Environmental Monitoring Report ________________________________________ Project Number: 47021-002 Loan Number: 3239-PAK(COL) Semi-Annual: July- December 2021 Document Date: March 2022 PAKISTAN: Federally Administered Tribal Areas Water Resources Development Project Prepared by Project Management Unit, SDU, Government of Khyber Pakhtunkhwa, Pakistan for the Asian Development Bank
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
2.1.3 Construction of Khar Canal Sub Surface Infiltration Gallery
21. The Khar Canal Project is located on Charmang Khwar Khar Canal site is located at a
distance of 1.2 km from Khar through paved road. As per site observation perennial
flow of 0.95 cumec exists in the khwar.
22. A network of subsurface pipe is proposed in the active flow channel of the khwar to
collect the flow. It is anticipated that from the scheme, culturable command area of 154
ha will be irrigated at cropping intensity of 133 % and design discharge of 116.5 lit/sec.
Total length of irrigation network is 7 km.
23. The project cost is estimated PRs. 49.179 million and anticipated to take 12 months to
complete. The results of the economic analysis show that the project is economically
viable (EIRR 31.76 %). The financial analysis also indicates the safe investment with
FIRR as 27.36 %.
24. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas and necessary facilities for the staff /
labour to be engaged for the subproject. All the anticipated adverse environmental
impacts of the subproject are mitigatable, temporary in nature and localized which can
130 % and design discharge of 86.9 lit/sec. Total length of irrigation network is
4.63 km.
31. The subproject cost is estimated Rs. 47.884 million and anticipated to take 12
months to complete. The results of the economic analysis show that the
subproject is economically viable (EIRR 27.37 %). The financial analysis also
indicates the safe investment with FIRR as 23.75 %.
32. At the time of feasibility and detail design of CAD of Raghagan Dam it was learned the
command area of Kamar Ragha Daag falls within the command area of Raghgan Dam
so it was decided that it will be irrigated from the right bank channel of Raghgan dam
which is more feasible option.
33. Kamar Ragha Dag subproject is being executed as Variation Order (VO) of CAD of
Raghagn Dam subproject which is already under construction.
34. The CAD of Raghagan Dam subproject based on Rapid Environmental Assessment
(REA) is categorized as “B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature
and will cause some disturbances to the local environment during execution like
material dumping, machinery work; borrow material, camp areas and necessary
facilities for the staff/ labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporary in nature and
localized which can be mitigated through implementation of EMP.
35. The Bar Kas Dam is proposed on Brag Khwar in Tehsil Landi Kotal of Khyber District.
Bar Kas Dam subproject site is located at a distance of about 50 Km from District
headquarter Jamrud. The proposed Bar Kas Dam is located at coordinates 71.1483 E
& 33.9915N.
36. A 15 m high and 131.00 m long Bar Kas RCC Slab/Box Local Material Filled Dam with
reservoir capacity of 0.267 Mm3 and spillway flood capacity of 230 m3/sec is proposed
at Barkas area of Khyber District to collect water from the Brag khwar and convey it to
the barani (rain-fed) command area. Cultivable command area of 75 ha will be irrigated
at cropping intensity of 120 % and design discharge of 21.95 lit/sec. Total length of
irrigation network is 3.15 km.
37. The project cost is estimated Rs. 324.557 million and anticipated to take 18 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 7.51 %). The financial analysis also indicates the safe
investment with FIRR as 6.29 %.
38. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
39. The Magoo Dand Dam is proposed on Aziz Khwar in Tehsil Bara of Khyber District.
Magoo Dand Dam subproject site is located at a distance of about 37 Km from district
headquarter Jamrud. The proposed Magoo Dand Dam is located at coordinates
71.4756° E and 33.7649°N.
40. A 15 m high and 60 m long Magoo Dand Concrete Gravity Dam with reservoir capacity
of 0.3094 Mm3 and design flood capacity of 97 cumecs is proposed at Magoo Dand
area of Khyber District to collect water from the Aziz khwar and convey it to the barrani
(rain-fed) command area. Cultivable command area of 76 ha will be irrigated at cropping
intensity of 125 % and design discharge of 0.02473 m3/sec (24.73 liter/sec). Total
length of delivery pipe irrigation network is 316 m and 3.195 km respectively.
41. The subproject cost is estimated Rs. 252.427 million and anticipated to take 18 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 10.15 %). The financial analysis also indicates the safe
investment with FIRR as 8.58%.
42. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
43. Khurshid Dam is located at coordinates 34°22'28.9"N 71°35'54.1"E across Nawey Dand
nullah/ khwar, a tributary of Swat River. The subproject is located in Prang Ghar area
about 40 km North East of Ghalani (District Headquarter) of Mohmand District.
44. Irrigation canal on left bank offtake from main dam to irrigate the command area. The
entire canal length of 2.7 km from intake point to tail end is partially choked by eroded
material and damaged at different locations by the local community. Utilizing the water
through solar pumps, at both sides of Khwar, from main reservoir and channel for
irrigating lands at higher elevation is observed in command area. Water conveyance
from dam to the fields is the crux of the project.
45. The major issue with the construction of command area development of Khurshid dam
is blockage of main road when the reservoir rises to normal conservation level (El 434
m) whereas the bed level of stream at river crossing is 432m, in order to make the road
accessible the locals have to drawdown the reservoir which results in water loss of 13
ha-m out of 52 ha-m of reservoir capacity which is approx. 25% loss of water/ benefits.
In order to overcome this issue, the present study includes multi barrel causeway, with
the height of 4.0m, which will result in utilization of top 25% reservoir capacity for the
agricultural benefits.
46. The subproject is divided into five (05) number of chunks totaling command area of 104
ha. This project includes development of command area by providing irrigation network
from the Khurshid irrigation channel though outlet. The proposed system under study
will be able to irrigate 104 ha. This project involves primary (rectangular section),
secondary and tertiary watercourses (Parabolic Precast E types), fall structures,
syphon, road culvert, drainage culverts, sumps, minors through Parabolic Type E,
nacca and washing pads etc.
47. The existing cropping intensity is 70%. Future irrigation intensity of subproject is
proposed as 126%. Total length of main irrigation channel under this subproject is 6.08
km.
48. The subproject cost is estimated to be Rs. 119.772 million and is anticipated to take 12
months period to complete. The results of the economic analysis show that the project
is economically viable (EIRR 12.86 %). The financial analysis also indicates the FIRR
as 10.94 %.
49. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
50. The Bada Khel weir sub-project is proposed on Lashora khwar. The sub-project site is
located at a distance of 12 km from Jamrud, Khyber District Headquarter. As per site
observation there is perennial flow in the khwar.
51. With the development of irrigation scheme, the perennial flows of the Lashora khwar
will be utilized to irrigate, command area of adjacent locality. The design and layout
planning of the irrigation scheme have been done by considering, topography,
command area and geology of the weir axis.
52. Bada Khel weir is proposed to collect water from the khwar and convey it to the
command area of approximately 26.77 hectares lying downstream of the proposed weir
site. Cultivable command area of 26.77 ha will be irrigated at cropping intensity of 81.8
% and design discharge of 14.7 lit/sec will be required to serve the purpose. Total length
of irrigation network is approximately 2.77 km.
