Page 1: Session 5 - GDAS PMP Study Group Presentation

© 2005 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice

GDAS PM Professions:PMP Study Group

Monique HowardOctober 16, 2008

Session #5: Time Management

Page 2: Session 5 - GDAS PMP Study Group Presentation

1. Please refer to the diagram given below: (all units are in days)

What is the project float if management wants to do this project within ten days?

A. 0 daysB. -4 daysC. 2 daysD. Cannot be determined because information in the question is inconsistent

Page 3: Session 5 - GDAS PMP Study Group Presentation

Correct Choice:     B  (-4 days)Justification:     The different paths possible are as follows:

* Start -> Task1 -> Task2 -> Task3 -> End : 10* Start -> Task1 -> Task2 -> Task3 -> Task6 -> End : 14* Start -> Task4 -> Task5 -> Task6 -> End: 13* Start -> Task4 -> Task5 -> Task3 -> Task6 -> End: 14* Start -> Task4 -> Task5 -> Task3 -> End: 10

So, the critical path is 14.

If the project has to be completed within 10 days, the project float is - 4 days (i.e 10 - 14)

Please note: A project may have a negative project float. To deal with such conditions, if the project has to be completed on time, the project manager will have to either fast-track or crash the project schedule.

Reference: pmstudy.com notes as mentioned above

Page 4: Session 5 - GDAS PMP Study Group Presentation

2. All the following are advantages of GERT (Graphical Evaluation and Review Techniques) as compared with PERT (Project Evaluation and Review Technique) EXCEPT:

A. Allows loopingB. Allows for dummy tasksC. Allows branchingD. Allows multiple project end results

Page 5: Session 5 - GDAS PMP Study Group Presentation

2. All the following are advantages of GERT (Graphical Evaluation and Review Techniques) as compared with PERT (Project Evaluation and Review Technique) EXCEPT:

A. Allows loopingB. Allows for dummy tasksC. Allows branchingD. Allows multiple project end results

Correct Choice:     B Justification:     Graphical Evaluation and Review techniques are similar to PERT but have the distinct advantages of allowing for looping, branching, and multiple project end results.

Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 679

Page 6: Session 5 - GDAS PMP Study Group Presentation

3. It is important to identify and document the specific work that is planned to be performed and also identify deliverables at the work package level. This is done as part of:

A. Activity DefinitionB. DecompositionC. Scope DefinitionD. Activity Sequencing

Page 7: Session 5 - GDAS PMP Study Group Presentation

3. It is important to identify and document the specific work that is planned to be performed and also identify deliverables at the work package level. This is done as part of:

A. Activity DefinitionB. DecompositionC. Scope DefinitionD. Activity Sequencing

Correct Choice:     A Justification:     Activity Definition: Defining the schedule activities involves identifying and documenting the work that is planned to be performed. The activity definition process will identify the deliverables at the lowest level in the WBS, which is called the work package.

Reference: PMBOK Third Edition, Page Number: 127

Page 8: Session 5 - GDAS PMP Study Group Presentation

4. In schedule development, mathematical analysis often produces a preliminary early-start schedule that shows peaks and valleys in the resource requirements. Resource leveling done to take care of this issue may result in all of the following EXCEPT:

A. Increase in project durationB. Utilization of weekends, extended hours or multiple shiftsC. Productivity increases by using different technologies and/or methodologiesD. Reduction in project cost 

Page 9: Session 5 - GDAS PMP Study Group Presentation

4. In schedule development, mathematical analysis often produces a preliminary early-start schedule that shows peaks and valleys in the resource requirements. Resource leveling done to take care of this issue may result in all of the following EXCEPT:

A. Increase in project durationB. Utilization of weekends, extended hours or multiple shiftsC. Productivity increases by using different technologies and/or methodologiesD. Reduction in project cost 

Correct Choice:     D  Justification:     pmstudy.com comments: As different techniques like crashing, fast tracking, resource reallocation etc. are being considered for resource leveling, there is a real possibility of an increase in costs.

Reference: PMBOK Third Edition, Page Number: 147

Page 10: Session 5 - GDAS PMP Study Group Presentation

5. All the following statements regarding the creation of Time Estimates are correct EXCEPT:

A. Mathematical analysis like CPM, GERT and PERT indicate the dates on which the activity can be scheduled given resource limits and other constraints.

