 1 1

31 Construction machinery parked at designated areas 1 1 1 1 1 1 1

32 Traffic issues managed well, no complaints on record 1 1 1 1 1 1 1

33 No complaints were made due to noise and vibration 1 1 1 1 1 1 1

Page 95: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 88

34 Construction activities carried out in daylight to reduce the impact of noise 1 1 1 1 1 1 1

35 No loss of forests and intrusion into wetlands 1 1 1 1 1 1 1

36 No damage to the Archaeological /Religious/Cultural or Historical sites 1 1 1 1 1 1 1

37 No damage reported to public services like electric, water, gas, sewer, or telephone lines 1 1 1 1 1 1 1

38 Contractors maintained Environmental Monitoring Record and submit Weekly Monitoring Checklist reports

1 1 1 1 0 0 0

39 Contractors maintained Grievances Log to register complaints from community 1 1 1 1 1 1 1

40 No complaint registered in the Grievance Log 1 1 1 1 1 1 1

41 Borrow areas identified, having suitable material, and approved by design team 1 1 1 1 1 1 1

42 Borrow Pits not established in RoW 1 1 1 1 1 1 1

43 No damage to the agriculture land due to borrow pits on agriculture land 1 1 1 1 1 1 1

44 Top 15 cm are stripped and stockpiled for redressing 1 1 1 1 1 1 1

45 Top 0.5 m is stripped of and stockpiled when deep ditching is carried out 1 1 1 1 1 1 1

46 Community consultation has been carried out for subproject activities/concerns 1 1 1 1 1 1 1

47 No complaint filed regarding transmission of Communicable diseases (such as STI’s and HIV/AIDS) 1 1 1 1 1 1 1

48 No shops or houses inside ROW 1 1 1 1 1 1 1

49 No negative impact on the means of livelihood of the community because of the construction work 1 1 1 1 1 1 1

50 Ambient air testing is carried out on quarterly basis at site 1 1 1 0 0 0 0

51 Ambient Noise testing is carried out on quarterly basis at site 1 1 1 0 0 0 0

52 Drinking water quality testing is conducted on quarterly basis at site 1 1 1 0 0 0 0

53 Environmental Complaint Register (ECR) is placed at site? 1 1 1 1 1 1 1

54 Solid waste is properly handled and disposed of properly at site 1 1 1 1 1 1 1

55 Record of solid waste generated per day is available at site 1 1 1 1 0 0 0

56 No damage to flora and fauna been reported at site 1 1 1 1 1 1 1

57 No injury/Fatality reported at site 1 1 1 1 1 1 1

Compliance Score 55 55 55 50 48 49 49

Compliance Percentage % 96.49 96.49 96.49 87.72 84.21 85.96 85.96

Minor Compliance Percentage % 3.51 3.51 3.51 12.28 15.79 14.04 14.04

Major Compliance Percentage % 0.00 0.00 0.00 0.00 0.00 0.00 0.00

1 Compliance

-1 Major Non-Compliance

0 Minor Non-Compliance

Page 96: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 89

ANNEX-3 Major Non-Compliance Notices

Page 97: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 90

Page 98: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Page | 91

ANNEX-4 Corrective Action Plan Sr. No

Date Raised

By Location Issues Category* Corrective Action

Responsibility

Original Target Date

Status

1 December

2021 CSC

All diversion Weirs sites

Barricading the construction sites

Moderate All under construction sites have to

be properly barricaded Contractor Immediate

Closed

2 December

2021 CSC

All Under Construction

sites Lack of PPE’s Major

Provide adequate PPEs to all workers

Contractor 15 Dec,

2021 Closed

3 December

2021 CSC

All under construction

sites

Covid SOP’s and guidelines

Major Ensure to follow and implement Covid-19 SOPs and guidelines.

Contractor 15 Dec,

2021 Closed

4 December

2021 CSC

All Under Construction

sites

Displaying Safety signages

Moderate Proper safety signs should be installed by the Contractors

Contractor 15 Dec,

2021 Partially Closed

*Category of Non-Compliance

1. Minor: Within fifteen days: Draw attention through copy of daily check list 2. Moderate: Beyond 15 days and up to 30 days: Issue warning recorded on check list as well as separate letter 3. Major: Beyond one month: Do not verify the contractor’s invoice.

