1. Fire fighting installations: hose reel, sprinkler and portable fire extinguisher
2. SMM2 measurement rules for fire fighting installations
3. Taking off list for fire fighting installations
4. Heading and description.
FIRE FIGHTING INSTALLATION
Standpipe Sprinkler Portable
Dry Standpipe
Wet Standpipe
Hose Reel
Wet Pipe System
Dry Pipe System
Pre-action System
Deluge System
-Water tank
- Pump
- Pipes
- Sprinkler
- Alarm
-Water tank
- Pump
- Pipes
- Sprinkler
- Fire Detector
- Alarm
HOSE REEL
PORTABLE FE
FIRE ALARM
1. Builder’s Work
2. Hose Reel System
Swing hose- reel, Water storage tank, Electrical duty pump, Diesel duty pump, Piping: incoming pipe -rising pipe, distribution pipe
3. Fire Alarm panel
Manual Break Glass, Fire Alarm Bell, Batteries, Batery Charger
4. Brasswork
Air release valve, Gate valve, Check valve, Strainer valve, Flexible joint
5. Portable Fire Extinguisher
6. Equipment and Ancillaries
Concrete plinth
7. Pipe Support
Pipe hanger
8. Sundries
Testing
MAIN COMPONENTS
1. The British Standards Institution 750 For Fire Hydrant
2. The British Standards Institution 5839 Part 1, 1980 For Fire Alarm System
3. The Requirements Of The Chief Inspectorate Of The Fire Services Malaysia.
The fire protection system installed are in full compliance and regulations
LAW AND REGULATIONS : FIRE FIGHTING INSTALLATIONS
COMPONENTS
Fire alarm panel
Manual break glass
Alarm bell
FIRE ALARM SYSTEM : MANUAL ALARM
AN ALARM PANEL: monitors the state of all parts (zones) of theinstallation.
POINT DETECTORS: individual heat or smoke detection unitswhich respond to an irregular situation in the immediate vicinity
LINE DETECTORS: a continuous type of detection comprising apair of conducting cables separated by low temperature meltinginsulation to permit a short circuit alarm when the cable contact.
POWER SUPPLY: These should have primary (normal electricity)and secondary (battery) power supplies.
Fire Alarm System : FIRE FIGHTING INSTALLATIONS
Smoke Detector : FIRE FIGHTING INSTALLATIONS
Fire alarm system isfunctioning as a componentswhich give warning sign tooccupants in a building if it isburning.
It normally, installed withdetector.
There is 2 type of detector, passive (Manual break glass) and active (Smoke detector, heat detector, light detector).
‘KELUAR’ sign and emergency light
Flashing lights
HOSE REEL SYSTEM : WET RISER
Pressurised using 1 unit of electrical pumpset as duty pump & 1 unit diesel engine pumpset as standby
Designed to operate an automatic mode (Pressure switch) & manual mode (manual starting from the pumpsets control panel)
Standard coil length 30m, 36m or 100m.
Specification :-Working Pressure : 220Psi (15 Bar)Minimum Burst Pressure : 696Psi (48 Bar)Test Pressure : 250Psi
HOSE REEL SYSTEM: FIRE FIGHTING INSTALLATIONS
TYPICAL HOSE REEL: FIRE FIGHTING INSTALLATIONS
General purpose synthetic delivery hose. Suitable for industrial and rural fire brigades as well as static building protection.
General industrial, commercial and civil engineering applications including waterauthorities where a high burst performance hose is not necessary
Lightweight and flexible Heat and cold resistant Anti rot and anti-twist
Synthetic Delivery Nose : FIRE FIGHTING INSTALLATIONS
Branch pipes provide an adjustable nozzle to allow the curtain of water to be altered from a narrow spray to a wide spray.
Nozzles provide a fixed jet of water. The basic branch pipe according to BS336 has an 21/2" inlet male instantaneous and outlet threaded 11/3" BSP male for either a plain jet or a branchpipe adjustable nozzle.
The branch pipe is controlled from SHUT-OFF through JET and SPRAY to wide angle CURTAIN by rotating the annular sleeve.
