Top Banner
Federal Democratic Republic of Ethiopia PROGRAM IMPLEMENTATION PLAN for PUBLIC SECTOR CAPACITY BUILDING PROGRAM (PSCAP) Volume I Draft Dated: November 15, 2004
89

PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

May 21, 2018

Download

Documents

buihuong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Federal Democratic Republic of Ethiopia

PROGRAM IMPLEMENTATION PLAN

for

PUBLIC SECTOR CAPACITY BUILDING PROGRAM

(PSCAP)

Volume I

Draft Dated: November 15, 2004

Page 2: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

About the Program Implementation Plan (PIP)……

This Program Implementation Plan (PIP) constitutes the overall operational guideline for the management, execution, and review of Ethiopia’s Sector-Wide Approach to its Public Sector Capacity Building Program (PSCAP). As such, the PIP also provides the framework within which (i) subsidiary guidelines, procedures manuals, and actions plans should be elaborated, and (ii) existing procedures (for example, those governing existing public sector capacity building projects) may be modified. Key features of program design including the institutional arrangements, provisions for fiduciary and fiscal management, as well as the monitoring and evaluation framework have been the subject of numerous reviews by the Government as well as independent experts, as well as joint and independent appraisals by members of Ethiopia’s aid consortia. They are therefore in accordance with international norms and aligned with Ethiopian norms. The PIP ultimately is a “live” document that may be further reviewed and refined, as needed, in consultation with relevant stakeholders and in accordance with the legal provisions agreed between the Government and its external financiers. The Program Implementation Plan (PIP) for PSCAP consists of eight sections described below. Section 1 provides an overview of the Public Sector Capacity Building Program (PSCAP) including a brief description of the strategic context within which Ethiopia’s “state transformation” and capacity building efforts were developed, and the rationale for the development of a SWAp for public sector capacity building. The section also explains the Program’s objectives, a summary of salient design features, expected outcomes, and key performance indicators. Section 2 describes the key components of the Program as well as their constituent subprograms. The “positive list” of capacity building activities financed under the Program is described, as well as those activities that constitute the “minimum mandatory” that all regions must complete is also delineated. Section 3 details the institutional arrangements underpinning PSCAP including the roles and responsibilities at the federal, regional, and local levels, as well as inter-ministerial and intergovernmental coordination mechanisms. Joint Government-Donor coordination and review mechanisms are defined. Section 4 explains the fiscal design features of PSCAP, and specifically, how it is aligned with Ethiopia’s resource allocation and management system including its designation as a specific purpose transfer, the rules of allocation and access, and procedures for planning, budgeting, execution, and reallocation. Section 5 provides an overview of financial management under PSCAP including funds flows, pooling arrangements, as well as accounting, financial reporting, auditing, and related assessments. A more detailed financial reporting guideline is attached in Volume II of the PIP. Section 6 lays out the PSCAP procurement management system including the roles and responsibilities at the federal and regional levels, as well as the various policies and regulations governing procurement. Section 7 contains the monitoring and evaluation framework that is required for the Program to track and achieve its expected outcomes. Roles and responsibilities, agreed program-level indicators for outcomes and outputs, as well as M&E “building blocks” (for example, activity-based monitoring and quality assessments) and reporting requirements are described.

Section 8 focuses on the Information, Education, and Communication (IEC) strategy and activities underpinning this complex, nation-wide program. Guidance on participation, sensitization, feedback, and disclosure are provided.

Page 3: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Table of Contents

Abbreviations and Acronyms................................................................................................. 1

Section 1. Program Overview ............................................................................................... 1

SWAp/Program Development Objectives .................................................................................... 5

Key Performance Indicators ........................................................................................................ 5

Section 2. Program Description............................................................................................ 6

2.1 Federal and Regional Components......................................................................................... 6

2.2 PSCAP Subprograms: “Building Blocks” for Federal and Regional Components.................. 7

2.3 PSCAP Subprograms: “Building Blocks” for Federal and Regional Components................ 11

Section 3. Institutional Arrangements............................................................................. 12

3.1 Federal Level Institutional Arrangements............................................................................ 12 3.1.2 Ministry of Finance and Economic Development (MOFED) ...............................................14 3.1.3 Federal Subprogram Offices and Executing Agencies .........................................................14 3.1.4 Other Eligible Beneficiary Institutions at the Federal Level.................................................16

3.2 Regional Level Institutional Arrangements .......................................................................... 16 3.2.1 Bureaus of Capacity Building............................................................................................16 3.2.2 Bureaus of Finance and Economic Development (BOFED).................................................17 3.2.3 Other eligible beneficiary institutions at regional and local levels ........................................18

3.3 Joint Government-Donor Coordination and Review Mechanism......................................... 18

Section 4. Resource Allocation and Management ........................................................ 20

4.1 Specific-Purpose Federal Program....................................................................................... 20

4.2 Budget Classification of PSCAP Expenditures ..................................................................... 20 4.2.1 Coding and Classification of the Federal Component ..........................................................20 4.2.2 Coding and Classification of the Regional Component........................................................21

4.3 Rules of Access (Eligibility Criteria)..................................................................................... 21

4.4 Incorporation of Inputs from Various Nation-Wide Reviews ............................................... 21

4.5 Fiscal Framework: Projecting and Dividing PSCAP Resources Over the Medium Term..... 22 4.5.1 Vertical Division of PSCAP Resources Into Five-Year Drawing Rights ...............................22 4.5.2 Horizontal Split of the Regional PSCAP Component Into Five-Year Drawing Rights ...........22

4.6 Rolling Medium-Term Planning for PSCAP........................................................................ 22 4.6.1 Planning PSCAP Activities As Part of Ethiopia’s Public Investment Program......................22 4.6.2 Annualizing Multiyear Drawing Rights to Arrive at the Annual Fiscal Plan..........................23 4.6.3 Arriving at the Annual Fiscal Plan.....................................................................................23

4.7 Budgeting Process ................................................................................................................ 23 4.7.1 Submitting Annual Budgets with Implementation Plans ......................................................23 4.7.2 Appraising Annual Implementation Plans ..........................................................................24 4.7.3 Submitting the Overall PSCAP Annual Budget and Implementation Plan to Cabinet ............24

Page 4: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- ii -

4.8 Execution............................................................................................................................. 25

4.9 Reallocation.......................................................................................................................... 25 4.9.1 Reallocation Across Year: Applied Five-Year Drawing Rights ............................................25 4.9.2 Reallocation In-Year: Applied to Annualized Drawing Rights .............................................26 4.10 The Supplemental Budget and High Performers ..................................................................27

Section 5. Financial Management..................................................................................... 30

5.1 Roles and Responsibilities for Financial Management.......................................................... 30

5.2 Accounting Policies and Procedures..................................................................................... 31

5.3 Funding Mechanisms ........................................................................................................... 31 5.3.1 Non-Pooled Resources......................................................................................................31 5.3.2 Pooled Resources.............................................................................................................31 5.3.3 Initial Advance and Replenishment of Forex Accounts from Donors to MoFED...................32 5.3.4 Funds Flow from MOFED to Beneficiaries ........................................................................32

5.4 Financial Performance Assessment. ..................................................................................... 32

5.5 Auditing ............................................................................................................................... 33

5.6 Internal Controls.................................................................................................................. 33

Section 6. Procurement Management............................................................................... 35

6.1 Procurement Management & Operations ............................................................................. 35 6.1.1 Federal Level Procurement Management Responsibilities ...................................................35 6.1.2 Procurement Management Responsibilities at the Regional Level........................................36 6.1.3 Specific Procurement Tasks and Responsibilities...............................................................36

6.2 Procurement Policies............................................................................................................ 36

6.3 Procurement Procedures...................................................................................................... 40 6.3.1 Procurement Planning (Goods and Services) ......................................................................40 6.3.2 Planning for Training Activities ........................................................................................40 6.3.3 Organization of the Supply Side of Training Under PSCAP ................................................41 6.3.4 Procurement Announcements...........................................................................................43 6.3.5 Procedures and Methods (Goods) ......................................................................................43 6.3.6 Procedures for Procuring Goods Using ICB or NCB methods..............................................44 6.3.7 Procedures for Selection of Consultants .............................................................................46 6.3.8 Overview of World Bank Procurement Procedures.............................................................50

Section 7. Monitoring & Evaluation ................................................................................. 51

7.1 Purpose and Objectives of the PSCAP M&E System............................................................ 51

7.2 PSCAP Activities, Outputs and Outcomes............................................................................ 51 7.2.1 Defining “Activities, Outputs, and Outcomes”....................................................................51 7.2.2 Participation and Performance Agreements........................................................................52

7.3 M&E Building Blocks .......................................................................................................... 52

7.4 Institutional Arrangements for M&E................................................................................... 54

7.4 PSCAP Indicators for M&E................................................................................................. 55 7.4.1 Indicators for PSCAP activities and outputs .......................................................................55 7.4.2 Available Data and Strategy for PSCAP M&E Data Collection ...........................................56

Page 5: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- iii -

7.5 Challenges and Recommendations for PSCAP M&E........................................................... 57

Section 8. Information, Education, & Communication (IEC)................................. 58

8.1 Purpose of IEC..................................................................................................................... 58

8.2 Guidelines for IEC under PSCAP........................................................................................ 58

8.3 Roles and Responsibilities at the Federal and Regional Level............................................... 59

8.4 The IEC Cycle —From Issue Identification to Feedback....................................................... 59 8.4.1 Identifying Priority Issues and Selecting Messages.............................................................59 8.4.2 Selecting and Segmenting Audiences.................................................................................60 8.4.3 Deploying Communication Channels with Feedback Mechanisms .......................................60 8.4.4 Identifying Output and Outcome Indicators........................................................................60 8.4.5 Implementing ...................................................................................................................61 8.4.6 Soliciting Feedback and Evaluating Results .......................................................................61

Page 6: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Abbreviations and Acronyms

AfDB African Development Bank BCB Regional Bureau of Capacity Building BOFED Regional Bureau of Finance and Economic Development CAS Country Assistance Strategy CAD Central Accounts Department CFU Counterpart Funds Unit CIDA Canadian International Development Agency CIF Cost, Insurance and Freight CIP Cost, Insurance and Carriage CPR Council of Peoples’ Representatives COMESA Community of Eastern and South Africa CSRP Civil Service Reform Program DCI Development Corporation of Ireland DCA Development Credit Agreement DLDP District Level Decentralization Program DfID Department for International Development EA Executing Agency EC European Commission ECuA Ethiopian Customs Authority EMCP Expenditure Management and Control Activities EOI Expressions of Interest FIRA Federal Inland Revenue Authority FMR Financial Monitoring Report FPA Financial Performance Assessment FTT Federal Technical Team GDP Gross Domestic Product GPN General Procurement Notice IAPSO Inter-Agency Procurement Services Office ICB International Competitive Bidding ICT Information and Communication Technologies ICTDA Information and Communication Technologies Development Authority IDA International Development Association IDC Indefinite Delivery Contract IEC Information, Education and Communication IMF International Monetary Fund JSRP Justice System Reform Program KfW Kreditanstalt fuer Wiederaufbau GOE Government of Ethiopia LIG Proposed Local Investment Grant Program GTZ German Technical Cooperation MABs Ministries, Agencies, and Bureaus MCB Ministry of Capacity Building MDG Millennium Development Goals M&E Monitoring and Evaluation MFA Ministry of Federal Affairs MOFED Ministry of Finance and Economic Development MOJ Ministry of Justice

Page 7: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 2 -

MOR Ministry of Revenue MOU Memorandum of Understanding NBE National Bank of Ethiopia NCB National Competitive Bidding NCBP National Capacity Building Program NGO Non-Governmental Organization OFAG Office of the Federal Auditor General PPD Planning and Programming Directorate PRSC Poverty Reduction Support Credit PSCAP Public Sector Capacity Building Program PEP Public Expenditure Program PIP Program Implementation Plan QBS Quality Based Selection QCBS Quality and Cost Based Selection ROPE Results-Oriented Performance Evaluation RTT Regional Technical Team SA Special Account SBCQ Selection Based on Consultant’s Qualification SDP Sector Development Program SDPRP Ethiopia’s Sustainable Development and Poverty Reduction Program SFB Selection on Fixed Budget SIDA Swedish International Development Agency SIL Sector Investment Loan SOE Statement of Expenditure SSS Single Source Selection SWAp Sector Wide Approach TA Technical Assistance TOR Terms of Reference TD Treasury Department TSRP Tax Systems Reform Program UMCBP Urban Management Capacity Building Program UNDB United Nations Development Business UNDP United Nations Development Program USAID United States Agency for International Development WTO World Trade Organization

Page 8: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Section 1. Program Overview Background Since its transition to multiparty in the early 1990s, Ethiopia has embarked on a long term strategy of “state transformation” characterized by bold attempts to implement multiple reforms in parallel; the massive scale-up of institutional development efforts across tiers of government; and the deliberate expansion of the scope of public sector capacity building initiatives. Spanning nearly a decade, Ethiopia’s transformation agenda has evolved over three phases in response to growing awareness that pervasive deficits in capacity have hampered the ability of the state to secure the fundamentals of poverty reduction and democratic development such as responsive service delivery, citizen empowerment, and good governance. Regionalization and public sector modernization in the mid- to late-1990s. The first phase of the Government’s state transformation strategy, launched in 1995, involved the creation of a federal state structure based on ethnically delineated regional states responsible for a broad range of the country’s political, economic, and social objectives including the delivery of essential public services. In accordance with the 1994 Constitution, the Government formally established an intergovernmental fiscal system and initiated the annual transfer of a formula -driven general purpose grant or subsidy to regions, consistent with its policy of “balanced regional progress.” It also undertook a significant redeployment of civil service staff to newly empowered regional executives.

Even as it established a radically new decentralized political and state system, the Government acknowledged the deep institutional constraints on basic functions such as policymaking, service delivery, and regulation. Core public management systems at the federal and regional levels were hampered by outdated civil service legislation and working systems; the absence of a medium-term planning and budgeting framework; ineffective financial and personnel management controls; inadequate civil service wages and inappropriate grading systems; poor capacity for strategic and cabinet-level decision-making; and insufficient focus on modern managerial approaches to service delivery. In recognition of these constraints, the Government embarked on a comprehensive Civil Service Reform Program (CSRP) in 1996. Indicative of Ethiopia’s “first generation” capacity building efforts, the CSRP sought to build a fair, transparent, efficient, effective, and ethical civil service primarily by creating enabling legislation, developing operating systems, and training staff in five areas: (i) Expenditure Control and Management, (ii) Human Resource Management, (iii) Service Delivery, (iv) Top Management Systems, and (v) Ethics. Successful efforts (for example, budgeting, planning, and accounting reforms) at the federal level were intended to provide prototypes for regional authorities. Complementary tax policy and administration reforms were also undertaken in line with the Government’s objectives of improving revenue performance to reduce aid dependency and adequately finance the expanding development agenda. The passage and implementation of a Value-Added Tax, as well as the implementation of a Taxpayer Identification Number (TIN) system proceeded. Early efforts in the justice system including the strengthening of court administration and the reform of the penal code and family law sought to deepen implementation of the 1994 Constitution.

The results of these efforts, implemented over the 1996-2000 period, were mixed. Despite notable achievements in public finance management, these initiatives have had only modest impact in relieving the institutional and capacity constraints within the Ethiopian civil service. There was little evidence of sustained improvement in output performance at the federal or regional levels. Core functions such as medium-term planning, accounting and auditing, and personnel management remain weak. Attempts to develop an affordable, medium-term public sector pay policy were also delayed, and civil servants—despite an across-the-board salary increase in 2001—continued to receive low salaries. Operational efficiency across federal ministries and regional bureaus remained poor. Furthermore, lags in the

Page 9: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 2 -

prototyping phase at the federal level forestalled CSRP implementation in regions and woredas. The considerable opportunity costs in terms of foregone improvements in institutional and service delivery performance at the regional and local levels were widely acknowledged.

Weaknesses in the design of reform initiatives such as an overly top-down approach, inexperience with managing national and international consultants, and funding gaps limited the impact of this first phase of transformation. Implementation delays resulted from the inordinate demands that the border conflict placed on the time of senior officials. Nevertheless, the Government’s generally pragmatic approach to implementing an ambitious regionalization and civil service reform agenda established Ethiopia as a serious state reformer by the late 1990s

The unfinished agenda in the post-conflict period. By late 1999, Ethiopia’s early public sector reform experience had significantly deepened its leadership’s appreciation of the role of institutional capacity building in securing the economic and political fundamentals of sustainable poverty reduction. Of particularly concerns were factors that hindered public sector efficiency, local empowerment, and accountability.