Page 99: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 92

ANNEX-5 Instrumental Monitoring Results

Water Quality Testing Results

Page 100: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 93

Page 101: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 94

Page 102: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 95

Page 103: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 96

Page 104: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 97

Page 105: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 98

Page 106: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 99

Air Quality Results

Page 107: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 100

Page 108: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 101

Page 109: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 102

Page 110: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 103

Page 111: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 104

Page 112: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 105

Page 113: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 106

Noise Level Results

Page 114: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 107

Page 115: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 108

Page 116: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 109

Page 117: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 110

Page 118: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 111

Page 119: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 112

Page 120: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 113

ANNEX-6: Environmental Management Plan

Activity Problem / Impact Mitigation Measures Timing to

Implement MM Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

Pre-Construction Stage Assure compliance with relevant construction field legislation.

Legal complications and delay in project

• Acquire construction permit/ Environmental NOC from local authorities.

• Preparation of SSEMPs for each site and get them approved by the Consultant, before the construction works start.

• Provide Water management guidelines if subprojects are executed near surface watercourse.

Before the construction of the project activities.

Number of reported non-compliances

Minimization and continued improvement in number of reported non-compliances

EPC Contractor

ESMU/ Consultant

Development of Strategies.

Problems arising due to non-compliance

• An ‘Operation Environmental Action Plan’ (OEAP) needs to be prepared demonstrating the manner in which the Contractor/Operator will comply with the requirements of management plans proposed in EMP/SSEMP.

• The following strategies and procedures will be developed prior to the commencement of Project operations:

• Project specific security and public access control strategy;

• Project specific waste management strategy

Pre-Operations Implementation Operation Environmental Action Plan’ (OEAP)

Beneficial in long terms with the implementation of Operation Environmental Action Plan’ (OEAP)

ESMU PMU & ADB

Page 121: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 114

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• Project specific air and noise control strategy;

• Project specific traffic control strategy;

Construction Stage Impacts Impacts on Land Resources Excavation • Noise &

Vibration

• HSE issues

• Vegetation loss will be avoided as much as possible and limited to demarcated construction area.

• Slope stabilization measures will be adopted such as adequate vertical and horizontal drains, cross drainage etc.

• Slope movements will be monitored around excavation work areas.

• Top six inches soil should be protected before excavation and should be placed back after completion of construction work.

• Excavated material shall preferably be reused after approval of quality control engineer of CSC.

• Non-reusable excavated material shall be safely dumped and leveled in barren land with approval from Environment specialist of CSC and

During Construction

• Implementation of SSEMP before start of works

• Annual reports and documentation of safety inspection

• Workforce /Community complaints

Not Significant (Minimal) Target = zero Threshold 1, with agreed mitigation

EPC Contractor

ESMU/CSC

Page 122: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 115

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

dumping location should be provided in SSEMP.

Waste Management

• Waste Pollution

• To minimize environmental impacts and avoid any need for disposal of earthwork materials or the importation and unnecessary storage of earth, the project will maximize the reuse of excavated materials.

• All of the construction activity will be contained inside construction area.

• Solid waste generation should be reduced and should be reused and recycled.

• Any residual spoil will have to be disposed in environment friendly manner, where it will be leveled and landscaped. The dumping sites must be approved by CSC environment specialist.

• To be made contractor’s obligation through contract document, as an SSEMP will be prepared by the contractor and waste management plan will be a part of it.

During construction stage

• EPC’s Site officer and EHS officer in place

• SSEMP including Waste Management Plan

• Zero Complaints from Community & Workers

• Internal auditing and reporting by EPC

Not Significant (Minimal)

EPC Contractor

ESMU/CSC

Labor camps and material storage

• Cultural & Social issues

• The contractor will, in consultation with RE, resolve the exact location of all these facilities within

During construction

• Monthly Reports (EPC)

Not Significant (Minimal)

Contractor ESMU/CSC

Page 123: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 116

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• Water & Sanitation issues

the barren land owned by the local community that will be provided by the community temporarily and free of cost.

• The location of these facilities will be at least 500 m away from the settlements.

• The contractor will not locate and construct any facilities without the written approval of the CSC.

• Supervision by Consultant

• EHS officer implementing SSEMP Information Events for work force

Soil pollution due to oils and lubricants / equipment poor maintenance and repairs / refueling at the construction site.

• Soil pollution

• Water pollution

• Strict rules will be imposed on workers and labors to ensure that no such spills are caused.

• If the spills take place, it must be followed by treatment prescribed above as per the degree of spill.

