Sr. Dr. Sarajul Fikri Mohamed Faculty of Built Environment MECHANICAL & ELECTRICAL WORKS MEASUREMENT (SBEQ3213) Week 12 : Fire Fighting System - Hose Reel, Sprinkler & Fire Extinguisher
63

12-Fire Fighting System

Dec 02, 2015

Download

Documents

sarathirv6

As per Malaysian SMM
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: 12-Fire Fighting System

Sr. Dr. Sarajul Fikri Mohamed

Faculty of Built Environment

MECHANICAL & ELECTRICAL WORKS MEASUREMENT (SBEQ3213)

Week 12 : Fire Fighting System - Hose Reel, Sprinkler & Fire Extinguisher

Page 2: 12-Fire Fighting System

TABLE OF CONTENTS

1. Fire fighting installations: hose reel, sprinkler and portable fire extinguisher

2. SMM2 measurement rules for fire fighting installations

3. Taking off list for fire fighting installations

4. Heading and description.

Page 3: 12-Fire Fighting System

FIRE FIGHTING INSTALLATION

Standpipe Sprinkler Portable

Dry Standpipe

Wet Standpipe

Hose Reel

Wet Pipe System

Dry Pipe System

Pre-action System

Deluge System

-Water tank

- Pump

- Pipes

- Sprinkler

- Alarm

-Water tank

- Pump

- Pipes

- Sprinkler

- Fire Detector

- Alarm

Page 4: 12-Fire Fighting System

HOSE REEL

PORTABLE FE

FIRE ALARM

Page 5: 12-Fire Fighting System

1. Builder’s Work

2. Hose Reel System

Swing hose- reel, Water storage tank, Electrical duty pump, Diesel duty pump, Piping: incoming pipe -rising pipe, distribution pipe

3. Fire Alarm panel

Manual Break Glass, Fire Alarm Bell, Batteries, Batery Charger

4. Brasswork

Air release valve, Gate valve, Check valve, Strainer valve, Flexible joint

5. Portable Fire Extinguisher

6. Equipment and Ancillaries

Concrete plinth

7. Pipe Support

Pipe hanger

8. Sundries

Testing

MAIN COMPONENTS

Page 6: 12-Fire Fighting System

1. The British Standards Institution 750 For Fire Hydrant

2. The British Standards Institution 5839 Part 1, 1980 For Fire Alarm System

3. The Requirements Of The Chief Inspectorate Of The Fire Services Malaysia.

The fire protection system installed are in full compliance and regulations

LAW AND REGULATIONS : FIRE FIGHTING INSTALLATIONS

Page 7: 12-Fire Fighting System

COMPONENTS

Fire alarm panel

Manual break glass

Alarm bell

FIRE ALARM SYSTEM : MANUAL ALARM

Page 8: 12-Fire Fighting System

AN ALARM PANEL: monitors the state of all parts (zones) of theinstallation.

POINT DETECTORS: individual heat or smoke detection unitswhich respond to an irregular situation in the immediate vicinity

LINE DETECTORS: a continuous type of detection comprising apair of conducting cables separated by low temperature meltinginsulation to permit a short circuit alarm when the cable contact.

POWER SUPPLY: These should have primary (normal electricity)and secondary (battery) power supplies.

Fire Alarm System : FIRE FIGHTING INSTALLATIONS

Page 9: 12-Fire Fighting System

Smoke Detector : FIRE FIGHTING INSTALLATIONS

Fire alarm system isfunctioning as a componentswhich give warning sign tooccupants in a building if it isburning.

It normally, installed withdetector.

There is 2 type of detector, passive (Manual break glass) and active (Smoke detector, heat detector, light detector).

Page 10: 12-Fire Fighting System

‘KELUAR’ sign and emergency light

Flashing lights

Page 11: 12-Fire Fighting System

HOSE REEL SYSTEM : WET RISER

Page 12: 12-Fire Fighting System

Pressurised using 1 unit of electrical pumpset as duty pump & 1 unit diesel engine pumpset as standby

Designed to operate an automatic mode (Pressure switch) & manual mode (manual starting from the pumpsets control panel)

Standard coil length 30m, 36m or 100m.

