Second Avenue Subway Newsletter Announcements Issue XXIII – March 2014 72nd Street Station Area Subscribe! Want to stay most informed? Send your email address to outreach@2AveSubway. com to sign up for our e-news distribution list. Be sure to specify “72nd St Station Area.” Construction of Ancillary 1 and Entrance 1 (northwest and northeast corners of 69th Street and Second Avenue respectively) will commence this month. The number of traffic lanes on Second Avenue must be reduced from four to three between 69th and 70th Streets to support these construction activities. Pedestrian walkways will be re-routed as necessary to support construction activities. Restaurant and stores will continue to have access to their entrances. This roadway traffic configuration will remain in effect until these structures have been built. Please see the new work zone configuration in the diagram below. During this time there will be “NO STOPPING ANYTIME” along the western curb lane of Second Avenue from 69th Street to 71st Street. New signage will be posted to ensure motorists are aware of the new restriction and to maintain the curb lane. Drivers in violation of the new regulation will be ticketed. Ancillary 1 and Entrance 1 Work Zone Changes (Commencing in February 2014) SAS Project News SAVE THE DATE: The next Second Avenue Subway Public Workshop will be at Temple Israel, 112 E. 75th Street between Park and Lexington Avenues on Wednesday, March 26 that 6:00 p.m. CIC The Second Avenue Subway Community Information Center (CIC), at 1628 Second Avenue, between 84th and 85th Streets, is open during the following hours: Monday: 10 a.m. – 6 p.m. Tuesday: Noon – 8 p.m. Wednesday: 10 a.m. – 6 p.m. Thursday: Noon – 8 p.m. Friday: 10 a.m. – 6 p.m. Saturday: 11 a.m. – 3 p.m. (second Saturday of each month) Coming in March at the CIC Beneath the Street: Geology of the Second Avenue Subway Thursday, March 13th at 6 p.m. Geologist Julie Freitas will answer questions and discuss the origins and characteristics of the rocks and soil under Second Avenue. She’ll also explain how geology influenced the construction methods used to build the subway. RSVP: (646) 449-8700 or https://transittalks5.eventbrite.com Boring Matters: How a Tunnel Boring Machine Works Thursday, March 27th at 6 p.m. Excavation expert Alaeden Jlelaty will explain how the tunnel boring machine (TBM) carved tunnels under Second Avenue. If you’ve ever wondered how a TBM navigates underground or how it grinds up rock and removes muck, Mr. Jlelaty will be at the CIC to explain all that and more! RSVP: (646) 449-8700 or https://transittalks7.eventbrite.com
2

Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/72nd-Mar_2014.pdfSecond Avenue Subway Newsletter Announcements Issue XXIII – March 2014 72nd Street Station Area Subscribe!

Jun 10, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/72nd-Mar_2014.pdfSecond Avenue Subway Newsletter Announcements Issue XXIII – March 2014 72nd Street Station Area Subscribe!

Second Avenue SubwayNewsletter

Announcements

Issue XXIII – March 2014

72nd Street Station Area

Subscribe!Want to stay most informed?Send your email address [email protected] to sign up for our e-newsdistribution list. Be sure tospecify “72nd St Station Area.”

Construction of Ancillary 1 and Entrance 1 (northwest and northeast corners of 69th Street and Second Avenue respectively) will commence this month. The number of traffic lanes on Second Avenue must be reduced from four to three between 69th and 70th Streets to support these construction activities. Pedestrian walkways will be re-routed as necessary to support construction activities. Restaurant and stores will continue to have access to their entrances. This roadway traffic configuration will remain in effect until these structures have been built. Please see the new work zone configuration in the diagram below.

During this time there will be “NO STOPPING ANYTIME” along the western curb lane of Second Avenue from 69th Street to 71st Street. New signage will be posted to ensure motorists are aware of the new restriction and to maintain the curb lane. Drivers in violation of the new regulation will be ticketed.

Ancillary 1 and Entrance 1 Work Zone Changes (Commencing in February 2014)

SAS Project NewsSAVE THE DATE: The next Second Avenue Subway Public Workshop will be at Temple Israel, 112 E. 75th Street between Park and Lexington Avenues on Wednesday, March 26 that 6:00 p.m.