• An Oil Spill Management Plan containing specific mitigation measures to be part of contractor site specific environmental management plan are:

• Spill prevention trays will be provided and used at refueling locations

• On-site maintenance of construction vehicles and equipment will be avoided, a vehicle maintenance area with impermeable floor will be designated.

Because the area can be subject to un seasonal heavy rain plan before and during construction (cut and fill, land reclamation etc.) while considering the climatic conditions.

Spill contingency plan is available at site Properly paved/cemented mechanical workshop No water bodies near the working area Staff Training over oil spillage All the vehicles and machinery seals are intact Containers are available for used oil

Not Significant (Minimal)

Contractor ESMU/CSC

Page 124: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 117

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• Regular inspections will be carried out to detect leakages in construction vehicles and equipment.

• Fuels and lubricants will be stored in covered and dyked areas, underlain with impervious lining.

• Spill control kit (shovels, plastic bags and absorbent materials) will be available near fuel and oil storage areas.

• Contaminated soil will be removed from the site and disposed in a manner to ensure protection of water sources

• Emergency plan for spill management will be prepared and inducted to the staff for any incident of spill.

• The bottom of any soak pit or septic tank will be constructed at least 100 meters away from springs and water bores

• Record of spills and Volume of removed contaminated soil will be maintained.

• Record of remedial measures taken will be maintained.

Page 125: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 118

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

Heavy Machinery near agricultural land

• Agriculture Land Damage

• It is contractor’s obligation not to cause such damage and strictly follow the design.

• Top six inches soil will be protected and land will be restored to its previous condition after completion of construction works.

Construction and post construction

• Monthly Reports (EPC)

• Supervision by Consultant

• EHS officer implementing SSEMP

Information Events for work force

Not Significant (Minimal)

Contractor ESMU/CSC

Earth borrow • Land owner problems

• Levelling of land after borrowing

• Issues to the local community

• Compensation difficulties

• No private land will be acquired for the borrow areas.

• The Contractor will ensure that selected borrow areas on irrigation land are clearly demarcated and approved by the engineer including the allowed depth of the excavation before starting excavation.

• The borrow areas will be leveled. The Contractor will not leave the borrow pits in such a condition that they are unsuitably filled with rain water and cause the problem for the community.

• If the borrow area is near to the settlements, then it should be fenced completely.

• If agriculture land needs to be used as borrowing area, then the Contractor will adopt the following

Construction and post construction

Top soil management Government approved site Approval for any other site by RE and Government Borrow area management generated and implemented Agreement in case of private land owner Grievance redress Mechanism Leveling of Borrow Area

Minor \Reduced

Contractor ESMU/CSC

Page 126: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 119

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

methods during the digging process.

• Fix the location of excavation.

• Remove thirty centimeters of the top soil and keep it on reserved site for re-spreading in the field.

• Excavate up to one-meter depth.

• Maintain the slope as far as possible.

• Place the top soil back during the restoration

• Pay compensation for any damages/ crop losses.

Movement and Operation of heavy machinery & vehicles

• Change in Soil characteristics e.g. soil erosion, contamination and compaction

• Avoid use of heavy machinery where possible.

• Contractors before handing the site back will apply such measures as to mitigate the impact of compaction and leave the site almost in the same state in which it was occupied.

• Pictures of the area should be taken before handing it over to contactor which will help the RE to ensure an acceptable state of soil while getting the area back from the contractor.

During construction

• Monthly Reports (EPC)

• Supervision by Consultant

• EHS officer implementing SSEMP

• Information Events for work force

Not Significant (Minimal)

Contractor ESMU/CSC

Construction material

Waste generation due to closure of site

• All shivers and material that remain after the closure of temporary

Completion of Construction

• Site Inspection

• Implementation of Environmental

Not Significant (Minimal) Short term during construction phase

Contractor ESMU/CSC

Page 127: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 120

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

leftovers and site restoration

Occupation of usable land.

construction sites are to be removed from the location and re-used/re-cycled where possible.

• All remains are to be disposed of in a manner that will not be harmful to environment.

Enhancement Program

Beneficial in long terms with the implementation of Environmental Enhancement Program

Impacts on Hydrology and Water Resources Washing of Vehicle and equipment in the stream

• Contamination of Surface water

• Contractor will demarcate a washing area for all sorts of washing activities, with running water facility connected to a dedicated drain flowing into the septic tanks. There would be restriction on servicing/ washing of vehicles and equipment at site.