B. Duration compression techniques including fast tracking and crashing can help in decreasing the project schedule

C. WBS classification allows for useful activity ordering and sorting.D. The duration of the project is the sum of the duration of all the tasks in the

project. 

Page 11: Session 5 - GDAS PMP Study Group Presentation

5. All the following statements regarding the creation of Time Estimates are correct EXCEPT:

A. Mathematical analysis like CPM, GERT and PERT indicate the dates on which the activity can be scheduled given resource limits and other constraints.

B. Duration compression techniques including fast tracking and crashing can help in decreasing the project schedule

C. WBS classification allows for useful activity ordering and sorting.D. The duration of the project is the sum of the duration of all the tasks in the

project. 

Correct Choice:     D  Justification:     The duration of the project should be calculated after drawing a network diagram and determining the critical path. The duration of the project is the length of the critical path, and not the sum of the duration of all the tasks in the project.

Reference: pmstudy.com notes as mentioned above

Page 12: Session 5 - GDAS PMP Study Group Presentation

6. A management control point can be placed at selected management points (specific components at selected levels) of the WBS above the work package level. These control points can be:

A. Used for rolling wave planning  B. Decomposed further to help in the creation of Work Authorization System  C. Used for planning known work content that does not have detailed schedule

activities  D. Used as a basis for planning when associated work packages have not yet

been planned 

Page 13: Session 5 - GDAS PMP Study Group Presentation

6. A management control point can be placed at selected management points (specific components at selected levels) of the WBS above the work package level. These control points can be:

A. Used for rolling wave planning  B. Decomposed further to help in the creation of Work Authorization System  C. Used for planning known work content that does not have detailed schedule

activities  D. Used as a basis for planning when associated work packages have not yet

been planned 

Correct Choice:     D  Justification:     Control Account : .... A management control point can be placed at selected management points (specific components at selected levels) of the WBS above the work package level. These control points are used as a basis for planning when associated work packages have not yet been planned.

Reference: PMBOK Third Edition, Page Number: 129

Page 14: Session 5 - GDAS PMP Study Group Presentation

7. In your project, some requested changes were generated from the Activity Definition Process. These changes will be processed through:

A. Activity Change Control System B. Corrective Action C. Integrated Change Control System D. Activity Sequencing

Page 15: Session 5 - GDAS PMP Study Group Presentation

7. In your project, some requested changes were generated from the Activity Definition Process. These changes will be processed through:

A. Activity Change Control System B. Corrective Action C. Integrated Change Control System D. Activity Sequencing

Correct Choice:     C Justification:     Requested changes are processed for review and disposition through the Integrated Change Control process.

Reference: PMBOK Third Edition, Page Number: 130

Page 16: Session 5 - GDAS PMP Study Group Presentation

8. Please refer to this diagram:

What is the effect on the project if the duration of task J is increased to 9 weeks?  

A. No effect since task J is not on the critical path   B. Risk of the project will increase  C. The overall time-frame required to complete the project will increase by 1

week  D. None of the above

Page 17: Session 5 - GDAS PMP Study Group Presentation

Correct Choice:     B (Risk of the project will increase)Justification: If the duration of task J is increased by 1 week, Start -> G -> I -> J -> End = 23 weeks; this also lies on the critical path (23 days).

Since there are 3 critical paths now, a delay in any of the critical paths will delay the overall project - this increases the overall risk for the project.

Reference: pmstudy.com notes as mentioned above

Page 18: Session 5 - GDAS PMP Study Group Presentation

9. A project has a critical path of twenty-three weeks. What is the impact on the critical path if the management wants you to complete the project in twenty weeks?

A. Duration of the critical path increases by three weeks.   B. Duration of the critical path decreases by three weeks.   C. Duration of the critical path remains same.   D. Duration of the critical path cannot be determined. 

Page 19: Session 5 - GDAS PMP Study Group Presentation

9. A project has a critical path of twenty-three weeks. What is the impact on the critical path if the management wants you to complete the project in twenty weeks?

A. Duration of the critical path increases by three weeks.   B. Duration of the critical path decreases by three weeks.   C. Duration of the critical path remains same.   D. Duration of the critical path cannot be determined. 

Correct Choice:     C  Justification:     Duration of critical path = 23 weeks

If the management wants to complete the project in twenty weeks, then the project float will be : 20 - 23 = -3 weeks The project float compares the critical path with an externally imposed date and may be negative. (you may be forced to fast-track or perform crashing to ensure that the project is completed within the dates required by the management)

But, there will be no change to the critical path.