Specification :-Working Pressure : 220Psi (15 Bar)Minimum Burst Pressure : 696Psi (48 Bar)Test Pressure : 250Psi

HOSE REEL SYSTEM: FIRE FIGHTING INSTALLATIONS

Page 13: 12-Fire Fighting System

TYPICAL HOSE REEL: FIRE FIGHTING INSTALLATIONS

Page 14: 12-Fire Fighting System

General purpose synthetic delivery hose. Suitable for industrial and rural fire brigades as well as static building protection.

General industrial, commercial and civil engineering applications including waterauthorities where a high burst performance hose is not necessary

Lightweight and flexible Heat and cold resistant Anti rot and anti-twist

Synthetic Delivery Nose : FIRE FIGHTING INSTALLATIONS

Page 15: 12-Fire Fighting System

Branch pipes provide an adjustable nozzle to allow the curtain of water to be altered from a narrow spray to a wide spray.

Nozzles provide a fixed jet of water. The basic branch pipe according to BS336 has an 21/2" inlet male instantaneous and outlet threaded 11/3" BSP male for either a plain jet or a branchpipe adjustable nozzle.

The branch pipe is controlled from SHUT-OFF through JET and SPRAY to wide angle CURTAIN by rotating the annular sleeve.

Branch Pipe and Nozzle : FIRE FIGHTING INSTALLATIONS

Page 16: 12-Fire Fighting System

HOSE REEL SYSTEM: DRY RISER

Page 17: 12-Fire Fighting System

System for dry riser

This range includes:

inlet breechings

inlet and outlet cabinets

outlet valves

standpipes, bars and keys.

Dry Riser & Inlet Breeching: FIRE FIGHTING INSTALLATIONS

Page 18: 12-Fire Fighting System

DRY RISER

Designed to house inlet breechings and landing valves

Georgian wired glass panel and spring cylinder lock with key

Manufactured from zintec, epoxy polyester powder coated - Red

Dry Riser Components: FIRE FIGHTING INSTALLATIONS

Page 19: 12-Fire Fighting System

19

FIRE FIGHTING SYSTEM

MEASUREMENT RULES

SECTION Q PLUMBING AND MECHANICAL ENGINEERING INSTALLATIONS

Page 20: 12-Fire Fighting System

Q.1 Information

Q.2 Clasification Of Work

Q.3 Location of works

PIPEWORKS

Q.7 Generally

Q.8 Pipe and Fittings

Q.9 Special Connection, etc

Q.10 Labour

Q.11 Sundries

Q.12 Pipework Support

Q.13 Connection

EQUIPMENT AND ANCILLARIES

Q.19 Generally

Q.20 Antivibration and sound insulation

Q.21. Equipment support

Q.22. Jointing

Q.24. Identification plates

BUILDER’S WORK

Q.31 Generally

Q.32. Particularly

Section Q: MEASUREMENT RULES

Page 21: 12-Fire Fighting System

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Q.2 Clasification of Work

D.Fire Fighting Installation

Page 22: 12-Fire Fighting System

GENERALLY

Q.1 INFORMATION

FIRE FIGHTING INSTALLATION

Generally

Q.1. Information

1 Particulars of the following shall be given :

a) Regulation, etc.

b) Kind and quality of material.

c) Gauge, thickness or substance of material.

d) Any tests, etc.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 23: 12-Fire Fighting System

Q.1.2 Assembling and jointing together the component

parts of composite units and providing any necessary

connecting flanges and jointing materials shall be deemed

to be included with the items concerned. Where composite

units are supplied by the Employer, particulars shall be

given of the assembly work involved.

Q.1.3 Patterns, moulds, templets and the like shall be

deemed to be included with the items.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 24: 12-Fire Fighting System

Q.1.4 Priming and painting off-site and proprietary

finishes or surface treatment applied as part of the

production process shall be described stating whether

applied before or after fabrication or assembly.