During Construction

• Documentation of audit and remedial actions where necessary

• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)

Not Significant (Minimal) Short term during construction phase

Contractor ESMU/CSC

Drinking Water supply

• Water borne diseases & other water related issues

• Contractor, under the guidance of Environment Specialist of CSC, will get spring water tested for chemical and biological contaminants, and assist in providing filtration to make water drinkable.

• There are numerous cost-effective water treatment models available in order to mitigate chemical and/or biological contamination. Sand filtration, Chlorination, UV treatment and oxidation are a few such methods.

Before construction and during the project activities.

• Documentation of audit and remedial actions where necessary

• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)

Not Significant (Minimal)

Contractor ESMU/CSC

Page 128: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 121

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

Municipal solid and liquid Waste Generation

• Nuisance and Soil Pollution, diseases due to dumping

• Solid waste bins will be placed at labor eating and resting areas.

• Latrines and washing areas with septic tanks will be erected by the contractor at the construction site.

• Waste from the project construction area and office area shall be segregated and collected by the Tehsil Municipal corporation for dumping at approved land fill site or if small amount then a natural gully or uncultivable land for dumping will be arranged with approval from CSC Environment Specialist.

• All these provisions will be incorporated in site Contractor Site Specific EMP for construction. Prior utilization, all the landfill sites or disposal sites will be approved by CSC Environment Specialist

During construction

• Implementation of SSEMP

• Site auditing

• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)

Not Significant (Minimal)

Contractor ESMU/CSC

Water Quality and Sedimentation Load

• Health issues to labour from water borne diseases

• Surface water quality deterioration

• Quarterly water sampling and testing will be conducted in order to ascertain water quality during different seasons.

• Two samples each from the labour camp and 10 m

During Construction and Post Construction

• Plan to be developed before completion of construction

Not Significant (Minimal)

Contractor

ESMU/ CSC PMU Merged Area Secretariat

Page 129: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 122

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

due to construction and operation of the project

downstream location of the weir and will be drawn for testing to make comparison of water quality with the baseline data to determine its suitability for labour consumption or any change in water quality due to construction of weir.

• Quarterly Water Monitoring Reports by EPA certified Laboratory

Impacts on Air Quality and Noise Pollution Dust/smoke Emission from plants and equipment

• Air pollution

• Lung Diseases

• Contractor’s contractual obligation will include keeping the dust and smoke within permissible level by using machinery, which is well maintained and with low noise.

• Land, all katcha roads and paths will be sprinkled with water after regular intervals.

• The contractor must avoid/ control the dust and smoke by carefully storing and distributing the construction material so as to cause minimum dust which again should be within the acceptable limits.

During Construction. Water sprinkling to be done on regular/daily basis.

• Water sprinkling Records

• Monthly reports EPC

• Site Inspection and Audits

• Monthly Monitoring Reports by EPA certified Laboratory

Not Significant (Minimal)

Contractor ESMU/CSC

Smoke from burning of waste or firewood

• Cutting of trees and shrubs

• Smoke pollution

• Contractor shall strictly prohibit burning of waste or of wood, especially extracted from nearby shrubs and bushes.

During construction

• EPC’s Site officer and EHS officer in place

• SSEMP Implementation

Not Significant (Minimal)

Contractor ESMU/CSC

Page 130: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 123

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• Diseases • Contractor must provide clean fuel like LPG cylinders to the labor to use for their daily purposes.

• Internal auditing and reporting by EPC

Operation of heavy mechanization and generators.

Noise pollution

and vibration

• Contractor’s contractual obligation is to use new, well maintained and low noise machinery preferably during day time.

• The drivers, operators and workers working on or near the heavy machinery must be provided with ear plugs. The contractor will ensure use of newer, well maintained machinery that creates minimum noise and emissions, as per National Environmental Quality Standards (NEQS 2000)

• Environment Specialist of CSC will ensure that this clause is added to the bidding and contract document.

• Night time construction activities will be strictly discouraged, and may only be carried out in exceptional cases, with prior permission of Resident Engineer.

• Noise monitoring will be carried out near sensitive

During Construction stage

• EPC Site Manager and EHS Officer in Place

• Audit and Inspection record of heavy mechanization and generators.

• Monthly Noise level Monitoring Reports by EPA certified Laboratory

• No. of Grievance’s (Target=0)

Not Significant (Minimal)

Contractor ESMU/CSC

Page 131: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 124

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

receptors on a quarterly basis.