Within the public sector, unpredictable resource flows have undermined the allocative and operational efficiency the public sector at the federal, regional, and local levels in Ethiopia. The incentive framework for personnel also needs to be reformed, given the current needs of the civil service. Anecdotal evidence revealed severe problems in retaining managerial and technical personnel. In ministries, agencies, and bureaus (MABs), the functions, systems, structures, and work practices were not aligned with Government’s medium-term development priorities and resource constraints.

With regards to empowerment, woredas or districts enjoyed little fiscal or administrative autonomy to respond to the local needs of their constituencies. Local level planning and prioritization processes—while consultative—were typically short-circuited by zonal officials, who would vet woreda levels plans in line with regional priorities. Project and program implementation were also burdened by overly centralized procedures for procurement of goods and services, and management of frontline personnel. The resulting inefficiencies were further exacerbated by endemic staffing and skills shortages, unclear accountability relationships, and inadequate organizational structures. By 2001, woredas were still deconcentrated units of regions rather than democratically elected executives in their own right. In addition, municipal governments were not adequately integrated into the larger legal and accountability framework of regional governance, and therefore, have been limited—in providing essential services to their residents—by their ability to raise own-source revenues.

Significant institutional weaknesses and capacity deficits are acknowledged across Ethiopia’s justice system including in areas such as lawmaking, law execution and enforcement, the functioning of courts, and the development of the legal professional. Weaknesses in the vertical and horizontal independence of the judiciary resulted from lack of transparency in the selection of judges, unclear organizational structures in the courts, outdated systems and procedures, shortages in trained judges and support staff, and lack of basic infrastructure and facilities. A lack of adequate budgetary resources has also hindered the emergence of a well-functioning judiciary, particularly in first instance courts in the federal system and woreda courts in the regions. Access to justice continues to be limited by supply -side constraints (for example, increasing representation and legal aid, reducing the costs of access, simplifying court documents, establishing alternative dispute resolution mechanisms), and demand-side constraints (for example, increased awareness of constitutional and legal rights, education of the poor about options for recourse and redress).

Page 10: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 3 -

Box 1.1: Ethiopia’s National Capacity Building Program (NCBP)

§ Civil service reform § Justice reform § Tax reform § District-level decentralization § Urban management § Information and communication technology § Cooperatives § Private sector § Textiles and garments § Construction sector § Agricultural training of vocational and technical levels § Industrial training of vocational and technical levels § Higher education § Civil Society

Ethiopia’s Home-Grown Response of National Capacity Building. In the immediate aftermath of the Ethio-Eritrean conflict, the Government once again took up the unfinished work of broad-based institutional development by launching a comprehensive National Capacity Building Program (NCBP) in order to the capacity building demands of its state and structural transformation agenda. The national capacity building framework envisages as capacity building system that (i) ensures efficiency and sustainability; (ii) supports the comprehensive development of human resources, organizations, systems and processes as a means of achieving the country's development goals; (iii) affords flexible implementation modalities in order to accommodate the dynamics of institutional change. A super-ministry, the Ministry of Capacity Building, was established in 2001 to provide policy direction, coordination amongst other partner institutions (for example, the Ministries of Finance and Economic Development, Revenue, and Federal Affairs), as well as monitoring and oversight of capacity building efforts. The Ministry, along with its counterpart regional bureaus and woreda offices, is tasked with programming and financing fourteen capacity building subprograms that support the dual SDPRP goals of state and structural transformation (Box 1.1).

Six of these fourteen subprograms directly involve the public sector and comprise (i) a woreda (district level) decentralization program that rapidly transferred delivery responsibilities with substantial fiscal and administrative authority to rural jurisdictions; (ii) municipal reform efforts designed to restructure and empower urban centers; (iii) reformulated civil service reforms focused increasingly on strengthening the public sector fiduciary framework and service delivery results on the ground; (iv) bold nation-wide initiatives to enhance connectivity and develop e-government applications such as the woreda- and school-net projects; (v) efforts to strengthen formal checks and balances and accountability mechanisms through reform of the justice system including the courts, law making and law enforcement institutions, and the legislative process; and (vi) an ongoing tax systems reform program that continues to align tax policy and administration at the federal and regional level with the demands of Ethiopia’s evolving macro-fiscal policies. In FY2002-03 and FY2003-04, the Government—through its Ministry of Capacity Building, Bureaus of Capacity Building, and other lead institutions—advanced the implementation of all six subprograms. Cons iderable domestic resources—ETB 108.4 million in FY2002-03 alone—were mobilized through the federal budget to carry out public sector capacity building activities. Progress-to-date is detailed in the first Annual Progress Report on the SDPRP and summarized below along with the Government’s forward looking strategy in each area.

Page 11: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 4 -

Notwithstanding the rapidly expanding scope and scale of its reform program, the Government soon recognized that public sector capacity building efforts through 2003 were still largely supported by fragmented donor projects and financed in an ad hoc manner. In many cases, direct capacity building support provided to regions has been offset in the general-purpose transfers. In addition, concerns related to the degree of transparency in the implementation of capacity building, problems in effectively leveraging global knowledge, as well as the bias towards intensive off-site training activities need to be addressed. Finally, the financing requirements of scaling up each of these above-mentioned subprograms indicated that Treasury resources alone would not suffice; significant external assistance would be required. The 2001-2003 experience with multiple reform efforts undertaken in parallel demonstrated the importance of exploiting the synergies between subprograms described above; using a flexible mechanism of support that could respond to the rapidly evolving needs of various subprograms; empowering regions and local authorities in setting priorities and achieving results; harmonizing donor support around a single design; and improving coordination across branches and tiers of government.

Scaling up “State Transformation”: Salient Design Features of the Sector-Wide Approach. In May 2003, the Government announced its intention to rapidly scale up support for the six core public sector reform programs as subprograms under a consolidated five-year federal program called the Public Sector Capacity Building Program or PSCAP. The Government’s vision, reflected in its national program document for the PSCAP, was based on three pillars—(i) simultaneous, nation-wide implementation of six above-mentioned programs (now called “subprograms), sequenced in line with regional and local priorities, (ii) alignment of program support with Ethiopia’s public financial management and intergovernmental system, and (iii) harmonization of the fiscal, fiduciary, and reporting requirements of various donors around a Sector-Wide Approach (SWAP). In the months that followed, several bilateral donors, in close collaboration with IDA, have responded favorably with commitments to support the SWAP approach and the pooling of funds around a single design solution. Salient features of the Government’s program include: § Designation of PSCAP as a federal specific purpose transfer program, appropriated at the federal

level and therefore not subject to offsets in regional subsidies; § Incorporation of donor commitments under PSCAP within the Government’s overall macroeconomic

fiscal framework and the overall vertical division of revenues between federal and regional levels; § Alignment of donor procedures with Government’s rolling medium-term planning, annual budgeting,

and monthly SOE-based disbursement procedures; § Explicit identification of rules of the game governing access, allocation, and execution including an

established vertical division of resources between federal and regional levels, and a simple formula to horizontal division of time-bound drawing rights to PSCAP resources across regional states, followed by performance-based disbursements as well as mid- and end-year reallocation of a share of drawing rights to performers;

§ Regular bottom-up regional, and eventually woreda and municipal planning of capacity building activities within assigned medium-term and annualized resource envelopes;

§ Pooling of donor resources around a single design under the SWAp, and alignment of non-pooled support with the Governments’ planning, budgeting, and M&E system;

§ Development of “matrix management” structure, in which federal subprograms provide the prototypes, technical advice, quality assurance, and recommendations on approvals of plans, while regions prioritize resources and activities based on a menu of subprogram activities through medium term and annual plans.

Page 12: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 5 -

SWAp/Program Development Objectives

The objective of the SWAp is to improve the scale, efficiency, and responsiveness of public service delivery at the federal, regional, local level services; to empower citizens to participate more effectively in shaping their own development; and to promote good governance and accountability. This objective will be achieved by scaling up Ethiopia’s ongoing capacity building and institutional transformation efforts in six priority areas—(i) Civil Service and Expenditure Management Reform; (ii) District-Level Decentralization; (iii) Urban Management; (iv) Tax Systems Reform; (v) Justice Systems Reform; and (vi) Information and Communications Technology.

Key Performance Indicators While specific outputs and outcome indicators across PSCAP subprograms are provided in Annex 1, key performance indicators of the expected impact of the program are provided below along with the contributing subprograms.

Expected impact on “institutional quality” Contributing PSCAP Subprograms 1. Increased predi ctability and adequacy of financial resources flows (in-year and across years) § Reduced budget variance § Reduced federal-regional and regional-local fiscal gaps

Civil Service Reform Tax Systems Reform

2. Greater inclusiveness and transparency of planning and prioritization processes § Established practice of participatory budgeting and public

reporting on budgets and performance at all levels § Regular involvement of civil society in planning and

policymaking, budgeting, and review processes

Civil Service Reform District-Level Decentralization Urban Management Capacity Building Tax Systems Reform

3. Enhanced revenue performance and fiscal autonomy § Increased own revenues and unconditional transfers as a

share of total expenditures at sub-national levels § Increased tax effort at all levels

District-Level Decentralization Urban Management Capacity Building Tax Systems Reform ICT

4. Enhanced incentive environment for public servants (gender disaggregated) § Increased average civil service salary as percentage of living

wage § Private-public wage comparison § Wage decompression ratios

Civil Service Reform District-Level Decentralization Urban Management Capacity Building

5. Improved quality and efficiency of operations § Improved service levels in terms of access, responsiveness

and cost efficiency in priority sectors § Reduced unit costs and processing time for essential rural,

urban, social, and legal services in priority sectors

All Subprograms

6. Improved transparency and accountability § Reduced incidence of corruption and arbitrariness in rule

enforcement (as judged by economic agents) § Increased access to justice, recourse and redress § Enhanced independence of the judiciary § Increased access to government information

All Subprograms

Page 13: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Section 2. Program Description

2.1 Federal and Regional Components The PSCAP scale -up will be supported through two components—(i) federal PSCAP, and (ii) regional consolidated PSCAP. Activities in both components are drawn from a menu of eligible expenditures in each of the six PSCAP subprograms or “building blocks” and one mandatory program support activity described below. For each component, medium term rolling plans and annual implementation plans are based on a prioritization and sequencing of activities across the six subprograms. Both medium term and annual plans are revised against implementation progress on a semi-annual and annual basis in line with the rules governing reallocation (described later in Section 4). Provide below is a description of the federal and regional components, as well as their constituent building blocks, that is, the six subprograms and mandatory program support (Figure 2.1).

§ Component 1—Federal PSCAP: This component supports federal level activities across each of the six subprograms including strengthening of strategic and implementation management functions to ensure effective coordination at the subprogram and program levels. The component also includes capacity building activities for which there are scale and network economies that justify national level prototyping (for example, the customization of particular information systems). It is envisaged that resources would be shifted year-to-year and in-year from poor performing to higher performing subprogram activities at the federal level.

§ Component 2—Regional PSCAP: The regional component constitutes the bulk of PSCAP and is designed to empower regions to adapt and implement national capacity building priorities envisaged under PSCAP’s six subprograms in a performance oriented and sustainable manner. Under this component, all participating regions will be required to complete a “minimum mandatory” set of capacity building activities drawn from each of the six subprograms and basic program support (Table 2.1). These “minimum mandatory” capacity building activities constitute the first in a sequence of capacity building activities across the six subprograms that each region will need to be complete before more sophisticated capacity building activities can be undertaken. Provided that the minimum mandatory are completed, participating regional governments have flexibility to prioritize other capacity building activities between subprograms in line with their particular regional needs in any given year, (for example, a greater emphasis on urban management as opposed to ICT) and also sequence capacity building activities within subprograms in line with “good practice” approaches prescribed by subprogram directors (for example, adopting regional prototype legislation for municipalities before restructuring them).

A Note on “Minimum Mandatory” Activities for Regions. Under this component, a region’s ability to emphasis specific subprograms over others is limited to ensure the progress across all subprograms in accordance with national policy prioritie s. The minimum mandatory constitute the first in a sequence of capacity building activities across the six subprograms that each region will need to be complete before more sophisticated capacity building activities can be undertaken. Substantively, the “minimum mandatory” constitutes the essential or basic elements of PSCAP and are therefore protected from the semi-annual and annual reallocation procedures described in Section 4. Some regions may complete the minimum mandatory within a year, while others may take two years to complete them. There is no specific time requirement for completion of the minimum mandatory. However, those regions that complete these activities earlier will be able to utilize their drawing rights to the PSCAP fund faster.

Page 14: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 7 -

2.2 PSCAP Subprograms: “Building Blocks” for Federal and Regional Components The objectives and specific menus of activities that fall within each subprogram of PSCAP are explained below. Selected and planned on an annual basis, these menus of capacity building activities (comprising combinations of technical assistance and consultancy services, goods and equipment, and training) provide the basic building blocks for the federal and regional components. Those subprogram activities that are essentially federal in their orientation will not be carried out under the regional component.

§ Subprogram 1—Civil service reform. This subprogram aims to promote the development of an efficient, effective, transparent, accountable, and ethical civil service. Subprogram activities comprise (i) strengthening Civil Service Reform Program coordinating structures; (ii) improving expenditure management and control through drafting of financial regulations and directives, roll-out of budgeting and accounts reforms, implementation of procurement reforms, development of medium-term planning systems, strengthening of internal and external audit, modernization of cash management, and the roll-out of financial management information systems; (iii) improving the governance of human resource management including the development of prototype policies on human resource development, time management, and remuneration, the implementation of the results-oriented appraisal system, the development of payroll and human resource information systems, and support for subsidiary regulations such as the code of ethics; (iv) improving performance and public service delivery through the roll-out of the Performance and Service Delivery Improvement Program (PSIP) in ministries, agencies, and bureaus; (v) improving accountability and transparency through parliamentary oversight and anti-corruption activities, and strengthening systems for monitoring fiscal and output performance including expenditure tracking surveys, cost efficiency studies, service delivery report cards; (vi) strengthening top management systems through training of senior managers and officials in strategic planning, performance measurement, top management development, and value for money management; and (vii) building the policy and institutional capacities of emerging regions through the development of basic civil service structures and systems. Linkages with the district-level decentralization, urban management, ICT, and tax systems reform subprograms should be reflected in federal and regional plans and coordinated during implementation.

Figure 2.1: PSCAP Components are Drawn from Activity Menus across the Six Subprograms

P r o g r a m S u p p o r t P r o g r a m S u p p o r t

S u b p r o g r a m 6 . I C TS u b p r o g r a m 6 . I C T

S u b p r o g r a m 1 . C i v i l S e r v i c e R e f o r mS u b p r o g r a m 1 . C i v i l S e r v i c e R e f o r m

S u b p r o g r a m 2 . D i s t r i c t L e v e l D e c e n t r a l i z a t i o nS u b p r o g r a m 2 . D i s t r i c t L e v e l D e c e n t r a l i z a t i o n

S u b p r o g r a m 3 . U r b a n M g t C a p a c i t y B u i l d i n gS u b p r o g r a m 3 . U r b a n M g t C a p a c i t y B u i l d i n g

S u b p r o g r a m 4 . T a x S y s t e m s R e f o r mS u b p r o g r a m 4 . T a x S y s t e m s R e f o r m

S u b p r o g r a m 5 . J u s t i c e S y s t e m s R e f o r mS u b p r o g r a m 5 . J u s t i c e S y s t e m s R e f o r m

Com

pone

nt 2

. Reg

iona

l PSC

AP

Com

pone

nt 1

. Fed

eral

PSC

AP

Page 15: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 8 -

Table 2.1: “Minimum Mandatory” Capacity Building Activities for Regions

PSCAP Subprograms

Minimum Mandatory Or the First in a Sequence of Activities to be Carried By Regions Across The Six Subprograms

CSRP

§ Elimination of backlog accounts at regional and local levels § Installation and training in medium term expenditure management procedures manual,

BIS, and BDA3 systems in all regional and woreda institutions § Completion of training in and adoption of result oriented performance evaluation

(ROPE) system in all regional bureaus and woredas. § The following PSIP-related activities launched in 75% of regional bureaus:

­ Completion of client score cards ­ Initiation of business process re-engineering.

