Page 1
Document of
The World Bank
FOR OFFICIAL USE ONLY
Report No: {PAD2130}
INTERNATIONAL DEVELOPMENT ASSOCIATION
PROJECT PAPER
ON A
PROPOSED ADDITIONAL CREDIT
IN THE AMOUNT OF 6.93 SDR MILLION
(US$9.5 MILLION EQUIVALENT)
AND A PROPOSED ADDITIONAL GRANT
IN THE AMOUNT OF 3.33 SDR MILLION (US$4.6 MILLION EQUIVALENT)
TO THE
REPUBLIC OF VANUATU
AND THE
PROJECT RESTRUCTURING
FOR THE
VANUATU AVIATION INVESTMENT PROJECT
December 16, 2016
Transport & ICT Global Practice
EAST ASIA AND PACIFIC REGION
This document has a restricted distribution and may be used by recipients only in the
performance of their official duties. Its contents may not otherwise be disclosed without World
Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Page 2
CURRENCY EQUIVALENTS
(Exchange Rate Effective October 31, 2016)
Currency Unit = Vanuatu Vatu
VUV 109.34 = US$1
US$1.373850 = SDR 1
FISCAL YEAR
January 1 – December 31
ABBREVIATIONS AND ACRONYMS
ADS/B Automatic Dependent Surveillance Broadcast
ARFF Aircraft Rescue and Fire Fighting
AVL Airports Vanuatu Ltd.
CAAV Civil Aviation Authority of Vanuatu
DA Designated Account
EA Environmental Assessment
EIRR Economic Internal Rate of Return
ESMF Environmental and Social Management Framework
FM Financial Management
FS Financial Statements
GBV Gender Based Violence
GDP Gross Domestic Product
GoV Government of Vanuatu
GRM Grievance Response Mechanism
GRS Grievance Redress Service
IA Implementing Agency
ICAO International Civil Aviation Organization
IDA International Development Association
IFR Interim Financial Report
MFEM Ministry of Finance and Economic Management
MIPU Ministry of Infrastructure and Public Utilities
NPF New Procurement Framework
PAIP Pacific Aviation Investment Program
PESMP Project Environmental and Social Management Plan
PICs
PDO
RPF
Pacific Islands Countries
Project Development Objective
Resettlement Policy Framework
SEST Surface Enrichment Spray Treatment
SON
SSL
Whitegrass International Airport
Safety and Security Levy
TAH Pekoa International Airport
TFSU Technical and Fiduciary Services Unit
USOAP Universal Safety Oversight Audit Program
VAIP Vanuatu Aviation Investment Project
Page 3
VLI Bauerfield International Airport
VPMU Vanuatu Project Management Unit
VSAT Very Small Aperture Terminal
VUV Vanuatu Vatu
WB World Bank
WTTC World Travel and Tourism Council
Vice President: Victoria Kwakwa
Country Director: Michel Kerf
Senior Global Practice Director (Acting):
Practice Manager:
Jose Luis Irigoyen
Almud Weitz
Task Team Leader: Christopher Bennett
Page 4
VANUATU
Vanuatu Aviation Investment Project (P161454)
CONTENTS
Project Paper Data Sheet i
Project Paper
I. Introduction 1
II. Background and Rationale for Additional Financing 1
III. Proposed Changes 9
IV. Appraisal Summary 17
22 V. World Bank Grievance Redress
Annexes
Annex 1: Revised Results Framework and Monitoring Indicators 24
Annex 2: Improved Safeguard Measures and Innovations 31
Annex 3: Greenhouse Gas Accounting 33
Page 5
i
ADDITIONAL FINANCING DATA SHEET
Vanuatu
Vanuatu Aviation Investment Project Additional Financing ( P161454 )
EAST ASIA AND PACIFIC
GTI02
Basic Information – Parent
Parent Project ID: P154149 Original EA Category: B - Partial Assessment
Current Closing Date: 31-Dec-2019
Basic Information – Additional Financing (AF)
Project ID: P161454 Additional Financing
Type (from AUS): Scale Up
Regional Vice President: Victoria Kwakwa Proposed EA Category: B
Country Director: Michel Kerf Expected Effectiveness
Date: 31-Mar-2017
Senior Global Practice
Director (Acting): Jose Luis Irigoyen Expected Closing Date: 31-Dec-2019
Practice
Manager/Manager: Almud Weitz Report No: PAD2130
Team Leader(s): Christopher R. Bennett
Borrower
Organization Name Contact Title Telephone Email
Ministry of Finance &
Economic Management Tony Sewen
Director
General +678 23 032
Project Financing Data - Parent ( Vanuatu Aviation Investment Project-P154149 ) (in USD
Million)
Key Dates
Project Ln/Cr/TF Status Approval
Date Signing Date
Effectiveness
Date
Original
Closing Date
Revised
Closing Date
P154149 IDA-56320 Effective 08-May-2015 03-Jun-2015 09-Jul-2015 31-Dec-2019 31-Dec-2019
P154149 TF-A0607 Effective 08-May-2015 03-Jun-2015 03-Jun-2015 31-Dec-2019 31-Dec-2019
Disbursements
Project Ln/Cr/TF Status Currency Original Revised Cancelled Disbursed Undisbu
rsed
%
Disbursed
Page 6
ii
P154149 IDA-56320 Effective USD 59.50 59.50 0.00 3.14 54.96 5.27
P154149 TF-A0607 Effective USD 0.30 0.30 0.00 0.07 0.23 24.31
Project Financing Data - Additional Financing Vanuatu Aviation Investment Project
Additional Financing ( P161454 )(in USD Million)
[ ] Loan [ ] Grant [X] IDA Grant
[X] Credit [ ] Guarantee [ ] Other
Total Project Cost: 14.1 Total Bank Financing: 14.1
Financing Gap: 0.00
Financing Source – Additional Financing (AF) Amount
International Development Association (IDA) 9.5
IDA Grant 4.6
Total 14.1
Policy Waivers
Does the project depart from the CAS in content or in other significant
respects? No
Explanation
Does the project require any policy waiver(s)? No
Explanation
Bank Staff
Name Role Title Specialization Unit
Christopher R. Bennett Team Leader
(ADM
Responsible)
Lead Transport
Specialist
TTL GTI02
Christopher J. De
Serio
Team Member Transport Specialist Co-TTL GTI02
Nora Weisskopf Team Member Transport Analyst Aviation Transport GTI02
Loren Jayne Atkins Counsel Associate Counsel Counsel LEGES
Cristiano Costa e Silva
Nunes
Procurement
Specialist (ADM
Responsible)
Senior Procurement
Specialist
Procurement GGO02
Page 7
iii
David Bruce
Whitehead
Financial
Management
Specialist
Financial
Management
Specialist
FM GGO02
Chanin Manopiniwes Team Member Infrastructure
Economist
Economic GTI02
Chau-Ching Shen Team Member Senior Finance
Officer
WFALN WFALN
Duangrat
Laohapakakul
Counsel Senior Counsel Legal LEGES
Kanya Hilary Baratha
Raj
Team Member Team Assistant ACS EACNF
Oliver George
Whalley
Team Member Transport Analyst Engineer GTI02
Penelope Ruth
Ferguson
Safeguards
Specialist
Consultant Environment GEE06
Ross James Butler Safeguards
Specialist
Senior Social
Development
Specialist
Social GSU02
Subha Latchmi Ram Team Member Team Assistant ACS EACNF
Extended Team
Name Title Location
Asif Faiz Consultant Washington, DC
Locations
Country First Administrative
Division
Location Planned Actual Comments
Vanuatu Tafea Tafea Province X X Whitegrass
Vanuatu Shefa Port-Vila X X Bauerfield Airport
Vanuatu Sanma Luganville X X Pekoa Airport
Institutional Data
Parent ( Vanuatu Aviation Investment Project-P154149 )
Practice Area (Lead)
Transport & ICT
Contributing Practice Areas
Additional Financing Vanuatu Aviation Investment Project Additional Financing ( P161454 )
Practice Area (Lead)
Page 8
iv
Transport & ICT
Contributing Practice Areas
Consultants (Will be disclosed in the Monthly Operational Summary)
Consultants Required ? Consulting services will be required.
Page 9
1
I. Introduction
1. This Project Paper seeks the approval of the Executive Directors to provide Additional
Financing in a total amount of 10.26 SDR million (US$14.1 million equivalent comprised of
US$4.6 national IDA grant, US$1.76 national IDA credit and a US$7.74 million regional IDA
credit 1
) to scale up the Vanuatu Aviation Investment Project (VAIP) (IDA-5632-VU, TF0A0004,
P154149). Along with the Additional Financing, the project will be restructured to amend the
project description in the Financing Agreement, update the results framework and disbursement
projections, as well as add a two-part effectiveness condition and revise the legal covenant “Safety
and Security Levy” (SSL).
2. The proposed Additional Financing will be used for additional activities in two
components:
(i) Component A: International Airport Infrastructure Investments (US$13.75
million):) An expanded scope of works is required at Bauerfield (VLI), Whitegrass (SON)
and Pekoa (TAH) International Airports to: (i) address the increased pavement
deterioration at Bauerfield, Whitegrass and Pekoa international airports; (ii) increase the
operational capacity of Bauerfield to accommodate larger aircraft and thus ensure the
country is prepared for future disasters; and, (iii) repair and/or expand the existing apron
or relocate the apron..
(ii) Component E: Project implementation support (US$0.35 million): A technical advisor
to the Vanuatu Project Management Unit (VPMU) will be financed to support the
implementation of the project. This is required due to the complexity and intensified
urgency of the project resulting from recent delays.