Reference: pmstudy.com notes as mentioned above

Page 20: Session 5 - GDAS PMP Study Group Presentation

10.You are doing a Monte Carlo Analysis in which you are defining a distribution of possible activity durations for each schedule activity and calculating a distribution of possible outcomes for the total project. Monte Carlo analysis is an example of:

A. Resource Leveling B. What-if Scenario Analysis C. Schedule Network Analysis D. Critical Path Method

Page 21: Session 5 - GDAS PMP Study Group Presentation

10.You are doing a Monte Carlo Analysis in which you are defining a distribution of possible activity durations for each schedule activity and calculating a distribution of possible outcomes for the total project. Monte Carlo analysis is an example of:

A. Resource Leveling B. What-if Scenario Analysis C. Schedule Network Analysis D. Critical Path Method

Correct Choice:     B Justification:     What-if Scenario Analysis: ... Simulation involves calculating multiple project durations with different set of activity assumptions. The most common technique is Monte Carlo Analysis

Reference: PMBOK Third Edition, Page Number: 146

Page 22: Session 5 - GDAS PMP Study Group Presentation

11.Your project SPI is 0.86 and the management has recommended that you should fast-track the project. You agree with the management but warn them that fast-tracking could: 

A. Facilitate duration compression B. Increase risk C. Ensure activities are done in parallel which would normally be done in

sequence D. Help shorten the project schedule without changing the project scope

Page 23: Session 5 - GDAS PMP Study Group Presentation

11.Your project SPI is 0.86 and the management has recommended that you should fast-track the project. You agree with the management but warn them that fast-tracking could: 

A. Facilitate duration compression B. Increase risk C. Ensure activities are done in parallel which would normally be done in

sequence D. Help shorten the project schedule without changing the project scope

Correct Choice:     B  Justification:     Fast Tracking can result in rework and increased risk

Reference: PMBOK Third Edition, Page Number: 146

pmstudy.com comments: Since increase in risk is a negative outcome of fast-tracking, you should warn your management about the increased risk. All the other options are benefits of fast-tracking.

Page 24: Session 5 - GDAS PMP Study Group Presentation

12.12. In schedule development, you create a distribution of probable results for each activity and use it to calculate the distribution of probable results for the total project. The technique that you are using is:

A. What-if Analysis B. Mathematical Analysis C. Monte Carlo Analysis D. Resource Leveling Heuristic

Page 25: Session 5 - GDAS PMP Study Group Presentation

12.In schedule development, you create a distribution of probable results for each activity and use it to calculate the distribution of probable results for the total project. The technique that you are using is:

A. What-if Analysis B. Mathematical Analysis C. Monte Carlo Analysis D. Resource Leveling Heuristic

Correct Choice:     C  Justification:     Simulation involves calculating multiple project durations with different sets of activity assumptions. The most common technique is called Monte Carlo Analysis, in which a distribution of probable results is defined for each activity and is used to calculate a distribution of probable results for the whole project.

Reference: PMBOK Third Edition, Page Number: 146

Page 26: Session 5 - GDAS PMP Study Group Presentation

13.You are going to make a presentation on the project to the senior management. In this context, the difference of a milestone chart as compared with a bar chart when making presentations is that unlike bar charts, milestones:

A. Show activity start and end dates B. Show dependencies among tasks C. Only identify the scheduled start or completion of major deliverables, and not

all the tasks D. Show supporting details

Page 27: Session 5 - GDAS PMP Study Group Presentation

13.You are going to make a presentation on the project to the senior management. In this context, the difference of a milestone chart as compared with a bar chart when making presentations is that unlike bar charts, milestones:

A. Show activity start and end dates B. Show dependencies among tasks C. Only identify the scheduled start or completion of major deliverables, and not

all the tasks D. Show supporting details

Correct Choice:     C  Justification:     Milestone charts (see Figure 6-10) are similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces.

Reference: PMBOK Third Edition, Page Number: 149

Page 28: Session 5 - GDAS PMP Study Group Presentation

14.Please refer to the figure below:

If these three tasks (i.e. Task A, Task B, Task C) are not part of the critical path of a project, what is the PERT estimate for the duration of the project?

A. 22.5 B. 10.33 C. 32 D. Cannot be determined

Page 29: Session 5 - GDAS PMP Study Group Presentation

Correct Choice:     D  Justification:     Since the tasks are not on the critical path of the project, we cannot determine the PERT estimate for the duration of the project. The PERT estimate can only be calculated for the critical path of the project.