§ Completion of top management training in Strategic Planning and Management, Change Management, Performance Management, and Leadership Development for agency heads of 75% of bureaus

DLDP

§ Completion of review and preparation of decentralization legal framework, functional assignments, and structures

§ Completion of assessments for: ­ human resource and training needs for woredas ­ the required office infrastructure and equipment for woredas

§ Review for adoption of region’s decentralization strategy document § Finalization of strategy and action plan for gender sensitized community participation § Technical assistance for implementation of region’s woreda decentralization strategy

and policy development, benchmarking and review of plans § Review for adoption for prototype minimum service standards

JSRP

§ Installation of court case management and case recording & transcribing systems in all regional supreme & high courts

§ Installation of color coded filing system in all woreda courts § Establishment of information counters in all regional high courts and woreda courts § Initiation of in-service training and professional development of all judges, lawyers

and court clerks

UMCBP

§ Development and adoption of region’s urban development policy and strategy § Development and adaptation for implementation of personnel management manuals

for local government authorities § Development and adoption of urban land legislation and the municipal proclamation § Completion of one round of bulk generic training to all relevant regional and

municipal staff

TSRP

§ Adoption of proclamations, regulations, and directives for income and TOT § Completion of 50% coverage for computerized tax payers identification number (TIN) § Completion of annual turnover survey § Completion of training on laws for tax administrators at regional and city

administration levels

ICT

§ Establishment and strengthening of Regional Data Centers § Completion of technical training on network management and system administration

for the Regional Date Center staff § Initiate basic training (computing) for designated ICT focal persons from all woredas

Program Support

§ Preparation and dissemination of basic IEC materials on PSCAP § Completion of training in PIP, procurement, financial management, and M&E

Page 16: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 9 -

§ Subprogram 2—District-level decentralization. The objective of the subprogram is to deepen the devolution of power to the lower tiers of regional government, to institutionalize decision-making processes at the grassroots level with a view to enhance local participation, to promote good governance, and to improve decentralized service delivery. Subprogram activities include support for (i) woreda manning and training including human resource policies, procedures, and plans as well as bulk training in areas critical to local government; (ii) technical assistance and training for grassroots participation including the development of guidelines and monitoring mechanisms, and the strengthening of civil society involvement at the local level; (iii) woreda institutional and organization development including assessment of functional assignments and enabling legislation, assistance in establishing structures and restructuring existing arrangements including local level accountability relationships; (iv) capacity building for policy and program development including technical assistance for woreda decentralization strategy and policy development, benchmarking and review of plans; (v) development of woreda fiscal transfer mechanisms and revenue mobilization capacities through the review and design of various intergovernmental fiscal instruments; (vi) strengthening of the planning system & financial management at the woreda level; and (vii) the development of minimum service standards in priority sectors. Linkages with the civil service reform, urban management, and tax systems reform subprograms should be reflected in federal and regional plans and coordinated during implementation.

§ Subprogram 3—Justice systems reform. This subprogram, currently a work-in-progress, is designed to promote the rule of law as well as the efficient and effective functions of the justice system as part of Ethiopia’s broader democratization and private sector development processes. Subprogram activities include (i) strengthening the Justice Systems Reform Program Office and regional equivalents; (ii) strengthening the courts by providing in-service training of judges and court clerks, court administration reform, development of records and case load management systems, and identification of measures to enhance access to justice; (iii) support for law reform including the development of systems and procedures for declaring income and property, identification of new areas for law development, compiling and preparation of laws and regulations, and drafting of stock exchange and other laws; (iv) strengthening of legislative process including training, technical advisory services, and acquisition of equipment for staff of federal and regional standing committees on legislative drafting and analysis of legislative process and management, as well as training for members of standing committees on principles of federal grant and intergovernmental fiscal framework, monitoring and impact assessment, HIV/AIDS and gender issues, accountability and participation; (v) law enforcement organ capacity enhancement through establishment of community policing system, upgrading existing national forensic laboratory; development of a national crime prevention strategy; development of a program of continuous relevant training for prosecutors, police officers, penitentiary staff, installation of IT systems and acquisition of equipment and others; and (vi) support to strengthen capacity of the members of parliament and its staff through training and workshops, provision of assistance related to the revision of existing laws and enacting new legal provisions where required, implementation of various studies on reform the law reform agenda, development, compilation, consolidation, publication and distribution of legislative proceedings and other relevant materials. Linkages with the civil service reform, urban management, ICT, and tax systems reform subprograms should be reflected in federal and regional plans and coordinated during implementation.

§ Subprogram 4—Urban management capacity building. This subprogram aims to enhance the capacity of municipalities in the delivery of services and enable urban centers to play a more effective role in social and economic development. The major activities envisaged under this subprogram include (i) technical assistance for the development of federal and regional policies

Page 17: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 10 -

related to urban development, housing, urban land, municipal structures, the formation of municipal associations; (ii) technical assistance for the deepening of municipal decentralization through the preparation of manuals governing resource management, review and organization of training and human resource needs, establishment of regional planning units, and development of fiscal transfer and revenue mobilization mechanisms; (iii) support for local government restructuring and capacity building including restructuring of water and sanitation, urban land, and other services, development and roll-out of financial, human resource, and land systems, and organizational and related reviews, as well as bulk training for municipal officials and staff. Linkages with the civil service reform, district-level decentralization, ICT, and tax systems reform subprograms should be reflected in federal and regional plans and coordinated during implementation.

§ Subprogram 5—Tax systems reform. The subprogram aims to encourage capital investment and development, increase tax revenues (through improved compliance and efficiency of collection), and ensure equity and fairness in the tax system through a comprehensive overall of the current legislation and tax administration system. These objectives are to be achieved through the following subprogram activities: (i) continued development of tax policy and legislation including amending the current income tax legislation to reflect the current business and investment environment, implementing presumptive and value-added taxes, strengthening enforcement powers of tax collection bodies, and sensitization of taxpayers inter alia through establishment of a Taxpayer office; (ii) roll-out of the computerized Tax Payers’ Identification Number (TIN) system in 74 regional centers, improving information sharing between the Federal Inland Revenue Authority (FIRA), Ethiopia Customs Authority (ECuA), as well as regional and city administrations; (iii) customs reform and modernization including the review of legal framework, review and implementation of customs procedures in line with COMESA, deepening of ongoing implementation of performance improvement in ECuA, establishment of a customs laboratory and training center, roll-out of management and core staff training in areas such as human resource development, IT management, WTO valuation system, commodity classification, and application of international conventions on simplification of customs procedures. Linkages with the civil service reform (for examples, performance activities in ECuA), justice, ICT, and tax systems reform subprograms should be reflected in federal and regional plans, and coordinated during implementation. The tax systems reform program should be coordinated with plans to develop sub-national taxes as envisaged under the district level decentralization and urban management subprograms.

§ Subprogram 6—Information & communications technologies (ICTs). The objective of this subprogram is to harness ICTs for the development of human resources, democratization, service delivery, and good governance. Several programs under PSCAP including CSRP, DLDP, Urban Management, and Tax Sector Reform are seeking to use ICTs in this manner. Successful implementation of ICT-based solutions across government will require support for (i) human resource development through the development of an ICT human resource strategy, ICT curricula for schools, vocational training centers, and universities, as well as the training of trainers, the establishment of distance learning centers, and the financing of research on the use of ICTs; (ii) ICT use for public service and good governance through the development of information systems strategies, development of service delivery applications, establishment of data centers and government portals, WAN and LANs, as well as the procurement of required hardware and software; and (iii) ICT for sector development including the installation of applications in the social and infrastructure sectors; and (iv) community-based ICT systems and services through the development of strategies, applications, and local content for community information centers to facilitate specific developmental activities. While the development of public sector applications such as financial, human resource, and land management systems will be procured under

Page 18: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 11 -

respective reform programs (for example, CSRP, UMCBP, TSRP), sector-specific applications(for example, agriculture) will be financed under the ICT subprogram. Plans for these applications will be coordinated between subprograms, regions, and ICTDA.

§ Program support. As a required activity at both the federal and regional level, program support is designed to ensure speedy implementation of the six subprograms in a holistic manner. It will finance incremental costs associated with operating requirements of Planning and Programming Departments or equivalents in regions, the Budget and Finance Directorate in the MCB, related subprogram offices that serve members of the federal and regional Technical Teams, and relevant offices in the Ministry and Bureaus of Finance and Economic Development. Specific support activities include the costs of program coordination and planning, training management, IEC activities, monitoring and evaluation, basic training, auditing, office supplies, equipment operation, transport, travel, and per diems.

2.3 PSCAP Subprograms: “Building Blocks” for Federal and Regional Components

The overall program cost is estimated to be USD 397.8 million over the course of five years. The required financing will be leveraged from domestic and external sources through a Sector-Wide Approach. Provided below is an estimated breakdown of program costs and funding sources. It is expected that these will be adjusted annually with projected improvements in bilateral donor support as well as mobilization of domestic resources. More detailed breakdown of program budget by region and subprogram are provided in the federally proclaimed annual budget and corresponding regional budgets. In addition, annual breakdown of estimated costs by expenditure categories (for example, training, consultancies, goods and equipment) are provided in the procurement plan(s), which is attached to the PIP and available upon request from the Planning and Program Directorate of the Ministry of Capacity Building, Addis Ababa.

Table 2.2: Estimated Cost of Program Compone nts

Component Sector Indicative

Costs (US$M)

% of Total Bank-

financing (US$M)

% of Bank-financing

1. Federal PSCAP Multi-sectoral 80.0 20% 20.0 25%

2. Regional PSCAP Multi-sectoral 317.8 80% 80.0 25% Total Program Cost 397.8 100% 100.0 25%

PROGRAM FINANCING PLAN (US$m)

Source Local Foreign Total

Government 137.5 - 137.5

IDA 65.4 34.6 100.0

CIDA 25.3 13.4 38.8

SIDA 5.6 3.0 8.6

Other Donors 73.2 39.8 113.0

Total: 307.0 90.8 397.8

Page 19: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Section 3. Institutional Arrangements The scale, complexity, and uniqueness of this program places a premium on four overriding implementation priorities—(i) coordination across tiers and branches of government, (ii) enforcement with clearly defined rules of the game (for example, for allocation and reallocation); (iii) information sharing and peer review (for example, on matters of performance) within the public sector and with the public at large; and (iv) extensive support to implementing agencies in the design, execution, and quality assurance of reform activities. Described below are institutional arrangements for effective implementation including the roles and responsibilities of federal, regional, local, and donor actors. Illustrated in Figure 3.1, these arrangements are designed to address the Government’s desire to rapidly scale up capacity building activities while effectively management the full array of implementation risks. 3.1 Federal Level Institutional Arrangements

3.1.1 Ministry of Capacity Building As the head of a “super-ministry,” the Minister of Capacity Building (MCB) and specifically, the State Minister of Capacity Building is responsible for the overall coordination of PSCAP, serves as co-chair of the Joint Government-Donor PSCAP Working Group; and coordinates Government participation in regular formal reviews of implementation progress. Among other things, MCB will be responsible for: § managing Ethiopia’s national capacity building efforts such as PSCAP on a macro level; § establishing policies, designing national strategies and ensuring their integration with

sectoral strategies; § developing guidelines for programming capacity building; § providing technical support to regions; and § evaluating ongoing program implementation.

For purposes of day-to-day management of PSCAP, the Ministry coordinates an inter-ministerial Federal Technical Team (FTT), and houses a Planning and Programming Directorate (PPD) as well as a Budget and Finance Directorate (BFD). Roles and responsibilities are described below.

Federal Technical Team (FTT). The FTT is led by the Director of MCB’s Planning and Programming Directorate and includes all PSCAP’s six subprogram directors, as well as representatives from key directorates of the Ministry of Finance and Economic Development (MOFED) including the Regional Affairs Directorate, Central Accounts Department, and Counterpart Funds Unit, and relevant officials of the Ministry of Federal Affairs. As the apex technical body managing PSCAP, the Federal Techincal Team (FTT) is responsible for:

§ reviewing, appraising, and recommending approval of annual plans submitted by federal

executing institutions and regions in line with technical criteria delineated in the PIP (for example, completion of the “mandatory minimum” capacity building activities, sequencing of reform activities, provision of regional financing for upfront civil works and ongoing recurrent costs of IT investments);

§ reviewing in-year and annual performance and recommending re-allocations of five-year drawing rights between non-performing and performing regions;

§ supporting the development of content of reform programs during implementation with the support of the PPD and BFD;

Page 20: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 13 -

§ supporting, providing quality control and reviewing outputs produced by consultants prior to approving payment;

§ defining equipment specification and undertaking acceptance tests of equipment procured;

§ developing communication and change management strategies; and § ensuring the quality and consistency of reform efforts and, if needed, recruiting additional

technical expertise on a temporary basis to assist in appraising applications of a specialized nature (for example, those under the ICT component).

Planning and Programming Directorate (PPD). A Planning and Programming Directorate (PPD), housed in MCB, serves as the secretariat for the Program, and specifically for the State Minister responsible for PSCAP and the Federal Technical Team. Under its Director, the PPD will house four teams focused on Policy Study and Program Design; Program Coordination; Planning and Budgeting; and Monitoring and Evaluation. Included in the PPD is a training coordinator responsible for bulking and managing similar training activities across subprograms. Among other things, the PPD will be responsible for:

§ issuing and enforcing operating guidelines; § assisting the FTT in the vetting of annual plans for quality and completeness; § ensuring participatory planning processes are undertaken; § facilitating coordination between members of the federal and regional technical teams; § assist in consolidating, managing, and organizing the tendering of training across six

subprograms among pre-qualified supply institutions; § helping the FTT provide detail follow-up and quality assurance during implementation; § implementing communication and change management strategies; and § consolidating quarterly, semi-annual, and annual progress reports.

The PPD also serves as the counterpart institution to the Joint Government-Donor PSCAP Working Group and shall therefore facilitate review and supervision missions, as well as information sharing such as disclosure of annual and other related reports, survey data, and other occasional papers.

Budget and Finance Directorate (BFD). The budget and finance directorate (BFD) of the MCB is responsible for overall monitoring of procurement under the Program. It is also tasked with procurement and financial management of the three federal level subprograms that fall within the Ministry’s mandate—namely CSRP (except “expenditure management and control” activities), DLDP, and JSRP (except “strengthening the judiciary’ activities). The directorate will commit to service standards in terms of efficiency and timeliness of financial management and procurement activities. These service standards will be determined and agreed during the project launch workshop and will become part of this PIP. Among other things, the directorate will be responsible for:

§ carrying out international competitive procurement of goods under the Program

supported by a full complement of local procurement specialists and international advisers;

§ vetting and finalizing Terms of Reference (TORs), preparing equipment specification, processing technical evaluation, drafting and negotiating contracts, and managing contracts in close collaboration with subprogram directors and staff in the CSRP, DLDP and JSRP Offices in the MCB; and

Page 21: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 14 -

§ working with regions and other executing institutions for international competitive procurement of goods.

3.1.2 Ministry of Finance and Economic Development (MOFED)

The Ministry of Finance and Economic Development (MOFED) is responsible for:

§ enforcing the rules of allocation and access for PSCAP as an intergovernmental transfer; § effecting vertical and horizontal divisions (specifically, the Regional Affairs Department)

of PSCAP resources in collaboration with the MCB; § issuing formula-based medium-term drawing rights or notional envelopes to govern

medium-term planning and annual budgeting; and § recommending mid-year and annual reallocations of five-year drawing rights.

Within MOFED, the Central Accounts Department (CAD) and Counterpart Funds Unit (CFU) are responsible for the overall financial management under the Program. While the CFU manages the various special accounts (including requesting replenishments), the CAD will focus on closing of local currency accounts and the consolidation of financial reports. Opening and closing the special account, transfer of funds to the local currency accounts, and the replenishment of funds are the responsibility of the Treasury Department (TD). 3.1.3 Federal Subprogram Offices and Executing Agencies The mandate for supporting the implementation of the six subprograms of PSCAP rests with subprogram offices as Executing Agencies (EAs). Overall, the role of executing agencies responsible for subprograms at the federal level is to ensure that this large constituency of eligible institutions are informed and consulted in the preparation of medium-term and annual plans. Specifically, the MCB houses the subprogram offices responsible for the Civil Service Reform. District-Level Decentralization, and Justice Systems Reform Subprograms. The newly created ICT Development Authority holds the mandate for the ICT Subprogram. For purposes of day-to- day management, the Expenditure Management and Control Program (EMCP) Coordinating Office within MOFED is responsible for “expenditure management and control” activities under the CSRP. The Ministry of Revenue manages the Tax Systems Reform Program, and the Ministry of Federal Affairs’ Urban Development and Capacity Building Office (UDCBO) has the responsibility for the Urban Management Capacity Building Program. Finally, the Supreme Court is responsible for day-to-day management of federal PSCAP activities related to “strengthening the judiciary.” As Executing Agencies, these subprogram and coordinating offices as well as the Supreme Court are delegated the financial management and procurement autonomy to carry out activities relevant to their reform mandates. In addition, the Ministry of Federal Affairs has established a taskforce to provide additional technical support to emerging regions such as Afar, Benishangul-Gumuz, Gambella, and Somali to carry out PSCAP-related activities. The roles and responsibilities of these Executing Agencies at the federal levels are detailed below.

Ministry of Revenue . The Tax System Reform Program Office at the MOR will be responsible for implementing the Tax System Reform subprogram at the federal level. The office will hire or designate a procurement officer to support the implementation. The office will:

§ prepare federal action plans for Tax Systems Reform subprogram; § advise regions on tax reform related activities;

Page 22: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 15 -

§ conduct training, workshops and seminars; § manage procurement for the tax system reform initiative at federal level except the

international procurement of goods; § monitor the implementation of agreed activities; § submit physical progress reports to PPD; § submit financial report to MOFED for replenishment of funds; and § serve as a member of the FTT.