• The NEQS for noise in residential areas is 55 dB (A) in the day-time and 45 dB (A) at night. It is recommended that noise levels close to sensitive receptors do not exceed 55 dB (A) during the day time as required by the NEQS.

Stone quarrying and Transportation of material

• Dust Emission and lungs diseases.

• Contractor shall use the road network carefully and repair any damages immediately.

• During transportation, covering of vehicle with sheet will be done.

• Unloading of vehicles will be done on designated sites.

During construction.

• Recording of violations and corrective measures

• Performance of Regular Driver Training (target 100% participation of drivers)

• Instruction and Information Events for workforce

• No. of accidents (Target=0)

Not Significant (Minimal)

Contractor ESMU/CSC

Impacts on Biological Resources Multiple project activities

• Damage to Flora and Fauna

• Impact on aquatic life

• Environment Specialist together with FATA line departments will ascertain the status of the site area in terms of occurrence of wildlife species, flora and

Rerouting and site identification during design stage and other matters during

• EPC internal monitoring and monthly reports

• Site auditing

Not Significant (Minimal) during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program

Contractor ESMU/CSC

Page 132: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 125

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

fisheries. And in accordance, recommend a watch and ward system that will be based on partnership between communities, wildlife, forest & fisheries departments and political administration. Each partner’s roles will be specified at the onset, and responsibilities assigned.

• Till the completion of the survey, contractor will ensure no extraction takes place from the surrounding vegetation for fuel wood or hunting of any birds by the labor employed.

• If such a case is witnessed, it will be brought to the notice of the project management as well as the concerned Assistant Political Agent (APA).

• Contractor’s obligation is to strictly respect the limits of construction site.

• Cutting of trees will be strictly prohibited and if no alternate is available plantation of trees will be done in case any tree is cut for project activities.

construction of relevant activities

• Photographic record of pre and post project

• Implementation of Environmental Enhancement Program

Page 133: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 126

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• Tree cutting will be restored by planting four trees against each tree cut.

• Borrow areas with least vegetation cover will be selected.

• The project will have a soft start for allowing time to reptiles to move away from the project site.

• There will be restriction and prohibition on hunting, shooting, trapping, and poaching of wild species.

• No night time activity will be carried out.

• Photographs of the project area will be taken at pre and post project stage.

• Continuous inspection of the area will be carried jointly with other agencies involved in maintenance of protected areas.

Impacts on Socioeconomic and Cultural Issues Project Activities

• Tribal tensions and rivalries

• For matters pertaining to social obligation and benefits of the communities, if needed, a social Framework Agreement shall be signed by the RE with communities to ensure their participation and full satisfaction in matters pertaining to them. All

Before and During construction

• Continued Community Consultation Records

• Implementation of Community Liaison Plan by EPC

• No. Of Grievance’s (Target=0)

Not Significant (Minimal)

Contractor ESMU/CSC

Page 134: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 127

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

matters where contractor is involved, these should be made as his contractual obligations.

• Project Team along with the Social Development Specialist will ensure continuous liaison with the communities throughout the construction phase of the project, so as to identify any such incident in time. Relevant political authorities will be kept abreast of the progress, as well as any such issue if in making.

• If, during the execution of the activities or excavation, any material is discovered onsite, which may be considered of historical or cultural interest, such as evidence of prior settlements, native or historical activities, evidence of any existence on a site, which may be of cultural significance, all work shall stop and the supervising contracting officer shall be notified immediately. The area in which the material was discovered shall be marked and the evidence preserved for examination.

Page 135: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 128

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• The contractor is required to develop Chance Find Procedure as part of the SSEMP.

Excavation activities

Impact on the existing civil infrastructure and facilities, especially underground installations (water supply and sewerage pipeline etc.) which cause obstacles in the provision of services to consumers

• Precisely situate the position of infrastructure and underground installations at the local works in cooperation with the relevant institutions at all levels of authority.

• Close liaison with local relevant authorities

• Should the damage take place, the contractor must contractually be bound to carry out repair immediately.

Before the construction of the dam and all other structures, the APs should be given sufficient time and compensation to satisfy them.

• Continued Community Consultation Records

• No. Of Grievance’s (Target=0)

• Monthly Reports on Information activities and response from community

• Liaison Records with local relevant authorities

Not Significant (Minimal)

Contractor CS Consultant / EMU in cooperation with concerned Department. I-e, Public Health etc.