Reference: pmstudy.com notes as mentioned above

Page 30: Session 5 - GDAS PMP Study Group Presentation

15.In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT: 

A. Activities that are not required as part of the project scope  B. Activities that are to be performed as part of the project  C. Activity identifiers and scope of work descriptions for each schedule

activity  D. Activities that are required as part of the project scope 

Page 31: Session 5 - GDAS PMP Study Group Presentation

15.In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT: 

A. Activities that are not required as part of the project scope  B. Activities that are to be performed as part of the project  C. Activity identifiers and scope of work descriptions for each schedule

activity  D. Activities that are required as part of the project scope 

Correct Choice:     A  Justification:     The activity list does not include any schedule activities that are required as part of the project scope.

Reference: PMBOK Third Edition, Page Number: 129

Page 32: Session 5 - GDAS PMP Study Group Presentation

16.Since you are in the preliminary stages of your project, you estimate that your project will last one year. However, an optimistic scenario is that it will get over within six months and a pessimistic scenario is eighteen months. This kind of estimate is also called:

A. Definitive   B. Capital Cost   C. Order of Magnitude   D. Feasibility 

Page 33: Session 5 - GDAS PMP Study Group Presentation

16.Since you are in the preliminary stages of your project, you estimate that your project will last one year. However, an optimistic scenario is that it will get over within six months and a pessimistic scenario is eighteen months. This kind of estimate is also called:

A. Definitive   B. Capital Cost   C. Order of Magnitude   D. Feasibility 

Correct Choice:     C  Justification:     The classes of estimates and their accuracy % is as follows:

* Definitive (+- 5%)* Capital Cost (+- 10% - 15%)* Appropriation ( +- 15% - 25%)* Feasibility (+_ 25% - 35 %)* Order of Magnitude ( > +- 35%)

Reference: Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page Number: 745

Page 34: Session 5 - GDAS PMP Study Group Presentation

17.If you are calculating an early start and early finish for each task, you are using: (choose the best answer)

A. PERT   B. CPM   C. GERT   D. PDM 

Page 35: Session 5 - GDAS PMP Study Group Presentation

17.If you are calculating an early start and early finish for each task, you are using: (choose the best answer)

A. PERT   B. CPM   C. GERT   D. PDM 

Correct Choice:     B  Justification:     The critical path method calculates the theoretical early start and finish dates, and the late start and finish dates, for all schedule activities without regard for any resource limitations, by performing a forward pass analysis and a backward pass analysis through the project schedule network paths.

Reference: PMBOK Third Edition, Page Number: 145

pmstudy.com comments: Critical Path Method(CPM) calculates a single, deterministic early and late start and finish date for each activity based on specified, sequential network logic and a single duration estimate.

Page 36: Session 5 - GDAS PMP Study Group Presentation

18.Float is the amount of time an activity can be delayed without delaying the project finish date. It can also be called: 

A. Slack  B. Total Float  C. Path Float  D. Critical Path

Page 37: Session 5 - GDAS PMP Study Group Presentation

18.Float is the amount of time an activity can be delayed without delaying the project finish date. It can also be called: 

A. Slack  B. Total Float  C. Path Float  D. Critical Path

Correct Choice:     A  Justification:     Float is also called slack

Reference: PMBOK Third Edition, Page Number: 361

Page 38: Session 5 - GDAS PMP Study Group Presentation

19.An activity has an optimistic estimate of ten days, pessimistic estimate of sixteen days, and most likely estimate of thirteen days. Assuming a normal distribution, what is the probability that the task will be completed within 10 - 16 days?

A. 99.99 % B. 99.73 % C. 95.46 % D. 68.26%

Page 39: Session 5 - GDAS PMP Study Group Presentation

19.An activity has an optimistic estimate of ten days, pessimistic estimate of sixteen days, and most likely estimate of thirteen days. Assuming a normal distribution, what is the probability that the task will be completed within 10 - 16 days?

A. 99.99 % B. 99.73 % C. 95.46 % D. 68.26%Correct Choice:     B Justification:     Please refer to Diagram about 6 Sigma below:

In a Normal Distribution, the PERT duration (also called mean)= (Pessimistic + 4* (Most Likely) + Optimistic)/6= (10 + 4 * 13 + 16)/6= 13

1 Standard Deviation (sigma)= (Pessimistic - Optimistic) / 6= (16 - 10) / 6= 1

So, if the task has to be completed within 10 days and 16 days, then the probability of completion within the timeframe is 99.73%(3 sigma) as shown in the exhibit.