Information, Communication and Technology Development Authority (ICTDA). The Project Management Unit that is established to implement World Bank-financed project at the Information, Communication and Technology Authority (ICTA) will be responsible for implementing the ICT subprogram at the federal level. The Unit will hire or designate a procurement officer to support the implementation of PSCAP. The responsibilities of the Unit under PSCAP are to:

§ prepare federal action plans for ICT subprogram; § advise regions as well as federal executing agencies on ICT related activities; § conduct training, workshops and seminars; § manage procurement for ICT subprogram at federal level except the international

procurement of goods; § monitor the implementation of agreed activities; § coordinate the implementation of ICT sub programs both at federal and regional levels § submit physical progress reports to PPD; § submit financial report to MOFED for replenishment of funds; and § serve as a member of the FTT.

Ministry of Federal Affairs (MFA). The Ministry of Federal Affairs has organized three units to support the implementation of of PSCAP namely: (i) the Urban Development Capacity Building Office; (ii) the Rural Development Department; and (iii) the Pastoral Department. The Urban Development Capacity Building Office (UDCBO) of Ministry of Federal Affairs will be responsible for implementing the Urban Management Capacity Building subprogram at the federal level. The office will hire or designate a procurement officer to support the implementation. The UDCBO will: § prepare federal action plans for the UMCB subprogram; § advise regions on urban development related activities; § conduct training, workshops and seminars; § manage procurement for the UMCB sub-program at federal level except the international

procurement of goods; § monitor the implementation of agreed activities; § submit physical progress reports to PPD; § submit financial report to MOFED for replenishment of funds; and § serve as a member of the FTT.

In addition, MFA’s Rural Development Department will provide technical support to Benishangul Gumuz and Gambella where gaps exist. The Pastoral Department of MFA will provide the same type of support to Afar and Somali regions. Ministry of Finance and Economic Development (MOFED). The Expenditure Management and Control Office will be responsible for implementing the governance of Expenditure

Page 23: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 16 -

Management and Control (EMC) sub-activity of the Civil Service Reform (CSR) subprogram at the federal level. The Office will hire or designate one additional procurement officer to support implementation, and will:

§ prepare federal action plans for the EMC sub-activity of the CSR subprogram; § advise regions on expenditure and control related activities; § conduct training, workshops and seminars; § manage procurement for the EMC sub-activity of CSR subprogram at the federal level

except those that involve international procurement of goods; § monitor the implementation of agreed activities; § submit physical progress reports to PPD; and § submit financial reports to MOFED for replenishment of funds; § support the CSRP Director on the FTT, as the need arises.

Federal Supreme Court. The Federal Supreme Court will be responsible for implementing the Court Reform activities under the JRSP at the federal level. The Office in the Supreme Court will hire or designate a procurement officer to support the implementation and is responsible :

§ prepare federal action plans for Court Reform subprogram; § advise regions on court reform related activities; § conduct training, workshops and seminars; § manage procurement for the court reform initiative at federal level except the

international procurement of goods; § monitor the implementation of agreed activities; § submit physical progress reports to PPD; § submit financial report to MOFED for replenishment of funds; and § serve as a member of the federal technical team.

3.1.4 Other Eligible Beneficiary Institutions at the Federal Level

Several other federal institutions are eligible to receive support—in-kind including through asset transfer—under PSCAP and its six subprograms. These include sector ministries (for example, for health, education, and infrastructure), authorities and agencies (for example, the Environmental Protection Agency), and other offices within the executive branch; public sector training institutions such as the Ethiopian Civil Service College; the judiciary or the courts; as well as supreme audit bodies such as the Office of the Federal Auditor General and legislative oversight institutions such as the Public Accounts committee.

3.2 Regional Level Institutional Arrangements

3.2.1 Bureaus of Capacity Building In each of Ethiopia’s eleven regions (including Addis Ababa and Dire Dawa), the Bureaus of Capacity Building (BCBs) are responsible for program coordination. For purposes of day-to-day management of PSCAP, the BCBs coordinate Regional Technical Teams (RTTs), and house Planning and Program Directorates (PPDs) or equivalents including Procurement Desks. Roles and responsibilities for each are described below. Regional Technical Teams (RTT). In each region, an RTT comprising inter alia the director of the regional Planning and Programming Directorate as well as subprogram directors from

Page 24: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 17 -

executing institutions such as the Bureau of Finance and Economic Development, the Bureau of Trade, Industry, and Urban Development, the Bureau of Capacity Building, and the Bureau of Justice serves as the quality assurance and coordination body for PSCAP. Among other things, it will. § ensure the consolidated regional plans meet eligibility, appraisal, and other criteria prior

to their endorsement by regional cabinets and submission to the FTT (if needed, with the assistance of an additional technical expert who may be recruited on a temporary basis in appraising applications of a specialized nature, for example, those under the ICT component);

§ support the development of content of reform programs during implementation with the support of PPDs;

§ provide quality control on outputs produced by consultants prior to approving payment; § define equipment specification and undertaking acceptance tests of equipment procured; § develop communication and change management strategies; and § ensure the quality and consistency of reform efforts.

Planning and Programming Directorates (PPD) or Equivalents. Planning and programming directorates (PPDs) or equivalents, housed in BCBs, will serve as secretariats for PSCAP in regions and it will maintain close links with the federal PPD. Each regional PPD will be responsible for : § enforce overall PSCAP operating guidelines and relevant regional guidelines; § assist the RTT in the vetting of annual plans for quality and completeness; § ensure participatory planning processes are undertaken; § facilitate coordination between members of the RTT; § assist in consolidating, managing, and organizing the tendering of training across six

subprograms among pre-qualified supply institutions; § help the RTT provide detail follow-up and quality assurance during implementation; § implement communication and change management strategies; § consolidate quarterly, semi-annual, and annual progress reports; and § facilitate regional involvement in supervision and review missions.

Procurement Desks. Procurement desks, established within regional BCBs, are tasked with carrying out all relevant regional procurement activities for PSCAP. The desks are supported by at least two local procurement specialists and work closely with the beneficiary institutions. They shall: § vet and finalize TORs; § undertake preparation of technical specification and evaluation; § draft and negotiate contracts; and § manage contracts.

3.2.2 Bureaus of Finance and Economic Development (BOFED) In each region, the Bureau of Finance and Economic Development (BOFED) is responsible for all relevant financial management activities required under the Program. It will: § manage funds flows through Channel 1; § ensure monthly consolidation of Statement of Expenses;

Page 25: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 18 -

§ ensure the accuracy and timeliness of financial reporting; and § effect payments on local and foreign contracts in line with the recommendations of the

regional PPD.

3.2.3 Other eligible beneficiary institutions at regional and local levels Several regional institutions are eligible to receive support—in-kind including through asset transfer—under PSCAP and its six subprograms. These include sector bureaus (for example, for health, education, and infrastructure) as well as authorities and agencies within the executive branch; public sector training institutions such as Regional Management Institutes; the regional and local judiciary or the courts; audit and oversight bodies; and woredas and municipalities. The actual transfer of PSCAP resources from regions to woredas and municipalities is not currently envisaged at this stage, the bulk of PSCAP support is expected to be delivered in-kind at the local level. In order to ensure a close match between regionally managed activities and woreda and municipal level needs, the PSCAP planning process is expected to incorporate a sample of woreda and municipal development plans. Woredas and municipalities are expected to be informed about eligible expenditures under PSCAP so that capacity building activities (for example, accounts and budget reform roll out or bulk and hands-on training) are appropriately reflected in development plans. The introduction of PSCAP transfers from regions to woredas and municipalities will be considered at a more advanced stage of program implementation.

3.3 Joint Government-Donor Coordination and Review Mechanism A Joint Government-Donor PSCAP Working Group is established to support information sharing on capacity building, as well as joint preparation, appraisal, and supervision activities. On the Government’s, MCB and MOFED are primarily involved in supporting this harmonization agenda. From the donors’ side, members include AfDB, CIDA, DCI, DfID, EC, Finland, France, Germany, IDA, Italy, Japan, Netherlands, SIDA, UNDP, and USAID. The Group, co-chaired by the Government and IDA, will be instrumental in supporting a Sector Wide Approach with pooling of funds and when necessary through non-pooling provision of special technical assistance. It is envisaged that the donor chair will rotate. A more detailed Terms of Reference for the Working Group is attached in Annex 3. During implementation, participating donors will jointly undertake the review of annual plans during Annual Review Meetings as well as monitoring and supervision activities. Specific financial and procurement management requirements such as prior and post review will be carried out by pooling donors in line with IDA’s rules, as per the global guidelines on SWAPs. An Memorandum of Understanding detailing these arrangements will define the modalities for management of donor resources for PSCAP. Attached in Annex 4, the MOU inter alia details mechanisms for utilization of funds consistent with the pooling arrangements described in the financial section of the PIP. The Joint Government-Donor PSCAP Working Group will convene quarterly meetings to share information and identify issues for the two formalized supervision missions – one of which will coincide with the Annual Review Meeting. The formalized supervision missions and the annual reviews will take stock of progress made against targeted plans.

Page 26: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 19 -

Figure 3.1: Institutional Arrangements for PSCAP at the Federal, Regional, and Local Levels

M i n i s t e r o f C a p a c i t y B u i l d i n g (A c c o u n t a b l e t o C o u n c i l o f M i n i s t e r s )

• E n s u r e s r u l e -b a s e d a l l o c a t i o n a n d r e -a l l o c a t i o n , p l a n a p p r o v a l , a n d e x e c u t i o n• C o o r d i n a t e s a c r o s s l e a d c a b i n e t m i n i s t r i e s a n d a c r o s s r e g i o n s• A p p r o v e s P S C A P p l a n s a n d b u d g e t s f o r f e d e r a l a n d r e g i o n a l c o m p o n e n t s• A p p r o v e s m i d -y e a r a n d a n n u a l r e a l l o c a t i o n o f P S C A P “ r i g h t s”• R e p o r t s o n a c h i e v e m e n t o f a g r e e d s e m i-a n n u a l a n d a n n u a l o u t p u t s f o r P S C A P

F e d e r a l P P D a n d B F D

• E v a l u a t e a p p l i c a t i o n s a n d r e c o m m e n d a p p r o v a l o f p l a n s a n d b u d g e t s i n c l u d i n g ( r e ) a l l o c a t i o n b y r e g i o n , s u b p r o g r a m• U n d e r t a k e q u a l i t y a s s u r a n c e , M & E d u r i n g i m p l e m e n t a t i o n

F e d e r a l L e a d a n d E l i g i b l e I n s t i t u t i o n sF e d e r a l L e a d a n d E l i g i b l e I n s t i t u t i o n s

• S u b p r o g r a m a n d r e l a t e d o f f i c e s i n M C B , M F A , M O F E D , a n d M O R• S e c t o r i n s t i t u t i o n s , c o u r t s , a n d p a r l i a m e n t a r y i n s t i t u t i o n s

• S u b p r o g r a m a n d r e l a t e d o f f i c e s i n M C B , M F A , M O F E D , a n d M O R• S e c t o r i n s t i t u t i o n s , c o u r t s , a n d p a r l i a m e n t a r y i n s t i t u t i o n s

F e d e r a l T e c h n i c a l T e a m

R e g i o n a l P P D w / P r o c u r e m e n t D e s k

R e g i o n a l L e a d a n d E l i g i b l e I n s t i t u t i o n s , W o r e d a s , M u n i c i p a l i t i e s , a n d S u b- r e g i o n a l E l i g i b l e I n s t i t u t i o n s

R e g i o n a l L e a d a n d E l i g i b l e I n s t i t u t i o n s , W o r e d a s , M u n i c i p a l i t i e s , a n d S u b- r e g i o n a l E l i g i b l e I n s t i t u t i o n s

R e g i o n a l L e a d I n s t i t u t i o n s•S u b p r o g r a m o f f i c e s i n e l i g i b l e b u r e a u s c o o r d i n a t e p l a n n i n g p r o c e s s • M o n i t o r a n d s u p e r v i s e i m p l e m e n t a t i o n

W o r e d a a n d M u n i c i p a l L e a d I n s t i t u t i o n s• C a p a c i t y b u i l d i n g o f f i c e s c o o r d i n a t e p a r t i c i p a t o r y p l a n n i n g• M o n i t o r a n d s u p e r v i s e i m p l e m e n t a t i o n

R e g i o n a l L e a d I n s t i t u t i o n s•S u b p r o g r a m o f f i c e s i n e l i g i b l e b u r e a u s c o o r d i n a t e p l a n n i n g p r o c e s s • M o n i t o r a n d s u p e r v i s e i m p l e m e n t a t i o n

W o r e d a a n d M u n i c i p a l L e a d I n s t i t u t i o n s• C a p a c i t y b u i l d i n g o f f i c e s c o o r d i n a t e p a r t i c i p a t o r y p l a n n i n g• M o n i t o r a n d s u p e r v i s e i m p l e m e n t a t i o n

R e g i o n a l T e c h n i c a l T e a m

R e g i o n a l C a p a c i t y B u i l d i n g B u r e a u H e a d sA c c o u n t a b l e t o R e g i o n a l C a b i n e t s f o r :

• E n d o r s e s p l a n s a n d b u d g e t s• E n s u r e s a p p r o p r i a t i o n o f r e g i o n a l c o n t r i b u t i o n s f o r i n f r a s t r u c t u r e a n d r e c u r r e n t c o s t s • R e p o r t s o n a c h i e v e m e n t o f a g r e e d s e m i-a n n u a l a n d a n n u a l o u t p u t s a n d r e s u l t s f o r t h e R e g i o n ’ s P S C A P

M i n i s t r y o f F i n a n c e a n d E c o n o m i c D e v e l o p m e n t

B u r e a u s o f F i n a n c e a n d E c o n o m i c D e v e l o p m e n t

I n d i c a t i v e r e s o u r c e e n v e l o p e s o r a p p r o v a l s

P l a n s a n d p r o g r e s s r e p o r t s

A c t u a l f u n d s f l o w s o r i n- k i n d t r a n s f e r s

• D i v i d e s P S C A P r e s o u r c e s v e r t i c a l l y a n d h o r i z o n t a l l y , i s s u e s f o r m u l a -b a s e d d r a w i n g r i g h t s

• M a n a g e s s p e c i a l a n d p o o l e d B i r ra c c o u n t , c l o s e s B i r r s u b p r o g r a m a n d r e g i o n a l a c c o u n t s

• R e l e a s e s f u n d s a c r o s s f e d e r a l a n d r e g i o n a l b o d i e s a g a i n s t S O E s

• I s s u e s b u d g e t s t o l e a d i n s t i t u t i o n s i n c o n s u l t a t i o n w i t h B C B

• S e e k s r e p l e n i s h m e n t o f b a s e d o n m o n t h l y c o n s o l i d a t e d S O E s u b m i s s i o n s t o M O F E D

• E f f e c t s p a y m e n t s o n c o n t r a c t s b a s e d o n B C B a p p r o v a l

• S u b m i t s t i m e l y f i n a n c i a l r e p o r t s

• I s s u e s a n d e n f o r c e s g u i d e l i n e s• S u p p o r t F T T i n p l a n n i n g , i m p l e m e n t a t i o n• C o n s o l i d a t e s p r o g r e s s r e p o r t s• P r o c u r e s f o r C S R P , D L D P , J S R P a n d I C B f o r g o o d s f o r P S C A P o v e r a l l

• E v a l u a t e a p p l i c a t i o n s a n d r e c o m m e n d a p p r o v a l o f p l a n s a n d b u d g e t s i n c l u d i n g ( r e ) a l l o c a t i o n b y r e g i o n , s u b p r o g r a m• U n d e r t a k e q u a l i t y a s s u r a n c e , M & E d u r i n g i m p l e m e n t a t i o n

• I s s u e s a n d e n f o r c e s g u i d e l i n e s• S u p p o r t R T T i n p l a n n i n g , i m p l e m e n t a t i o n• C o n s o l i d a t e s p r o g r e s s r e p o r t s• U n d e r t a k e s r e g i o n a l p r o c u r e m e n t f o r a l l s i x s u b p r o g r a m s

Page 27: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Section 4. Resource Allocation and Management This section describes the fiscal design feature of the Program, specifically, how the resource allocation and management system underpinning PSCAP aligns with the Ethiopian fiscal system. Provided bellows are the rules of access and allocation for drawing rights; its appraisal criteria for plans from federal and regional institutions; its planning, budget, and execution system with the Government’s public financial management (including the chart of accounts and financial calendar); and finally, PSCAP’s performance-oriented execution and reallocation guidelines. A summary of the planning, budgeting, and execution cycle, in accordance with the financial calendar, is provided in Table 4.1. 4.1 Specific-Purpose Federal Program As a specific -purpose federal program, PSCAP serves as a pillar of Ethiopia’s evolving intergovernmental fiscal system. The Program allocates five-year drawing rights to additional federal resources across federal and regional beneficiary institutions. Failure to utilize these time-bound rights results in their reallocation from poor performers to high performers within a given fiscal year and across fiscal years. These performance-oriented features of PSCAP represent an important innovation in terms of the design of fiscal transfers within the Ethiopian public finance system. At the same time, the basic planning, budgeting, and execution system of Program is fully with the requirements of the Government’s public financial management as well as its SDPRP monitoring systems. Federal and regional institutions participating in PSCAP use the Government’s chart of accounts for financial reporting, comply with the financial calendar for issuance of resource ceilings, prepare rolling medium-term and annual plans in line with established procedures, disburse funds on a reimbursable basis against SOE submissions, and finally, submit financial and physical progress reports. Alignment with the Government’s system is designed to ensure that the planning and execution of capacity building activities is undertaken in a flexible manner in line with the changing demands on the ground. It is also intended to improve the accountability framework within which public sector capacity building activities at the federal, regional and local government levels are financed and implemented in GOE’s state transformation process. 4.2 Budget Classification of PSCAP Expenditures The Government of Ethiopia’s Chart of Accounts will be utilized to plan, budget, and report on PSCAP expenditures. Specifically, Cabinet will proclaim PSCAP annually in the GOE budget as a program under the MCB, which is designated as a public body. Allocations to the 6 eligible federal institutions and the 11 regions will be proclaimed under PSCAP subject to mid-year reallocations based on performance.