3. The expanded scope will not detract from VAIP’s current activities, no additional
safeguards will be triggered, and there will be no change to the current (Category B) safeguards
rating. There will be no changes to the project development objective (PDO), implementation
arrangements, procurement or financial management.
4. The project description in the Financing Agreement will be amended to include the
expanded works at Bauerfield airport including the potential relocation of the apron, pavement
rehabilitation at Whitegrass and Pekoa airports, and removal of the domestic terminal
reconstruction at Bauerfield. There will be two changes to the Results Framework to reflect: (i) a
need for increased Aircraft Rescue and Fire Fighting (ARFF) capacity at Bauerfield airport; and,
(ii) include the pavement works at Whitegrass and Pekoa airports. The disbursement estimates will
be updated to reflect the expected timing of the Additional Financing.
5. The project’s legal covenant “Safety and Security Levy” (Financing Agreement I.G.1 and
I.G.2) is overdue. In light of significant progress made by the Recipient to fulfil the covenant’s
obligations the covenant will be revised and will become an effectiveness condition. The
effectiveness condition contains the following two parts: (i) the Civil Aviation Authority of
Vanuatu (CAAV) has commenced the collection of the SSL from departing international air
1 3.33 SDR national grant, 1.28 SDR national credit and 5.65 SDR regional credit.
Page 10
2
passengers; and, (ii) CAAV and Airports Vanuatu Ltd. (AVL) have prepared and adopted the
Disbursement Framework.
6. In addition, the responsible party for collection of the levy (I.G.1) will be revised to be
CAAV rather than AVL. This is to ensure compliance with local legislation as stipulated in the
Civil Aviation Act of Vanuatu. The responsibility for continued compliance with the disbursement
framework and auditing requirements (I.G.2) will also be revised to include both AVL and CAAV.
II. Background and Rationale for Additional Financing
7. Country Context. The Republic of Vanuatu is a small nation located in the South Pacific
about 2,000 km to the east of Australia. Comprised of about 80 islands, the country’s land area is
some 12,200 km2. With an almost entirely Melanesian population of about 265,000, it is one of the
more populated Pacific Island Countries (PICs). Efate Island is the location of the capital Port Vila,
which is the gateway for most visitors to Vanuatu.
8. Vanuatu’s per capita gross domestic product (GDP) in 2014 was US$3,075. The key
pillars of Vanuatu’s economy are the agriculture sector and the service industry. Tourism in
particular plays a key role. According to the World Travel and Tourism Council (WTTC), the
direct contribution of travel and tourism comprised nearly 19 percent of GDP in 2014. This
contribution is expected to grow annually by 4.3 percent until 2024.
9. Vanuatu is highly susceptible to natural disasters. For example, the devastation caused by
Cyclone Pam in March 2015 included deaths, widespread displacement of communities,
destruction of houses and buildings, as well as damage to Vanuatu’s three international airports,
roads and wharves, communications systems, and other critical infrastructure. The relief effort was
hampered by a lack of apron capacity at Bauerfield airport. Vanuatu’s reliance on tourism, and its
susceptibility to natural disasters, make air transportation a critical pillar in the country’s economic
and social development.
10. Governance challenges resulting from frequent changes in leadership and policy direction
have hampered the air transport sector’s development, with shifting priorities that saw the
discontinuation of a potential public-private partnership transaction with the International Finance
Corporation (2012), as well as the nullification of a concession agreement with Vanuatu Trade
Development Pte. Ltd (VTDP) for the construction of a new greenfield airport on Efate (2014)2.
Challenges in the management of AVL, the state owned enterprise responsible for the country’s
three international airports (Bauerfield, Pekoa and Whitegrass), has also had an impact on the
country’s ability to address its critical aviation infrastructure needs.
11. Project Background. In December 2011, IDA approved the Pacific Aviation Investment
Program (PAIP), a regional, horizontal Adaptable Program Loan that consists of a series of projects
designed to: (i) ensure that critical aviation infrastructure meets operational safety requirements;
and, (ii) strengthen regulatory compliance of international air transport of participating countries in
the region. Phase I included projects in Kiribati, Tonga and Tuvalu; Phase II included Samoa; and
Phase III brought Vanuatu into the PAIP Program. Through PAIP, IDA also approved the Pacific
2 Under this concession VTDP was to undertake the necessary maintenance repairs to Bauerfield runway and keep it fully
operational until the new airport was completed
Page 11
3
Aviation Safety Office (PASO) Reform Project in September 2013 in support of the PICs
regulatory mandates.
12. The VAIP was approved on May 8, 2015 and became effective on 9 July 2015, with total
project financing of US$59.8 million. The IDA funding of US$59.50 million was comprised of a
US$5.86 million national IDA Credit and a US$53.64 million regional IDA Credit. The Pacific
Region Infrastructure Facility (PRIF) contributed a US$300,000 grant for the direct engagement of
PASO in regulatory advisory services. Table 1 shows the total financing, including this Additional
Financing.
Table 1: VAIP Funding Sources
Financing (US$ million ) by Funding Source
IDA
PRIF Total
National
Grant
National
Credit
Regional
Credit
Original Project $ - $ 5.86 $ 53.64 $ 0.30 $ 59.80
Additional Financing $ 4.6 $ 1.76 $ 7.74 $ - $ 14.10
Total $ 4.6 $ 7.63 $ 61.39 $ 0.30 $ 73.90
13. The PDO is “to improve operational safety and oversight of international air transport and
associated infrastructure in Vanuatu”. Project outcomes are being monitored through four
indicators: (i) Regulatory certification of safety and security at Bauerfield International Airport; (ii)
State requirements for safety measured by Universal Safety Oversight Audit Programme (USOAP)
reaches global International Civil Aviation Organization (ICAO) average; (iii) modernization of air
traffic management through installation of key equipment; and, (iv) implementation of a regional
SSL for departing international passengers.
14. Project Components. VAIP has the following components:
Component A - International Airport Infrastructure Investments (total cost
approximately US$50.77 million, including taxes and contingencies): This component
invests in international aviation infrastructure to meet and maintain minimum ICAO safety
and security standards at Vanuatu’s three international airports: Bauerfield, Whitegrass
and Pekoa Airports.
Component B - Aviation Sector Reform and Training (total cost approximately
US$1.53 million, including taxes and contingencies): This component aims to strengthen
the CAAV, Ministry of Infrastructure and Public Utilities (MIPU) and other line
ministries’ technical capacity through the development of an Aviation Sector Plan,
targeted technical assistance to strengthen institutional capacity as well as dedicated
training.
Component C - Strengthening Airport Operations and Management Capacity (total
cost approximately US$1.14 million, including taxes and contingencies): This
component’s objective is to strengthen AVL’s airport operations and management
capacity through the development of an Airport Master Plan, targeted technical assistance
and training.
Component D - Emergency Reconstruction after Cyclone Pam (total cost
approximately US$3.88 million, including taxes and contingencies): This component
Page 12
4
provides support to the Government of Vanuatu (GoV) with emergency reconstruction
activities in the form of goods and works.
Component E - Project Support (total cost approximately US$2.48 million, including
taxes and contingencies): This component covers project management and operating
costs, advisory and administrative support as well as subscriptions cost for ‘Very Small
Aperture Terminal’ (VSAT) communications systems and financial audits.
15. Project Progress. The Project is in the second year of a five year implementation
schedule. The progress towards achieving the PDO and project implementation progress have been
rated Satisfactory and Moderately Satisfactory, respectively, since July 13, 2015.
16. Despite initial delays due to Cyclone Pam’s recovery efforts, and two changes of
government since Project effectiveness, implementation progress has been made as follows:
Component A - Airport Infrastructure Investments: Airport infrastructure investments
have progressed considerably:
i. Emergency repair works for the Bauerfield runway pavement were completed in
March-April 2016 and September 2016, allowing international jet operations to
continue.3 These works comprised Surface Enrichment Spray Treatment (SEST) of
the selected pavement surface to eliminate foreign object debris incidents as the
surface stone was very loose in some areas. In addition to this, cold mix asphalt
patches were applied to selected areas to remove and replace weak pavement areas.
ii. The Bauerfield airport detailed designs for the airside pavement works and airfield
ground lighting on the runway, taxiway, repair and expansion of the existing apron
have been completed, with bidding and contract award anticipated before the end
of December 2016. This bid award will also include “design and build” repairs for
Whitegrass and Pekoa runways.
iii. Procurement of the Supervision Consultant for the pavement works and airfield
ground lighting, navigational aids and air traffic control equipment is in progress
with award expected by December 2017.
iv. The contract for two Aircraft Rescue and Fire Fighting (ARFF) vehicles has been
awarded. The vehicles will be delivered in 2017 and support ARFF compliance to
achieve Category 8 outcomes. New fire safety uniforms and other equipment have
been procured and are in use.
v. Procurement of aeronautical communications (ADS-B ground stations) is
completed and equipment will arrive in early 2017.
vi. The site location and specifications of the regional point-to-point aeronautical
communication network is commencing in December 2016, and its supply and
installation are expected to be completed in 2017.
Component B – Aviation Sector Reform and Training: The project has mobilized an
aviation advisor to the CAAV to provide guidance on safety management and quality
3 In January 2016, Air New Zealand suspended all flights due to safety concerns over the Bauerfield airport runway condition.
The following week, both Qantas and Virgin Australia also suspended their code share agreement and flights, respectively.
After emergency repairs were completed, Virgin Australia resumed flights in May 2016, but Air New Zealand did not,
indicating that scheduled services would only resume after the full rehabilitation of the pavement.
Page 13
5
management systems. A technical assistance contract for developing an Aviation Sector
Strategy has been awarded with completion expected by June 2017. PRIF funding has also
been used to facilitate PASO involvement in advising on regulatory matters.