CICThe Second Avenue Subway Community Information Center (CIC), at 1628 Second Avenue, between 84th and 85th Streets, is open during the following hours:Monday: 10 a.m. – 6 p.m.Tuesday: Noon – 8 p.m.Wednesday: 10 a.m. – 6 p.m.Thursday: Noon – 8 p.m.Friday: 10 a.m. – 6 p.m. Saturday: 11 a.m. – 3 p.m. (second Saturday of each month)

Coming in March at the CIC Beneath the Street: Geology of the Second Avenue SubwayThursday, March 13th at 6 p.m.Geologist Julie Freitas will answer questions and discuss the origins and characteristics of the rocks and soil under Second Avenue. She’ll also explain how geology influenced the construction methods used to build the subway.RSVP: (646) 449-8700 or https://transittalks5.eventbrite.com Boring Matters: How a Tunnel Boring Machine Works Thursday, March 27th at 6 p.m.Excavation expert Alaeden Jlelaty will explain how the tunnel boring machine (TBM) carved tunnels under Second Avenue. If you’ve ever wondered how a TBM navigates underground or how it grinds up rock and removes muck, Mr. Jlelaty will be at the CIC to explain all that and more! RSVP: (646) 449-8700 or https://transittalks7.eventbrite.com

Page 2: Second Avenue Subway - MTAweb.mta.info/capital/sas_pdf/72nd-Mar_2014.pdfSecond Avenue Subway Newsletter Announcements Issue XXIII – March 2014 72nd Street Station Area Subscribe!

72nd StreetStation Structure

Contractor:SSK Constructors, JV

Budget:$469.5 Million

Award Date:October 2010

Contract Forecast Completion:Winter 2014

For community related concerns,please contact Lisa Blugh-Willis [email protected]

72nd StreetStation Finishes

Contractor:Judlau Contracting Inc.

Budget:$271.3 Million

Notice to Proceed Date: September 2013

Contract Forecast Completion:

Winter 2015

Project Overview

72nd Street Station Area – March 2014Second Avenue Subway Newsletter

Follow the SAS project on the MTA website at http://mta.info/sas

72nd Street Station - Entrance 1 at 69th Street and Second Avenue.

The future 72nd Street Station will have three new entrances including 11 escalators, and five street-level ADA accessible elevators at the southeast corner of 72nd Street and Second Avenue. Current work in this area includes construction of the station cavern and tunnels from the 72nd Street Station to the existing Lexington Av/63rd Street Station. This contract includes the demolition of buildings for ancillary locations at 72nd Street and 69th Street, and requires utility relocation for the installation of support of excavation walls. The estimated completion of this contract is Winter 2014.

A follow-on contract will then complete the mezzanine, platform, ancillary structures, station entrances, and the mechanical, electrical, and plumbing systems for the station. The estimated completion of the follow on contract is Winter 2015. Future plans regarding surface-level staging areas needed for this follow-on work will be conveyed to stakeholders and the community through ongoing project outreach and at regular Construction Advisory Committee meetings.

MONDAY-FRIDAY: 7:00 a.m. to 10:00 p.m.

SATURDAY: 10:00 a.m. to 7:00 p.m. (as needed)

Work is permitted underground 24/7.

For concerns regarding Second Avenue Subway construction activities after business hours or on weekends please use the SAS 24/7 hotline # (212) 792-9716

SURFACE UndergroundLEVEL

Construction Update

Work Hours

• Concrete truck staging will continue between E. 74th and E. 76th Streets.

• Continue concrete pours at Ancillary 2 (northwest corner of E. 72nd Street and Second Avenue) and Entrance 3 (southeast corner of E. 72nd Street and Second Avenue).

• Continue utility relocation work for Entrance 1 construction within garage of 301 E. 69th Street and basement of 1322 Second Avenue.

• Station finishes contractor, Judlau, commences occupation and utilization of all work zones along alignment (E. 66th to E. 74th Streets).

• Reconfiguration of Ancillary 1 and Entrance 1 work zones to accommodate delivery, staging and storage of materials and equipment.

• As work zones along Second Avenue are reconfigured to allow for the Station Finishes contractor’s work activities and access, there may be additional changes to these work zones.

• Installation of waterproofing system, concrete flooring, and walls within Ancillary 1, Ancillary 2 and Entrance 3.

• Continue material deliveries and installation of temporary utilities within Ancillary 1.

• Continue installation of formwork for main cavern mezzanine slab and placement of reinforcing steel and concrete.

• Continue deliveries through Ancillary 2 and Entrance 3.