Q.1.5 Except where otherwise stated the method of fixing

and the provision of nails, bolts, nuts, holes, screws, plugs,

shot-fired pins and the like shall be given in the description

of the work.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 25: 12-Fire Fighting System

Q.1.6 The nature of the background to which work is to be fixed shall be given in the description. Any necessary drilling of the backgrounds shall be deemed to be included. Backgrounds shall be classified as follows :

a) Building-board which shall be deemed to include hardboard, compressed cement sheet, plasterboard, fibreboard and similar materials which do not grip woodscrews.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 26: 12-Fire Fighting System

Q.1.6 The nature of the background ….

b) Timber which shall be deemed to include softwood, hardwood, blockboard, plywood and similar materials which will grip wood-screws when a lead-hole has been drilled.

c) brickwork, concrete or stone work

d) plain metal

e) glass

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 27: 12-Fire Fighting System

Q.1.7. Temporary work shall be so described. Removing

temporary work and making good after shall be

deemed to be included with the item.

Q.1.8. Connecting to existing services – shall be described

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 28: 12-Fire Fighting System

GENERALLY

Q.2. CLASSIFICATION OF WORK

Q.2.1 Work together with its metalwork, supports and the like(unless associated with more than one installation) shall beclassified as follows and given under an appropriateheading :

d) Fire Fighting Installation

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 29: 12-Fire Fighting System

SETS OF FIRE FIGHTING EQUIPMENTS

Hose Reel

Portable FE

Fire alarm

Page 30: 12-Fire Fighting System

Q.3. LOCATION OF WORK

Location of works :

a. Internally

b. Externally

c. In plant rooms

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 31: 12-Fire Fighting System

PIPE WORKS

Q.7 GENERALLY

1. Purpose-made pipes and purpose-made pipe fittings shallbe described.

2. Pipes and pipe fittings which are wrapped, coated or linedby the manufacturer shall be so described stating the type oftreatment.

3. Pipework required to be temporarily fixed in position,dismantled for chromium-plating or other special finishingand subsequently refixed shall be so described.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 32: 12-Fire Fighting System

Q.8 PIPE AND FITTING

1. Pipes (measured over all pipe fittings, short running

lengths and branches) shall be given in metres stating the

type and the normal size.

Purpose-made pipe shall be so described and given

separately. Curved pipes shall be so described stating the

mean radius.

Joints in the running length shall be given in the

description stating the method of jointing.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 33: 12-Fire Fighting System

Q.8 PIPE AND FITTING

3. Flexible pipes and extensible pipes (measured as fully extended) shall each be so described.

4. Pipes laid or fixed in ducts, trenches and chases or embedded in in-situ concrete or screeds shall each be so described.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 34: 12-Fire Fighting System

PIPING INSIDE SWITCH ROOM

HEAT DETECTORHOSE REEL PIPE

CONDUIT

Pipe Fittings: FIRE FIGHTING INSTALLATIONS

Page 35: 12-Fire Fighting System

Q.9. SPECIAL CONNECTIONS, ETC.

1. Special connections and special joints in pipes shall

each be enumerated separately (except where given in

the description of another enumerated item) stating the

nominal size and kind of pipe concerned and the method of

jointing. Classification shall be as follows :

a) Connections between pipes of differing materials and

differing grades of the same material.

b) Connections between pipes and appliances or

equipment.

c) Connections to existing pipes.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 36: 12-Fire Fighting System

Q.10.LABOURS

Labours on pipes (e.g. made bends, made springs, made

offsets, beaded ends, ornamental ends, etc.) shall be deemed

to be included with the pipes on which they occur.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 37: 12-Fire Fighting System

Q.11 SUNDRIES

6. Pipe-sleeves through walls, floors ceilings shall be

enumerated stating the type, lengths, the nominal size and kind

of pipe passing through and the type of packing required, and

if to be supplied for fixing by other trades, this shall be so

described.