4.2.1 Coding and Classification of the Federal Component PSCAP budget coding and classification for the federal level allocation will be structured as follows: (a) Public Body codes will be designated as “Ministry of Capacity Building”; (b) Program code will be designated as “Public Sector Capacity Building”; (c) Sub-Agency codes will only be designated for the CSRP, DLDP and JSRP as “Planning and Programming Directorate; (d) Subprogram codes will be designated as Ministry of Revenue; Ministry of Federal Affairs; Ministry of Finance and Economic Development; Information, Communication Technology Development Authority and Federal Supreme Court; and (e) Project code will be

Page 28: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 21 -

designated for each subprogram (i.e. Urban Management and Reform Project, Tax Systems Reform Project, Information & Communications Technology Reform Project, Civil Service Reform Project, District Level Decentralization Reform Project, Justice Systems Reform Project, and Program Support Project).

4.2.2 Coding and Classification of the Regional Component PSCAP budget coding and classification for the regional level allocation will be structured as follows: (a) Public Body code will be designated as “Ministry of Capacity Building”; (b) Program code will be designated as “Public Sector Capacity Building”; (c) Sub-Agency code will be designated; (d) Subprogram code will designated for each region (i.e. Tigray Public Sector Capacity Building, Afar Public Sector Capacity Building, Amhara Public Sector Capacity Building, etc.); and (e) Project Code will be designated for each regional subprogram (i.e. Civil Service Reform Project, Justice System Reform Project, Tax Systems Reform Project, Urban Management Reform Project, Information & Communications Technology Reform Project, District Level Decentralization Reform Project, and Program Support Project).

4.3 Rules of Access (Eligibility Criteria) PSCAP is envisaged as a nation-wide program, designed to help remedy the severe public sector capacity constraints at the federal, regional, and local levels. To ensure the consistency of PSCAP activities undertaken by a wide array of beneficiaries with national policies and priorities, the Government has established clear rules of access. These access rules or eligibility criteria are detailed below and should be met by federal executing institutions as well as regions before their annual implementation plans can be considered for financing under the Program:

§ submission of signed “Participation and Performance Agreement” by the relevant minister responsible for federal subprogram or relevant cabinet member for region (sample participation and performance agreements are included in Volume 2 of this PIP);

§ Establishment of appropriate governance and implementation arrangements; § completion of relevant capacity assessments across all participating sectors and levels of

participating institutions, especially in the case of woreda and municipa l strengthening; § timely submission of endorsed costed medium-term rolling plans, as well as technically

sound, feasible annual implementation/procurement plans in line with financial calendar; § explicit provision for evaluation of annual performance including dissemination to the

public of such evaluations, satisfaction score cards, etc, as part of the consultative planning process.

4.4 Incorporation of Inputs from Various Nation-Wide Reviews As key inputs to the PSCAP planning, budgeting, and execution process, several review processes should be underway at the close of any given fiscal year. Specifically, the Government is responsible for consolidation of PSCAP outturn data (based on Statements of Expenditures) for the previous year by subprogram and region. These data are compiled in the form of a consolidated physical and financial report by the Planning and Programming Directorate and submitted as an input to the Joint Annual Performance Review Mission (ARM) no later than September 30. The ARM for PSCAP is held not later than October 1 each year and its findings—widely distributed—should serve as inputs to the SDPRP Annual Progress Report (to be issued in late October each year) as well as the annual multi-year planning exercise for PSCAP (see below).

Page 29: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 22 -

4.5 Fiscal Framework: Projecting and Dividing PSCAP Resources Over the Medium Term Each year, during the Government’s multi-year planning exercise, the Ministry of Finance and Economic Development (MOFED)—in close consultation with the Ministry of Capacity Building (MCB)—will ensure the medium-term projections of available PSCAP resources from external and Government resources—estimated in Year 0, February 2004, to be approximately Birr 3.3 billion over the 5 year planning period—are appropriately reflected in the Macro-Economic and Fiscal Framework (MEFF), which is prepared no later than October 26. Once the overall available pool of resources available over the medium-term has been established, both Ministries will initiate a formal dialogue with Executing Agencies and other relevant PSCAP stakeholders on the vertical and horizontal division of resources and issue revised medium-term indicative planning figures for federal subprogram and regions no later than November 10. Guidelines for the vertical and horizontal split are described below and should provide the basis for joint Government-donor review:

4.5.1 Vertical Division of PSCAP Resources Into Five-Year Drawing Rights

During program preparation, an original 80-20 percent vertical division of PSCAP resources (drawn from domestic and donor sources) over five years was effected between regional and federal levels of government respectively. Each year, the actual allocations for federal and regional components of PSCAP should be revised on changes in resource projections. Changes in the proportions between federal and regional allocations (i.e., the 80-20 split) should be undertaken in a transparent manner, in dialogue with federal and regional authorities, no more frequently than once a year, and on the basis of clear criteria such as the previous year’s performance as well as existing multi-year commitments at federal and regional level.

4.5.2 Horizontal Split of the Regional PSCAP Component Into Five-Year Drawing Rights

Once the vertical split has been reviewed each year, a horizontal split of the regional component is undertaken on the basis of the established formula for the federal-regional subsidy as well as re-pooled drawing rights which high performers could draw down. The formula consists of three factors—the region’s population, its level of development gap, and its previous years’ own revenue performance—weighted at 65%, 25%, and 10% respectively. During program preparation, the above-mentioned formula was applied and five-year drawing rights were assigned to each region. In future years, the formula will be reviewed and revised as necessary and any changes or modifications will be made on the basis of extensive consultations, and widely publicized to all regions and related beneficiaries.

4.6 Rolling Medium-Term Planning for PSCAP

4.6.1 Planning PSCAP Activities As Part of Ethiopia’s Public Investment Program As one of the Federal Government’s major capital spending initiatives, PSCAP is reflected within the Government’s Public Investment Program. PSCAP planning is therefore integrated and aligned with the Public Investment Program preparation timetable, as laid out in the financial calendar. Accordingly, following the issuance of revised indicative medium-term planning figures, federal EAs and regions (under the guidance of their Regional Technical Teams)

Page 30: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 23 -

undertake and submit to the PSCAP Federal PPD their revised and appropriately costed rolling five-year PSCAP Action Plans no later than December 25. As noted in the eligibility criteria, the revisions of these plans should be undertaken in a participatory manner involving consultations with various regional and local stakeholders. Furthermore, revised PSCAP Action Plans should reflect the public sector capacity building priorit ies identified in woreda and municipal development plans. A sample of these local level development plans should be submitted to RTTs and the FTT as a basis for verifying, over time, that national capacity building priorities are being systematically fitted to local priorities.

4.6.2 Annualizing Multiyear Drawing Rights to Arrive at the Annual Fiscal Plan Revised PSCAP Action Plans should also include proposals from EAs, especially regions, on how they intend to annualize five-year drawing rights (or remaining drawing rights in subsequent years of program implementation). Annualization of drawing rights in any given year shall clearly defined rules to ensure that utilization of PSCAP resources follows overall projected disbursement rates over the five-year life of the Program. These are as follows:

§ the overall annual disbursement profile (as percentage of commitments) agreed with the

largest donor (in this case, IDA) in any given year shall serve a standard minimum percentage that each region applies to its remaining drawing rights to arrive at an annual proposed budget for that year (For example, in year 1, IDA’s first year disbursement profile of approximately 10% will be the minimum percentage that each region can propose for utilization of its five-year drawing right in year 1. The proposed budget for any participating region can therefore be no less than 10% of its five-year formula-driven resource envelope for PSCAP);

§ regions may propose to utilize more than the minimum standard percentage of their drawing rights in any given year, but should do so after considering the capacity required to execute the Program and utilize allocate resources at an accelerated pace;

§ the proposed annual utilization rate for a region’s drawing rights shall provide the basis for the region’s annual disbursement profile, its cash flow projection, and therefore, the benchmark against which mid-year and annual reallocation procedures will be applied.

4.6.3 Arriving at the Annual Fiscal Plan

The Federal Technical Team (FTT), MCB, and MOFED review and finalize revised medium-term consolidated PSCAP Action Plans (by federal and regional components) no later than February 8. As part of this exercise, on the recommendation of the FTT, both ministries finalize the Annual Fiscal Plan for PSCAP part of the Government’s overall fiscal plan) no later than January 24.

4.7 Budgeting Process

4.7.1 Submitting Annual Budgets with Implementation Plans Based on the Annual Fiscal Plan (i.e., the annualized drawing rights), federal EAs will prepare their PSCAP budgets along with annual procurement plans no later than March 1. These are submitted to the FTT via the Planning and Programming Directorate (PPD) for appraisal and review. Similarly, regions submit their annual budgets with implementation plans (i.e.,

Page 31: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 24 -

elaborated procurement plans) to the Federal PPD no later than February 22 so that their Regional Technical Teams can pre-appraise, review, endorse, and submit their plans to the FTT no later than March 1. Regional Technical Teams, under the guidance of respective BCBs, are expected to have prepared their matching budgets for PSCAP activities (for example, for civil works and O&M) at the same time.

4.7.2 Appraising Annual Implementation Plans

The FTT then reviews and appraises annual implementation plans under the federal and regional components against the following appraisal criteria established within and across subprograms:

§ relevance of planned activities given existing assessments is established, as well as

provisions for additional assessment where required are included; § inclusion of the “minimum mandatory” capacity building—especially with regard to

financial management, procurement, and related program support activities—is established as a necessary precursor to any more advanced activities;

§ demonstration that civil works required to house any goods (e.g. especially ICT) are in place, and that budgetary provisions have been made for additional upfront civil works and ongoing recurrent as well as operations and maintenance requirements of goods procurement;

§ evidence that annual plans are based on consultation with key stakeholders including local governments, regional bureaus, communities, and other stake holders, and that this consultative planning process becomes increasingly “bottom up” in each successive year as evidenced by steadily increasing numbers of woreda and municipal action plans, formal public consultations, participation of reference and focus groups in the planning process;

§ sector-specific criteria such as sequencing, the previous year’s performance, and the submission of relevant TORs; and

§ explicit focus on issues related to gender and HIV/AIDS mitigation.

The FTT, through the PPD, shall provide comments and suggest revisions in federal and regional plans as a basis for finalizing annual implementation and procurement plans. Once revised, the plans should be submitted to IDA for no objection no later than March 15. The FTT finalizes these plans for the federal and regional components no later than March 22 for review by the State Minister and Minister of Capacity Building. Any proposed adjustments to the final FTT recommendations will be communicated to members of the donor community through the regular joint review mechanisms.

4.7.3 Submitting the Overall PSCAP Annual Budget and Implementation Plan to Cabinet The Minister of Capacity Building will submit PSCAP’s annual plan for the Year Y+1 along with the overall budget to the Council of Ministers no later than May 22. Matching requirements in regional budgets (for civil works and recurrent costs) will be submitted to regional cabinets at the same time. The Cabinets should recommend the federal and regional budgets inclusive of PSCAP budgets no later than June 2. Approval and adoption by federal and regional legislatures will be undertaken roughly between June 8 and July 2, in anticipation of the coming fiscal year.

Page 32: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 25 -

4.8 Execution Once proclaimed and allocated, execution of PSCAP budgets begin at the start of the FY on July 8. Following an initial release to cover implementation-financing requirements for up to the first quarter, funds are released to federal and regional EAs for monthly reimbursement against consolidated SOEs. Detailed procedures for submission of replenishment requests are provided in the following section. 4.9 Reallocation The performance oriented features of this federal specific program are enshrined in its unique reallocation procedures that will be apply to under-utilized five year drawing rights

4.9.1 Reallocation Across Year: Applied Five-Year Drawing Rights At the end of each year, up to 50% of the five-year drawing rights of individual regions will be subject annual reallocation from poor performers to high performers. Reallocation recommendations by the PSCAP Federal Technical Team will comply with the following rules and be clearly communicated to all stakeholders:

§ a cut-off point of fund utilization (as evidenced by SOE replenishment requests), 75%

in both cases, will be established. Regions performing above this cut-off point are not subject to reallocation.

§ a minimum entitlement equivalent to 25% of the approved annual plan in any given year will be established for all regions to ensure that under-performers continue to have incentives and resources to establish a the minimum statutory level of capacity.

§ at end-year, poor performers or those with 25% or less of fund utilization (as evidenced by SOE replenishment requests) will have 50% of their remaining five-year drawing rights re-pooled and reallocated to high performers purely on the basis of performance ranking;

§ reallocation decisions shall be published and communicated to all stakeholders in a transparent manner and shall be reflected as adjustments to overall five-year drawing rights.

Annual reallocation decisions will be effected in the content with the planning and annual budgeting cycles described above and will therefore comply with the timetables and other relevant procedures appertaining thereto.

Page 33: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 26 -

4.9.2 Reallocation In-Year: Applied to Annualized Drawing Rights PSCAP also envisages mid-year reallocation of annualized drawing rights, i.e., a re-appropriation between regions within a federal budget line. Key performance criteria used as a basis for these in-year adjustments are SOE submissions and activity-based progress reports. Accordingly, federal executing institutions and regions submit their consolidated reports on year-to-date SOE submissions and activity-based performance, as well as projected budget utilization through the end of year Y to the Federal Technical Team (FTT) no later than January 22. The FTT will recommend in-year reallocations across regions on the basis of the following rules (similar to those applicable for annual reallocation), which are to be clearly reiterated to all regions and federal institutions at the start of each year:

§ a cut-off point of fund utilization (as evidenced by SOE replenishment requests), 75%

of projected a given year’s cash flows in both cases, will be established. Regions performing above this cut-off point are not subject to reallocation;

§ a minimum entitlement equivalent to 25% of the approved annual plan in any given year will be established for all regions to ensure that under-performers continue to have incentives and resources to establish basic levels of capacity;

§ at mid-year, poor performers or those with 25% or less of fund utilization (as evidenced by SOE replenishment requests) will have 50% of their remaining annualized drawing rights re-pooled and reallocated to high performers;

§ in-year reallocations will be reflected in readjustments to the annual and five-year envelopes;

§ access rules for high performers seeking to draw down on re-pooled drawing rights are the submission of revised plans (with revised projections for utilization through end-year), compliance with financial and physical reporting requirements, and satisfactory achievement of the in-year cut-off point.

Box 4.1: Measuring Execution In-Year and Across Years for the Purposes of Reallocation

Over the course of program preparation, a broad range of measures was developed to track financial and physical performance and their proximate impact of on institutional quality outcomes. An M&E framework was developed based on these discussions and is presented in Section 7. For the purposes of reallocation in-year and across years, however, Ethiopia’s own experience with Sector Development Programs and that of other countries implementing large-scale intergovernmental transfer programs suggests that PSCAP requires an easily understood measure of execution for the purposes of making objective reallocation decisions within and across fiscal years. The Government therefore plans to use replenishment requests for Statements of Expenditures (SOEs) by Executing Agencies at the federal and regional level is the simplest indicator of fund utilization against planned expenditures, and providing summary information on actual implementation activity (for example, specific types of training, completion of consultancies, purchase of goods). It is important to note that this measure cannot replace a full-fledged financial and physical monitoring system. Nor can it replace much more in-depth supervision and evaluation of activities, outputs, and outcomes. The mechanisms for M&E more broadly are discussed in Section 7.

