Top Banner
Project Risk Management
30

Session 18 -2 PMP 4th edition

May 08, 2015

Download

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Session 18 -2  PMP 4th edition

Project Risk Management

Page 2: Session 18 -2  PMP 4th edition

Project Risk Management

Knowledge Area

Process

Initiating Planning Executing Monitoring & Contol Closing

Risk  Plan Risk ManagementIdentify RiskPerform Qualitative Risk AnalysisPerform Quantitative Risk AnalysisPlan Risk Response

Monitor and Control Risks

Enter phase/Start project

Exit phase/End project

InitiatingProcesses

ClosingProcesses

PlanningProcesses

ExecutingProcesses

Monitoring &Controlling Processes

Page 3: Session 18 -2  PMP 4th edition

Perform Quantitative Risk Analysis

• The process of numerically analyzing the effect of identified risks on overall project objectives.

Inputs

1. Risk register2. Risk management plan3. Cost management plan4. Project scope statement5. Organizational process assets

Tools & Techniques

1. Data gathering and representation techniques

2. Quantitative risk analysis and modeling techniques

3. Expert judgment

Outputs

1. Risk register updates

If not necessary, this process may be skipped.

Page 4: Session 18 -2  PMP 4th edition

Quantitative Risk Analysis

• Is a numerical evaluation (more objective)• This process may be skipped.

• Purpose of this process– Determine which risk events warrant a response.– Determine overall project risk (risk exposure).– Determine the quantified probability of meeting project objectives.

– Determine cost and schedule reserves.– Identify risks requiring the most attention.– Create realistic and achievable cost, schedule, or scope targets.

Page 5: Session 18 -2  PMP 4th edition

•Data Gathering and Representation Techniques• • Interviewing. quantify the probability and

impact of risks on project objectives. For instance, information would be gathered on the optimistic (low), pessimistic (high), and most likely scenarios for some commonly used distributions.

Page 6: Session 18 -2  PMP 4th edition

Probability distributions. Continuous probability distributions, used in modeling and simulation represent the uncertainty in values such as durations of schedule activities and costs of project components.

Page 7: Session 18 -2  PMP 4th edition

Quantitative Risk Analysis and Modeling TechniquesCommonly used techniques include both event-oriented and project-oriented analysis

Sensitivity Analysis

• To determine which risks have the most potential impact to the project• Changing one or more elements/variables and set other elements to its baseline then see the impact.

• One typical display of sensitivity analysis is the tornado diagram

Page 8: Session 18 -2  PMP 4th edition

Decision Tree and EMV

• EMV used with Decision Tree to choose between many alternative which take into account the future  events

• Example:

(Impact) ty)(ProbabiliEVM

Expected monetary value

P=0.2

P=0.8

P=0.2

P=0.1P=0.7

outcome

300.000$

- 40.000$

- 50.000$

- 20.000$

60.000$

EMV

300.000x0.2 =60.000

-40.000x0.8 =-32.000

-50.000x0.2 =-10.000

-20.000x0.1=-2.000

60.000x0.7 =42.000

=28.000$

=30.000$

Page 9: Session 18 -2  PMP 4th edition

• Modeling and simulation.(Monte Carlo technique)

• A project simulation uses a model that translates the specified detailed uncertainties of the project into their potential impact on project objectives.

• Iterative simulations are typically performed using the Monte Carlo technique.

Page 10: Session 18 -2  PMP 4th edition

Risk Register Updates

• Update/add additional information to previous output i.e. Risk Register, which include:

– Prioritize list of quantified risks– Amount of contingency time and cost reserve needed– Possible realistic and achievable completion dates, project cost, with confidence level

– The quantified probability of meeting project objectives– Trends

Page 11: Session 18 -2  PMP 4th edition

Plan Risk Response

• The process of developing option and action to enhance opportunities and to reduce threats to project objectives.

Inputs

1. Risk register2. Risk management plan3. Cost management plan4. Project scope statement5. Organizational process assets

Tools & Techniques

1. Strategies for negative risks or threats

2. Strategies for positive risks or opportunities

3. Contingent response strategies

4. Expert judgment

Outputs

1. Risk register updates2. Risk-related contract decisions

3. Project management plan updates

4. Project document updates

Page 12: Session 18 -2  PMP 4th edition

Plan Risk Responses

• Do something to eliminate threats  before they happens• Do something to make sure the opportunities happens• Decrease the probability and/or impact of threats• Increase the probability and/or impact of opportunities 