53. The project cost is estimated Rs. 22.477 million and anticipated to take 12 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 12.63 %). The financial analysis also indicates the safe
investment with FIRR as 11.16 %.
54. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
55. The Neeli Tangi weir sub-project is proposed on Neeli Tangi khwar and is located at a
distance of 68 km from Jamrud Khyber District Head Quarter. As per site observation
there is perennial flow in the khwar.
56. With the development of irrigation scheme, the perennial flows of the Neeli Tangi khwar
will be utilized to irrigate, command area of adjacent locality. The design and layout
planning of the irrigation scheme have been done by considering, Topography,
Command area and geology of the weir axis.
57. Neeli Tangi weir is proposed to collect water from the khwar and convey it to the barrani
command area. Cultivable command area of 80.36 ha will be irrigated at cropping
intensity of 100 % and design discharge of 21.11 liter /sec (0.75 cfs). Total length of
irrigation network is 7.12 km.
58. The project cost is estimated Rs. 58.437 million and anticipated to take 12 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 12.02 %). The financial analysis also indicates the safe
investment with FIRR as 10.16 %.
59. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
60. The Tarkho Kas Weir sub-project is proposed on Matu Nullah near village Naghara in
Tirah vallay in District Khyber and is located at a distance of 79 km from Jamrud Khyber
District head quarter. As per site observation there is perennial flow exist in the Nullah.
61. Tarkho Kas Weir is proposed to collect water from Matu Nullah and convey it to the
command area. Cultivable command area of 90 ha will be irrigated at cropping intensity
of 100 % and design discharge of 28.9 lit/sec. Total length of irrigation network is 5290
m.
62. The project cost is estimated Rs. 64.577 million and anticipated to take 12 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 12.23 %). The financial analysis also indicates the safe
investment with FIRR as 10.33 %.
63. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
64. The Tor Dara weir sub project has two weirs one on the main Tor Dara Nullah and the
other on its small tributary near village Natu Khel in Tirah Valley, District Khyber and is
located at a distance of 100 km from Peshawar.
65. During various visits at site the hydrological observation was made and found the
perennial flow in a range of 5-8 cusecs. In the last site visit was made approximately 5
cusecs of flows was observed on Tor Dara nullah and 0.30 cusecs was observed in its
tributary.
66. Tor Dara Weir and Natu Khel Weirs are proposed to collect water from Tor Dara Nullah
and its tributary to convey the available flows to the command area laying at both right
and left side of Tor Dara Nullah. Gross command area is 96 hectares and cultivable
command area is 93 hectares which is proposed to be irrigated at cropping intensity of
100 % with the design discharge of 22.90 lit/sec and 6.45 lit/sec for Tor Dara and Natu
Khel Weir respectively.
67. The main features of the project include construction of weirs, irrigation channels,
retaining walls, fall structures, road culverts and drainage culverts, on-farm water
management works and improvement of ware sheds through forestation. The project
cost is estimated as Rs. 93.804 million and is anticipated to take 12 months period to
complete. The results of the economic analysis show that the sub project is
economically viable (EIRR 12.03%). The financial analysis also indicates the safe
investment with FIRR as 10.23%.
68. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
Gallery and Serai Bazar Shah Infiltration Gallery) were completed in all respects and
were reported in 8thSAEMR January-June 2021. While in the current reporting period
three subprojects have been completed namely (CAD of Warsak Left Bank Kanal, Haji
Lawang Kas Weir and Tabai Small Dam). The subprojects completion report
(Environment Compliance part) for 19 subprojects were also submitted previously.
2.2.1 Construction of Haji Lawang Kas
71. The Haji Lawang Kas subproject is located downstream of confluence of Watalai and
Charmang Khwars. Haji Lawang site is located at a distance of 2.3 km from Khar
through paved road. As per site observation perennial flow of 2.16 cumec exists in the
khwar.
72. A network of subsurface pipe is proposed in the active flow channel of the khwar to
collect the flow. It is anticipated that from the scheme, culturable command area of 39
ha will be irrigated at cropping intensity of 133 % and design discharge of 78.3 lit/sec.
Total length of irrigation network is 1.95 km.
73. The project cost is estimated PRs. 23.207 million and anticipated to take 12 months to
complete. The results of the economic analysis show that the project is economically
viable (EIRR 15.14 %). The financial analysis also indicates the safe investment with
FIRR as 12.79 %.
74. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas and necessary facilities for the staff /
labour to be engaged for the subproject. All the anticipated adverse environmental
impacts of the subproject are mitigatable, temporary in nature and localized which can
2.2.2 Construction of CAD of Warsak Left Bank Canal
78. Warsak Dam is a mass concrete gravity dam located at coordinates 34°09′50″N & 71°21′29″E on the Kabul River, approximately 20 km northwest of the city of Peshawar
in the Khyber Pakhtunkhwa province of Pakistan.
79. Warsak Left Bank Canal offtakes from main Warsak dam through left bank irrigation
conduit 2 Km downstream of the main dam to irrigate the command area. The capacity
of left bank irrigation conduit is 45 cusecs. Total length of the canal is 18.4 miles.
80. Water conveyances from channel to the fields are unlined which causes excessive
seepage resulting in water shortages at the tail end. The present feasibility study
undertakes the on-farm water management by lining the watercourses and construction
of proper Nuccas. Irrigation Department KP has also executed a separate project for
lining of main channels. This was thoroughly discussed with the official of Irrigation
Department and it was mutually agreed that FWRDP will undertake the on-farm water
management while Irrigation Department will continue with the main irrigation channels.
81. As per Irrigation Department, water availability for the Warsak Left bank Canal System
is120 Acre/Cusecs which seems to be enough to feed the proposed command area.
Agriculture study including crop water requirement carried out under this subproject
reveals that the allowance kept by the Irrigation Department is sufficient and with
execution of this subproject the present irrigation intensity will increase from 108% to
150%.
82. The subproject is divided into two (02) numbers of chunks totaling command area of
926 ha. The subproject includes lining of watercourses by using parabolic type-D
segments, Type-E segments, and PCC channel at some locations including allied
structures (Nuccas, Culverts and Washing pads). Total length of watercourses network
in On-Farm Water Management Works under this subproject is estimated to be 64.647
Km.
83. The total project cost is estimated to be Rs. 238.749 million and is anticipated to take
15 months period to complete. The results of the economic analysis show that the
project is economically viable (EIRR 16.53 %). The financial analysis also indicates the
safe investment with FIRR as 14.27 %.
84. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it does not involve
permanent land acquisition. No indigenous people or women headed households are
found in the subproject area. Safety of public and workers, security problems, risk of
communicable diseases, vector borne diseases etc. are of temporary nature which can
be mitigated through well managed operations. Expected benefits of the subproject are
88. The Tabai Dam is proposed on Tabai Khwar of Tehsil Landi Kotal of Khyber district.
Tabai Dam sub project site is located at a distance of 43 km from Ali Masjid through
paved road and about 60 Km from district headquarter Jamrud. The proposed Tabai
Dam is located at coordinates 70.9715 E & 33.9977 N.