7. Wall, floor or ceiling plates shall be grouped together

as plates and enumerated stating the type and size.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 38: 12-Fire Fighting System

PIPE-SLEEVES

Page 39: 12-Fire Fighting System

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Q.12 PIPEWORK SUPPORTS

12.1 Standard pipe supports shall be given in the description of the pipes stating the type and spacing of the supports.

12.2. Non-standard pipe supports shall be described and enumerated (no).

Page 40: 12-Fire Fighting System

Q.12 PIPEWORK SUPPORTS

12.1 Standard pipe supports shall be given in the description of the pipes stating the type and spacing of the supports.

12.2. Non-standard pipe supports shall be described and enumerated (no).

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 41: 12-Fire Fighting System

Q.12 PIPEWORK SUPPORTS

4. Components or assemblies of components (e.g.

clips, saddles, pipe-hooks, holderbats, brackets,

rollers, chairs and hangers or black-plates and girder-

lugs) used to fix supports for more than one pipe shall

be enumerated separately stating the type and size of

components. Spring compensated components shall

be so described stating the loading and movement to

be accommodated.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 42: 12-Fire Fighting System

Pipe Supports: FIRE FIGHTING INSTALLATIONS

Page 43: 12-Fire Fighting System

PIPE SUPPORT

Page 44: 12-Fire Fighting System

Q.13 CONNECTIONS

Connections to public mains, making good public

highway and any other work which may only be carried

out by a Public Undertaking or Local Authority shall be

given as a provisional sum.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 45: 12-Fire Fighting System

EQUIPMENT AND ANCILLARIES

Q.19 Generally

1. Unless otherwise stated, equipment such asboilers, generators, heaters, water treatment plant,tanks cylinders, calorifiers, pumps, coolers, air-handling unit, fans, refrigerator equipment, meters,sanitary fittings, etc. and ancillaries such as sootdoors to boilers, valves and cocks, gauges,automatic controls etc. shall be enumerated andrelated to the specification referred to in clauseQ.1.1.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 46: 12-Fire Fighting System

EQUIPMENT AND ANCILLLARIES

Q.19 Generally

2. Shall be described in conjunction with a manufacturer’s detailed specification (Q.19.2)

3. Any limiting dimensions on the size shall be given. (Q.19.3)

4. Electrical connection shall be given in accordance with section R . (Q.19.4)

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 47: 12-Fire Fighting System

Main pump is fully operated byelectricty

Standy by or back up pump whenthe electrical pump can notfunction due to electricity shutdown

135 main flow, 40 m pressure and 2900 rpm

Equipment and ancillaries, Q.19. and measured in NO

Electrical & Diesel Pump: FIRE FIGHTING INSTALLATIONS

Page 48: 12-Fire Fighting System

Equipments and

ancillaries

– Clause Q.19.

– Unless otherwise

stated, equipment

such as tank shall be

enumerated (no).

Water Storage Tank: FIRE FIGHTING INSTALLATIONS

Page 49: 12-Fire Fighting System

EQUIPMENT AND ANCILLLARIES

Q.20 Anti-vibration and sound insulation

Anti-vibration mountings for plant shall be

enumerated stating the type and the size. Anti-

vibration material and sound-insulating material in

plant bases shall be given in square metres stating

the nature of the material and the thickness.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 50: 12-Fire Fighting System

Anti Vibration Material: FIRE FIGHTING INSTALLATIONS

Page 51: 12-Fire Fighting System

EQUIPMENT AND ANCILLLARIES

Q.21 Equipment supports

1. Equipment supports shall be enumerated and

described.

2. Particulars of the method of fixing shall be

given in the description in accordance with

clauses Q.1.5-6.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 52: 12-Fire Fighting System

EQUIPMENT AND ANCILLLARIES

Q.22 Jointing

Particulars of the method of jointing shall be given in

the description of the equipment.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 53: 12-Fire Fighting System

EQUIPMENT AND ANCILLLARIES

Q.24 Identification Plates

Identification plates shall be deemed to be included.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 54: 12-Fire Fighting System

SUNDRIES

Q.30 Generally

1. Draining and refilling existing system shall be

given as a provisional or prime cost sum.

