Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction
Second Avenue Subway
Community Board 8
Second Avenue Subway Task Force Update
November 1, 2016
Tom Peyton
Second Avenue Subway
Program Director - Construction
Phase 1 Overview
• The Re-routed Q
train will travel
from the new 96th
Street Station
south through
Manhattan and
into Brooklyn,
terminating at
Coney Island
Current Progress
• The Second Avenue Subway Project is on budget
and scheduled for revenue service in December
2016
• Overall Construction is 98% complete as of October 1, 2016
• NYC Transit revenue service training is underway
96th St. Station Finishes, Systems, Ancillary Buildings and Entrances
86th St. Station Finishes, Systems, Ancillary Buildings and Entrances
72nd St. Station Finishes, Systems, Ancillary Buildings and Entrances
63rd St. Station Upgrade
All Stations Track, Power, Signals & Communications Systems
5 Active Contracts
Testing
Track Geometry Car – September 2016
Testing
Track Geometry Car – September 2016
Testing
Pre Revenue Service Train – October 2016
Station Areas
63rd Street Station Rehabilitation
Station Upgrade Contract
Contract Value incl. AWOs: $190.8 M
Award Date: January 13, 2011
Forecast Completion: December 2016
Construction Progress
Architectural finishes are near completion and station
systems testing is underway
Sidewalk reconstruction is complete
Work zone on the NE corner of 64th Street and Third Avenue has been removed
Plaza on the NW corner of 63rd Street and Third Avenue
has been opened to the public
Current Progress
The Plaza at 63rd Street and Third Avenue is open to the public.
Current Progress
Ancillary 2 (NW corner of 63rd Street & Third Avenue)
Current Progress
Entrance 1 (SE corner of 63rd Street & Third Avenue)
Project Completion Look Ahead
STATION
Completion of ceilings and wall tiles, lighting, and column
enclosures
Testing of mechanical, electrical, and plumbing systems in
new station area
ENTRANCE 1
Installation of finishes and tiles
Testing of elevators and escalators
STREETSCAPE
Trees in the station area will be planted this fall season
72nd Street Station
Finishes, MEP Systems, Ancillary Buildings and Entrances Contract
Contract Value incl. AWOs: $286.1 M
Award Date: February 14, 2013
Forecast Completion: December 2016
Construction Progress
The station and track has been energized
Ancillary 1 (NW corner of 69th Street and Second Avenue) and
Ancillary 2 (NW corner of 72nd Street and Second Avenue)
façade work is nearing completion
Entrance 1 and Entrance 2 escalator installation nearing
completion
Entrance 3 (SE corner of 72nd Street and Second Avenue)
façade work and elevator installation nearing completion
Tunnel Smoke Systems Management (TSSM), HVAC, Fire
Protection System (FPS), elevator and escalator testing in
progress
Current Progress
Ancillary 1 (NW corner of 69th Street & Second Avenue)
Current Progress
Ancillary 2 (NW corner of 72nd Street & Second Avenue)
Current Progress
Entrance 3 (SE corner of 72nd Street & Second Avenue)
Current Progress
Sidewalk Restoration (east side of 70th-71st Street & Second Avenue)
Current Progress
Sidewalk Restoration (east side of Second Avenue between 72nd and 73rd Streets)
Current Progress
Sidewalk Restoration (NE corner of 73rd Street and Second Avenue)
Project Completion Look Ahead
MAIN STATION CAVERN
Installation of:
Floor tiles, ceiling panels, conduits, mechanical, electrical
and plumbing systems at the mezzanine level
Tunnel Smoke Systems Management (TSSM), HVAC, Fire
Protection System (FPS), elevator and escalator testing in
progress
Installation of fare array gates and turnstiles
ENTRANCE 1
Architectural finishes and lighting work to continue at escalator
incline portion of Entrance 1
Installation of street and mezzanine-level escalators
Installation of wall tiles, duct work, conduit work and finishes
Project Completion Look Ahead
ANCILLARY 1, ANCILLARY 2, ENTRANCE 3
Construction of façades
Electrical and mechanical equipment installation and
testing for revenue service
Installation of escalators and elevators at Ancillary 2
86th Street Station