Multiple project activities related to HSE

• Risk of injuries at work

• Spread of COVID-19

• The contractor will ensure that proper HSE protocols are in place, including protective gear, drinking water, sanitation, energy supply and overall safety for the labor.

• Evacuation plans in case of fire or any other accidents will also be prepared, and drills carried out to ensure the labor is aware of responding to such a situation.

Prior to commencement and during construction

• Site Inspection

• Monthly EPC Reports

• PPEs issuance records

• Health and safety Plans in Place and Implemented

• Implementation of Construction Site Organization Plan

Not Significant (Minimal)

Contractor ESMU/CSC

Page 136: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 129

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• A detailed HSE Plan will be formulated in SSEMP.

• The Construction processes are dynamic with significantly varying number of workers on a construction project site from day to day. The workers coming from diverse environments and working closely together increases the risk of exposure to COVID 19. The

project will follow both GOP

SOPs and ADB guidelines on

COVID-19.

• Without prejudice to the following, all possible and prescribed actions shall be taken at the project site, as should facilitate the health of all life present at the site.

• Every construction project shall make proper arrangements for uninterrupted building services including but not restricted to, electricity, fuel, water supply, water disposal and sanitation, communication links, washrooms with hand hygiene and shower facility and with proper and

Page 137: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 130

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

adequate supply of soaps and disinfectants.

• All incidences of appearance of the symptoms of COVID-19 shall be immediately documented and maintained at the site and information regarding which shall be immediately communicated through e-mail or else, to the designated health facility, and the sick worker shall be transported to the health facility for further advice and action. The site manager must establish a link with a nearby healthcare facility with arrangements for quick transportation of workers in case of an emergency.

• Persuade the workers to inform the authorities for their safety and of other if they observe any signs and symptoms in a colleague.

• Do not allow any worker at the construction site who has the symptoms.

• Display the awareness banners about hand hygiene and physical distancing, where you can, around the work site.

Page 138: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 131

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• The lunch breaks and stretch breaks of the workers must be staggered to avoid the clustering of workers. Workers must not sit at less than 2 meters distance while having meals and while any other activity requiring interpersonal communications.

• In case of workers sleeping in at the site of construction, a safe distance of 2 meters must be ensured in the sleeping rooms •

• A supply of safe drinking water must be made available at the project site and maintained.

• Every individual must use face mask. Face mask shall be replaced as and when soiled or otherwise removed. Outer surface of face mask must not be touched with hands. Workers should wash their hands as frequently as practicable and shall not to touch their face with their hands during work.

• Workers must maintain no less than two arm lengths between them before, during after work at all the

Page 139: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 132

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

times. They shall not make physical contact and shall be required to maintain separate personal gears and assets which must be clearly labelled and stored without intermix.

• Use safe transport arrangements which should not be crowded and should have social distancing in place during the entire process from pickups till drops at destination.

Operation Stage Impacts and Maintenance (O&M) Earth and Borrowing activities, fertilization for crops

• Change in visual character and soil erosion

• Restoration and Environmental enhancement plan to be prepared.

• Use of borrow areas with Engineer’s approval at specified depth.

• Limited movement of machinery.

• Documentation of area.

• Ensuring areas under crops are not used as borrow areas.

• Leveling and dressing of borrow areas; Water sprinkling.

• Rescue of any encountered species.

Pre-Operations • Implementation of Environmental enhancement plan

• EPC Construction Completion Report

• Site Inspection

Not Significant (Minimal) Short term during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program

Contractor ESMU/CSC EPA ADB

• Soil pollution due to

• Agriculture Directorate shall introduce Agriculture

Post Construction

• Agriculture extension

Minor Agriculture Directorate

PMU

Page 140: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 133

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

excessive application of fertilizers and pesticides

extension programs targeting use of Integrated Pest Management (IPM), green manure, and limiting use of pesticides/ fertilizers to required levels only will target farmer communities to inform and train them. In general, in erstwhile FATA area the farmer uses mostly the Farm yard manure or green manure. The pesticide use is also rare, because of less vegetables and fruit production.

program developed before completion of construction

• Use of irrigation water for cultivating high delta crops

• Cultivation of high delta crops will be strictly discouraged.

• Cropping pattern in accordance with the water balance model will be suggested and promoted.