89. A 15 m high and 49.50 m long Tabai concrete gravity Dam with reservoir capacity of
0.206 Mm3 and spillway flood capacity of 95 m3/sec is proposed at Tabai area of
Khyber district to collect water from the khwar and convey it to the barrani command
area. Culturable command area of 50 ha will be irrigated at cropping intensity of 120 %
and design discharge of 14.64 lit/sec. Total length of irrigation network is 2.75 km.
90. The project cost is estimated Rs. 153.44 million and anticipated to take 18 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 7.27 %). The financial analysis also indicates the safe
investment with FIRR as 5.64 %.
91. The subproject, based on Rapid Environmental Assessment (REA), is categorized as
“B” as per Asian Development Bank’s Safeguard Policy Statement (SPS) 2009. The subproject bears site specific impacts of temporary nature and it will cause some
disturbances to the local environment during execution like material dumping,
machinery work; borrow material, camp areas, link roads and necessary facilities for
the staff / labour to be engaged for the subproject. All the anticipated adverse
environmental impacts of the subproject are mitigatable, temporarily in nature and
localized which can be mitigated through implementation of EMP.
92. Contractor is bound to develop Site Specific Environmental Management Plan
(SSEMP), Traffic Management Plan, Solid Waste Management and Material
Management Plan, Occupation Health and Safety Plan etc. before starting the
construction activities and to ensure that no damage is done to the wildlife, public
infrastructure and local culture, customs, and traditions.
93. This subproject has been completed for civil works and the overall environmental
safeguard performance of the said subproject was rated satisfactory while the details
99. Project Management Unit (PMU) has made IEEs/EMPs of subproject as part of contract
agreement of contractor under general clauses. Contractor must abide these clauses
to ensure implementation of IEEs/EMPs in their entirety. DCSC must ensure
environment and social safeguard compliance and impact monitoring through the
contractor. ESMU orientated DCSC and contractors on environmental and social
safeguard compliances and monitoring in progress review meetings and during field
inspections. ESMU also delivered guidelines for environmental and social safeguards
monitoring of subprojects to DCSC and the contractors. Furthermore, ESMU undertook
monitoring visits of subprojects to assess the progress on environmental monitoring and
environmental management practices and advised contractor to ensure all
environmental compliances.
100. DCSC has reported progress on IEEs/EMPs implementation through its Monthly
Progress Reports. PMU prepares and submits Quarterly Progress Reports (QPRs) on
environment and social aspects to ADB. PMU holds progress review meetings
periodically wherein DCSC and contractor participate and give updates on
environmental compliance monitoring. PMU provides guidance to DCSC and
contractors to resolve environmental issues and to streamline environmental monitoring
and environmental management activities.
101. A good working relationship is being maintained between the contractors and DCSC
during the execution of the subprojects. Training workshops are arranged by the
Environment Inspectors on site for the capacity building of the contractors and their
relevant staff. They are briefed on updating the environment monitoring checklists by
following IEEs/EMPs. Contractor is bound to submit these checklists to DCSC on
weekly basis. Environmental Inspectors undertake site visits of contractor’s camps and subprojects sites and discuss measures for improvement in environmental safeguards
with contractors and their staff.
102. The contractor will be responsible for execution of construction activities and for
environmental protection through their field staff. The contractor is subject to
environmental protection liabilities under national environmental laws, ADB’s Environmental Safeguards, project IEE/EMP provisions and under their contract with
107. Two (02) subprojects are under construction in Mohmand District while six (06) are substantially completed. Their physical progress as December 2021 is presented in the following Exhibit:
Physical Progress of Sub Projects in Mohmand District
S.No Name of Sub-
Project Contractor Name
CCA
(Ha)
Commencement
Date
Completion
Date
Revised
Completion Date
Physical
Progress
Structural Progress
[Executed/Total Scope]
Weir/ Gallery/ Dam
(m/m)
Irri. Channel
(KM/KM)
OFWM
(KM/KM)
1 Saro Shah M/S PMC-JHK (JV) 100 25th -Jul-19 24th -Jul-20 22nd February
2021 79%
30 m (Weir)
(100%).
2.2/2.9
(75%)
4.2/4.2
(100%)
126 No of panel
installed at site.
2 CAD of Khurshid
Dam
M/S MBCC & Builders-
M/s PMC (Joint Venture) 104 29th December 2020 29th December 2021 55%
108. Six (06) subprojects are under construction in Khyber District while two subproject (Shangade Weir and Tabai Dam) is completed. Their physical progress as of December 2021 is presented in the following Exhibit:
Physical Progress of Sub Project in Khyber District
S.No Name of Sub-Project Contractor Name Commencement
Date Completion
Date
Physical Progress
(%)
Structural Progress [Executed/Total Scope]
REMARKS
Dam (m/m)
Irri. Channel (KM/KM)
OFWM
(KM/KM)
Inspecti-on
Hut
1 Bar Kas Dam M/S Tribal Global Construction 14-July-2020 14-Jan-2022 64.4% 64.1% 98.6% 18%
89.6%
Expected to be completed in time.
2 Magoo Dand Dam M/s National RCC Works 1-october-2020 31-March-2022
48.65%
43.86% 45% 2%
25.5%
• Social issue at main irrigation channel was resolved during a joint (R.E +PIU + T/L Designer) visit to the site on Friday dated Dec 17, 2021.
• The progress is lagging
3 Bada Khel Weir M/s New Malik Afridi & Co 16 February, 2021 15 February,
2022
50%
95 44% 35% -
The works are partially resumed on 28
Dec 2021. Delivery Pipe encasement & Sumps are
remaining.
Water Pressure testing is conducted for HDPE Delivery pipe on 28 Dec 2021.
RD.0+509 – RD. 0+820
4 Neeli Tangi Weir
M/s Habib Khan Builders
22 September, 2021 22 June, 2022
11.5 %
- - - -
• Mix design Cylinder for G-10, G-15, G-20 and G-30 has been casted.
• Steel Sample submitted for testing.
• Jointly survey of Neeli tangi COMPLETED.
• Excavation of Neeli Tangi Weir COMPLETED.
• Tarkho kas, Tor Dara and Natu Khel in Progress.
• Neeli Tangi excavation of Channel 2 in Progress.
• Tarkho kas excavation of channel in progress
5 Tarkho Kas Weir 22 September, 2021 22 June, 2022
3.1 General Description of Environmental Safeguards Activities
111. Environment Specialist of DCSC developed weekly environmental monitoring
checklists (see Annex-7 A) for environmental compliance of the subprojects. This
checklist is based on the recommended mitigation measures given in the EMP for
environmental safeguard at different stages of the subprojects. Contractors were
orientated how to fill out the checklist. A checklist for the Semi-Annual Environmental
Monitoring Report has also been formed to analyse the follow up of the ongoing
subprojects (see Annex-2).