Reference: pmstudy.com notes as mentioned above; pmstudy.com comments: To know more about 6 sigma calculations, please refer to Project Management - A Systems Approach to Planning, Scheduling and Controlling, Page 693 - Page 695

Page 40: Session 5 - GDAS PMP Study Group Presentation

20.Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources. The critical chain combines deterministic and probabilistic approaches. Initially, the project schedule network diagram is built using non-conservative estimates for activity durations within the schedule model, with required dependencies and defined constraints as inputs. The critical path is then calculated. After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. The resulting schedule often has an altered critical path.

The critical chain method adds non-work schedule activities to maintain focus on the planned activity durations, also referred to as:

A. Duration BuffersB. Resource LevelingC. Reverse Resource LevelingD. Crashing

Page 41: Session 5 - GDAS PMP Study Group Presentation

20.Critical chain is a schedule network analysis technique that modifies the project schedule to account for limited resources. The critical chain combines deterministic and probabilistic approaches. Initially, the project schedule network diagram is built using non-conservative estimates for activity durations within the schedule model, with required dependencies and defined constraints as inputs. The critical path is then calculated. After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. The resulting schedule often has an altered critical path.

The critical chain method adds non-work schedule activities to maintain focus on the planned activity durations, also referred to as:

A. Duration BuffersB. Resource LevelingC. Reverse Resource LevelingD. CrashingCorrect Choice:     A 

Justification:     The critical chain method adds duration buffers that are non-work schedule activities to maintain focus on the planned activity durations.

Reference: PMBOK Third Edition, Page Number: 147

Page 42: Session 5 - GDAS PMP Study Group Presentation

21.If the number of critical paths in the project increases, but the duration of the project remains the same, what should the project manager do?

A. Perform crashing to complete project on timeB. Fast track the projectC. Perform additional risk planningD. Decrease the scope of the project

Page 43: Session 5 - GDAS PMP Study Group Presentation

21.If the number of critical paths in the project increases, but the duration of the project remains the same, what should the project manager do?

A. Perform crashing to complete project on timeB. Fast track the projectC. Perform additional risk planningD. Decrease the scope of the project

Correct Choice:     C  Justification:      If the number of critical paths increases for the project, delay in any one of the critical paths has the potential for delaying the project. So, the risk of the project (in meeting the project schedule) increases. Hence additional risk planning has to be performed.

Reference: pmstudy.com notes as mentioned above

Page 44: Session 5 - GDAS PMP Study Group Presentation

22. You got news that because of bad weather, your shipment has got delayed by two weeks. What should be the FIRST step that you should take?   

A. Fast track the project to ensure that the project schedule is not delayed.  B. Review the performance reports to determine which planned dates have not

been met, and the impact on the critical path.  C. Try to get additional supplies from an alternate location as soon as possible.  D. Take corrective action to minimize the impact of the delay.

Page 45: Session 5 - GDAS PMP Study Group Presentation

22. You got news that because of bad weather, your shipment has got delayed by two weeks. What should be the FIRST step that you should take?   

A. Fast track the project to ensure that the project schedule is not delayed.  B. Review the performance reports to determine which planned dates have not

been met, and the impact on the critical path.  C. Try to get additional supplies from an alternate location as soon as possible.  D. Take corrective action to minimize the impact of the delay.

Correct Choice:     B  Justification:     Performance reports provide information on schedule performance, such as which planned dates have been met and which have not.

Reference: PMBOK Third Edition, Page Number: 153

pmstudy comments: Since performance reports are used to track project execution, they should be consulted first when there is a delay in the project to determine the potential impacts

Page 46: Session 5 - GDAS PMP Study Group Presentation

23. A planning package is a:

A. Unit of the project plan  B. Unit of the scope management plan C. WBS component below the control account  D. Template used for the project

Page 47: Session 5 - GDAS PMP Study Group Presentation

23. A planning package is a:

A. Unit of the project plan  B. Unit of the scope management plan C. WBS component below the control account  D. Template used for the project

Correct Choice:     C  Justification:     A planning package is a WBS component below the control account, but above the work package