Finishes, Entrances, Ancillaries, and MEP Systems Contract
Contract Value: $223,000,000
Award Date: June 12, 2013
Forecast Completion: December 2016
86th Street Station Progress
Façade installation has begun on Ancillary structures
Test trains are running in the station
The structural frame for the elevator at E. 86th Street has
been installed
East side sidewalk restoration is nearing completion
Installation of artwork by MTA Arts & Design is underway
Fan testing at Ancillary structures is underway
Construction Progress
27
Installation of façade at Ancillary 1 (NE corner of 83rd Street)
Construction Progress
Sidewalk restoration at 83rd Street (SW side)
Construction Progress
Sidewalk restoration on the east side of Second Avenue (82nd – 83rd Streets)
Construction Progress
Sidewalk restoration on the east side of Second Avenue (87th – 88th Streets)
Project Completion Look Ahead
82nd Street to 88th Street
Completion of east side sidewalk restoration between 82nd
and 88th Streets
Installation of Ancillary 1 and 2 façade tile
West side sidewalk restoration will begin on Second Avenue
between 84th and 88th Streets
83rd Street between 2nd and 3rd Avenues
Above ground work will continue including installation of building
finishes on Ancillary 1
Sidewalk reconstruction work
86th Street between 1st and 2nd Avenues
Sidewalk and elevator finishing work
86th Street between 2nd and 3rd Avenues
Above ground work including installation of building finishes on Ancillary 2
Project Completion Look Ahead
Underground Construction
Installation of architectural finishes; wall panels, tiles, floor
tile, acoustical panels and service carriers on the platform
and mezzanine levels
Installation of station signage and customer information
screens (CIS)
Installation of art work
Project Completion Look Ahead
96th Street Station
Finishes, MEP Systems, Ancillary Buildings and Entrances Contract
Contract Value: $324,600,000
Award Date: June 22, 2012
Forecast Completion: December 2016
96th Street Station Progress
• Sidewalks restored along east
and west side of Second
Avenue, side streets nearly
complete
• Tree planting scheduled for
November
• Roadway restoration on side
streets in process
• Final testing of station safety,
HVAC, elevators, and
escalators
• Station finishes, wayfinding
signs, art and floor tile nearly
completeInstallation of street level elevator cab at Entrance 3 during testing
96th Street Station Progress
Façade of Ancillary 2 west side of Second Avenue
and 97th Street
96th Street Station Progress
Façade of Ancillary 1 east side of Second Avenue
and 93rd Street
96th Street Station Progress
Bike lane striping on the east side of Second Avenue
104th – 105th Streets 93rd – 94th Streets
96th Street Station Progress
Bus lane striping west side of Second Avenue
between 98th – 99th Streets
96th Street Station Progress
Sidewalk restoration south side of 97th Street
between First & Second Avenues
96th Street Station Progress
Sidewalk restoration matching tint and pattern west side of
Second Avenue and 92nd Street
96th Street Station Progress
Installation of entrance canopy east side of Second Avenue at 94th Street
96th Street Station Progress
Installation of entrance glass west side of Second Avenue
between 95th – 96th Streets
Project Completion Look Ahead
• Completion of street level restoration
• Tree planting in the fall planting season
• Completion of station finishes
• Advanced testing of all systems before handover to NYCT
• Completion of Entrance 2 & Entrance 3 glass canopy and
plaza pavers
45
Track, Power, Signals and Communications Systems Contract
Contract Value incl. AWOs: $292.8 M
Award Date: January 18, 2012
Forecast Completion: December 2016
Systems Installation
• Signal system has been installed
• Con Edison feeders at 86th and 96th
Street stations are energized
• Geometry trains were run and
interferences with systems were
resolved
• Signal train and stress train ran in
October as scheduled
• In service testing is complete
• Inspection is ongoing
Systems Installation
Installation of wayside traction
power cables to 3rd Rail
Questions