Brookline Reconstruction ProjectPioneer Avenue to Starcamp Street
Project Sponsors
City of PittsburghPennsylvania Department of Transportation
Federal Highway Administration
Consultant TeamMichael Baker Jr., Inc. John J. Clark & Associates
Santangelo &Lindsay, Inc.
Brookline Boulevard Reconstruction Project:Here Tonight to:
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
• Present Final Designs• Present Schedule for Construction
• Room Set Up:TablesBoards
Brookline Boulevard Reconstruction Project:Project Limits
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Pioneer
Starcamp
Brookline Boulevard Reconstruction Project:Project Development Process:
• Design Charrette• Development of Alternatives• Public Meeting #1 (December 2006)• Identify Preferred Alternative• Public Meeting #2 (May 2009)• Final Design• Public Meeting #3 (March 2012)• Construction
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Project Elements
• New Sidewalks/Crosswalks• Traffic Signals/Pavement Markings• Curb Extensions• ADA Ramps/Audible signals• Street Lighting• Street Trees / Landscaping• Roadway Mill/Pave/Markings
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Typical Roadway Pan
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Typical Landscaping Plan
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Sidewalk Treatments
Brookline Boulevard Reconstruction Project:Lights and Furniture
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Landscaping Palette
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Typical Landscaping Plan
Complete Designs June 2012Advertise Construction Aug. 2012Award Contract Sept. 2012Notice To Proceed Dec. 2012Start Construction March 2013
Phase 1A/1EPhase 1B/1DPhase 1C/1FPhase 2A/1CPhase 2B/2DPhase 2EPhase 3
FINISH CONSTRUCTION: November 2013
Brookline Boulevard Reconstruction Project:Project Schedule
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Construction Phasing
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:Maintaining Traffic/Access
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
Brookline Boulevard Reconstruction Project:
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh
QUESTIONS/COMMENTS
Brookline Reconstruction ProjectPioneer Avenue to Starcamp Street
Project Sponsors
City of PittsburghPennsylvania Department of Transportation
Federal Highway Administration
Consultant TeamMichael Baker Jr., Inc. John J. Clark & Associates
Santangelo &Lindsay, Inc.
Brookline Boulevard Reconstruction Project:Project Schedule
Bureau of Transportation and Engineering / Department of Public Works / City of Pittsburgh