• For the remaining (residual) threats that cannot be eliminated:– Do something if the risk happens (contingency plan).– Do something if contingency plan not effective (fallback plan)– The risks result in applying risk response strategy is called

(secondary risk)– The risk trigger is events that trigger the contingency response– Workaround is unplanned risks

Page 13: Session 18 -2  PMP 4th edition

Strategies for Threats

1- Avoid– Eliminate the threat entirely– Example: remove  dangerous test or person or material from project

Page 14: Session 18 -2  PMP 4th edition

Strategies for Threats

• 2-Transfer (Deflect, Allocate)

– Shift some or all the negative impact

 of a threat to a third party

Example : insurance or outsource the 

work

Page 15: Session 18 -2  PMP 4th edition

Strategies for Threats

• 3-Mitigate– Implies a reduction in the probability    and/or impact of an adverse risk    event to be within acceptable   threshold limits

• Example : provide training for team       members, Wear a helmet head

Page 16: Session 18 -2  PMP 4th edition

Strategies for Threats

• 4- Accept– Deal with the risks– Project management plan is      not changed

• Example : Increasing material prices (contingency)

Page 17: Session 18 -2  PMP 4th edition

Strategies for Opportunities

• Exploit– Seek to ensure the opportunities definitely happen

– Example: allocate experience manpower  in critical path to complete project early

Page 18: Session 18 -2  PMP 4th edition

Strategies for Opportunities

• Share– Allocate some or all of the ownership of the opportunity to a third party who is best able to capture the opportunity for the project benefit.

– Example: buy machine

Page 19: Session 18 -2  PMP 4th edition

Strategies for Opportunities

• Enhance– Increase the probability and/or the positive impacts of an opportunity.

– Example: negotiation for the equipment earlier to secure lower price

Page 20: Session 18 -2  PMP 4th edition

Strategies for Opportunities

• Accept– Not actively pursuing an opportunity

– Example: decrease material price

Page 21: Session 18 -2  PMP 4th edition

Monitor & Control Risk

• The process of ..– implementing risk response plans, – tracking identified risks, – monitoring residual risks, – identifying new risks, and – evaluating risk process effectiveness throughout the project.

Inputs

1. Risk register2. Project management plan

3. Work performance information

4. Performance report

Tools & Techniques

1. Risk reassessment2. Risk audits3. Variance and trend analysis

4. Technical performance measurement

5. Reserve analysis6. Status meetings

Outputs

1. Risk register updates2. Organizational process assets updates

3. Change requests4. Project management plan updates

5. Project document updates

Page 22: Session 18 -2  PMP 4th edition

• Risk Reassessment• Monitor and Control Risks often results in

identification of new risks, reassessment of current risks , and the closing of risks that are outdated.

• Project risk reassessments should be regularly scheduled.

.

Page 23: Session 18 -2  PMP 4th edition

• Risk Audits• Risk audits examine and document the

effectiveness of risk responses in dealing with identified risks and their root causes, as well as the effectiveness of the risk management process

Page 24: Session 18 -2  PMP 4th edition

QUESTIONS?

Page 25: Session 18 -2  PMP 4th edition

1- Heba is a Project Manager for software migration at a bank. A major risk that has been identified is attrition of resources. As a strategy to respond to this risk, Heba, with support from Senior Management, provides good increments to his team members. What type of risk response is heba following?

A-Accept

B-Avoid

C-Transfer

D-Mitigate

Page 26: Session 18 -2  PMP 4th edition

2-Which of these is not a valid response to positive risks?

A-Exploit

B-Mitigate

C-Enhance

D-Share

Page 27: Session 18 -2  PMP 4th edition

3-After conducting a SWOT Analysis, you have determined that a business deal is worth pursuing. You are required to use Agile development practices. In your company, there is no expertise in Agile development. Hence, you partner with another organization that specializes in Agile development. This is an example of:

a) Sharing a Positive Risk

b) Mitigating a Negative Risk

c) Exploiting a Positive Risk

d) Accepting a Negative risk

Page 28: Session 18 -2  PMP 4th edition

4-During which stage of Risk planning are modeling

techniques used to determine overall effects of

risks on project objectives for high probability, high

impact risks?

A-Risk identification

B-Risk response planning

C-Qualitative risk analysis

D-Quantitative risk analysis

Page 29: Session 18 -2  PMP 4th edition

• 5-if the team cannot identify a suitable

response to an identified risk . Which risk

response would they apply?

A- avoidance

B-acceptance

3- mitigation

4-transference

Page 30: Session 18 -2  PMP 4th edition

Thank you