Component C – Strengthening Airport Operations and Management Capacity: A
desktop review of proposed investments focused on Bauerfield pavement and navigational
aids was completed in 2015. The Airport Master Plan contract has been awarded with
completion expected by June 2017.
Component D – Emergency reconstruction after Cyclone Pam: Emergency repairs of
airport infrastructure in Pekoa and Whitegrass resulting from Cyclone Pam are currently
under tender with award expected by early 2017.
17. Closing Date: Despite the aforementioned implementation delays, the project is still on
track to conclude before the current closing date of December 31, 2019.
18. Legal Covenants. The project is in compliance with all covenants except the legal
covenant regarding the SSL in Section I.G. of the Financing Agreement. The covenant has two
components: (i) the collection of an AU$5 SSL for departing international passengers (I.G.1.)
originally due on July 1, 2016; and, (ii) the adoption of the associated Disbursement Framework4
requirements for the SSL (I.G.2) due on the March 31, 2016. The delays in fulfilling these dated
covenants are primarily a result of the 2016 disruption to Parliament and subsequent change of
Government. The GoV is currently working on finalizing the legislation to introduce the SSL, and
GoV approval of the SSL is anticipated during the next sitting of Parliament. Collection is expected
to begin in early 2017 once the legislation is enacted and the necessary arrangements are made to
have the SSL added to the ticket price. The draft Disbursement Framework for the allocation of the
SSL between CAAV and AVL, as well as how the funds may be used and audited, were discussed
during the November 2016 appraisal mission and the principles agreed.
19. As the SSL’s revenue is to be used for sustaining the project investments and capacity
development, and these activities have only just commenced due to the aforementioned delays, the
failure to introduce the levy on time has not materially affected the project to date. However,
moving forward, to ensure all requirements for the collection and disbursement of sustainable
financing for airport safety and security are in place, a two-part effectiveness condition will be
required for the AF. The condition will require: (i) collection of the AUD$5 SSL by CAAV; and,
(ii) preparation and adoption of the disbursement framework by AVL and CAAV. The legal
covenant “Safety and Security Levy” (I.G.1 and I.G.2) will be revised to require the Recipient to
collect the levy, use the levy in accordance with the disbursement framework and furnish to the
Technical and Fiduciary Services Unit (TFSU) the annual audit reports throughout the project
implementation period. The responsible party for collection of the levy (I.G.1) will be revised to be
CAAV rather than AVL. This is to ensure compliance with local legislation as stipulated in the
Civil Aviation Act of Vanuatu. The responsibility for continued compliance with the disbursement
4 The adoption of a Disbursement Framework is critical to ensure that funds are hypothecated for expenditures for safety and
security related purposes. The Disbursement Framework is required to be adopted by CAAV and AVL and outlines the
mechanism by which funds are collected and deposited, defines eligible expenditures from the SSL revenue including
requirements for annual forecasting of the activities to be financed, processes for auditing and the preparation of annual
reports.
Page 14
6
framework and auditing requirements (I.G.2) will also be revised to include both AVL and CAAV
rather than only CAAV.
20. Financial Management and Disbursements: There are no outstanding audits. As of
October 24, 2016, the disbursement rate for the original IDA Credit (US$59.5 million) was five
percent (approximately US$2.95 million). The associated PRIF Grant (TF-A0607) of US$300,000
has disbursed 24.3 percent. The disbursement rates of both the original IDA Credit and proposed
Additional Financing are expected to accelerate significantly in 2017, as the civil works for the
runways at the three project airports, with an estimated cost of US$40.3 million, are currently under
bidding with civil works anticipated to commence in April 2017. The estimated US$ 7 million for
navigation aids and runway lighting supply and installation are also anticipated to commence by
mid-2017.
21. The GoV uses a central treasury account. A separate General Ledger code will be created
in the Smartstream accounts for this Additional Financing, including the IDA credit and IDA grant
respectively, to record funds receipts and disbursements, while funds physically sit in the one
central treasury account, which leads to the case of a ‘pooled’ designated account for all
government and donor funds, managed by the Ministry of Finance and Economic Management
(MFEM). General ledger sub codes are used in the accounting system to identify and control each
project within the single treasury account.
22. Retroactive financing up to $1 million will be provided for eligible expenditures to be
incurred from September 1, 2016, provided that Bank’s relevant procurement guidelines are
followed. This has been done so as to support the GoV’s preference to use the donor grant funding
for technical assistance activities rather than credit funds.
23. Procurement framework. In July 2016 the World Bank adopted new procurement
framework to be used for all new projects, including Additional Financing. The project has
received approval from the Chief Procurement Office (CPO) to use the prior Procurement
Guidelines for this Additional Financing for the following reasons:
(i) VAIP is part of the PAIP program, which includes Kiribati, Samoa, Tonga, Tuvalu
and Vanuatu. PAIP draws upon regional implementation arrangements that offer
sectoral, procurement and project management expertise through the PAIP TFSU.
The continuation of the application of the Procurement Guidelines would allow the
continuation of the seamless procurement arrangements for PAIP;
(ii) PAIP is undertaking both national and regional procurements. It would be
problematic for regional procurements when the program has four countries using
the Procurement Guidelines and one with the New Procurement Framework (NPF);
(iii) the single major procurement for VAIP is for the pavement and runway repairs to
Bauerfield, Whitegrass and Pekoa airports, with an estimated total cost of US$46.7
million. The bidding is underway and should be completed before this Additional
Financing is processed. The remaining procurements will be of much smaller value
and benefit less from the NPF; and,
(iv) adoption of the NPF at this stage would require preparation of a Project Procurement
Strategy for Development and re-drafting the bidding documents, which could cause
significant implementation delays. It would also demand considerable time to train
the implementation units on the NPF.
Page 15
7
24. Rationale for Additional Financing. The Additional Financing of US$14.10 million is
necessary in order to meet the scaled up project’s total funding requirements and to fund a technical
advisor to the VPMU. As noted earlier, financing is required to: (i) expand the scope of works
necessary to address the increased pavement deterioration at Bauerfield, Whitegrass and Pekoa
international airports; (ii) increase the operational capacity of Bauerfield to facilitate larger aircraft
and thereby help ensure the country is prepared for future disasters; (iii) repair and/or expand
existing apron or relocate the apron; and, (iv) address need for additional technical assistance for
project implementation. Despite the low disbursement rate to date, the timing of the AF scale-up is
determined by the fact that all airfield pavement works, including the expanded scope of works, are
being procured through a single tender, the bid closing date for which is scheduled for December
19, 2016. The original project was prepared rapidly over three months under emergency procedures
and now that detailed engineering investigations have been completed additional funding for works
and technical assistance is required due to:
Pavement Needs.
o Bauerfield: When the project was originally appraised, it was estimated that 600
m of the Bauerfield runway would require full rehabilitation. Detailed pavement
investigations have since found that 2000 m require rehabilitation, resulting in an
increase to the estimated cost for the runway civil works. Additional drainage
requirements were also identified in 2015 after Cyclone Pam.
o Whitegrass: The Whitegrass runway has been found to be in need of an overlay
to ensure continued jet operations.
o Pekoa: Pekoa runway requires a SEST surface rejuvenation treatment which will
address the oxidative damages and extend the surface life.
Operational Capacity at Bauerfield. The original project design for Bauerfield met the
requirements for smaller Code C type aircraft.5. However, a review of AVL’s 2011
draft Master Plan financed by the project in late 2015 indicated potential scope to
accommodate larger Code E aircraft at Bauerfield, with appropriate modifications to
pavement strength and geometry. The proposed upgrade will help ‘future proof’ the
investments and also allow the airport to cater for potential long-haul charter operations
from Asia, which have been identified as important to support tourism growth.
Repairs and Expansion to Existing Apron or Relocation of Apron. The GoV has
indicated interest in the development of a new terminal at Bauerfield airport, most
likely to be located on the other side of the runway. Funding for the new terminal has
not been confirmed, nor has its timeline. The parent project is currently undertaking an
Airport Master Plan study that will identify the exact location and scope of the new
apron if the new terminal were to be built. The Airport Master Plan should be
completed in the first half of 2017. To address the uncertainties with regard to a
potential new terminal building the project is planning to approach this as follows:
5 Classification of aircraft type is based on airplane wingspan and outer main gear wheel span in accordance with ICAO
Annex 14 Aerodromes.
Page 16
8
o Repairs to the existing apron: The current apron pavement will receive a
maintenance treatment under the project to address the surface condition. This is
required as the construction of any new terminal is a medium-term proposition.
o Expansion of the existing apron: If the GoV decides not to pursue the
construction of a new terminal in the medium term, the project will expand the
existing apron. The expansion would enable Bauerfield to accommodate more
and larger aircraft, including types used for higher-capacity emergency relief
operations6.
o Construct new apron: If the GoV confirms funding for and construction of a
new terminal in the medium term and the location and scope is confirmed by the
Master Plan, the project may construct a new apron (and associated taxiway) at a
new location as identified in the Master Plan. The existing apron would be used
for general aviation purposes once the new apron is open.
Technical Advisor to the VPMU. Due to the complexity and urgency of the project,
intensified by the recent delays, the VPMU has requested additional support with the
overall management of the project.
25. Climate resilience measures. A screening of the proposed project for short and long term
climate change and disaster risks was undertaken using the World Bank Climate and Disaster Risk
Screening Tool. The key risks are those related to the volcanic activities in the region, the
associated earthquake exposure, the potential for increased number of tsunamis with higher
intensity, as well as extreme precipitation and flooding. The latter was a major issue during
Cyclone Pam in 2015.