Post construction

Agriculture extension program developed before completion of construction

Not Significant (Minimal)

Agriculture Directorate

PMU

Monitoring programmes

Mitigation plan implementation cannot be gauged

The following monitoring programmes will be developed prior to the commencement of Project operations:

• Landslide monitoring;

• Water quality monitoring

• Watershed and flood telemetry monitoring

Operational stage

Site Inspection Monitoring Reports

Beneficial in long terms with the implementation of Operation Environmental Action Plan’ (OEAP)

Irrigation Department

PMU

Training/ educational programmes.

Effect on employees` efficiency during project

The following educational programmes will be developed prior to the commencement of Project operations:

Operational stage

Implementation of Training Events and Programs

Highly Beneficial Irrigation Department

PMU

Page 141: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Semi-annual Environmental Monitoring Report Page 134

Activity Problem / Impact Mitigation Measures Timing to Implement MM

Performance Indicator

Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented

Implementation Responsibility

Supervision Responsibility

• Employee induction programme on environmental awareness;

• Employee code of conduct;

• Health and Safety training programme

Page 142: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 135

ANNEX-7 A: Weekly Monitoring Checklist

Description Status Additional Comments

A-Physical Conditions 1-Ambient air quality Are dust emissions being regulated through sprinkling water on the routes being used by the Contractor? □Yes □No

Are vehicle speeds being monitored to avoid excessive dust emissions at dust prone areas? □Yes □No

Are vehicle properly tuned/maintained to reduce air emissions? □Yes □No

2. Noise Control

Are noise levels remained within safe limits (<75dB)? □Yes □No

In case excessive noise levels are detected have appropriate mitigation measures been taken? □Yes □No

Is restriction on playing tape records and blowing pressure horns etc. is being observed? □Yes □No

2-Waste Material

Has any natural drainage been disturbed or altered? □Yes □No

Are the waste bins emptied regularly in the burn pit? □Yes □No

Is food waste disposed in the open? □Yes □No

Is the combustible waste burnt regularly in the burn pit? □Yes □No

Is any medical waste generated and handled properly? □Yes □No

3-Fuel/Lubricant

Are the fuel tanks properly marked with their contents? □Yes □No

Are the fuels and oils handled in a safe manner, ensuring no leakage or spillage? □Yes □No

Any spillage of liquid waste occurred? □Yes □No

If spillage occurred, managed properly? □Yes □No

4-Traffic management

Is vehicle speed limit of 30 km/hr. being followed? □Yes □No

Is the movement of all project vehicles and personnel been restricted to within the work areas? □Yes □No

Do all vehicles and equipment have muffles to reduce noise levels whilst working close to communities? □Yes □No

Movement of machinery restricted to designated routes? □Yes □No

Construction vehicles, machinery and equipment stated in designated places within RoW? □Yes □No

B-Biological Conditions 1-Flora

Has any tree cut/uprooted? □Yes □No

Have trees and branches been used as fuel wood? □Yes □No

2-Fauna

Are the drivers careful and watchful about wild and domestic animals? □Yes □No

Page 143: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 136

Any damage to animals? □Yes □No

C-Socio-economic

1-Community

During construction have good management practices been adopted by avoiding disturbance to areas adjacent to work area? □Yes □No

Are complaints from local communities being registered and responded to? □Yes □No

Have the local communities been formally notified about methods for registering complaints? □Yes □No

Is un-necessary interference to adjoining private agriculture land avoided? □Yes □No

Are damages (if any) to private property repaired and/or compensated by the Contractor? □Yes □No

Are metaled roads properly maintained? □Yes □No

2-Work Force

Are proper hygienic facilities being provided? □Yes □No

Are sufficient guards for security deployed? □Yes □No

Name _______________________________ Signature ___________________

Additional Comments:

Page 144: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 137

ANNEX-7 B: Urdu Brochures for Environmental Awareness for Contractor staff

Page 145: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 138

Page 146: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 139

Page 147: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 140

Page 148: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 141

Page 149: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 142

Page 150: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 143

Page 151: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 144

Page 152: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 145

ANNEX-8: Guidelines for Camp Site Selection

• Contractor should locate camp facilities preferably at distance of 500 m or with the approval of DCSC at a minimum distance of 100 m from existing settlements, built up areas or wildlife habitats.

• The construction camp will be established in areas where vegetation cover removal

and tree cutting can be avoided.

• The camp areas should have adequate natural drainage to facilitate the flow of treated effluents preferably within the works and services land.

• The camp site should not be at blind spots, sharp turns to avoid any accidents due to

movement of machinery from the camp area. Properly designed warning signs and speed humps should be provided at inlet and outlet of the camp site.