112. Environmental Inspector of DCSC conducted environmental safeguard trainings of
contractor’s staff and workers on each subproject with the purpose to build capacity of the staff in environmental compliance monitoring and in ensuring environmental
safeguards for the subprojects. These trainings focused on EMPs of the subproject,
environmental monitoring checklists, environmental monitoring activities and Health,
Environment and Safety (HSE) of staff and workers. Knowledge on potential hazards
on the site and procedures to avoid such hazards and actions in case of any
incident/accident were communicated to contractor’s staff and workers. Environment Specialist of DCSC has followed up these trainings by assessing the capacity of
contractors’ staff and workers during site visits.
3.2 Site Audits
113. Contractors are supposed to conduct internal audits and review by their own staff to
ensure a safe, healthy, and secure environment, both physically and behaviourally, for
workers, equipment, property, visitors, and the public. DCSC has undertaken site
inspections of all under execution subprojects. The findings of these inspections are
being updated regularly in monthly environmental monitoring reports. Contractors are
advised to submit weekly environmental monitoring checklists to DCSC and implement
the environmental compliance activities in accordance with the approved IEEs/EMPs.
Contractors are improving their environmental compliance, yet they slack in some
areas. To ensure implementation of EMP the contractors were asked to nominate their
focal persons/site inspectors who will be responsible for environmental safeguards
implementation for weir sites while for dams’ sub-projects the contractors have
dedicated HSE Managers in their staff. The nominated site inspectors were trained on
EMP/SSEMP implementation and directed to submit weekly checklist regularly to
DCSC as previously weekly checklists were not submitted on regular basis.
114. Environmental Inspectors of DCSC carried out field visits of all subprojects on regular
basis. During these field visits meetings are convened with the contractors' staff and
workers, visual observations and photographs are taken and key findings are discussed
with the concerned engineering staff and the contractors. Recommendations are
communicated to the contractor to address environmental issues and non-compliances
n) During the reporting period, no major grievances were recorded. Contractors
are addressing the issues in consultation with PIU and DCSC. Other minor
onsite grievances are being addressed in consultation with local communities
and village chiefs.
o) There are no damages to houses or shops at any site.
p) No damage to Archaeological /Religious/Cultural or Historical sites.
q) First Aid Kits are available at construction sites.
117. The corrective action plan and trainings brought major change in the behavior of
contractors. As a result, environmental compliance is seriously considered in project
execution. Site inspectors has been trained and SSEMPs are being developed for each
subproject. The implementation of SSEMP and further trainings is bringing major
change in the behavior of the contractor’s staff towards environment friendly construction of all the sub projects. The contractors have assured they will not harm the
local environment and will take all the necessary steps for the protection and
conservation of natural environment and will make sure the health safety of workers
and local community.
3.3 Issues Tracking (Based on Non-Conformance Notices)
118. The overall environmental progress of almost all of the subprojects improved during this
reporting period. The total average compliance status was 91%, which is calculated on
the basis of observation checklist attached as Annex-2 and shown in Exhibits 32, 33
and 34 for District Mohmand, Bajaur and Khyber respectively.
Environmental Compliance %
Saro Shah CAD Warsak CAD Khurshid Avg
Conformance % 91 96 96 95
Minor Nonconformance %
9 4 4 5
Major Nonconformance %
0 0 0 0
Overall conformance Level of All Sub-Projects at District Mohmand
Environmental Compliance %
Kharkai Haji Lawang
Kas Khar Canal CAD Raghagan Avg
Conformance % 89 89 84 95 89
Minor Nonconformance %
11 11 16 5 11
Major Nonconformance %
0 0 0 0 0
Overall conformance Level of All Sub-Projects at District Bajaur
presented in Exhibit below depicts that percentage of closed issued is being increased
and overall trends are positive.
Issues Trending
123. Copy of NCN’s for major Non-Conformances is provided in Annex-3.
3.5 Unanticipated Environmental Impacts or Risks
3.5.1 COVID-19 Pandemic
124. Coronavirus disease (COVID-19) is an infectious disease caused by a newly discovered
coronavirus. COVID-19 can affect your lungs and airways. Symptoms can be mild,
moderate, severe or fatal. Most people who fall sick with COVID-19 will experience mild
to moderate symptoms and recover without special treatment.
125. Construction processes are dynamic with significantly varying number of workers on a
construction project site from day to day. The workers coming from diverse
environments and working closely together increases the risk of exposure to COVID 19.
126. The COVID-19 outbreak represents significant health and safety risks that were not
anticipated at project appraisal stage and is thus not reflected in any of the project’s safeguards instruments, most importantly the environmental management plan (EMP).
127. In accordance with the Asian Development Bank (ADB) Safeguard Policy Statement
2009 (SPS) and the loan agreement between ADB and the borrower, the borrower is
required to assess implications of unanticipated risks and impacts under the project;
and to identify and implement necessary risk mitigation measures.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
5
10
15
20
25
30
1 2 3 4 5 7 8 9
Issues Trending
Issues in SAEMAR % issues Closed % issues closed late/open
digital noise level meter to know the noise value at subproject locations. The field
instrumental Monitoring results reveals that the noise results is within limits of NEQS
and WHO guidelines.
137. Contractors are advised to keep their machinery in good condition and provide
personal protective equipment’s (PPEs) like ear plugs to the working staff at noise generating sites. Speed of the trucks and other vehicles used for construction activities
were to be controlled and the construction activities were to be limited to daytime only.
138. The environmental monitoring conducted during December 2021 deduces that no noise
or vibration related complaints from public or workers were registered at any of the
subproject site. However, Environment team of DCSC has reinforced contractor staff to
adopt mitigation measures to reduce the impact of noise and vibration as delineated in
EMPs. DCSC environment team repeatedly advised the contractors to keep their
machinery in good condition and provide personal protective equipment (PPE) like ear
plugs to the working staff to worn at noise generating sites. DCSC advised the
contractor to provide PPEs to workers. Contractors of all subproject’s sites were
advised to control vehicle speed and restrict construction activities to daytime only.
DCSC advised the contractors to carry out noise monitoring by using noise meter on
regular basis. Noise testing was carried out at sub projects where construction activities
were in progress.
139. Results of instrumental monitoring of noise are given in the exhibit below:
Noise Testing Results
4.3.3 Air Quality Monitoring
140. The ambient air of an area may be polluted due to emissions of Carbon Oxides (COX),
Sulphur oxides (SOX), Nitrogen Oxides (NOx) and Particulate Matter (PM10). The
industry that may produce high emissions of gases and other toxic elements is not
present in the any of the subproject area so only dust and smoke emissions were to be
170. In most workplaces, accidents are a nuisance for the worker and a headache for Project
Management Team. However, at construction sites, accidents have the potential to be
life threatening. With every new story about environmental disasters and trapped
labourers, construction sites become less and less appealing — even as the population
grows and demands new, updated structures increases. Regarded as one of the most
dangerous professions, construction work on the job site can be considered anything
but entirely safe. Obviously, the employers do need to mitigate safety hazards to
construction workers, but the workers need to keep in mind a lot of precautions
themselves when working in such hazardous conditions.