Branch Pipe and Nozzle : FIRE FIGHTING INSTALLATIONS
HOSE REEL SYSTEM: DRY RISER
System for dry riser
This range includes:
inlet breechings
inlet and outlet cabinets
outlet valves
standpipes, bars and keys.
Dry Riser & Inlet Breeching: FIRE FIGHTING INSTALLATIONS
DRY RISER
Designed to house inlet breechings and landing valves
Georgian wired glass panel and spring cylinder lock with key
Manufactured from zintec, epoxy polyester powder coated - Red
Dry Riser Components: FIRE FIGHTING INSTALLATIONS
19
FIRE FIGHTING SYSTEM
MEASUREMENT RULES
SECTION Q PLUMBING AND MECHANICAL ENGINEERING INSTALLATIONS
Q.1 Information
Q.2 Clasification Of Work
Q.3 Location of works
PIPEWORKS
Q.7 Generally
Q.8 Pipe and Fittings
Q.9 Special Connection, etc
Q.10 Labour
Q.11 Sundries
Q.12 Pipework Support
Q.13 Connection
EQUIPMENT AND ANCILLARIES
Q.19 Generally
Q.20 Antivibration and sound insulation
Q.21. Equipment support
Q.22. Jointing
Q.24. Identification plates
BUILDER’S WORK
Q.31 Generally
Q.32. Particularly
Section Q: MEASUREMENT RULES
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.2 Clasification of Work
D.Fire Fighting Installation
GENERALLY
Q.1 INFORMATION
FIRE FIGHTING INSTALLATION
Generally
Q.1. Information
1 Particulars of the following shall be given :
a) Regulation, etc.
b) Kind and quality of material.
c) Gauge, thickness or substance of material.
d) Any tests, etc.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.1.2 Assembling and jointing together the component
parts of composite units and providing any necessary
connecting flanges and jointing materials shall be deemed
to be included with the items concerned. Where composite
units are supplied by the Employer, particulars shall be
given of the assembly work involved.
Q.1.3 Patterns, moulds, templets and the like shall be
deemed to be included with the items.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.1.4 Priming and painting off-site and proprietary
finishes or surface treatment applied as part of the
production process shall be described stating whether
applied before or after fabrication or assembly.
Q.1.5 Except where otherwise stated the method of fixing
and the provision of nails, bolts, nuts, holes, screws, plugs,
shot-fired pins and the like shall be given in the description
of the work.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.1.6 The nature of the background to which work is to be fixed shall be given in the description. Any necessary drilling of the backgrounds shall be deemed to be included. Backgrounds shall be classified as follows :
a) Building-board which shall be deemed to include hardboard, compressed cement sheet, plasterboard, fibreboard and similar materials which do not grip woodscrews.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.1.6 The nature of the background ….
b) Timber which shall be deemed to include softwood, hardwood, blockboard, plywood and similar materials which will grip wood-screws when a lead-hole has been drilled.
c) brickwork, concrete or stone work
d) plain metal
e) glass
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.1.7. Temporary work shall be so described. Removing
temporary work and making good after shall be
deemed to be included with the item.
Q.1.8. Connecting to existing services – shall be described
Measurement Rules : FIRE FIGHTING INSTALLATIONS
GENERALLY
Q.2. CLASSIFICATION OF WORK
Q.2.1 Work together with its metalwork, supports and the like(unless associated with more than one installation) shall beclassified as follows and given under an appropriateheading :
d) Fire Fighting Installation
Measurement Rules : FIRE FIGHTING INSTALLATIONS
SETS OF FIRE FIGHTING EQUIPMENTS
Hose Reel
Portable FE
Fire alarm
Q.3. LOCATION OF WORK
Location of works :
a. Internally
b. Externally
c. In plant rooms
Measurement Rules : FIRE FIGHTING INSTALLATIONS
PIPE WORKS
Q.7 GENERALLY
1. Purpose-made pipes and purpose-made pipe fittings shallbe described.
2. Pipes and pipe fittings which are wrapped, coated or linedby the manufacturer shall be so described stating the type oftreatment.
3. Pipework required to be temporarily fixed in position,dismantled for chromium-plating or other special finishingand subsequently refixed shall be so described.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.8 PIPE AND FITTING
1. Pipes (measured over all pipe fittings, short running
lengths and branches) shall be given in metres stating the
type and the normal size.