26. All technical designs include climate resiliency measures to address extreme precipitation
and flooding risks. The project undertook detailed studies to assess drainage at Bauerfield and
considered these in the pavement designs. These measures will include the construction of swales
to manage water run-off from the airport, additional storm water pits and rock riprap protections to
avoid erosion.
27. Rationale for use of Regional IDA. The PAIP Program countries have drawn on
significant resources from regional IDA with some 76% of the total PAIP Program funded by
regional IDA (see Table 2). Regional IDA funds provide access to supplemental capital for the
financing of investments in international airport infrastructure, the costs of which are otherwise
beyond (or significantly absorb) the resources available from national IDA allocations. PAIP
qualified for regional IDA because: (i) the investments generate significant cross-boundary benefits
and network effects (when activities were only of national benefit, national IDA is used); (ii) there
is clear evidence of regional commitment through PASO; (iii) there is active support from regional
donors (Asian Development Bank, Australia, New Zealand, and PRIF); and, (iv) PAIP provides a
platform for harmonization of regional aviation policy and standards, as well as harmonization and
implementation of important regional safety and security infrastructure. The primary justification
for utilizing Regional IDA resources in VAIP is the recognition that the cross country benefits of
regional connectivity can only accrue after the investments in improved airport infrastructure meet
operational requirements, thereby enabling air service providers to assess intra-regional passenger
and air freight opportunities.
6 The exact location of the apron will be confirmed through the ongoing Master Plan assignment.
Page 17
9
Table 2: PAIP Regional IDA Funding by Recipient
Recipient National
IDA (%)
Regional
IDA (%)
Total WB
Financing
($ million)
Kiribati 27 73 30.01
Tonga 30 70 34.46
Tuvalu 50 50 20.79
Samoa 16 84 41.62
Vanuatu (Original) 10 90 59.50
Vanuatu (Additional Financing) 17 83 73.60
PASO 100 2.15
Program (with Additional Financing)
202.63
28. Alternatives to Additional Financing Considered. There are no viable alternatives to
the scaling up of works proposed under Component A and technical assistance under Component
E. In the absence of a safe aviation operating environment at Vanuatu’s international airports
(particularly Bauerfield) there is the risk that aircraft operations may see further international jet
cancellations, with significant implications for Vanuatu’s tourism and economy7. The project team
investigated whether it would be possible to finance the necessary investments from within the
existing envelope by reallocating funds but this was not possible because:
It has been necessary to reallocate upwards of US$2 million to finance temporary
emergency runway repairs at Bauerfield to address cancellations of some international jet
operations;
As noted earlier, both Whitegrass and Pekoa airports are experiencing accelerated runway
deterioration, thus require repairs, thereby placing additional demands on project funds;
and,
Even with the deferral/cancellation of the maximum number of activities there would still
be a funding gap of over US$7 million, which would in turn undermine the achievement of
the PDO.
III. Proposed Changes
Summary of Proposed Changes
Additional Financing in a total amount of US$14.10 million is sought to increase the scope of civil works for
runway rehabilitation at Bauerfield, Whitegrass and Pekoa international airport, improved pavement geometry
at Bauerfield airport, repairs and possible extension of the existing apron or construction of a new apron and to
finance a technical advisor for the VPMU. There will be no changes to implementation arrangements,
procurement and financial management. There will also be no change to the current Environmental Category B
classification.
7 The financial impact on the Vanuatu economy resulting from flight cancellations was estimated at $US 260,000 per day. This
estimate is based on tourism arrivals by air statistics from the Vanuatu Statistics office and a recent report commission by the
NZ Tourism Research Institute financed by IFC
(https://tourism.gov.vu/assets/docs/reports/IVS/VanuatuInternationalVisitorSurvey2014_2015AnnualReportNZTRIFinal.pdf).
Page 18
10
There will be changes to:
Activities and Cost: There are two changes to the activities and cost:
o Component A: There will be an expanded scope of works for the pavement rehabilitation and
improvement activities under Component A with a component cost increase of US$13.75
million. The expanded scope of works includes: (i) improvement to runways at Bauerfield,
Pekoa and Whitegrass; (ii) geometric improvements (widening of existing taxiways and
expansion of turning bays) at Bauerfield airport to allow for larger aircraft to operate at the
airport; and, (iii) improvements to the existing apron, or potentially a new apron at Bauerfield
airport. The relocation of the Bauerfield domestic terminal building will be cancelled and funds
will be reallocated to pavement rehabilitation works at Pekoa and Whitegrass Airports as these
require urgent treatments to ensure flights are not interrupted. Cancellation of the proposed
improvements to the domestic terminal at Bauerfield and the potential construction of a new
apron reflect the medium term objective of the GoV to build a new terminal.
o Component E: There will be a component cost increase of US$0.35 million allocated to
component E “Project Support” to finance a technical advisor for the VPMU.
Results Framework: Two intermediate level indicators will be modified as follows: (i) the end target
of the “Fire Standards at VLI achieved” indicator will be elevated from ARFF Category 7 to Category 8
to reflect capability of handling larger jet aircraft; and, (ii) the inclusion of Whitegrass and Pekoa
airports, together with Bauerfield, to reflect the pavement repairs at all three international airports.
Disbursement: The disbursement estimates will be updated to reflect the Additional Financing of
US$14.10 million.
Effectiveness conditions: The project will have two effectiveness condition: (i) the collection of the
AUD$5 dollar SSL by CAAV; and, (ii) the preparation and adoption of a Disbursement Framework for
the levy by AVL.
Legal Covenant: The dated legal covenant “Safety and Security levy” (I.G.1 and I.G.2) is revised to
remove the dates and make the legal covenant an undated covenant to be met throughout project
implementation. This revision is appropriate in light of the inclusion of the effectiveness condition for
the AF. The responsible party for the collection of the levy (I.G.1) will be revised to be CAAV, rather
than AVL, to comply with the Civil Aviation Act of Vanuatu. The responsibility for continued
compliance with the disbursement framework and auditing requirements (I.G.2) will also be revised to
include both AVL and CAAV.
Change in Implementing Agency Yes [ ] No [ X ]
Change in Project's Development Objectives Yes [ ] No [ X ]
Change in Results Framework Yes [ X ] No [ ]
Change in Safeguard Policies Triggered Yes [ ] No [ X ]
Change of EA category Yes [ ] No [ X ]
Other Changes to Safeguards Yes [ ] No [ X ]
Change in Legal Covenants Yes [ X ] No [ ]
Change in Loan Closing Date(s) Yes [ ] No [ X ]
Page 19
11
Cancellations Proposed Yes [ ] No [ X ]
Change in Disbursement Arrangements Yes [ ] No [ X ]
Reallocation between Disbursement Categories Yes [ ] No [ X ]
Change in Disbursement Estimates Yes [ X ] No [ ]
Change to Components and Cost Yes [ X ] No [ ]
Change in Institutional Arrangements Yes [ ] No [ X ]
Change in Financial Management Yes [ ] No [ X ]
Change in Procurement Yes [ ] No [ X ]
Change in Implementation Schedule Yes [ ] No [ X ]
Other Change(s) Yes [ ] No [ X ]
Development Objective/Results PHHHDO
Project’s Development Objectives
Original PDO
The project development objective is to improve operational safety and oversight of international air transport
and associated infrastructure in Vanuatu.
Change in Results Framework PHHCRF
Explanation:
The upgrading of Bauerfield airport to cater for Category E aircraft will require a higher category of
ARFF capability. The results framework will reflect this by revising the end target for the intermediate
indicator “Fire Standards at VLI Achieved” from Category 7 to Category 8.
The project is now also financing pavement repairs to Whitegrass and Pekoa airports so the
intermediate indicator, which was previously only for Bauerfield, is revised to “Repairs to Bauerfield,
Whitegrass and Pekoa Airport pavements in line with implementation schedule.”
Compliance PHHHCompl
Covenants - Additional Financing ( Vanuatu Aviation Investment Project Additional Financing -
P161454 )
Source of
Funds
Finance
Agreement
Reference
Description of
Covenants Date Due Recurrent Frequency Action
IDA I.G.2
The Recipient
shall,
throughout the
Project
implementatio
n period,
Continuous New
Page 20
12
ensure that
CAAV and
AVL: (i) use
the Safety and
Security Levy
in accordance
with the
Disbursement
Framework;
and, (ii) furnish
to the TFSU,
by not later
than March 31
of each year,
annual audit
reports
prepared in
accordance
with the
Disbursement
Framework,
for collation
and
distribution to
the
Association.
Change in Legal Covenant
Compliance with the legal covenant “Safety and Security Levy”, Section I.G. in the Financing Agreement is
overdue. The covenant is composed of two components, the collection of an AU$5 SSL for departing
international passengers (I.G.1.) originally due on July 1, 2016 and the adoption of the associated
Disbursement Framework requirements for the SSL (I.G.2) originally due on the March 31, 2016.8 The delay
has resulted from a change in Government in 2015 that put the project on hold for almost a year. The new
Government that was put in place in 2016 has a strong interest in the success of the project and there is full
commitment towards introducing the SSL. The GoV is currently working on finalizing the legislation for the
SSL and has recently engaged legal services for guidance. The draft Disbursement Framework was discussed
during the November 2016 appraisal mission and has been agreed in principle. As the SSL's revenue is to be
used for sustaining the project investments and capacity development, and these activities have only just
commenced due to the aforementioned delays, the failure to introduce the SSL on time has not materially
impacted the project. There is also broad recognition of the financial benefits provided by the SSL among all
stakeholders, so there is renewed interest in getting this in place at the earliest. To ensure sustainable financing
8 Although reflected in the Financing Agreement, part I.G.2 was accidentally omitted in the Portal. The legal covenant was
therefore added as “new” in the Portal although already being in place as part of the Financing Agreement of the parent
project. The wording has been revised to reflect the effectiveness condition and the joint responsibility of AVL and CAAV for
the covenant.