2. Disconnecting, setting aside and refixing

equipment for the convenience of other trades shall

be given as an item stating the relevant particulars.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 55: 12-Fire Fighting System

SUNDRIES

Q.30 Generally

3. Temporarily operating each installation (except

for testing) shall be given as an item stating any

required qualifications of the attendant, the duration of

the operating period in hours and the purpose and

particulars of any special insurance cover required by

the Employer. Provision of solid fuel, liquid fuel, gas

and electricity for power and lighting shall be

deemed to be included with the item

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 56: 12-Fire Fighting System

SUNDRIES

Q.30 Generally

4. Testing each installation shall be given as an item stating any required qualifications of the attendant, the number of stage tests in addition to the final, the purpose of the tests, the instruments and appliances required to be provided and particulars of any special insurance cover required by the Employer. Provision of solid fuel, liquid fuel, gas and electricity for power and lighting shall be deemed to be included with the item.

5. Preparing plans or diagrams of the installations as fitted shallbe given as an item stating the kind of information required tobe shown and the number of copies of each drawing requiredto be provided.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 57: 12-Fire Fighting System

BUILDER’S WORK

Q.31 GENERALLY

1. Unless otherwise stated, all items of builder’s

shall be given in accordance with the appropriate

section.

2. Builder’s works in connection with plumbing and

mechanical engineering installations shall be

grouped together under an appropriate heading.

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 58: 12-Fire Fighting System

BUILDER’S WORK

Q.32 PARTICULARLY

1. Excavating trenches for pipes not exceeding 55mm nominal size shall be given in accordance with clause D.12.9

2. For pipe over 55mm shall be given in accordance with clause V.2

3. Cutting away for making good after M&E works……

Measurement Rules : FIRE FIGHTING INSTALLATIONS

Page 59: 12-Fire Fighting System

TAKING OFF LIST

Page 60: 12-Fire Fighting System

1.Hose Reel System

Swing hose reel

Water tank

Electrical duty pump

Diesel standby pump

3.Brass Works

Ball float valve

Strainer valve

Stop valve

Flexible connection

Check valve

Gate valve

Pressure gauge

2.Pipe Works

Incoming pipe

Distribution pipe

Rising pipe

Painting to pipe

4.Fire Alarm System

5.Portable Fire Extinguisher

6.Builder’s work

7.Testing

Taking off Lists: FIRE FIGHTING INSTALLATIONS

Page 61: 12-Fire Fighting System

Preamble

Hose Reel System

– Swing hose reel - NO

– Water storage tank - NO

– Electrical duty pump - NO

– Diesel standby pump - NO

Piping Works

• 50 mm Diameter incoming pipe - M

• 50 mm Diameter rising pipe – M

• 50 mm Diameter distribution pipe - M

Brasswork

• 50 mm Diameter air release valve – NO

• 50 mm Diameter gate valve – NO

• 50 mm Diameter check valve – NO

• 50 mm Diameter strainer valve – NO

• 50 mm Diameter flexible joint – NO

• 25 mm Diameter gate valve – NO

TAKING OFF LIST

Page 62: 12-Fire Fighting System

Fire Alarm System

– Control gear – NO

– Junction box – NO

– Manual break glass – NO

– 2 x 2.5 mm cable – M

– 50 mm Diameter conduit – M

Portable Fire Extinguisher

– 9 kg Fire extinguisher - NO

– Hydrant Hose Cabinet – NO

Lighting Installation

– Keluar sign - NO

– 5A Emergency light – NO

Testing

– Allow for testing the foregoing fire fighting system – ITEM

Builder’s Work

– Excavate trench to receive pipe - M

TAKING OFF LIST

Page 63: 12-Fire Fighting System

THANK YOUfor your kind attention