Purpose-made pipe shall be so described and given
separately. Curved pipes shall be so described stating the
mean radius.
Joints in the running length shall be given in the
description stating the method of jointing.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.8 PIPE AND FITTING
3. Flexible pipes and extensible pipes (measured as fully extended) shall each be so described.
4. Pipes laid or fixed in ducts, trenches and chases or embedded in in-situ concrete or screeds shall each be so described.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
PIPING INSIDE SWITCH ROOM
HEAT DETECTORHOSE REEL PIPE
CONDUIT
Pipe Fittings: FIRE FIGHTING INSTALLATIONS
Q.9. SPECIAL CONNECTIONS, ETC.
1. Special connections and special joints in pipes shall
each be enumerated separately (except where given in
the description of another enumerated item) stating the
nominal size and kind of pipe concerned and the method of
jointing. Classification shall be as follows :
a) Connections between pipes of differing materials and
differing grades of the same material.
b) Connections between pipes and appliances or
equipment.
c) Connections to existing pipes.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.10.LABOURS
Labours on pipes (e.g. made bends, made springs, made
offsets, beaded ends, ornamental ends, etc.) shall be deemed
to be included with the pipes on which they occur.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.11 SUNDRIES
6. Pipe-sleeves through walls, floors ceilings shall be
enumerated stating the type, lengths, the nominal size and kind
of pipe passing through and the type of packing required, and
if to be supplied for fixing by other trades, this shall be so
described.
7. Wall, floor or ceiling plates shall be grouped together
as plates and enumerated stating the type and size.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
PIPE-SLEEVES
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.12 PIPEWORK SUPPORTS
12.1 Standard pipe supports shall be given in the description of the pipes stating the type and spacing of the supports.
12.2. Non-standard pipe supports shall be described and enumerated (no).
Q.12 PIPEWORK SUPPORTS
12.1 Standard pipe supports shall be given in the description of the pipes stating the type and spacing of the supports.
12.2. Non-standard pipe supports shall be described and enumerated (no).
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Q.12 PIPEWORK SUPPORTS
4. Components or assemblies of components (e.g.
clips, saddles, pipe-hooks, holderbats, brackets,
rollers, chairs and hangers or black-plates and girder-
lugs) used to fix supports for more than one pipe shall
be enumerated separately stating the type and size of
components. Spring compensated components shall
be so described stating the loading and movement to
be accommodated.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Pipe Supports: FIRE FIGHTING INSTALLATIONS
PIPE SUPPORT
Q.13 CONNECTIONS
Connections to public mains, making good public
highway and any other work which may only be carried
out by a Public Undertaking or Local Authority shall be
given as a provisional sum.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
EQUIPMENT AND ANCILLARIES
Q.19 Generally
1. Unless otherwise stated, equipment such asboilers, generators, heaters, water treatment plant,tanks cylinders, calorifiers, pumps, coolers, air-handling unit, fans, refrigerator equipment, meters,sanitary fittings, etc. and ancillaries such as sootdoors to boilers, valves and cocks, gauges,automatic controls etc. shall be enumerated andrelated to the specification referred to in clauseQ.1.1.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
EQUIPMENT AND ANCILLLARIES
Q.19 Generally
2. Shall be described in conjunction with a manufacturer’s detailed specification (Q.19.2)
3. Any limiting dimensions on the size shall be given. (Q.19.3)
4. Electrical connection shall be given in accordance with section R . (Q.19.4)
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Main pump is fully operated byelectricty
Standy by or back up pump whenthe electrical pump can notfunction due to electricity shutdown
135 main flow, 40 m pressure and 2900 rpm
Equipment and ancillaries, Q.19. and measured in NO
Electrical & Diesel Pump: FIRE FIGHTING INSTALLATIONS
Equipments and
ancillaries
– Clause Q.19.
– Unless otherwise
stated, equipment
such as tank shall be
enumerated (no).
Water Storage Tank: FIRE FIGHTING INSTALLATIONS
EQUIPMENT AND ANCILLLARIES
Q.20 Anti-vibration and sound insulation
Anti-vibration mountings for plant shall be
enumerated stating the type and the size. Anti-
vibration material and sound-insulating material in
plant bases shall be given in square metres stating
the nature of the material and the thickness.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
Anti Vibration Material: FIRE FIGHTING INSTALLATIONS
EQUIPMENT AND ANCILLLARIES
Q.21 Equipment supports
1. Equipment supports shall be enumerated and
described.