Page 21
13
for airport safety and security and eligibility of the Project for Additional Financing, the following two
requirements are effectiveness conditions for the AF: (i) collection of the levy by CAAV; and, (ii) preparation
and adoption of the disbursement framework by CAAV and AVL. The existing dated legal covenants are
amended to require the Recipient to collect the levy, use the levy in accordance with the Disbursement
Framework and furnish to the TFSU the annual audit reports throughout the project implementation period. In
addition, the responsible party for the collection of the levy (I.G.1) has been revised to be CAAV instead of
AVL. This is required to comply with the Civil Aviation Act of Vanuatu. The responsibility for continued
compliance with the disbursement framework and auditing requirements (I.G.2) has also be revised to include
both AVL and CAAV.
Covenants - Parent ( Vanuatu Aviation Investment Project - P154149 )
Ln/Cr/TF
Finance
Agreement
Reference
Description of Covenants Date
Due Status
Recurre
nt Frequency
Action
IDA-56320
Financing Agreement:
VPMU | Description: The
VPMU shall be
maintained throughout the
Project implementation
period with adequate
resources and competent
and qualified staff in
adequate numbers
required for the Project. |
Complied
with Continuous No Change
IDA-56320
Financing Agreement:
Program Steering
Committee | Description:
The Recipient shall
nominate the chairman of
the VPMU Steering
Committee (or their
designated representative)
as its member to the
Program Steering
Committee.
Complied
with Continuous No Change
IDA-56320
Financing Agreement:
Regional Procurement
Evaluation Committee |
Description: The
Recipient shall, in
collaboration with the
other Program Countries,
ensure that the Regional
Procurement Evaluation
Committee is maintained
Complied
with
Continuous No Change
Page 22
14
throughout the Project
implementation period and
comprised of
representatives of the
Program Countries, TAL
(through TFSU) and
PASO. | Frequency:
CONTINUOUS
IDA-56320
Financing Agreement:
Safety and Security Levy |
Description: The
Recipient shall take all
measures required on its
part to ensure that AVL
shall, from not later than
July 1, 2016, and
thereafter throughout the
Project implementation
period, collect from
departing international
passengers a levy in a
minimum amount
equivalent to five
Australian Dollars (AU$5)
to recover aviation safety
and security expenditures
incurred by the Recipient.
Delayed Continuous Revised
IDA-56320 Safety and
Security Levy
Unless otherwise agreed
with the Association in
writing, the Recipient
shall take all measures
required on its part to
ensure that CAAV shall,
throughout the Project
implementation period,
collect from departing
international air
passengers a levy in a
minimum amount
equivalent to five
Australian Dollars (AU$5)
to recover aviation safety
and security expenditures
incurred by the Recipient
(“Safety and Security
Delayed Continuous Proposed
Page 23
15
Levy”).
Conditions
Source of Fund Name Type
IDA Safety and Security Levy Effectiveness
Description of the Condition
CAAV has commenced the collection of the Safety and Security Levy from departing international air
passengers.
Source of Funds Name Type
IDA Safety and Security Levy Effectiveness
Description
CAAV and AVL have prepared and adopted the Disbursement Framework
Risk
Risk Category Rating (H, S, M, L)
1. Political and Governance High
2. Macroeconomic Substantial
3. Sector Strategies and Policies High
4. Technical Design of Project or Program Substantial
5. Institutional Capacity for Implementation and Sustainability High
6. Fiduciary Substantial
7. Environment and Social Low
8. Stakeholders High
9. Other
OVERALL High
Finance
Loan Closing Date - Additional Financing ( Vanuatu Aviation Investment
Project Additional Financing - P161454 )
Source of Funds Proposed Additional Financing Loan Closing Date
International Development Association
(IDA)
31-Dec-2019
IDA Grant 31-Dec-2019
Change in Disbursement
Estimates
(including all sources of Financing)PHHCDE
Page 24
16
Explanation:
The Additional Financing of US$ 14.10 will be reflected in the disbursement schedule.
Expected Disbursements (in USD Million)(including all Sources of Financing)
Fiscal Year 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
Annual 0.80 31.00 26.00 15.70 0.40 0.00 0.00 0.00 0.00 0.00 0.00
Cumulative 0.80 31.80 57.80 73.50 73.90 0.00 0.00 0.00 0.00 0.00 0.00
Allocations - Additional Financing (Vanuatu Aviation Investment Project
Additional Financing - P161454 )
Source of
Fund
Currenc
y
Category of
Expenditure
Allocation
Disbursement %(Type
Total) (inclusive of
taxes)
Proposed Proposed
IDA USD
Goods, works,
consulting/non-
consultants services,
Audit, Training, TFSU
Costs & Project
Operating Costs (other
than under B.2)
9.5
100.00
Total: 9.5
IDA USD
Goods, works,
consulting/non-
consultants services,
Audit, Training, TFSU
Costs & Project
Operating Costs (other
than under B.2)
4.6
100.00
Total: 4.6
Components
Change to Components and
Cost
PHHCCC
Explanation:
The Additional Financing (AF) is necessary to meet the total funding requirements for all identified project
activities. The five original project components remain, but with the following changes:
Component A - International Airport Infrastructure Investments:
An expanded scope of works for the pavement repairs at Bauerfield and civil works to address
pavement issues for Whitegrass and Pekoa airports;
Page 25
17
Geometric improvements at Bauerfield airport (widening of taxiways and expansion of turning bays) to
allow for larger aircraft to operate at the airport;
Repair and possible expansion of the existing apron or potentially a new apron (and associated taxiway)
at the other side of the runway;
Cancellation of the current activity “Relocation of Bauerfield domestic terminal building” to reallocate
funds towards pavement civil works at Whitegrass and Pekoa airports
Component E – Project Support
A technical advisor will be financed to support the VPMU with project implementation.
Total Financing: The total financing is now US$73.90 million (see Table 1 for breakdown).
Current Component
Name
Proposed Component
Name
Current
Cost (US$M)
Proposed
Cost
(US$M)
Action
Component A:
International Airport
Infrastructure
Investments
Component A:
International Airport
Infrastructure
Investments
50.77 64.52
Revised
Component B:
Aviation Sector
Reform and Training
Component B: Aviation
Sector Reform and
Training
1.53 1.53
No Change
Component C:
Strengthening of
Airport Operations
and Management
Capacity
Component C:
Strengthening of
Airport Operations and
Management Capacity
1.14 1.14
No Change
Component D:
Emergency
Reconstruction
Component D:
Emergency
Reconstruction
3.88 3.88
No Change
Component E: Project
Support
Component E: Project
Support 2.48 2.83
Revised
Total: 59.80 73.90
Appraisal Summary
Economic and Financial Analysis PHHASEFA
Explanation:
As with the original project, the cost benefit analysis is predicated on the assumption that any loss in tourism
Page 26
18
GDP would entail a loss of economic welfare. In the case of the Additional Financing, the economic analysis
has been adjusted to reflect the change in scope of works of the pavement rehabilitation, by adding an
additional $14.1 million, the one-year implementation delay and the preparatory design works completed under
the parent project to date. In the updated economic analysis, the original methodology has not been changed.
The updated economic analysis covers the ten year period from 2015 to 2025. In the “with-project” scenario,
the additional investment of US$14.1 million was added to the original amount of US$59.8 million. The
investments made through the project will allow jet services to continue normally with contributions to GDP
according to the World Travel and Tourism Council’s (WTTC) estimates. WTTC’s analysis estimates the
direct contribution of travel and tourism to GDP at US$156.8 million (which is about 19.2 percent of total
GDP), with an expected growth rate of approximately 4.3 percent p.a. over the next 10 years.
In the “without-project” scenario, no actions would be taken until forced to do so, i.e., when jet services cease
due to unsafe conditions. Emergency action to bring the runway and facilities back into safe and serviceable
condition would require a series of activities assumed to take six months, taking into account preparatory
design works completed under the parent project. Such activities would involve finalization of design works,
securing of funding, a procurement process, and works completed. During the half year, it is assumed that the
impact of fewer flights would be a loss of approximately US$41 million. This estimate is based on reported
estimated annual loss of US$82.13 million, which is in line with the US$96.4 million estimation of annual
tourism expenditures in 2015 based on numbers of tourism arrival by air (see footnote 5 presented earlier).
The benefits of ensuring the project’s development objectives would include: (i) proposed spending on safety
and security is not postponed to later date, which could result in avoided accidents; and, (ii) no tourism and
travel GDP is lost. The base-case assumes that, without the project, airlines would cease service by 2017 and
that about US$41 million of tourism GDP would be lost during that year. This yields an EIRR of 85.2 percent
and the NPV of US$28.3 million using a discount rate of 10 percent, compared to an EIRR of 108 percent and
NPV of US$29.9 million for the original project. If the airlines were to cease services later, the EIRR would be
lower than for the base case. Yet, since the end of services by airlines cannot be forecasted with certainty, it is
likewise not possible to ascertain when the airlines would cease to provide services without the project, and
how much tourism GDP would be affected. The EIRR sensitivity analysis regarding these two factors is
illustrated in the figure below. This analysis shows that the proposed investments are economically very
robust.
Page 27
19
Implicit in the economic analysis is the assumption that the pavements, navigation aids, communications
equipment, etc. will be maintained into the future. The PAIP program is working to address this challenge
from a regional perspective through the establishment of: (i) a regional airfield pavement management system
which will facilitate planning; and, (ii) a long-term performance based maintenance contract for key
infrastructure. The design of these two activities is underway at present and it is anticipated that they will be
under way in 2017.