Reference: PMBOK Third Edition, Page Number: 129

Page 48: Session 5 - GDAS PMP Study Group Presentation

24.Please refer to this diagram:

What is the slack of task G?A. 0 weeks B. 1 week C. -1 weekD. Cannot be determined

Page 49: Session 5 - GDAS PMP Study Group Presentation

Correct Choice:     A  Justification:     Justification: Please refer to this diagram:

START -> G -> I -> C -> D -> END: 23 lies on the critical path. So, slack of task G = 0

Reference: pmstudy.com notes as mentioned above

Page 50: Session 5 - GDAS PMP Study Group Presentation

25. In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of:

A. Activity Sequencing B. Activity Duration Estimating C. Schedule Development D. Activity Definition

Page 51: Session 5 - GDAS PMP Study Group Presentation

25. In your project, you realize the importance of determining the start and finish dates for project activities. If the project start or end dates are not realistic, then the project may not be completed on time. This is done as part of:

A. Activity Sequencing B. Activity Duration Estimating C. Schedule Development D. Activity Definition

Correct Choice:     C  Justification:     Project Schedule Development, an iterative process, determines the planned start and finish dates for project activities. Schedule development can require that duration estimates and resource estimates are reviewed and revised to create an approved project schedule

Reference: PMBOK Third Edition, Page Number: 143

Page 52: Session 5 - GDAS PMP Study Group Presentation

26. You have taken information on project scope and resources and then developed duration of activities for input to schedules. Since there was very limited information about the project, you used the actual duration of a previous, similar activity as the basis for estimating future activity. What should you do next?

A. Use diagramming techniques like GERT and Systems Dynamics B. Calculate theoretical early and late start and finish dates for all project

activities C. Use Standardized Networks to expedite preparation of Project Network

Diagrams D. Subdivide project work packages into smaller more manageable components

for better management control

Page 53: Session 5 - GDAS PMP Study Group Presentation

26. You have taken information on project scope and resources and then developed duration of activities for input to schedules. Since there was very limited information about the project, you used the actual duration of a previous, similar activity as the basis for estimating future activity. What should you do next?

A. Use diagramming techniques like GERT and Systems Dynamics B. Calculate theoretical early and late start and finish dates for all project

activities C. Use Standardized Networks to expedite preparation of Project Network

Diagrams D. Subdivide project work packages into smaller more manageable components

for better management controlCorrect Choice:     B  Justification:     Analogous Duration Estimating means using the actual duration of a previous similar schedule activity as the basis for estimating the duration of a future schedule activity - this is done as part of Activity Duration Estimating.

Reference: PMBOK Third Edition, Page Number: 141

pmstudy.com comments: Activity Duration Estimating will be followed by Schedule Development - one tool and technique used is Schedule Network Analysis (which involves calculating theoretical early and late start and finish dates : Refer PMBOK Page 145) - so, correct choice is # 2

Page 54: Session 5 - GDAS PMP Study Group Presentation

27.Activity definition involves identifying and documenting the specific activities that must be performed to produce the deliverables and sub-deliverables identified in the work breakdown structure (WBS). All the following statements about the activity list produced as an output from activity definition are true EXCEPT: 

A. The activity list must include all activities that will be performed on the project  

B. The activity list may include some activities that are not required as part of the project  

C. The activity list should include descriptions of each activity to ensure that the project team members will understand how the work is to be done  

D. The activity list is used in the schedule model and is a component of the project management plan

Page 55: Session 5 - GDAS PMP Study Group Presentation

27.Activity definition involves identifying and documenting the specific activities that must be performed to produce the deliverables and sub-deliverables identified in the work breakdown structure (WBS). All the following statements about the activity list produced as an output from activity definition are true EXCEPT: 

A. The activity list must include all activities that will be performed on the project  

B. The activity list may include some activities that are not required as part of the project  

C. The activity list should include descriptions of each activity to ensure that the project team members will understand how the work is to be done  

D. The activity list is used in the schedule model and is a component of the project management plan

Correct Choice:     B  Justification:     The activity list does not include any schedule activities that are required as part of the project scope.

Reference: PMBOK Third Edition, Page Number: 129

pmstudy.com comments: Option 2 refers to "Gold Plating" or adding features not mentioned in the project scope - this practice is not recommended by PMI

Page 56: Session 5 - GDAS PMP Study Group Presentation

Wrap Up

Conference Number: 547-941-6414 or 866-547-8978Passcode: Leader – 844306338, Participant – 370670831