2. Particulars of the method of fixing shall be
given in the description in accordance with
clauses Q.1.5-6.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
EQUIPMENT AND ANCILLLARIES
Q.22 Jointing
Particulars of the method of jointing shall be given in
the description of the equipment.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
EQUIPMENT AND ANCILLLARIES
Q.24 Identification Plates
Identification plates shall be deemed to be included.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
SUNDRIES
Q.30 Generally
1. Draining and refilling existing system shall be
given as a provisional or prime cost sum.
2. Disconnecting, setting aside and refixing
equipment for the convenience of other trades shall
be given as an item stating the relevant particulars.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
SUNDRIES
Q.30 Generally
3. Temporarily operating each installation (except
for testing) shall be given as an item stating any
required qualifications of the attendant, the duration of
the operating period in hours and the purpose and
particulars of any special insurance cover required by
the Employer. Provision of solid fuel, liquid fuel, gas
and electricity for power and lighting shall be
deemed to be included with the item
Measurement Rules : FIRE FIGHTING INSTALLATIONS
SUNDRIES
Q.30 Generally
4. Testing each installation shall be given as an item stating any required qualifications of the attendant, the number of stage tests in addition to the final, the purpose of the tests, the instruments and appliances required to be provided and particulars of any special insurance cover required by the Employer. Provision of solid fuel, liquid fuel, gas and electricity for power and lighting shall be deemed to be included with the item.
5. Preparing plans or diagrams of the installations as fitted shallbe given as an item stating the kind of information required tobe shown and the number of copies of each drawing requiredto be provided.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
BUILDER’S WORK
Q.31 GENERALLY
1. Unless otherwise stated, all items of builder’s
shall be given in accordance with the appropriate
section.
2. Builder’s works in connection with plumbing and
mechanical engineering installations shall be
grouped together under an appropriate heading.
Measurement Rules : FIRE FIGHTING INSTALLATIONS
BUILDER’S WORK
Q.32 PARTICULARLY
1. Excavating trenches for pipes not exceeding 55mm nominal size shall be given in accordance with clause D.12.9
2. For pipe over 55mm shall be given in accordance with clause V.2
3. Cutting away for making good after M&E works……
Measurement Rules : FIRE FIGHTING INSTALLATIONS
TAKING OFF LIST
1.Hose Reel System
Swing hose reel
Water tank
Electrical duty pump
Diesel standby pump
3.Brass Works
Ball float valve
Strainer valve
Stop valve
Flexible connection
Check valve
Gate valve
Pressure gauge
2.Pipe Works
Incoming pipe
Distribution pipe
Rising pipe
Painting to pipe
4.Fire Alarm System
5.Portable Fire Extinguisher
6.Builder’s work
7.Testing
Taking off Lists: FIRE FIGHTING INSTALLATIONS
Preamble
Hose Reel System
– Swing hose reel - NO
– Water storage tank - NO
– Electrical duty pump - NO
– Diesel standby pump - NO
Piping Works
• 50 mm Diameter incoming pipe - M
• 50 mm Diameter rising pipe – M
• 50 mm Diameter distribution pipe - M
Brasswork
• 50 mm Diameter air release valve – NO
• 50 mm Diameter gate valve – NO
• 50 mm Diameter check valve – NO
• 50 mm Diameter strainer valve – NO
• 50 mm Diameter flexible joint – NO
• 25 mm Diameter gate valve – NO
TAKING OFF LIST
Fire Alarm System
– Control gear – NO
– Junction box – NO
– Manual break glass – NO
– 2 x 2.5 mm cable – M
– 50 mm Diameter conduit – M
Portable Fire Extinguisher
– 9 kg Fire extinguisher - NO
– Hydrant Hose Cabinet – NO
Lighting Installation
– Keluar sign - NO
– 5A Emergency light – NO
Testing
– Allow for testing the foregoing fire fighting system – ITEM
Builder’s Work
– Excavate trench to receive pipe - M
TAKING OFF LIST