Technical Analysis PHHASTA
Explanation:
The Additional Financing will cover a project scale up to include an expanded scope of works under the
existing Component A “International Airport Infrastructure Investment” (US$13.75 million) and a technical
advisor to the VPMU under the existing Component E “Project Support” (US$0.35). The scale-up under
Component A in will serve to: (i) address the increased pavement deterioration since appraisal of the original
project; (ii) enable Bauerfield airport to accommodate larger aircraft to stimulate tourism and increase disaster
response capacity; and, (iii) repair and/or expand existing apron or relocate the apron at Bauerfield airport.
The following additional works and services will be financed:
For Bauerfield airport:
o The VLI 11/29 Runway is 2.6 km in length and 45 m wide, the current surface is asphalt.
Runway upgrade works were last completed in the late 1990’s. The runway is past the end of its
service life and has suffered severe structural failure. This has necessitated two sets of
emergency repairs in 2016 to keep the airfield operational for jet aircraft. Damages are
particularly critical within the heavy trafficked areas of the runway and with the commencement
of the main works, some 2000 meters will undergo complete rehabilitation and the balance an
overlay. The runway will be milled to a depth of at least 100mm along the pavement length. A
heavy tack coat will be applied to the existing coral base asphalt and a new AC20 base layer
will be laid up to 300m thick followed by the surface asphalt level of at least 50mm. The
runway is also having new shoulder areas added along its length with a width of 7.5m on each
side. The shoulders will have a 200mm base course and will be sealed with either asphalt or
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
80.0%
90.0%
100.0%
20 30 40 50 60 70 80 90
EIR
R
Impact to tourism as jet service stops ($m)
2017
2018
2019
2020
The year of delayed investment
Page 28
20
SEST;
o Enhanced runway drainage to be better prepared for future disasters and extreme weather
events. Works will include increasing the capacity of the northern swale drain by widening and
deepening the existing drain so as the grade it to the La Colle river channel some 150 meters
from the western end of the runway and allow for drainage from this side of the runway. This
option would reduce the pressure on the existing cross runway culverts, reduce the peak
discharge across the runway to 2 m3/s from 2.5 m
3/s, and reduce the instances and pooling and
flooding of the runway. Opening the northern drain to allow drainage to the La Colle flood plain
will also reduce the volume of runoff discharged through the southern drain and will more
evenly distribute the water flow into the flood plain from the airfield helping to lessen any
localized flooding outside the boundary fence;
o Increased pavement strength (61/F/C/X/T) for an estimated two movements of Code E Aircraft
per week over the design life;
o Turning bays on both runway ends will be expanded for Code E aircraft and provided with
appropriate lighting;
o Taxiways will be widened minimally to accommodate Code E aircraft; and,
o The project will either repair and/or expand the existing apron or construct a new apron within
the existing boundary to support the potential development of a new terminal9. The decision
whether to finance works on the existing apron or a new apron is dependent on the GoV’s
decision whether to construct a new terminal in the medium term as well as the outcome of the
Airport Master Plan anticipated to be finalized in the first half of 2017.
For Whitegrass airport the works are being tendered as a design build contract. The design and
construction solution will consist of pavement resurfacing by the Contractor. The primary tasks to be
undertaken are:
o Removal and replacement of asphalt surfacing;
o Painting of runway, taxiway and apron marking to be ICAO compliant; and,
o Improvements to navigation aids and communications equipment.
For Pekoa airport the works will also be tendered as a design build contract with the design and
construction works including:
o SEST surface treatment for the runway, apron and taxiway areas;
o Painting of runway, taxiway and apron marking to be ICAO compliant; and,
o Improvements to navigation aids and communications equipment.
Technical Advisor to the VPMU: A Technical advisor will be financed to support the VPMU in the
implementation of the project.
Social Analysis PHHASSA
Explanation:
Safeguard Policy OP/BP 4.12 on Involuntary Resettlement was triggered in the original project and remains
triggered. No new risks or impacts from those identified during preparation have been identified, based on the
detailed designs for pavement works. There is no involuntary resettlement in the project.
9 In the event this new terminal is cancelled the project would instead extend the existing apron on eastern and
western sides by an additional approximately 12,500 m2.
Page 29
21
The majority of the project’s activities are on existing land within airport precincts. It is envisaged that two off-
site activities may take place: (i) trenching for power cables; and, (ii) upgrading of a track to access navigation
aids. To account for this, a Resettlement Policy Framework (RPF), based on the PAIP Environmental and
Social Management Framework (ESMF), is included in the Project Environmental and Social Management
Plan (PESMP) to cover these and any other eventualities. While the PESMP strongly discourages the opening
of new quarries, it includes a “Code of Practice” which would cover the opening of a quarry should it be
required, and this calls for the RPF to be applied as well as meeting environmental health and safety standards.
As described in Annex 2, the project is undertaking a number of enhancement and innovations to improve the
social and environmental outcomes. These are reflected in the PESMP and the contract bid documents for
major civil works. These include undertaking education programs for workers on HIV/AIDS, Gender Based
Violence (GBV), and ‘Child Protection’, improved focus on worker occupational health and safety (OHS), and
more.
The project will have a very positive social impact. The loss of international flights due to Bauerfield’s poor
pavement condition had a major negative impact on tourism, resulting in job losses in the sector, particularly
amongst women. Efforts are under way to try and quantify this effect. The project will ensure that the airport
will operate in a safe and efficient manner, as well as being able to handle demands from future emergencies.
In addition to the above, OP/BP 4.12 applies in accordance with Interim Guidelines on the Application of
Safeguard Policies to Technical Assistance (TA) Activities in Bank-Financed Projects and Trust Funds
Administered by the Bank (January 2014). This is because there is the potential that the Aviation Master Plan
may lead to increases in noise disturbance, land acquisition and resettlement, which may arise from the
recommendations and implementations of these technical assistance activities.
The proposed Airport Master Plan and Aviation Sector Strategy to be developed under the project will cover
all international airports in Vanuatu: Bauerfield Airport, Whitegrass Airport on Tanna Island and Pekoa
Airport on Espiritu Santo. The potential subprojects that may be identified through the master planning and
strategy development process are unknown; however they may include activities with the potential for
environmental and social impacts (e.g. runway lengthening, terminal expansion, runway rehabilitation etc.).
The potential impacts associated with any downstream activities identified through the Master Plan were
addressed in the Terms of Reference through the provision that: “The potential safeguard implications shall be
incorporated within the master plan to ensure they are considered in the development of subprojects. Where the
master plan process has the potential to impact on communities outside the airports, these communities, with
representatives of both men and women groups, will be engaged in a meaningful way in the master plan
process.” The safeguard implications of any recommendations will be reviewed by the Bank prior to reports
being finalized.
Furthermore any downstream subprojects proposed as a result of the Master Plan (either as part of this project,
or as linked activities) will be screened for environmental and social risks and impacts. This process will
determine the policies triggered, the classification of safeguard category and the specific instrument(s) that
may be required. Safeguards instruments will be prepared prior to Bank clearance.
The WB’s policy on indigenous peoples (OP/BP 4.10) is only triggered in the Pacific where all of the
following four defining characteristics are present:
a) Self-identification as members of a distinct indigenous cultural group and recognition of this identity by
Page 30
22
others.
b) Collective attachment to geographically distinct habitats or ancestral territories in the project area and to
the natural resources therein.
c) Customary cultural, economic, social, or political institutions that are separate from those of the dominant
society and culture.
d) An indigenous language, often different from the official language of the country or region.
Projects situated in Vanuatu do not usually trigger OP 4.10 as only characteristic (b) is relevant.
As noted earlier, a new terminal is potentially planned by the GoV. If the new terminal is not financed by the
World Bank, it will be considered to be an “associated facility” and thus linked from a social safeguards
perspective. This is because the proposed new terminal is: (i) directly and significantly related to the project;
(ii) will likely be constructed contemporaneously with the current project (i.e. before 2019); and, (iii) impacts
on the ability of the project to deliver the development outcome related to regulatory compliance of the entire
aerodrome. The World Bank’s safeguard policies will therefore apply. It is envisaged that the PESMP would
be updated, consulted on and applied to the terminal construction.
Environmental Analysis PHHASEnvA
Explanation:
The project remains Category B under Safeguard Policy OP 4.01 Environmental Assessment. There will be no
change to environmental risks or issues as a result of Additional Financing.
Project impacts primarily relate to the transport and construction impacts of runway, apron construction and/or
expansion and pavement resurfacings. The impacts will be mitigated through the use of the PESMP, consistent
with the PAIP ESMF. The PESMP was prepared and disclosed during preparation, and has been updated to
reflect the detailed designs. Separate PESMPs were prepared for each airports. Major impacts will relate to
construction processes and the transport of materials to the site.
Other investments in buildings (e.g. fire tender shelters), lighting, navigation aids, etc. are expected to have
minor environmental impacts—all of which are readily managed.
As described in Annex 2, the project is implementing a number of improved safeguards measures and
innovations to improve the social and environmental outcomes. These are reflected in the PESMP and the
contract bid documents for major civil works. These address issues such as: (i) ensuring imported materials
such as aggregate and equipment meet strict biosecurity precautions; (ii) requiring removal of hazardous and
inorganic waste by the contractor to the country of origin; (iii) improved contractual remedies for non-
compliance with PESMP; (iv) clear requirements for preparation of contractor’s ESMP, its clearance and
disclosure; and, (v) ‘Codes of Practice’ in the PESMP for quarrying, OHS, and establishment of worker’s
camps.