Page 34: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 27 -

The FTT will hold discussions with regions on its review and recommendations for in-year reallocation between regions within annualized budgets no later than February 8. Following these discussions, the reallocation proposal will be submitted for no objection by IDA on February 15, and then MCB and MOFED issue in-year reallocations between regions and federal institutions no later than February 22.

4.10 The Supplemental Budget and High Performers

In the case in-year reallocations prove insufficient for high performers, MCB may seek to draw down on future years’ annualized drawing rights or allocations. In such cases, high performers should demonstrate nearly full (over 85%) utilization of annual drawing rights and realistic projections for utilization that exceed available resources from in-year reallocation.

Once reviewed by the Federal Technical Team, the proposed use of future annualized drawing rights (financed in part of fully through IDA support) through the Government’s supplemental budget mechanism should be submitted to IDA for no objection. Following IDA’s no objection and finalization by the MCB, allocations within the supplemental budget for high performers will be finalized and communicated to the EAs in question as well as all other stakeholders involved in PSCAP.

Page 35: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Table 4.1: PSCAP’s Alignment with the Financial Calendar—the Planning, Budgeting, and Execution Cycle

Dates Cycle/Stage Government Actions Multi-Donor Actions I. PLANNING

July 8- Sept 30 Consolidation of budget and outturns

1. Consolidation of PSCAP outturn data by subprogram and region for Year Y-1 2. Preparation of consolidated report on physical and financial performance as input to Joint Annual Performance Review Mission no later than 30 Sept

Oct 1 Joint Annual Review

Mission Findings submitted for multi-year planning and SDPRP Annual Progress Report no later than 1Nov

Participate in ARM for PSCAP

Oct 30 SDPRP Annual Progress Report

1. APR published and widely distributed including inputs from Annual Performance Review Mission on PSCAP

July 8- Nov 10

Multi-year planning including findings of annual performance reviews for PSCAP

1. Joint Annual Performance Review Mission findings and data collection on PSCAP indicators no later than Sept 30 2. Preparation and approval of MEFF inclusive of available PSCAP resources for Y+1, Y+2, Y+3, etc. no later than 26 Oct 3. Regional and Federal dialogue on vertical and horizontal division of PSCAP resources including Federal Technical Team’s recommendation on reallocation of five-year drawing rights, and issuance of revised medium-term indicative planning figures for federal subprograms and regions no later that Nov 10

Review and verify methodology for vertical and horizontal split

Nov 11 – Feb 8 Public Investment

Program preparation, inclusive of PSCAP

1. Federal executing institutions and regions undertake and submit revisions of rolling five-year plans within revised medium-term envelopes no later than Dec 25 2. Federal Technical Teams, MCB, and MOFED review and finalize revised medium-term plans no later than Feb 8 3. Annual Fiscal Plan for PSCAP (as part of overall fiscal plan) finalized by MOFED and MCB no later than Jan 24

Review of annual fiscal plan for PSCAP with other Direct Budget Support Donors

III. BUDGETING A. Budget Preparation

Feb 8- Mar 22 Submission of PSCAP annual budget requests

1. Federal executing institutions submit their PSCAP budgets including preparation of first year procurement plan within annualized drawing rights no later than Mar 1 2. Regional Technical Teams review, finalize, and endorse annual budget submissions to Federal Technical Team no later than Mar 1 3. Federal Technical Team reviews, finalizes, and recommends overall annual budget for PSCAP no later than Mar 22

Review and no objection by IDA on annual procurement plan(s)

Page 36: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

Mar 23-May 22

Preparation of Recommended Federal Budget and Matching

Regional Budgets

1. Overall budget recommendation to Council of Ministers inclusive of PSCAP is made at the federal level 2. Matching requirements in regional budgets (i.e., for civil works and ongoing recurrent expenditure implications of PSCAP) recommended to cabinets

May 23 – Jun 2 Budget Recommendation

1. Council of Ministers reviews recommended budget inclusive of PSCAP and approves no later than Jun 2 2. Regional cabinets review and recommend matching budget requirements for PSCAP and approves no later than Jun 2

B. Legislative Adoption and Appropriations

Jun 8 – Jul 2 1. Approval by Federal and Regional legislatures of recommended budget

inclusive of PSCAP

C. Budget Implementation and Mid-year Reallocation of PSCAP funds Jul 8 – Jul 14 1. Notification of proclaimed federal and regional budgets

Jul 8 – Aug 15 1. Allocation of proclaimed federal and regional budgets Jul 8 – Jul 6 1. Execution of proclaimed budget

Jan 8 – Feb 8

Mid-year reallocation process for PSCAP

1. Federal executing institutions and Regional Technical Teams submit consolidated report on in-year SOE and activity-based performance and projected utilization through end of year Y to Federal Technical Team no later than Jan 15 2. Federal Technical Team dialogues with regions on its review and recommendations for in-year reallocation between regions within annualized budgets for year Y no later than Feb 8 3. MCB and MOFED finalize and issue in-year reallocation between regions and federal executing institutions no later than Feb 22 4. Proposals for use of supplemental budget by high performers should be submitted to IDA for no objection, and finalized by MCB in line with relevant financial management regulations

Review and no objection by IDA of in-year reallocation proposals

Dates Cycle/Stage Government Actions Multi-Donor Actions

Page 37: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 30 -

Section 5. Financial Management The financial management section provides an overall guidance for the financial management and disbursement. Detailed instructions for all aspects of the financial management including commitments, disbursements and all other financial transactions such as funds transfers and advances, asset management, accounting, internal controls and auditing are provided in the more detailed Financial Reporting Guidelines, attached as Annex 1. 5.1 Roles and Responsibilities for Financial Management The overall coordinator of the program at national level is the Ministry of Capacity Development (MCB). The Bureaux of Capacity Building in regions are the coordinators of the program in their respective regions. The Ministry of Finance & Economic Development (MoFED) is responsible for the overall financial management aspect of the program. It opens accounts for the program, receives funds from the donors, release funds to beneficiaries, collect reports from the beneficiaries and consolidate and report on the use of funds to donors, government and other stakeholders. At regional level, Bureaus of Finance & Economic Development (BOFEDs) perform the same activity. Table 5.1: Delegation of Major Responsibilities

Activity Responsible Body The agreed proportion of the government’s budget for PSCAP is transferred to the Pooled Birr Account.

MOFED based on instructions by MCB Budget & Directorate

FOREX accounts for the IDA and other donor contributions are opened at the National Bank of Ethiopia

MOFED

Withdrawal application for the initial deposit to the FOREX accounts is prepared

MOFED Counterpart Fund Unit (CFU) in consultation with PPD

Actual contributions from IDA and Donors are received

MOFED will receive in the appropriate Bank accounts on behalf of GOE

Agreed proportion of donors’ contributions are transferred to the Pooled Birr Account

MOFED CFU will effect in consultation with MCB

Project Accounts are opened • MCB Budget & Finance Directorate for Civil Service Reform, District-Level Decentralization and Justice Reform Subprograms

• Information & Communication Technology Development Authority (ICTDA) PMU for the Information & Communications Technology Reform (ICTR) subprogram

• MOFED for the Expenditure Management and Control Coordinating Office

• Ministry of Revenue Tax Systems Reform Program Office for the Tax Systems Reform subprogram

• Ministry of Federal Affairs UDCB Office for the Urban Development Capacity Building subprogram

• Federal Supreme Court for the Court Reform • Bureaus of Capacity Building (BCBs) in each region

Agreed proportions from the Pooled Birr Account are transferred to various project accounts at federal and regional level

MOFED CFU upon instructions by PPD

Closing of Accounts MOFED Central Accounts

Page 38: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 31 -

5.2 Accounting Policies and Procedures PSCAP financial management will be aligned with the general principles of the Sector-Wide Approach whereby the program will align resource allocation, planning, budgeting, and execution practices and procedures with those established under Ethiopia’s public financial management regulations. The federal and regional institutions participating in the Program shall use Government’s Chart of Accounts for financial reporting with few additional codes described in the Financial Reporting Guidelines; comply the financial calendar for issuance of resource ceilings, prepare rolling medium-term and annual plans in line with established government procedures, disburse funds on a reimbursable basis against SOE submissions, and finally, submit financial and physical progress reports. The Financial Reporting Guidelines provide detailed instruction on the accounting policies and procedures, Chart of Accounts, financial reporting and auditing arrangements. 5.3 Funding Mechanisms PSCAP resources will flow to federal and regional beneficiaries through Channel 1 method as a single flow specific purpose grant through MOFED. Under the Channel 1 procedure, each beneficiary controls the release of funds and reports upward on their utilization. The same principles apply to both recurrent and capital budgets. Pooling of resources has been agreed as the main modality for PSCAP. However, the funds from IDA have been allocated in two ways: (a) Pooled Category: and (b) Non-Pooled Category. The latter has been setup in order to allow the government to use IDA funds immediately even prior to the finalization of the agreements with other Donors on Pooling.

5.3.1 Non-Pooled Resources

The IDA non-pooled category will be disbursed on the basis the traditional disbursement method for disbursing IDA funds, that is, based on Special Account, SOE procedures and direct payment procedures. To ensure that parallel and differing SOE and disbursement procedures are not introduced under the Program, the government and the Bank will ensure that disbursement from the Non-Pooled Funds category will cease, and remaining funds reallocated to the Pooled Funds category once utilization of the pooling arrangements is initiated.

5.3.2 Pooled Resources

As a basis for disbursing IDA funds from the Pooled Funds category, the government, the World Bank, and relevant pooled donors (or cooperating partners) will need to (i) execute an MOU as well as annual Side Agreements governing the proportion of expenditures to be replenished by respective cooperating partners, and (ii) SOE format with sufficient detail indicated in the Financial Guideline will be used to replenish the Special Account for pooled fund.

Accordingly, for each donor, including IDA, MOFED will open a Special Account (SA) in US Dollars at the National Bank of Ethiopia. In addition, MOFED will open one Birr account—the “pooled account”—for which money from the SAs and the government contribution will be deposited. The Birr account will serve as a consolidated fund for all donors and the government. MOFED will be responsible for the day-to-day management of the SAs and the pooled Birr account. Funds will be moved from the Foreign Exchange Special Accounts in the National Bank of Ethiopia to the Pooled PSCAP Account, and forwarded to the beneficiaries, based on the approved budget and agreed disbursement plan. Thus, released funds of one donor can be

Page 39: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 32 -

replenished from another donor on the basis of claims made. Although donor funds will be allowed to be kept in SAs in foreign currency, they will be transferred into Birr as soon as they are to be used and sent to the regions to cover anticipated expenditures. Part of the donor funds, however, will be kept in foreign exchange to be disbursed at the request of MCB and the regional capacity building bureaus through their regional finance bureaus. These funds will be drawn from the particular region’s allocation and be used to cover the costs of imported goods.

5.3.3 Initial Advance and Replenishment of Forex Accounts from Donors to MoFED In the case of IDA funds, the initial advance to the FOREX Account (Special Account) will be based on a proportion of the estimated expenditures shown in the Annual Work Plan and Budget. Subsequent replenishments to the FOREX Account will be made on the basis of Statement of Expenditures (SOEs) that will be compiled, consolidated and submitted by the CFU to the donors. 5.3.4 Funds Flow from MOFED to Beneficiaries The starting point for the funds flow process is the final approval of the detailed annual plans and budget for the fiscal year around June of each year (the planning and budgeting cycle is explained in the previous section). The approved annual plans with the corresponding budget envelopes will be circulated to all concerned. At the regional level, the consolidated plan and budget will be monitored by the Regional Bureaus of Capacity Building (BCBs) while the consolidated plan and budget at the Federal level will be monitored by the Planning and Programming Directorate (PPD). The latter will continuously coordinate and guide the BCBs in monitoring these budgets. Bureaus of Finance and Economic Development (BoFEDs) will receive funds based on the annual program and budget provided by MOFED in the same way as they currently receive budgets for salaries. MOFED will disburse funds through BoFEDs. At the Federal Level, relevant federal executing agencies (i.e. MOFED, MCB, ICTDA, MFA, MOR and Federal Supreme Court) will also receive funds directly from MOFED.

The initial amount that will be released to the relevant institutions by MOFED will be equivalent to the first quarter’s requirements as indicated in the approved PSCAP annual action plan. Funds will be moved from the Pooled Birr Account and forwarded to the executing agencies at the federal level and BOFEDs who will effect the payments based on the approved budget and agreed procurement plan. Subsequent replenishments will be released monthly by MOFED to implementing agencies after the submission by the latter of a Disbursement Request approved and cleared by MCB accompanied by the monthly reports according to the format presented in the Financial Reporting Guidelines.

5.4 Financial Performance Assessment.

A Financial Performance Assessment (FPA) should be conducted in May/June and November/December each year. The FPA can be part of the semi-annual review process. The FPA will be used to: (a) determine whether there is continuing sufficient accounting capacity across federal and regional beneficiaries; (b) verify expenditures using relevant supporting documentation; (c) conduct physical inspection of investments; (d) review the status of audits; (e) review cash-flow forecasts; (f) review reports of transfers of funds from PSCAP; and (g) assess compliance by with program objectives.

Page 40: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 33 -

5.5 Auditing The Office of the Auditor General (OFAG) is the independent External Auditor for all program expenditures from donors and Government budgets – national and regional. The scope of the audit by OFAG will be based on the sample TOR attached to Volume 2 of PIP. Audits are conducted at the end of every fiscal year of program activity and will cover all PSCAP expenditures including those from federal and regional budgets, those provided in the form of commodities and personnel, and

those passing through sector ministries. The financial year of PSCAP is that of the Government, from July 8 to July 7. The accounts are closed on the last day of the financial year, Sene 30 (July 7) of every calendar year. 5.6 Internal Controls At all levels, wherever expenditures are made or committed, there needs to be put in placer an effective internal control system. An audit can identify problems after they have occurred, while an internal control system prevents the problems from occurring in the first place. The general principles for effective internal control mechanisms are as follows:

First, the control environment consists of the actions, policies and procedures that reflect the overall attitude and awareness of the senior management regarding the importance of control. The control environment includes: (a) the organizational structure of project management; (b) methods of assigning authority and responsibility; (c) management supervision and methods for monitoring performance; (d) the internal audit function; (e) personnel policies and practices; and (f) external influences, such as regulatory bodies.

Second, it is important to ensure that the Program is run with financial efficiency and integrity. These steps constitute the internal controls for the project and will comprise of policies and procedures

Figure 5.1: Funds Flow and Reporting Arrangements under PSCAP

P S C A P Pooled Local Currency Account

a t NBE/CB (MOFED)

P S C A P Pooled Local Currency Account

a t NBE/CB (MOFED)

Government of EthiopiaContribution

Local Current Accounts(Lead federal institutions)Local Current Accounts

(Lead federal institutions)Local Currency Accounts

(Regional BOFEDs )Local Currency Accounts

(Regional B O F E D s)

IDA Special Account in USDa t N B E ( M O F E D )

IDA Special Account in USDat NBE (MOFED)

One Special Account in USDfor each other pooling donor

a t N B E ( M O F E D )

One Special Account in USDfor each other pooling donor

a t NBE (MOFED)

IDA Credit Account Washington, DC

Reporting on expenditures

Flow of funds

Page 41: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 34 -

adopted by management to assist it in achieving its objectives of ensuring, as far as possible, the orderly and efficient conduct of its operations, including: (a) adherence to management policies, laws and regulations; (b) safeguarding of assets; (c) prevention and detection of fraud and error; (d) promoting orderly, economic, efficient and effective operations; (e) accuracy/completeness of records; and (f) timely preparation of financial information.

Third, systems of internal control for the Program should ensure that: (a) every transaction that should have been entered into the accounting system is recorded; (b) no unauthorized transactions are recorded; (c) those transactions that are entered are analyzed and posted correctly; (d) source programs, which control the operation of the accounting system (original entry and subsequent analysis and postings), cannot be tampered with; (e) unauthorized access is denied; (f) assets of the entity are neither misappropriated nor used in an uneconomical or inefficient fashion; (g) management policies (in budgets, long-range forecasts, etc.) are complied with; (h) deviations from plans are noted, investigated and timely responses made; (i) financial information is communicated in the most effective way so that those entitled to it may maximize their use of it; and (j) the financial statements show a true and fair view.