171. Thus, construction sites must be strived to safeguard their employees if not for the
ethical reasons, then for the economic ones. Here are eight ways construction
businesses can reduce workplace accidents. The following Good Practices at project
sites
6.1.1 Awareness
172. Before any worker — no matter his or her role or experience level — can set foot on a
construction site, he or she must be fully cognizant of the possible hazards. Ignorant
workers are perhaps the biggest dangers at any construction sight, as their unknowing
mistakes put everyone else at risk. Understanding of perils at hand and sustaining a
perpetual state of alertness is perhaps the number-one best way to prevent accidents
for which awareness campaign and risk assessment of each activity is done before start
of the new activity for the staff.
6.1.2 Training
173. Though most of a construction worker’s skills can be gained on the job, safety is one skill set that is best learned before works enter the construction site. Occasional
trainings are held on all sites for the labourers on standard safety and security practices.
Experienced workers were also provided with same trainings to refresh their knowledge
of standard safety by attending regular training sessions throughout the project cycle.
6.1.3 Communication
174. Accidents are more likely to occur when workers are unsure what to expect. Direct
communication regarding the day’s goals and activities resulted in cut down on
surprises that could cause bodily harm. Construction workers and supervisors are
17. At the end we can say that achievement is possible, when all the stakeholders involved
in Environmental Planning and Compliance work heartily and fully follow the prescribed
Guidelines.
18. Therefore, during the construction period of afore-mentioned subprojects, no accidents
were reported.
19. It is first project in the Tribal belt of Pakistan, where we achieved fully up to some extent
the Environment Compliance according to the Guidelines of Donor Agency.
E. Recommendations
20. The project’s design and implementation experience has yielded significant technical and institutional lessons on the nature of conditions in the water sector; as it is likely
that development of small and medium-sized irrigation schemes will continue to feature
in the sector development agenda, it is essential that these experiences are reflected
in ADB’s future analytical work, specifically in the assessment, strategy, and roadmaps
prepared as part of the country partnership strategy process.
21. An enabling environment is needed to allow farmers to supply the demand for their
production. Examples include
(i) a policy and institutional framework that promotes sound water resource
management;
(ii) a legal framework for water user associations that promotes cost recovery at least
sufficient to finance sustainable operation and maintenance (O&M);
(iii) rural infrastructure (e.g., roads that allow farmers to market their products, and farm
inputs to be delivered when they are needed);
(iv) efficient markets that are free of price distortions and barriers to competition for
both farm products and agricultural inputs; and
(v) access to information on demand, prices, and technology.
22. To successfully capture the opportunities created by growing markets, supportive
alliances must be created among upstream and downstream business partners (i.e.,
suppliers and service providers of agricultural inputs and implements such as farm
machines, agricultural processing entities and others related to markets). Extension
services must be provided; there must be access to improved seeds, fertilizers,
pesticides, and technologies; and private sector merchants must be involved in
marketing the incremental products.
23. In addition to the Environment Documentation, the Environment Compliance
Supervision at all level i.e., Client, Supervision Consultants and Contractor must be fully
technically sound and adequate in number to fulfil the requirements of the project.
Major Ensure to follow and implement Covid-19 SOPs and guidelines.
Contractor 15 Dec,
2021 Closed
4 December
2021 CSC
All Under Construction
sites
Displaying Safety signages
Moderate Proper safety signs should be installed by the Contractors
Contractor 15 Dec,
2021 Partially Closed
*Category of Non-Compliance
1. Minor: Within fifteen days: Draw attention through copy of daily check list 2. Moderate: Beyond 15 days and up to 30 days: Issue warning recorded on check list as well as separate letter 3. Major: Beyond one month: Do not verify the contractor’s invoice.
Activity Problem / Impact Mitigation Measures Timing to
Implement MM Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
Pre-Construction Stage Assure compliance with relevant construction field legislation.
Legal complications and delay in project
• Acquire construction permit/ Environmental NOC from local authorities.
• Preparation of SSEMPs for each site and get them approved by the Consultant, before the construction works start.
• Provide Water management guidelines if subprojects are executed near surface watercourse.
Before the construction of the project activities.
Number of reported non-compliances
Minimization and continued improvement in number of reported non-compliances
EPC Contractor
ESMU/ Consultant
Development of Strategies.
Problems arising due to non-compliance
• An ‘Operation Environmental Action Plan’ (OEAP) needs to be prepared demonstrating the manner in which the Contractor/Operator will comply with the requirements of management plans proposed in EMP/SSEMP.
• The following strategies and procedures will be developed prior to the commencement of Project operations:
• Project specific security and public access control strategy;
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Project specific air and noise control strategy;
• Project specific traffic control strategy;
Construction Stage Impacts Impacts on Land Resources Excavation • Noise &
Vibration
• HSE issues
• Vegetation loss will be avoided as much as possible and limited to demarcated construction area.
• Slope stabilization measures will be adopted such as adequate vertical and horizontal drains, cross drainage etc.
• Slope movements will be monitored around excavation work areas.
• Top six inches soil should be protected before excavation and should be placed back after completion of construction work.
• Excavated material shall preferably be reused after approval of quality control engineer of CSC.
• Non-reusable excavated material shall be safely dumped and leveled in barren land with approval from Environment specialist of CSC and
During Construction
• Implementation of SSEMP before start of works
• Annual reports and documentation of safety inspection
• Workforce /Community complaints
Not Significant (Minimal) Target = zero Threshold 1, with agreed mitigation
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
dumping location should be provided in SSEMP.
Waste Management
• Waste Pollution
• To minimize environmental impacts and avoid any need for disposal of earthwork materials or the importation and unnecessary storage of earth, the project will maximize the reuse of excavated materials.
• All of the construction activity will be contained inside construction area.
• Solid waste generation should be reduced and should be reused and recycled.
• Any residual spoil will have to be disposed in environment friendly manner, where it will be leveled and landscaped. The dumping sites must be approved by CSC environment specialist.
• To be made contractor’s obligation through contract document, as an SSEMP will be prepared by the contractor and waste management plan will be a part of it.
During construction stage
• EPC’s Site officer and EHS officer in place
• SSEMP including Waste Management Plan
• Zero Complaints from Community & Workers
• Internal auditing and reporting by EPC
Not Significant (Minimal)
EPC Contractor
ESMU/CSC
Labor camps and material storage
• Cultural & Social issues
• The contractor will, in consultation with RE, resolve the exact location of all these facilities within
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Water & Sanitation issues
the barren land owned by the local community that will be provided by the community temporarily and free of cost.
• The location of these facilities will be at least 500 m away from the settlements.
• The contractor will not locate and construct any facilities without the written approval of the CSC.
• Supervision by Consultant
• EHS officer implementing SSEMP Information Events for work force
Soil pollution due to oils and lubricants / equipment poor maintenance and repairs / refueling at the construction site.
• Soil pollution
• Water pollution
• Strict rules will be imposed on workers and labors to ensure that no such spills are caused.
• If the spills take place, it must be followed by treatment prescribed above as per the degree of spill.