Greenhouse Gas (GHG) emissions accounting. The International Civil Aviation Organization (ICAO) carbon
emissions calculator was used to estimate the project’s potential impact on GHG emissions. The ICAO
methodology uses a distance-based approach that draws on current and publicly available data on the fuel
consumption of a range of aircraft types. The focus of this analysis is solely on international operations to
Bauerfield airport and does not include any domestic operations as these are not expected to be materially
influenced by the project. The project will enable larger, higher capacity aircraft to serve Bauerfield airport,
which may result in a reduction in the number of flights assuming constant demand. This change in schedule is
Page 31
23
estimated to results in a reduction of around 370 tons of CO2 per year. Additional savings in GHG emissions
will be achieved by: (i) a reduction in taxiing time over the current operations; (ii) the adoption of low energy
lighting; and, (iii) operational efficiencies that will arise from the availability of ADS/B and other improved
navigation aids—none of which could be quantified for the GHG analysis. More details are given in Annex 3.
Risk
Explanation:
The overall risk rating of the project is High. The sector does not have a history of strong governance, and has
not been seen to provide adequate fiscal resources for safety oversight, airport operations and management.
The political and governance risk is high due to several changes of Government over a relatively short period,
resulting in major policy changes. Over that period there have also been multiple changes of leadership at AVL
which has led to a high risk with regard to institutional capacity for implementation and sustainability. The risk
to the stakeholders is also high—as evidenced by the suspension of flights by some airlines, and the associated
impact on the tourism industry. The macroeconomic risk is substantial, due to the impact of Cyclone Pam in
2015 on the economy. The technical risk is substantial as the scale and complexity of the civil works are major,
and the works need to be completed in a timely manner without materially interrupting flights. The fiduciary
risk is substantial as there is no recent experience with a World Bank financed project of similar magnitude.
V. World Bank Grievance Redress
29. Communities and individuals who believe that they are adversely affected by a World
Bank (WB) supported project may submit complaints to existing project-level grievance redress
mechanisms or the WB’s Grievance Redress Service (GRS). The GRS ensures that complaints
received are promptly reviewed in order to address project-related concerns. Project affected
communities and individuals may submit their complaint to the WB’s independent Inspection Panel
which determines whether harm occurred, or could occur, as a result of WB non-compliance with
its policies and procedures. Complaints may be submitted at any time after concerns have been
brought directly to the World Bank's attention, and Bank Management has been given an
opportunity to respond. For information on how to submit complaints to the World Bank’s
corporate Grievance Redress Service (GRS), please visit http://www.worldbank.org/GRS. For
information on how to submit complaints to the World Bank Inspection Panel, please visit
www.inspectionpanel.org.
30. The project has established a Grievance Response Mechanism (GRM) for monitoring and
managing all grievances. Statistics from the GRM are publicly reported at www.vaip.vu and these
are used as Results Indicators.
Page 32
24
Annex 1: Results Framework
Project
Name: Vanuatu Aviation Investment Project Additional Financing
(P161454)
Project
Stage: Additional Financing Status: DRAFT
Team
Leader(s)
:
Christopher R. Bennett Requesting
Unit: EACNF Created by: Nora Weisskopf on 08-Sep-2016
Product
Line: IBRD/IDA
Responsible
Unit: GTI02 Modified by: Nora Weisskopf on 15-Sep-2016
Country: Vanuatu Approval FY: 2017
Region: EAST ASIA AND PACIFIC Lending
Instrument: Investment Project Financing
Parent Project
ID: P154149
Parent Project
Name: Vanuatu Aviation Investment Project (P154149)
Project Development Objectives
Original Project Development Objective - Parent:
The project development objective is to improve operational safety and oversight of international air transport and associated infrastructure in
Vanuatu.
Results
Core sector indicators are considered: Yes Results reporting level: Project Level
Project Development Objective Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
No Change Regulatory certification of
safety and security at
Bauerfield (VLI) maintained
Text Value VLI certified VLI Certified Re-validation of
certification of
VLI in
accordance with
CAR-Part 139.
Page 33
25
Date 05-Mar-2015 31-Aug-2016 30-Jun-2019
Comment
No Change State requirements for safety
measured by Universal Safety
Oversight Audit Programme
(USOAP) reaches global ICAO
average
Number Value 47.51 47.51 41.38
Date 05-Mar-2015 31-Aug-2016 30-Jun-2019
Comment
No Change Modernization of air traffic
management achieved
Text Value No VSAT or
ADS-B
ADS-B ground
stations procured
and due to arrive
early 2017.
VSAT design
procurement
underway.
VSAT or ADS-
B operational
Date 05-Mar-2015 31-Aug-2016 30-Jun-2018
Comment
No Change Regional safety and security
levy for departing international
passengers implemented
Text Value No levy No levy. AU$5 collected
from each
departing
international
passenger.
Date 05-Mar-2015 31-Aug-2016 30-Jun-2016
Comment Legislation for
implementation
of levy currently
underway.
Intermediate Results Indicators
Status Indicator Name Core Unit of Measure Baseline Actual(Current) End Target
No Change Navigation and safety aids in
line with implementation
Percentage Value 0.00 0.00 100.00
Date 05-Mar-2015 31-Aug-2016 30-Jun-2017
Page 34
26
schedule Comment
Revised Repairs to Bauerfield,
Whitegrass and Pekoa Airport
pavements in line with
implementation schedule
Percentage Value 0.00 0.00 100.00
Date 05-Mar-2015 31-Aug-2016 30-Jun-2018
Comment
Revised Fire Standards at VLI
Achieved
Text Value Category 6 Category 6 Category 8
Date 05-Mar-2015 31-Aug-2016 30-Jun-2018
Comment
No Change Airport Master Plan and
Aviation Sector Strategy in line
with implementation schedule
Percentage Value 0.00 0.00 100.00
Date 05-Mar-2015 31-Aug-2016 30-Jun-2018
Comment Contracts for
both
assignments
awarded.
No Change Successful implementation of
agreed training plan
Text Value No Training
Plan
No training plan Training Plan
completed
Date 05-Mar-2015 31-Aug-2016 31-Dec-2017
Comment
No Change Grievance registered related to
delivery of project benefits by
gender that are actually
addressed
Percentage Value 0.00 100.00 100.00
Date 05-Mar-2015 31-Aug-2016 31-Dec-2017
Comment No grievances
received to date.
No Change Grievances responded and/or
resolved within the stipulated
services standards for response
times
Percentage Value 0.00 100 75.00
Date 05-Mar-2015 31-Aug-2016 31-Dec-2017
Comment No grievances
received to date.
No Change Project-supported
Yes/No Value No Yes Yes
Page 35
27
organization(s) publishing
periodic reports on GRM and
how issues were resolved
Date 05-Mar-2015 31-Aug-2016 31-Dec-2017
Comment Statistics
published on
line but no
grievances to
date.
Page 36
28
Indicator Description
Project Development Objective Indicators
Indicator Name Description (indicator definition etc.) Frequency Data Source /
Methodology
Responsibility for
Data Collection
Regulatory certification of
safety and security at
Bauerfield (VLI)
maintained
Although Bauerfield airport is currently certified, the
CAAV with the support of the PASO will undertake a
detailed assessment of Bauerfield Aerodrome at the
end of the project in accordance with Vanuatu Civil
Aviation Rules (Part139), which conforms to both
New Zealand Civil Aviation Rules 139 and applicable
portions of ICAO Annex 14 (international standards
for aerodrome design and operations). If compliance
is achieved CAAV will re-issue certification of the
aerodrome to AVL.
Aligned with
PASO oversight
schedule.
CAR-Part 139 as
adopted by
CAAV, which
conforms to
applicable portions
of ICAO Annex
14.
CAAV/VMPU
State requirements for
safety measured by
Universal Safety Oversight
Audit Programme
(USOAP) reaches global
ICAO average
USOAP audits focus on the State’s capability for
providing safety oversight by assessing whether
critical elements of a safety oversight system have
been implemented effectively. Audit teams also
determine the State's level of implementation of
safety-relevant ICAO Standards and Recommended
Practices (SARPs), associated procedures, guidance
material and practices. The audit protocol is a
comprehensive checklist, covering all elements of the
State’s safety oversight program subject to the audit.
These audit protocols are used as the primary tool for
conducting the audit. The extent (in percentage) of
lack of compliance is determined based on the
findings of the audit. The most recent USOAP audit
available was undertaken in 2006.
End of Project ICAO Audit CAAV/VPMU
Modernization of air traffic
management achieved
The results indicator measures the completed and
successful installation of ADS-B, a low-cost
surveillance system, and a VSAT system, a dedicated
communications network, neither of which is
currently available.
Once Project progress
reports
AVL/CAAV/VMPU
Page 37
29
Regional safety and
security levy for departing
international passengers
implemented
(Text)
The results indicator will measure the successful
introduction, collection and expenditure accounting of
the departing international passenger levy to cover
costs associated with: (i) services from the PASO; (ii)
maintenance of security and safety equipment; and,
(iii) any expenditure to ensure effective safety
oversight by the CAAV. The levy is collected as part
of the ticket price and remitted to the MFEM who will
disburse the funds in accordance with a framework
cleared by the Bank.
Once Project progress
reports
MFEM/AVL/MIPU/
VPMU
Intermediate Results Indicators
Indicator Name Description (indicator definition etc.) Frequency Data Source /
Methodology
Responsibility for
Data Collection
Navigation and safety aids
in line with implementation
schedule
Supply and installation of navigation and safety aids
leading to improved operational safety.