Page 42: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 35 -

Section 6. Procurement Management This section lays out the roles and responsibilities at the federal and regional levels, as well as the various policies and regulations governing procurement management under the Program. Detailed instructions on the policies and procedures governing procurement, particularly those related to IDA rules, are provided in Annex 2 of Volume I of the PIP. 6.1 Procurement Management & Operations

6.1.1 Federal Level Procurement Management Responsibilities

Ministry of Capacity Building. Budget and Finance Directorate will be responsible for the overall procurement monitoring and international procurement of goods under the program. In addition, the Directorate will provide procurement support to the three federal level sub-programs housed in MCB, namely the civil service reform (CSRP), justice system reform (JSRP) and district level decentralization (DLDP). It will work closely with CSRP, DLDP and JSRP Offices in finalizing the TORs and specifications, technical evaluation and drafting of contracts. Two (2) local procurement specialists and one (1) international procurement adviser will support the Department. The BFD shall:

§ coordinate and monitor procurement implementation across the federal and regional levels; § facilitate procurement training for implementing agencies through the international procurement

specialist housed in MCB; § provide regions and federal implementing units with standard procurement specifications of goods,

consultants and sample generic TORs; § carry out international procurement of goods (all ICB contracts will be financed by IDA) through

appropriate bodies and/or contracting the procurement to private agencies; § act as the procurement unit for the CSRP, DLDP and JSRP subprograms from preparation of bidding

documents and RFPs, until award of contract. The contracts for procurement of goods would be signed by MCB. The contracts for the selection of consultants may be signed by MCB or the respective program directors as required; and

§ consolidate procurement reports for PSCAP.

The MCB will also organize a Tender Evaluation Committee that will comprise a procurement specialist and designated representatives of the subprogram for the procurement is being made. If MCB requires expertise to carry out the evaluation, it could hire an independent consultant to assist the evaluation committee.

Federal Executing Agencies. Federal Executing Agencies (EAs) that will be involved in undertaking procurement for PSCAP include: (a) Ministry of Federal Affairs; (b) Ministry of Finance and Economic Development; (c) Information and Communication Technology Development Authority; (d) Urban Development Capacity Building Office; (e) Ministry of Revenue; and (f) Federal Supreme Court. These EAs will be involved in undertaking procurement of local goods and all consultancy services and shall:

§ carry out procurement tasks in an effective manner using the most economic and efficient methods

and in accordance with the guidelines described in this PIP; § contract out management and supervision responsibilities to procurement consultants, if needed § prepare timely procurement reports for submission to MCB § work closely with relevant bureaus, offices and agencies on all procurement matters.

Page 43: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 36 -

The Federal EAs will also organize Tender Evaluation Committees, which should include a procurement specialist. If any EA requires expertise to carry out the evaluation, it could hire an independent consultant to assist the Evaluation Committee.

6.1.2 Procurement Management Responsibilities at the Regional Level

Bureaus of Capacity Building. Procurement Desks housed in BCBs will be responsible for procurement management at the regional level except for international procurement of goods. Budget and Finance Directorate of MCB will handle the latter. Two (2) local procurement specialists will support the Desk. The procurement desk will:

§ Act as the procurement unit for executing sector bureaus from preparation of bidding documents and RFPs, until award of contract. The contracts for procurement of goods would be signed by BCB. The contracts for the selection of consultants may be signed by BCB or the respective executing sector bureaus as required. The executing sector bureaus would actively participate in the preparation of Specifications and Terms of References and technical evaluation of bids and proposal;

§ Carry out its procurement tasks in an effective manner using the most economic and efficient methods and in accordance with the guidelines described in this PIP;

§ Contract out management and supervision responsibilities to procurement consultants, if needed § Prepare timely procurement reports for submission to MCB § Work closely with relevant bureaus, offices and agencies on all procurement matters.

BCBs will also organize Tender Evaluation Committees that should consist of no more than five individuals. These should include a procurement specialist and designated representatives of bureaus for which the procurement is being made (for example, the Bureau of Urban Development for UMCBP activities). If BCB requires expertise to carry out the evaluation, it could hire an independent consultant to assist the evaluation committee.

6.1.3 Specific Procurement Tasks and Responsibilities The procurement responsibilities for PSCAP are summarized in Table 6.1. However, all international procurement will be handled by MCB’s Budget and Finance Directorate.

6.2 Procurement Policies PSCAP funds will not be utilized for procurement of works. The Government is planning to develop new standard bidding documents for the procurement of goods, works and services. In the meantime, procurement for PSCAP will be guided by World Bank guidelines. For goods procurement will be in accordance with the Guidelines: Procurement under IBRD Loans and IDA Credits of January 1995, last revised in January 1999. Bank Standard Bidding Documents for Goods, the Standard Pre-Qualification Document (if Applicable) and the Standard Evaluation Forms shall be used. Consultants will be selected in accordance with the Guidelines: Selection and Employment of Consultants by World Bank Borrower of January 1997 lastly revised in May 2002. IDA’s Standard Request for Proposals (SRFP), the Forms of Contracts as needed (lump Sum, time based and or simplified contracts for short-term assignments and individual consultants) as well as the Sample Form of Evaluation Report for Selection of Consultants shall be used for all consulting assignments. These standard formats will be provided separately by MCB.

Page 44: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 37 -

Table 6.1: Responsibilities For Effective Management of the Procurement Cycle

Steps in the Procurement Cycle Responsible Body

PROCUREMENT PLANNING Preparation of procurement plans • Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram Offices for

corresponding subprograms • ICT Development Authority (ICTDA) PMU for ICT • MOFED’s Expenditure Management and Control Coordinating Office for EMC aspects of CSRP • Ministry of Revenue’s Tax System Reform Office • Ministry of Federal Affairs’ UDCBO • Federal Supreme Court for court reform aspects of JSRP • Executing Agencies (including beneficiary agencies) and consolidated by BCBs for all regions • MFA’s Rural and Pastoral Development Directorates, on request from emerging regions

Consolidation and review of procurement plans • MCB’s Budget & Finance Directorate

PROCUREMENT IMPLEMENTATION OF GOODS

Preparation of Specifications • Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram Directors • ICTDA-PMU • MOFED Expenditure Management and Control Coordinating Office • Ministry of Revenue Tax System Reform Office • Ministry of Federal Affairs UDCBO for the Urban Management Capacity Building subprogram • Federal Supreme Court • Executing Agencies (BOFED and BCBs with beneficiary agencies) for all regions

Preparation of Bid Documents • MCB Finance & Budget Directorate for Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram

• ICTDA-PMU for ICT subprogram • MOFED Expenditure Management and Control Coordinating Office • Ministry of Revenue Tax System Reform Office • Ministry of1 Federal Affairs UDCBO for the Urban Management Capacity Building subprogram • Federal Supreme Court • Bureaus of Capacity Building all regions

Advertising • Same as above Public Bid Opening • Same as above Bid Evaluation • Same as above Bid Award • Same as above Contract Management • Same as above

Page 45: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 38 -

Steps in the Procurement Cycle Responsible Body

PROCUREMENT IMPLEMENTATION OF CONSULTANTS

Preparation of TORs

• Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram Directors • ICTDA-PMU • MOFED’s Expenditure Management and Control Coordinating Office • Ministry of Revenue’s Tax System Reform Office • Ministry of Federal Affairs’ UDCBO • Federal Supreme Court • Executing Agencies (including beneficiary institutions) with BCBs and BOFEDs for all regions

Preparation of Requests for Proposals (RFP) • MCB Finance & Budget Directorate for Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram

• Information & Communication Technology Development Authority (ICTDA) PMU for the ICT subprogram

• MOFED Expenditure Management and Control Coordinating Office • Ministry of Revenue Tax System Reform Office • Ministry of1 Federal Affairs UDCBO for the Urban Management Capacity Building subprogram • Federal Supreme Court • Bureaus of Capacity Building all regions

Advertising • Same as above Receiving proposals • Same as above Evaluating proposals • Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram Directors

• Information & Communication Technology Development Authority (ICTDA) PMU for the ICT subprogram

• MOFED Expenditure Management and Control Coordinating Office • Ministry of Revenue Tax System Reform Office • Ministry of Federal Affairs UDCBO for the Urban Management Capacity Building subprogram • Federal Supreme Court • Executing sector Bureaus for all regions to provide technical inputs only on the technical evaluation

Approval of the Evaluation results • MCB Finance & Budget Directorate for Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram

• ICTDA-PMU for the ICT subprogram • MOFED Expenditure Management and Control Coordinating Office • Ministry of Revenue Tax System Reform Office • Ministry of1 Federal Affairs UDCBO for the Urban Management Capacity Building subprogram • Federal Supreme Court • Bureaus of Capacity Building all regions

Page 46: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 39 -

Steps in the Procurement Cycle Responsible Body

Contract Negotiation & Management • Civil Service Reform, District-Level Decentralization and Justice Reform Subprogram Offices • ICT Development Authority (ICTDA) PMU • MOFED’s Expenditure Management and Control Coordinating Office • Ministry of Revenue’s Tax System Reform Office • Ministry of Federal Affairs’ UDCBO • Federal Supreme Court • Executing Agencies (including beneficiary agencies) and consolidated by BCBs for all regions • MFA’s Rural and Pastoral Development Directorates, on request from emerging regions

Page 47: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 40 -

6.3 Procurement Procedures

6.3.1 Procurement Planning (Goods and Services) Procurement implementation can only be carried out with the appropriate procurement plans already well articulated and fully developed. Therefore, a comprehensive procurement plan with appropriate timetables needs to be prepared well in advance and before actual implementation because completion of various activities hinges on the ability of the procurement staff to engage services or deliver goods ahead of time. The procurement plans for procurement of goods and consultant services are attached in Section 4 of the PIP. The detailed procurement plan defines the work to be carried out, provides cost estimates of the proposed activity, lay out a logical sequence of the procurement steps (i.e. preparation of documents, clearances, evaluations, etc.) and identifies the responsible body for the procedural and technical, monitoring and evaluation aspect of the process. An ideal plan should provide the following information:

§ the types of procurement to be carried out (i.e. goods, services, etc.); § the methods of procurement to be utilized (i.e. ICB, NCB, shopping, comparison of CVs,

etc.) § the time required for the entire process taking into account delivery & completion dates; § the stakeholders involved in the process; § the human skills required when procuring these items; § the most economic and efficient way of procuring these items

The procurement plan should be developed on the basis of the approved detailed annual plan and will cover 18 months. The specific procedures and guidelines on procurement processes and steps to help the planning process are laid out in the following paragraphs.

6.3.2 Planning for Training Activities

Implementation of training activities is slightly different from the conventional procurement planning process for goods and services. This is due to the manner in which its costs are classified. Training costs should normally be associated with expenses associated with: (a) tuition/registration fees; (b) cost of transport, meals, accommodation and other allowances; (c) rental of facilities; and (d) cost of production of training materials, etc. In cases where bulk training is contracted to a firm or group of consultants and the training requires development and organization of customized training , the fees paid will be classified as consultancy expenditure. In general terms, the methods used for planning training will de pend on the nature of the training activity. A sample training-planning template is attached in Volume II of the PIP. The planning process for training should comply with the following requirements:

§ the training activity is included in the annual plan; § the proposed timing and duration has been indicated; § the beneficiaries have been identified; § the objective of the training is specified and linked with the subprogram objectives; and § the cost has been properly estimated. Training itself shall be carried in the following manner:

§ individuals to undergo training acquire certificates, diplomas, etc.; § large group of individuals to undergo in-house or external training; § stakeholders attending meetings/seminars/workshop/consultations; and

Page 48: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 41 -

§ individuals and/or groups to undergo local and overseas study tours.

6.3.3 Organization of the Supply Side of Training Under PSCAP In additional to the general provisions noted above, there are specific requirements for PSCAP related to leveraging economies of scale in the packaging training activities at the federal and regional levels, and more systematically organizing the supply of training to ensure efficiency and effectiveness. Based on these considerations, Executing Agencies involved in PSCAP should make full use of local public sector as well as private and autonomous suppliers, and international suppliers in the delivery of training depending on the nature of the activity. The Government has identified three types of training activities—“in house,” “generic” and specialized training activities—and developed corresponding delivery modalities for each. These are discussed below and illustrated in Figure 6.1. Procurement procedures for each type of training delivery modality are detailed as well.

There is a critical role to be played by public sector suppliers such as the Civil Service College and Regional Management Institutes in the provision of “in-house” skills development as well as sensitization with Government policies. These types of training initiative can be financed from the program on a unit cost basis, i.e., covering the actual cost of the training sessions rather than the overhead or salaries of personnel in these public institutions. With respect to highly specialized forms of training such as development of skills for the maintenance of IS/IT networks or best practice land management systems, will be financed on the basis of competitive tendering. The appropriate method of selection is QBS (described later in this section). For “generic” training, PSCAP will use two stage approach such as: (a) pre-qualification of public autonomous, private, university, and non-profit suppliers; and (b) competition using QCBS method. This approach is an ideal way of organizing and increasing supply response to capacity building demands generated under PSCAP.

These procedures for the above-mentioned approach to organizing the supply of training is provided below. In-house skills development: These are usually related to sensitization workshops on new government policies and implementation procedures. These type of training activities can be handled by public sector training institutions such as the civil service college, and management institutes. The user will identify the in-house training, the institution that will conduct the training, the duration and the cost. These information will be included in the procurement plan for approval by IDA/Donors. In house training will be financed on a unit

Figure 6. 1 A three-pronged approach to delivering training In-house Generic Specialized

Uni

t Cos

tT

ende

r

• Pre

-qua

lifica

tion

• Ten

derin

g on

a le

ast c

ost b

asis

Page 49: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 42 -

cost basis i.e., covering the actual cost of the training sessions. These include workshop venue rental, transportation, refreshment and per-diem for the trainees and other direct costs of the training. Overhead or salaries of personnel in the public institutions providing the training will not be covered by IDA/donors. § consolidate in-house training activities (subject, duration, no. of participants) from the

annual implementation plan; § identify the public institution that is best to provide the training and include it in the

procurement plan; § notify the institution; § undertake the training; § carry out delivery evaluation from the trainees; § carry out impact assessment of the training at workplace. Specialized Training: These are areas where a highly specialized knowledge is required from the firms that will provide the training such as development of skills for the maintenance of IT networks, best practice land management etc. These type of trainings will be financed on the basis of competitive tendering like any other consultancy firm. The training service will be advertised to get expressions of interest and short-listed firms will be asked to prepare their technical and financial proposals. IDA’s/Donors no objection will be sought for the TOR, RFP and draft contract when the training activity costs US$ 100,000 or more. The following are the key steps to implement specialized training § prepare Terms of Reference for the specific specialized training; § advertise for the specific specialized training; § short-list from the firms expressing interest; § send the Request for Proposal to the short-listed firms; § evaluate the technical proposal; § evaluate the financial proposal; § prepare a combined (technical and financial) report; § notify the winner; § prepare and undertake contract negotiations; § carry out the training; § carry out delivery evaluation from the trainees; § carry out impact assessment of the training at workplace. Generic Training: “Generic” training covers areas such as strategic management, financial management, leadership development, communication, computers skills, M&E, etc. For these activities, training activities of similar nature will be bulked by each region and at the federal level. Private, non-profit organizations and autonomous public bodies will be pre-qualified based on clearly defined criteria and the n will be asked to compete on a least cost basis for these bulked contracts. IDA’s no objection will be sought for the pre-qualification and for the specific training that costs US$ 100,000 or more. The following are the key steps to implement “generic” training.

§ consolidate generic training activities of a similar nature from implementation plans; § advertise once a year (see the Expressions of Interest to prequalify); § pre-qualify suppliers based on the criteria matrix (see the prequalification matrix); § request financial proposal for a specific training from the pre-qualified suppliers; § evaluate the financial proposal; § notify the winner; § undertake contract negotiations; § carryout the training; § carryout delivery evaluation from the trainees; § carry out impact assessment of the training at workplace.

Page 50: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 43 -

6.3.4 Procurement Announcements General Procurement Notice (GPN). Prior to receipt of funds from the donors, especially the World Bank, a General Procurement Notice (GPN) is required to be published in the United Nations Development Business (UNDB). This is a publication of wide circulation published by the UN to inform the public of development projects across the world. Placement of announcements at the UNDB is free of charge. Typically, the GPN describes the objective of the program, the scope of procurement, and the name and address of the person to be contacted for additional information regarding the announcement. A sample GPN is shown in Section IV of the PIP. It is also advisable to send copies of the GPN to Embassies and trade representatives established in Addis Ababa. MCB is responsible for publishing and updating the GPN yearly. Specific Procurement Notice (SPN). Specific Procurement Notices also need to be published for high value contracts (thresholds are explained later in this section) for solicitation of bids for specific activities. The SPN generally contains the following details: § name of procurement agency; § tender number; § detailed description of the items or services being procured; § price of the tender/bid document; § bid/performance bond as a percent of the bid value; § place, final or closing date, and time of bid submission; § opening day of the bid; and § address details, telephone, fax, email and others.

The Executing Agency responsible for the procurement for which SPN is required is responsible for publishing the SPN. Announcements for Small Value Procurement Packages. For relatively small value items, the announcements can be done through the local newspapers posted at places where potential contractors and suppliers exist. These notices can also be posted at regional and zonal, and even on some woreda notice boards.