• An Oil Spill Management Plan containing specific mitigation measures to be part of contractor site specific environmental management plan are:
• Spill prevention trays will be provided and used at refueling locations
• On-site maintenance of construction vehicles and equipment will be avoided, a vehicle maintenance area with impermeable floor will be designated.
Because the area can be subject to un seasonal heavy rain plan before and during construction (cut and fill, land reclamation etc.) while considering the climatic conditions.
Spill contingency plan is available at site Properly paved/cemented mechanical workshop No water bodies near the working area Staff Training over oil spillage All the vehicles and machinery seals are intact Containers are available for used oil
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Regular inspections will be carried out to detect leakages in construction vehicles and equipment.
• Fuels and lubricants will be stored in covered and dyked areas, underlain with impervious lining.
• Spill control kit (shovels, plastic bags and absorbent materials) will be available near fuel and oil storage areas.
• Contaminated soil will be removed from the site and disposed in a manner to ensure protection of water sources
• Emergency plan for spill management will be prepared and inducted to the staff for any incident of spill.
• The bottom of any soak pit or septic tank will be constructed at least 100 meters away from springs and water bores
• Record of spills and Volume of removed contaminated soil will be maintained.
• Record of remedial measures taken will be maintained.
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
Heavy Machinery near agricultural land
• Agriculture Land Damage
• It is contractor’s obligation not to cause such damage and strictly follow the design.
• Top six inches soil will be protected and land will be restored to its previous condition after completion of construction works.
Construction and post construction
• Monthly Reports (EPC)
• Supervision by Consultant
• EHS officer implementing SSEMP
Information Events for work force
Not Significant (Minimal)
Contractor ESMU/CSC
Earth borrow • Land owner problems
• Levelling of land after borrowing
• Issues to the local community
• Compensation difficulties
• No private land will be acquired for the borrow areas.
• The Contractor will ensure that selected borrow areas on irrigation land are clearly demarcated and approved by the engineer including the allowed depth of the excavation before starting excavation.
• The borrow areas will be leveled. The Contractor will not leave the borrow pits in such a condition that they are unsuitably filled with rain water and cause the problem for the community.
• If the borrow area is near to the settlements, then it should be fenced completely.
• If agriculture land needs to be used as borrowing area, then the Contractor will adopt the following
Construction and post construction
Top soil management Government approved site Approval for any other site by RE and Government Borrow area management generated and implemented Agreement in case of private land owner Grievance redress Mechanism Leveling of Borrow Area
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
methods during the digging process.
• Fix the location of excavation.
• Remove thirty centimeters of the top soil and keep it on reserved site for re-spreading in the field.
• Excavate up to one-meter depth.
• Maintain the slope as far as possible.
• Place the top soil back during the restoration
• Pay compensation for any damages/ crop losses.
Movement and Operation of heavy machinery & vehicles
• Change in Soil characteristics e.g. soil erosion, contamination and compaction
• Avoid use of heavy machinery where possible.
• Contractors before handing the site back will apply such measures as to mitigate the impact of compaction and leave the site almost in the same state in which it was occupied.
• Pictures of the area should be taken before handing it over to contactor which will help the RE to ensure an acceptable state of soil while getting the area back from the contractor.
During construction
• Monthly Reports (EPC)
• Supervision by Consultant
• EHS officer implementing SSEMP
• Information Events for work force
Not Significant (Minimal)
Contractor ESMU/CSC
Construction material
Waste generation due to closure of site
• All shivers and material that remain after the closure of temporary
Completion of Construction
• Site Inspection
• Implementation of Environmental
Not Significant (Minimal) Short term during construction phase
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
leftovers and site restoration
Occupation of usable land.
construction sites are to be removed from the location and re-used/re-cycled where possible.
• All remains are to be disposed of in a manner that will not be harmful to environment.
Enhancement Program
Beneficial in long terms with the implementation of Environmental Enhancement Program
Impacts on Hydrology and Water Resources Washing of Vehicle and equipment in the stream
• Contamination of Surface water
• Contractor will demarcate a washing area for all sorts of washing activities, with running water facility connected to a dedicated drain flowing into the septic tanks. There would be restriction on servicing/ washing of vehicles and equipment at site.
During Construction
• Documentation of audit and remedial actions where necessary
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal) Short term during construction phase
Contractor ESMU/CSC
Drinking Water supply
• Water borne diseases & other water related issues
• Contractor, under the guidance of Environment Specialist of CSC, will get spring water tested for chemical and biological contaminants, and assist in providing filtration to make water drinkable.
• There are numerous cost-effective water treatment models available in order to mitigate chemical and/or biological contamination. Sand filtration, Chlorination, UV treatment and oxidation are a few such methods.
Before construction and during the project activities.
• Documentation of audit and remedial actions where necessary
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
Municipal solid and liquid Waste Generation
• Nuisance and Soil Pollution, diseases due to dumping
• Solid waste bins will be placed at labor eating and resting areas.
• Latrines and washing areas with septic tanks will be erected by the contractor at the construction site.
• Waste from the project construction area and office area shall be segregated and collected by the Tehsil Municipal corporation for dumping at approved land fill site or if small amount then a natural gully or uncultivable land for dumping will be arranged with approval from CSC Environment Specialist.
• All these provisions will be incorporated in site Contractor Site Specific EMP for construction. Prior utilization, all the landfill sites or disposal sites will be approved by CSC Environment Specialist
During construction
• Implementation of SSEMP
• Site auditing
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal)
Contractor ESMU/CSC
Water Quality and Sedimentation Load
• Health issues to labour from water borne diseases
• Surface water quality deterioration
• Quarterly water sampling and testing will be conducted in order to ascertain water quality during different seasons.
• Two samples each from the labour camp and 10 m
During Construction and Post Construction
• Plan to be developed before completion of construction
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
due to construction and operation of the project
downstream location of the weir and will be drawn for testing to make comparison of water quality with the baseline data to determine its suitability for labour consumption or any change in water quality due to construction of weir.
• Quarterly Water Monitoring Reports by EPA certified Laboratory
Impacts on Air Quality and Noise Pollution Dust/smoke Emission from plants and equipment
• Air pollution
• Lung Diseases
• Contractor’s contractual obligation will include keeping the dust and smoke within permissible level by using machinery, which is well maintained and with low noise.
• Land, all katcha roads and paths will be sprinkled with water after regular intervals.
• The contractor must avoid/ control the dust and smoke by carefully storing and distributing the construction material so as to cause minimum dust which again should be within the acceptable limits.
During Construction. Water sprinkling to be done on regular/daily basis.
• Water sprinkling Records
• Monthly reports EPC
• Site Inspection and Audits
• Monthly Monitoring Reports by EPA certified Laboratory
Not Significant (Minimal)
Contractor ESMU/CSC
Smoke from burning of waste or firewood
• Cutting of trees and shrubs
• Smoke pollution
• Contractor shall strictly prohibit burning of waste or of wood, especially extracted from nearby shrubs and bushes.
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Diseases • Contractor must provide clean fuel like LPG cylinders to the labor to use for their daily purposes.
• Internal auditing and reporting by EPC
Operation of heavy mechanization and generators.