• If camp land is on lease, the land owners should be compensated as per lease agreements.

Camp Site Management

• Contractor shall provide copy of the Environmental management Plan (EMP) at the concerned sites. Copy of the EMP should be available at camp site all the times.

• Contractor will nominate and authorize the individual(s) with role and responsibility to

implement EMP measures.

• EMP recommendations should be clearly understood by the concerned implementing individual(s).

• Contractor shall comply with the safety precautions for constructions as per ILO

convention 62.

• Contractor shall provide PPE to construction workforce and monitor if they are appropriately used.

• The labour shall be provided with the adequate potable water at site.

• Wood shall not be used as fuel or for any other activity.

• Contractor shall provide LPF cylinders for cooking and heating purposes.

• Contractor shall provide first aid kit at camp site and nominate/train individuals to

address any emergency.

• Camp site will be fenced to prevent trespassing.

• Maintain good liaison with local communities.

• Contractor shall maintain grievances log, where all community complaints are registered and follow up actions should be recorded.

Page 153: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 146

Worker’s Training

• Contractor shall provide trainings to effectively implement project specific EMP. It may involve special trainings of workers on specific jobs.

• Training of construction workforce on health and safety and use of PPE (safety

shoes, helmets, gloves, masks).

• Construction workforce training in the storage and handling of material and chemicals that can potentially cause soil contamination and/or explosion.

• Contractor shall prohibit hiring of child labour and forced labour.

• Contractor shall encourage hiring of local labour.

Plans and Procedures

• Contractor shall prepare and submit health and safety plan.

• Contractor shall prepare and submit emergency response procedures for a) Spills and leakages b) Accident c) Fire fighting d) Electric

• Contractor shall prepare and submit worker’s training plan.

Waste Management

• Contractor will be responsible for treatment of wastewater from camp toilets. Wastewater will primarily pass through septic tank and later be discharge into soak pit.

• Solid waste generated during construction at campsite will be properly collected at source, treated, and safely disposed of only in selected waste disposal sites.

• Fuel and oil storage areas should be located away from any watercourses. They should be properly paved with contaminated ditch to control any spillage.

• Contractor will be responsible to contain, collect, clean-up and properly dispose-off the wastes in case of any emergency spill.

• Drinking water sources shall be at least 50 m away from soak pit to avoid contamination.

• Contractor will be responsible to implement proper dust and noise abatement procedures at camp site.

Page 154: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 147

ANNEX-9: Photo Log

Pictorial View: Onsite Trainings

Page 155: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 148

Pictorial View: Environmental Monitoring

Page 156: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 149

Pictorial View: Construction Sites

A view of entrance at Camp Office

Vehicle Parking at Camp

Warning in Local Language about GRM Site Fencing with Warning Tape

Page 157: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 150

Warning Sign Board at Site A View of Bar Kas Dam

A view of Tabai Dam A View of Labour Camp

A view of Magoo Dand Dam

Warning Sign Board at Site

Page 158: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 151

A view of Labour Camp at Magoo Dand Dam

Hygiene Facilities at Site

A view of Katcha Road with precautionary board Warning and precautionary board at construction

yard

Page 159: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 152

Warning Sign Board at subproject access Project Sign Board Displayed at Site

Warning Sign Board at subproject access Steel Fixing Workers at Site

Workers Wearing PPEs

Improved Drainage at Subproject

Page 160: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 153

Treatment of Kitchen Waste

Kitchen Waste Land Fill

Site Fencing with Warning Tape

Excavated Areas Barricaded

Use of Wheelbarrow to avoid agricultural land

damage

A View of Jay Dam Reservoir

Page 161: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 154

ANNEX-10 Maps Showing Dumping Sites of the Contractors for Each Subproject

Kharkai Weir Subproject

Khar Canal Subproject

Page 162: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 155

CAD of Raghagan Dam Subproject

Saro Shah Subproject

Page 163: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 156

CAD of Khurshid Dam Subproject

CAD of Warsak Left Bank Canal Subproject

Page 164: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 157

Barkas Dam Subproject

Badakhel Weir Subproject

Page 165: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 158

Neeli Tangi Weir Subproject

Tarkho kas Weir Subproject

Page 166: Environmental Monitoring Report (July-December 2021)

Semi-Annual Environmental Monitoring Report July-December 2021 ANNEX

Annex: Semi-annual Environmental Monitoring Report Page 159

Tor Dara Weir Subproject

Magoo Dand Dam Subproject