Annual through
completion
Project progress
reports
AVL/VPMU
Repairs to Bauerfield,
Whitegrass and Pekoa
Airport pavements in line
with implementation
schedule
Completed rehabilitation and repairs to all
pavements at Bauerfield, Whitegrass and Pekoa
Airports
Annual through
completion
Project progress
reports
AVL/VMPU
Fire Standards at VLI
Achieved
Achievement of Category 8 ARFF operations
capable of handling largest aircraft serving the
Bauerfield. Current Category 6 requires vehicles that
carry 11,800 litres of water; with discharge rate
(foam/liters) of 4,000 per minute; Category 8
requires vehicles that carry 27,300 liters of water;
with discharge rate (foam/liters) of 7,200 per minute
Once Project progress
reports
AVL/VMPU
Airport Master Plan and
Aviation Sector Strategy in
line with implementation
schedule
Completion of both studies to guide long-term
sustainable sector development
Annual through
completion
Project progress
reports
VMPU
Page 38
30
Successful implementation
of agreed training plan
Training for AVL and CAAV for capacity building. End-of-Project Project progress
reports
CAAV/AVL/VMPU
Grievance registered related
to delivery of project
benefits by gender that are
actually addressed
Citizen engagement indicator in accordance with the
2014 Results Framework and M&E Guidance Note.
Modified to include gender.
Annual through
completion
Grievance and
Complaints
Logging System
VPMU
Grievances responded
and/or resolved within the
stipulated services
standards for response
times
Citizen engagement indicator in accordance with the
2014 Results Framework and M&E Guidance Note.
Annual through
completion
Grievance and
Complaints
Logging System
VPMU
Project-supported
organization(s) publishing
periodic reports on GRM
and how issues were
resolved
Citizen engagement indicator in accordance with the
2014 Results Framework and M&E Guidance Note.
The project has established a website which displays
the resolution rate for grievances and time to resolve.
Continual Web site linked to
Grievance and
Complaints
Logging System
VPMU
Page 39
31
Annex 2: Improved Safeguard Measures and Innovations
1. In light of recent recommendations for the transport global practice to improve safeguards
compliance, VAIP is being used to strengthen existing measures and pilot a number of innovations
to elevate the ability to monitor effectiveness and achieve compliance with safeguard policies.
Supervision
Requires quarterly inspections by Supervision Consultant’s safeguards specialist to check on
performance of Resident Engineer who is tasked with day-to-day safeguards oversight.
Independent auditing will be done quarterly by the VPMU’s safeguards specialist in conjunction
with the resident engineer and the Consultant’s safeguards specialist.
Contractor’s Contract
Tightening of Contractual Requirements
Major revisions to the particular conditions of contract to improve safeguards compliance:
o Preparation, clearance by supervision engineer, and disclosure on client’s web site of
Contractor’s Environment and Social Management Plan (CESMP) before commencing
civil works.
o Contractual remedies for non-compliance with CESMP.
o Biosecurity requirements for imported materials.
o Exporting of hazardous and inorganic waste materials.
o Background checks on international staff and requirements to sign ‘Code of Conduct’
related to GBV and protecting children.
o Occupational health and safety (see below).
Occupational Health and Safety (OHS)
Requirements:
o The PESMP contains a ‘Code of Practice’ with a detailed set of requirements for OHS
covering all aspects including reporting and personal protective equipment.
o Potential pilot test existing app for reporting on OHS issues.
Financing: The bid documents for major civil works contain provisional sum (percentage of the
engineer’s estimate) to fund the costs of covering OHS activities, would only be payable on
proof of record, e.g. time sheets, material invoices etc., for the following:
o Provision of "Dedicated safety professionals" as a full time role.
o Personal Protective Equipment for the Contractor’s team.
o Safety signage, safety literature etc.
Page 40
32
o Labour costs for attending dedicated safety training such as working at heights, confined
space training, first aid training etc.
o Participation on HIV/AIDs, GBV and Child Protection training
o Alcohol testing of staff
If the provisional sum is not spent, the unspent allowance remains with the Client. If it is over
spent, then that is to the Contractor’s account.
Qualifications:
o To be qualified for bidding for major civil works, contractors will be required to meet the
following:
‘For the purposes of this project the employer is adopting a code of practice for
occupational health and safety based on good international industry practice. To be
qualified for bidding contractors will be required to have in place an occupational health
and safety management system which is compliant with, or equivalent to, OHSAS 18000
(http://certificationeurope.com/ohsas-18000-health-safety-managment-standards/) and is
acceptable to the client. The contractor shall specify which occupational health and safety
standards are to be applicable to the project, and provide evidence of application of such
standards on a project of similar size and complexity during the past 5 years. The
standards to be adopted may include those of Australia, Canada, New Zealand, the EU and
the US, which are referred to in the World Bank Group EHS Guidelines.
o With their bids, Contractors will be required to submit statistics for their workplace safety
performance for the past 5 years on:
Number of fatal injuries
Number of notifiable injuries
Number of lost time injuries
Number of medical treatment injuries
Number of first aid injuries
Number of recordable strikes of services
Lost Time Injury Frequency Rate
Total Recorded Frequency Rate
Page 41
33
Supervision:
o The supervision engineer is required to monitor OHS guidance during their regular
duties. Also included is the requirement that there be monthly/bi-monthly independent
OHS audits by a certified auditor as part of the consultant’s supervision team.
o The Contractor will be required to report monthly on their performance with the above
indicators supplied during bidding, as well as:
Number of alcohol tests
Proportion of positive alcohol tests
Number of site health and safety audits conducted by contractor
Number of safety briefings
Number of near misses
Number of traffic management inspections
Number of sub-contractor reviews
Number of stop work actions
Number of positive reinforcements
Others
HIV/AIDS, Gender Based Violence and Child Protection
Undertaking a structured HIV/AIDS education program using the ‘Road to Good Health’ toolkit
(www.theroadtogoodhealth.org)
Pilot testing the use of ‘Codes of Conduct’ and training to address GBV and protect children.
Quarrying
No new quarries are anticipated but PESMP includes Code of Practice for Quarrying should they
be necessary.
Workers Camps
No workers camps are anticipated but the PESMP includes the requirement that they be
established in accordance with the IFC-EBRD Guidelines.
Grievance and Reporting
System: Have already established an online system for reporting on grievances
(http://www.vaip.vu/) and publishing statistics to meet the IDA citizen engagement
requirements.
Page 42
34
Annex 3
Greenhouse Gas Accounting
1. Methodology. The International Civil Aviation Organization (ICAO) carbon emissions
calculator10
was used to estimate the project’s potential impact on GHG emissions. The ICAO
methodology uses a distance-based approach that draws on current and publicly available data on the
fuel consumption of a range of aircraft types. The focus of this analysis is solely on international
operations and does not include any domestic operations. The ICAO Carbon Emissions Calculator
was used and combined with data from: (i) DiiO SRS analyzer, a database for airline schedules; (ii)
Virgin Australia airline’s website; and, (iii) ICAO engine emissions databank.
2. Assumptions. The GHG analysis for this project was completed based on the following
assumptions:
Baseline: The primary objective of this project is the rehabilitation of Bauerfield airport to
avoid cancellation of jet operations, and now also to allow for the reinstatement of
temporarily cancelled flights. The emissions resulting from these reinstated flights were
therefore assumed to be part of the baseline rather than accounted for as additional GHG
generated by the project.
Passenger Load Factors: The calculations assume that all flights attain a 78 percent
passenger load factor relative to the total number of seats available by aircraft type. This is
based on the average load factors for each region provided in the Methodology of the
ICAO Carbon Emissions calculator.
Emissions generated from the project. The Additional Financing will enable operational
enhancements that accommodate the potential for larger aircraft (Code E aircraft) to
service Bauerfield airport. Based on an analysis of the existing carriers operating into
Bauerfield, their current network and aircraft fleet mix, it was assumed that Virgin
Australia would be the only existing airline that would potentially upgrade from the
existing aircraft used, a B737-800, to a larger B787 Code E aircraft. Given the increased
seat capacity of a 787, but limited additional passenger demand, it was also assumed that
Virgin Australia would replace their current schedule of 12 monthly 737-800 aircraft
movements with 8 monthly 787 aircraft movements. Since the Master Plan has not been
completed it was not possible to consider additional generated traffic in the calculations.
3. Results. The analysis calculates an annual decrease of 370 tons carbon emission from this project.
The reduction in emissions result from larger aircraft being able to serve the airport and consequent
reduction in the frequency of aircraft movements (from 12 to 8). Additional reductions could be
expected from:
Emission reductions from more efficient taxiing: Specific runway areas, particularly close
to the entrance to the taxiway located at the midpoint of the runway, have deteriorated
significantly. To avoid further deterioration, jet aircraft are currently not allowed to apply
heavy brakes in these areas. This forces aircraft to travel towards the end of the runway,
10
http://www.icao.int/environmental-protection/CarbonOffset/Pages/default.aspx
Page 43
35
turn, and return to the taxiway to reach the apron. This generates additional fuel burn and
resultant emissions. Full details are on file.
ADS-B Surveillance: Surveillance of aircraft may potentially allow for optimized routing
of aircraft within the Pacific. Given the difficulty to assess these impacts, these are only
mentioned here but have not been included in the analysis.
Apron enlargement: The enlarged apron may allow for push-back and tow ground
handling equipment. This infers that, rather than power-in and power-out maneuvering on
the apron, aircraft would generate fewer emissions. Given the difficulty to assess these
impacts, these are only mentioned here but have not been included in the analysis.
Low-energy lighting: The implementation of low energy lighting will have a positive
GHG impact, but it was not considered in the GHG analysis due to a lack of available
data.