Noise pollution
and vibration
• Contractor’s contractual obligation is to use new, well maintained and low noise machinery preferably during day time.
• The drivers, operators and workers working on or near the heavy machinery must be provided with ear plugs. The contractor will ensure use of newer, well maintained machinery that creates minimum noise and emissions, as per National Environmental Quality Standards (NEQS 2000)
• Environment Specialist of CSC will ensure that this clause is added to the bidding and contract document.
• Night time construction activities will be strictly discouraged, and may only be carried out in exceptional cases, with prior permission of Resident Engineer.
• Noise monitoring will be carried out near sensitive
During Construction stage
• EPC Site Manager and EHS Officer in Place
• Audit and Inspection record of heavy mechanization and generators.
• Monthly Noise level Monitoring Reports by EPA certified Laboratory
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
receptors on a quarterly basis.
• The NEQS for noise in residential areas is 55 dB (A) in the day-time and 45 dB (A) at night. It is recommended that noise levels close to sensitive receptors do not exceed 55 dB (A) during the day time as required by the NEQS.
Stone quarrying and Transportation of material
• Dust Emission and lungs diseases.
• Contractor shall use the road network carefully and repair any damages immediately.
• During transportation, covering of vehicle with sheet will be done.
• Unloading of vehicles will be done on designated sites.
During construction.
• Recording of violations and corrective measures
• Performance of Regular Driver Training (target 100% participation of drivers)
• Instruction and Information Events for workforce
• No. of accidents (Target=0)
Not Significant (Minimal)
Contractor ESMU/CSC
Impacts on Biological Resources Multiple project activities
• Damage to Flora and Fauna
• Impact on aquatic life
• Environment Specialist together with FATA line departments will ascertain the status of the site area in terms of occurrence of wildlife species, flora and
Rerouting and site identification during design stage and other matters during
• EPC internal monitoring and monthly reports
• Site auditing
Not Significant (Minimal) during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
fisheries. And in accordance, recommend a watch and ward system that will be based on partnership between communities, wildlife, forest & fisheries departments and political administration. Each partner’s roles will be specified at the onset, and responsibilities assigned.
• Till the completion of the survey, contractor will ensure no extraction takes place from the surrounding vegetation for fuel wood or hunting of any birds by the labor employed.
• If such a case is witnessed, it will be brought to the notice of the project management as well as the concerned Assistant Political Agent (APA).
• Contractor’s obligation is to strictly respect the limits of construction site.
• Cutting of trees will be strictly prohibited and if no alternate is available plantation of trees will be done in case any tree is cut for project activities.
construction of relevant activities
• Photographic record of pre and post project
• Implementation of Environmental Enhancement Program
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Tree cutting will be restored by planting four trees against each tree cut.
• Borrow areas with least vegetation cover will be selected.
• The project will have a soft start for allowing time to reptiles to move away from the project site.
• There will be restriction and prohibition on hunting, shooting, trapping, and poaching of wild species.
• No night time activity will be carried out.
• Photographs of the project area will be taken at pre and post project stage.
• Continuous inspection of the area will be carried jointly with other agencies involved in maintenance of protected areas.
Impacts on Socioeconomic and Cultural Issues Project Activities
• Tribal tensions and rivalries
• For matters pertaining to social obligation and benefits of the communities, if needed, a social Framework Agreement shall be signed by the RE with communities to ensure their participation and full satisfaction in matters pertaining to them. All
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
matters where contractor is involved, these should be made as his contractual obligations.
• Project Team along with the Social Development Specialist will ensure continuous liaison with the communities throughout the construction phase of the project, so as to identify any such incident in time. Relevant political authorities will be kept abreast of the progress, as well as any such issue if in making.
• If, during the execution of the activities or excavation, any material is discovered onsite, which may be considered of historical or cultural interest, such as evidence of prior settlements, native or historical activities, evidence of any existence on a site, which may be of cultural significance, all work shall stop and the supervising contracting officer shall be notified immediately. The area in which the material was discovered shall be marked and the evidence preserved for examination.
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• The contractor is required to develop Chance Find Procedure as part of the SSEMP.
Excavation activities
Impact on the existing civil infrastructure and facilities, especially underground installations (water supply and sewerage pipeline etc.) which cause obstacles in the provision of services to consumers
• Precisely situate the position of infrastructure and underground installations at the local works in cooperation with the relevant institutions at all levels of authority.
• Close liaison with local relevant authorities
• Should the damage take place, the contractor must contractually be bound to carry out repair immediately.
Before the construction of the dam and all other structures, the APs should be given sufficient time and compensation to satisfy them.
• Continued Community Consultation Records
• No. Of Grievance’s (Target=0)
• Monthly Reports on Information activities and response from community
• Liaison Records with local relevant authorities
Not Significant (Minimal)
Contractor CS Consultant / EMU in cooperation with concerned Department. I-e, Public Health etc.
Multiple project activities related to HSE
• Risk of injuries at work
• Spread of COVID-19
• The contractor will ensure that proper HSE protocols are in place, including protective gear, drinking water, sanitation, energy supply and overall safety for the labor.
• Evacuation plans in case of fire or any other accidents will also be prepared, and drills carried out to ensure the labor is aware of responding to such a situation.
Prior to commencement and during construction
• Site Inspection
• Monthly EPC Reports
• PPEs issuance records
• Health and safety Plans in Place and Implemented
• Implementation of Construction Site Organization Plan
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• A detailed HSE Plan will be formulated in SSEMP.
• The Construction processes are dynamic with significantly varying number of workers on a construction project site from day to day. The workers coming from diverse environments and working closely together increases the risk of exposure to COVID 19. The
project will follow both GOP
SOPs and ADB guidelines on
COVID-19.
• Without prejudice to the following, all possible and prescribed actions shall be taken at the project site, as should facilitate the health of all life present at the site.
• Every construction project shall make proper arrangements for uninterrupted building services including but not restricted to, electricity, fuel, water supply, water disposal and sanitation, communication links, washrooms with hand hygiene and shower facility and with proper and
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
adequate supply of soaps and disinfectants.
• All incidences of appearance of the symptoms of COVID-19 shall be immediately documented and maintained at the site and information regarding which shall be immediately communicated through e-mail or else, to the designated health facility, and the sick worker shall be transported to the health facility for further advice and action. The site manager must establish a link with a nearby healthcare facility with arrangements for quick transportation of workers in case of an emergency.
• Persuade the workers to inform the authorities for their safety and of other if they observe any signs and symptoms in a colleague.
• Do not allow any worker at the construction site who has the symptoms.
• Display the awareness banners about hand hygiene and physical distancing, where you can, around the work site.
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• The lunch breaks and stretch breaks of the workers must be staggered to avoid the clustering of workers. Workers must not sit at less than 2 meters distance while having meals and while any other activity requiring interpersonal communications.
• In case of workers sleeping in at the site of construction, a safe distance of 2 meters must be ensured in the sleeping rooms •
• A supply of safe drinking water must be made available at the project site and maintained.
• Every individual must use face mask. Face mask shall be replaced as and when soiled or otherwise removed. Outer surface of face mask must not be touched with hands. Workers should wash their hands as frequently as practicable and shall not to touch their face with their hands during work.
• Workers must maintain no less than two arm lengths between them before, during after work at all the
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
times. They shall not make physical contact and shall be required to maintain separate personal gears and assets which must be clearly labelled and stored without intermix.
• Use safe transport arrangements which should not be crowded and should have social distancing in place during the entire process from pickups till drops at destination.
Operation Stage Impacts and Maintenance (O&M) Earth and Borrowing activities, fertilization for crops
• Change in visual character and soil erosion
• Restoration and Environmental enhancement plan to be prepared.
• Use of borrow areas with Engineer’s approval at specified depth.
• Limited movement of machinery.
• Documentation of area.
• Ensuring areas under crops are not used as borrow areas.
• Leveling and dressing of borrow areas; Water sprinkling.
• Rescue of any encountered species.
Pre-Operations • Implementation of Environmental enhancement plan
• EPC Construction Completion Report
• Site Inspection
Not Significant (Minimal) Short term during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
excessive application of fertilizers and pesticides
extension programs targeting use of Integrated Pest Management (IPM), green manure, and limiting use of pesticides/ fertilizers to required levels only will target farmer communities to inform and train them. In general, in erstwhile FATA area the farmer uses mostly the Farm yard manure or green manure. The pesticide use is also rare, because of less vegetables and fruit production.
program developed before completion of construction
• Use of irrigation water for cultivating high delta crops
• Cultivation of high delta crops will be strictly discouraged.
• Cropping pattern in accordance with the water balance model will be suggested and promoted.
Post construction
Agriculture extension program developed before completion of construction
Not Significant (Minimal)
Agriculture Directorate
PMU
Monitoring programmes
Mitigation plan implementation cannot be gauged
The following monitoring programmes will be developed prior to the commencement of Project operations:
• Landslide monitoring;
• Water quality monitoring
• Watershed and flood telemetry monitoring
Operational stage
Site Inspection Monitoring Reports
Beneficial in long terms with the implementation of Operation Environmental Action Plan’ (OEAP)
Irrigation Department
PMU
Training/ educational programmes.
Effect on employees` efficiency during project
The following educational programmes will be developed prior to the commencement of Project operations:
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
Implementation Responsibility
Supervision Responsibility
• Employee induction programme on environmental awareness;
A-Physical Conditions 1-Ambient air quality Are dust emissions being regulated through sprinkling water on the routes being used by the Contractor? □Yes □No
Are vehicle speeds being monitored to avoid excessive dust emissions at dust prone areas? □Yes □No
Are vehicle properly tuned/maintained to reduce air emissions? □Yes □No
2. Noise Control
Are noise levels remained within safe limits (<75dB)? □Yes □No
In case excessive noise levels are detected have appropriate mitigation measures been taken? □Yes □No
Is restriction on playing tape records and blowing pressure horns etc. is being observed? □Yes □No
2-Waste Material
Has any natural drainage been disturbed or altered? □Yes □No
Are the waste bins emptied regularly in the burn pit? □Yes □No
Is food waste disposed in the open? □Yes □No
Is the combustible waste burnt regularly in the burn pit? □Yes □No
Is any medical waste generated and handled properly? □Yes □No
3-Fuel/Lubricant
Are the fuel tanks properly marked with their contents? □Yes □No
Are the fuels and oils handled in a safe manner, ensuring no leakage or spillage? □Yes □No
Any spillage of liquid waste occurred? □Yes □No
If spillage occurred, managed properly? □Yes □No
4-Traffic management
Is vehicle speed limit of 30 km/hr. being followed? □Yes □No
Is the movement of all project vehicles and personnel been restricted to within the work areas? □Yes □No
Do all vehicles and equipment have muffles to reduce noise levels whilst working close to communities? □Yes □No
Movement of machinery restricted to designated routes? □Yes □No
Construction vehicles, machinery and equipment stated in designated places within RoW? □Yes □No
B-Biological Conditions 1-Flora
Has any tree cut/uprooted? □Yes □No
Have trees and branches been used as fuel wood? □Yes □No
2-Fauna
Are the drivers careful and watchful about wild and domestic animals? □Yes □No
• Contractor should locate camp facilities preferably at distance of 500 m or with the approval of DCSC at a minimum distance of 100 m from existing settlements, built up areas or wildlife habitats.
• The construction camp will be established in areas where vegetation cover removal
and tree cutting can be avoided.
• The camp areas should have adequate natural drainage to facilitate the flow of treated effluents preferably within the works and services land.
• The camp site should not be at blind spots, sharp turns to avoid any accidents due to
movement of machinery from the camp area. Properly designed warning signs and speed humps should be provided at inlet and outlet of the camp site.
• If camp land is on lease, the land owners should be compensated as per lease agreements.
Camp Site Management
• Contractor shall provide copy of the Environmental management Plan (EMP) at the concerned sites. Copy of the EMP should be available at camp site all the times.
• Contractor will nominate and authorize the individual(s) with role and responsibility to
implement EMP measures.
• EMP recommendations should be clearly understood by the concerned implementing individual(s).
• Contractor shall comply with the safety precautions for constructions as per ILO
convention 62.
• Contractor shall provide PPE to construction workforce and monitor if they are appropriately used.
• The labour shall be provided with the adequate potable water at site.
• Wood shall not be used as fuel or for any other activity.
• Contractor shall provide LPF cylinders for cooking and heating purposes.
• Contractor shall provide first aid kit at camp site and nominate/train individuals to
address any emergency.
• Camp site will be fenced to prevent trespassing.
• Maintain good liaison with local communities.
• Contractor shall maintain grievances log, where all community complaints are registered and follow up actions should be recorded.
• Contractor shall provide trainings to effectively implement project specific EMP. It may involve special trainings of workers on specific jobs.
• Training of construction workforce on health and safety and use of PPE (safety
shoes, helmets, gloves, masks).
• Construction workforce training in the storage and handling of material and chemicals that can potentially cause soil contamination and/or explosion.
• Contractor shall prohibit hiring of child labour and forced labour.
• Contractor shall encourage hiring of local labour.
Plans and Procedures
• Contractor shall prepare and submit health and safety plan.
• Contractor shall prepare and submit emergency response procedures for a) Spills and leakages b) Accident c) Fire fighting d) Electric
• Contractor shall prepare and submit worker’s training plan.
Waste Management
• Contractor will be responsible for treatment of wastewater from camp toilets. Wastewater will primarily pass through septic tank and later be discharge into soak pit.
• Solid waste generated during construction at campsite will be properly collected at source, treated, and safely disposed of only in selected waste disposal sites.
• Fuel and oil storage areas should be located away from any watercourses. They should be properly paved with contaminated ditch to control any spillage.
• Contractor will be responsible to contain, collect, clean-up and properly dispose-off the wastes in case of any emergency spill.
• Drinking water sources shall be at least 50 m away from soak pit to avoid contamination.
• Contractor will be responsible to implement proper dust and noise abatement procedures at camp site.