6.3.5 Procedures and Methods (Goods)

Procurement of goods can be done in any one of the following methods: § International Competitive Bidding Procedures (ICB)1; § National Competitive Bidding Procedures (NCB); and § National or International Shopping Procedures (NIS) The most economic and efficient way to procure goods is through international competitive bidding (ICB) procedures. ICB procedures require that all prospective bidders be notified through the announcement of the procurement in an international publication of wide circulation (see paragraph above on GPN) for about 4 to 6 weeks. Goods estimated to cost more than USD 150,000 should be procured under ICB procedures using World Bank’s Standard Bidding Documents. However, when the procurement is of relatively lower value (i.e. less than USD 150,000 equivalent), National Competitive Bidding procedures can be used. NCB requires that the announcement must be published in a national publication of wide circulation for not less than 3 weeks. For goods that are available off-the-shelf and/or

1 All ICB procurement will be financed by IDA.

Page 51: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 44 -

items of very small value (i.e. less than USD 50,000 equivalent), its procurement can be done through national and international shopping (NIS). NIS is done through comparison of at least three quotations from reputable suppliers in or outside the country. Another method of procuring goods of relatively small value (i.e. not more than USD 100,000) is procurement through UN Agencies (IAPSO or the Inter -Agency Procurement Services Office). Solicitations for national and International shopping will:

§ be issued in writing to at least three reputable suppliers (it may be better to approach five

or six suppliers because not all three suppliers may respond, so that at least three competitive quotations are received.);

§ include specifications, and if goods are not immediately available, the delivery time; § give the estimated cost, including cost of inland transportation and insurance; § be opened at the same time for evaluation (to avoid abuse), and § in the case of International Shopping quotations, be solicited from at least three suppliers

in two different countries. 6.3.6 Procedures for Procuring Goods Using ICB or NCB methods Preparation of Bid Documents . The first step in the procurement of goods is the preparation of the bid documents that will include the specification of the goods, contractual conditions and the instructions to bidders. The volume of the bid documents can vary according to the type and size of the contract. The responsible procurement staff must ensure that if standardized documents are not used that the documents are clear and comprehensive and the goods and services to be supplied are described with sufficient details to enable bidders to compete in a very competitive manner. The bid documents include:

§ instruction to bidders; § general conditions of contract; § special conditions of contract; § technical specifications; § forms of bids and bid security/bid bond; § forms for performance bond; § evaluation criteria and data sheet.

It is essential that the inputs of the appropriate procurement specialist and technical experts be obtained during the preparation of the specifications. Standard bidding documents should be used as much as possible.

Bid Notification and Advertising . After the bidding documents are prepared, advertisements should be issued in the appropriate English and Amharic media. The announcements need to be floated within a sufficient period of not less than 3 weeks and up to 6-12 weeks for large procurement of goods especially those will are subject to international competition. National Competitive Bidding (NCB) can be advertised between three to eight weeks. As stated earlier, procurement of large value goods can also be advertised in the United Nations Development Business (UNDB) with the help of the World Bank Country Office in Addis Ababa.

Sale of Bid Documents. Costs related to production of bidding documents and placement of advertisements can be recovered through the sale of the bidding documents. A complete set of bidding documents are sold to interested bidders upon submission of a written application and upon payment of a non-refundable fee as specified in the specific procurement notice.

Bid Opening Procedure . The most common method used for procurement of goods is the one-envelope system that involves the opening of all the bids all at one. The date and time of the bid opening should always be the same as the one stated in the bid document. The following are the key procedures to be followed:

Page 52: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 45 -

§ bids should be opened in public (i.e. in the presence of bidders or their representatives

who choose to attend, and all members of the procurement committee); § the bidders or their legal representatives should sign a register to confirm their

attendance; § the bidders’ names, total amount of bid, modification, bid withdrawals and the presence

or absence of the required bid security and such other details, if the procuring agency finds it necessary, should be announced at the opening;

§ bids received after the closing date and time indicated, and also those not opened and read out at the bid opening shall not be considered for evaluation; and

§ except for bids submitted late, no bids should be rejected before the opening, and a bidder present at the bid opening should not be permitted to discuss any matter relating to any bid.

A tabulation of bids read out should be prepared at the bid opening and be signed by the person who opened and read the bids and any other member of the bid evaluation committee who attend the bid opening. The opened bids, including the envelopes, should remain in a locked box or cabinet, until the evaluation process begins.

Bid Evaluation. The evaluation of competitive tenders passes through several stages: 1st Stage - Preliminary Examination. During this stage, a preliminary evaluation of bids is undertaken to verify their overall responsiveness in terms of: § Completeness § Proper signatures and seals, if necessary § Arithmetical correction § Compliance to all requirements specified in the bid document § Proper provision of bid/performance bonds § Adhering to instructions by the bidders The checking process serves as a preliminary screening mechanism for the subsequent evaluation exercises. Only those bids that meet the criteria specified in the bidding documents will be further evaluated. The reason for rejecting bids in this preliminary examination should be clearly recorded. 2nd Stage - Detailed Evaluation of Bids. This stage is the time when bids will be evaluated based on the price offered and other relevant specifications noted in the bidding document. The bid price read out at the bid opening has been adjusted to correct for any arit hmetical errors at the prices used for the evaluation. Evaluation and comparison of bids could be based on prices of (a) CIF (Cost Insurance and Freight), or (b) CIP (Cost Insurance and Carriage), when multi modular transportation is used. This usually applies to supply of imported goods. EXW (ex-works prices) is used for goods offered from within the country together with the costs for required services such as installation, training and commissioning, where such services are relevant. CIF is normally used for pricing imported goods to be shipped by sea or land transportation. 3rd Stage - Bid Evaluation. The tender/bid evaluation/procurement committee should conduct bid evaluations. The procurement officer should keep a record of the evaluation proceedings and provide the following documents to the committee:

§ Copies of bidding documents as issued to bidders, including the information to bidders

(IFB); § Minutes of the bid opening, signed by the committee members;

Page 53: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 46 -

§ Tabulation of bids read out, signed by the committee members; § Preliminary bid examination and report with reasons for bid rejections; and § Protests raised by bidders, if any.

The committee evaluating the bids should consider all complete, valid and substantially responsive bids at the time of preliminary examination. The Committee’s evaluation should at all times comply with the criteria indicated in the bidding document. No new criteria should be introduced during the bid evaluation. Typical evaluation criteria as specified in the technical specifications and should be met include: (a) delivery and installation time; and (b) availability of after sales service and spare parts. All evaluation criteria must be quantifiable and should be assessed on an objective manner.

Evaluation should be completed as quickly as possible and the winning bidder should be promptly notified and then awarded the contract. If the winning bidder fails to respond to the award, its bid can be rejected. The committee, then, considers the next lowest evaluated bidder for the contract, and so on. 4th Stage - Post Evaluation Considerations . In the absence of pre qualification, the purchaser will determine to his/her satisfaction whether the bidder selected as having submitted the lowest offer is qualified to satisfactorily perform the contract. This evaluation process will take into account the bidder’s financial, technical and production capabilities. The committee can use information from the bid document and other substantiated information available to it, or it could secure the information from banks or other organizations, as a basis for post evaluation assessment. 5th Stage - Award of Contract. The contract should be awarded to the successful bidder within the period of validity of the bid. The successful bidder should be notified in writing through registered letter, cable, and telex as convenient. At the time of notification, the purchaser will send to the bidder the completed Contract Form incorporating all agreements between the parties. Within 14 days of receipt of the Contract Form for local contracts and 30 days for international contracts, the successful bidder needs to sign and date the contract, and return it to the purchaser. Within 14 days of receipt of notification of award from the purchaser, the successful bidder should furnish a performance security in accordance with the conditions of contract. Following the furnishing of the required bid security by the successful bidder, the purchaser will notify the unsuccessful bidders and will discharge their bid securities. Contract Administration. For goods, inspection is generally difficult especially when it involves procurement of large number of items procured internationally. In these instances, it might be advisable for the purchaser to inspect the goods prior to shipment or it may use a pre-shipment agent. Final acceptance must also be made upon arrival at the place of final destination. Contracts for standardized items, such as office equipment, computers, etc., need to be accompanied by clear performance and warranty clauses and an effective system of inspection at arrival. Payment for imported goods is usually made through a letter of credit on shipment, with the balance due upon delivery of the items to the final destination. There is usually a penalty for late delivery. It is therefore, important to have a good system of follow-up on the performance of each supplier so that penalties can be imposed, if needed.

6.3.7 Procedures for Selection of Consultants

A major portion of PSCAP funds will be utilized for the recruitment of consultants. For this purpose, a separate manual has been prepared entitled “Procedures for the Selection of Consultants” that provides information on the detailed steps for selecting/recruiting consultants including the types of contracts to be used. This manual is available upon request

Page 54: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 47 -

from MCB. The following paragraphs will, therefore, only deal with the consultant selection methods and standard forms to be used when engaging consultants. The first step in the selection process of consultants is the preparation of Terms of Reference (TOR). Sample TORs are also provided in Volume 2 this PIP. The samples are not exhaustive but are useful as a basis for drawing up the recommended scope and details of an activity.

TORs should include the following information:

§ Background information about the agency seeking the consultancy service; § Objective of the consultancy; § Scope/details of the work to be done; § Preferred methodology, if there is any; § Manner of presenting proposals—financial/technical; § Key steps in the consultancy; § Indicators for the work to be done; and § Time to be allocated to the assignment.

Consultant Selection Methods . Methods to be used for selection of consultants include:

§ Quality and Cost Based Selection (QCBS); § Quality Based Selection (QBS); § Least Cost Selection (LC); § Selection Based on Consultants Qualifications (SBCQ) § Single Source Selection (SSS);

Individual Consultants. There will also be selection of individual consultants under PSCAP. Such selection process is less complex than recruitment of consulting firms. Selection of individual consultants primarily entail using more simplified procedures. The process includes preparation of terms of reference, advertising, short listing, intervie wing, negotiating and awarding the contract. Individual consultants may be selected in accordance with Section V of the World Bank’s Guidelines. Quality and Cost Based Selection (QCBS). QCBS is a method based on the quality of the proposals and the cost of the services to be provided. It is the method that would be frequently used to select consultants under the program and when the: § scope of work of the assignment can be precisely defined and the TOR is well specified;

and § the Executing Agency and the consultants can estimate with reasonable precision the staff

time as well as the other inputs and costs required of the consultants. The Request for Proposal (RFP) under QCBS would indicate the expected staff time estimated by the implementing agency to carry out the assignment. However, this estimate would not bind the consultants and they could propose the level of inputs that they consider appropriate. Under QCBS the technical and financial proposals are submitted at the same time in separate sealed envelopes (two-envelope system). Proposals received after the submission deadline would be rejected. Evaluation of proposals is carried out in two stages: first quality, and then cost. The technical envelopes are opened by the Evaluation Committee immediately after the closing time for submission of proposals; the financial proposals will remain sealed until the technical evaluation and the evaluation report are completed, approved by the IDA, and the

Page 55: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 48 -

technical scores are disclosed publicly. The financia l envelopes of those consultants who submitted responsive technical proposals meeting the minimum qualifying mark are opened in the presence of the consultants or their representatives. The proposals are then evaluated. Once the financial proposals are eva luated, a combined evaluation of the technical and financial proposals is carried out by weighting and adding the quality and the cost scores. The consultant obtaining the highest combined score is invited for negotiations. Since price is a factor of selection, staff rates and other unit rates will not be negotiated.

Since with QCBS, consultants are required to compete on the basis of price besides quality, discussion of the proposed remuneration rates for staff-months and for reimbursable expenses during contract negotiations will not be permitted even if those costs turn out to be above expectations, except for exceptional reasons. As a general rule consultant services will be selected though the Quality and Cost Based Selection (QCBS) method. For contracts estimated to cost less than the equivalent of US$ 200,000 per contract, the shortlist may be made up entirely of national consultants in accordance with section 2.7 of “World Bank Guidelines for Selection of Consultants” (copy of the guidelines can be requested from the Resident Mission in Addis Ababa), provided that foreign consultants who wish to participate are not excluded from consideration. Indefinite Delivery Contract (IDC) procured by using QCBS method may be used for large contracts involving technical assistance taking into consideration the capacity limitation of Regional Offices. Quality Based Selection (QBS). QBS is based on an evaluation of the quality of the proposals and the subsequent negotiation of the financial proposal and the contract with the consultant who submitted the highest ranked technical proposal. QBS will be used when:

§ Downstream impact of the assignment is so large that the quality of the services becomes

of overriding importance for the outcome of the project; § Scope of work of the assignment and TOR are difficult to define because of the novelty or

complexity of the assignment, or the need to select among innovative solutions, or due to particular physical, social, or political conditions;

§ Assignment can be carried out in substantially different ways, such that cost proposals may not easily be comparable; and

§ Introduction of cost as a factor of selection renders competition unfair.

QBS are used for assignments such as strategic studies in new fields of policy and reforms and assignments in which traditional consultants, NGOs and/or UN Agencies can compete. Under QBS, the implementing agency may request submission of the technical proposals only. After evaluation of the technical proposal, the consultant with the highest-ranking technical proposal will be invited to present its financial proposal. At the discretion of the implementing agency, it may also request that the financial proposals to be submitted at the same time as the technical proposals but in separate envelopes (two-envelope system). In that case, the financial proposals should be kept safely until the full technical evaluation is completed and approved by the relevant authorities. Only the financial proposal of the winning consultant is opened; the others are returned unopened after negotiations with the winning firm are successfully concluded. The RFP generally provides the staff-months only as an estimate. The staff effort indicated by the consultants may differ considerably from such estimate, depending on the particular methodology adopted by the consultant.

Since the TOR of assignments under QBS is generally less defined and relatively more complex than under QCBS, contract negotiations with the winning consultants could be lengthy and complicated. In this case, the implementing agency may decide to hire individual advisers to assist in the most critical aspects of the technical evaluation, e.g., discussion of the

Page 56: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 49 -

plan of work, staff rates and reimbursable expenses, and the definition of the consultants’ staff-months. Selection Based on Consultant’s Qualifications (SBCQ). The SBCQ method applies to very small assignments for which the cost of a full-fledged selection process would not be justified. Under SBCQ the technical specialists will first prepare the TOR; then requests expressions of interest and qualification information on the consultants’ experience and competence relevant to the assignment; establish a shortlist; and selects the consultant with the best qualifications and references. The selected consultant will be asked to submit a combined technical and financial proposal and is then invited to negotiate the contract if the technical proposal proves to be acceptable. The SBCQ method aims at reducing the cost and time needed to hire a consultant. This approach does not, however, disregard quality, since some very small assignments are very important (e.g., highly specialized advisory services with a limited scope and duration, or assignments that, although small, require consultants with the best possible qualific ations). SBCQ will be considered for assignments such as: § Brief evaluation studies at critical decision points of projects (e.g., review of alternative

solutions with large downstream effects); § Executive assessment of strategic plans; § High level, short term, legal expertise; and § Participation in project review expert panels.

Consulting assignments costing less than US$ 100,000 may procured by using Selection Based on Consultants Qualifications (SBCQ) by comparing the qualification of consultants who have expressed an interest in the job or who have been identified. Least-Cost Selection Method. Services for audit and other similar services may be procured under contracts awarded using least-cost selection method in accordance with the provisions of clauses 3.1 and 3.6 of the World Bank’s Consultant Guidelines. Single Source Selection (SSS). Under SSS, the normal procedure is to ask a specific consultant to prepare technical and financial proposals, which are then negotiated. Since there is no competition, this method will be proposed only in exceptional cases and would be made on the basis of strong and convincing justifications where it offers clear advantages over the competition. The justification should indicate whether:

§ the assignment represents a natural or direct continuation of a previous one awarded

competitively, and the performance of the incumbent consultant has been satisfactory; or § a quick selection of the consultant is essential, e.g., in emergency operations; or § the contract is very small in value; or § only one consulting organization has the qualifications or has experience of exceptional

worth to carry out the assignment.

When single sourcing is used for continuation of an assignment, the implementing agency will ask the consultant to prepare technical and financial proposals on the basis of the TOR prepared by the technical specialist or by an independent adviser with no relation to the incumbent. This will be the basis for negotiating a continuation contract. In the case of consulting assignments, members of the evaluation committee will not be allowed to have any communication with shortlisted firms from the date of their appointment to the date on which the contract is awarded. The evaluation committee will submit its report and

Page 57: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 50 -

recommendation to the designated decision making authority for review and transmission to IDA for no-objection if the contract is subject to its prior review, or for review and award for contracts subject to post review.

6.3.8 Overview of World Bank Procurement Procedures

The following paragraphs provide additional general information pertaining to procurement using World Bank procedures as it pertains to the relevant provisions of the Legal Agreement. For example, specific procurement arrangements such as use of standard documents, thresholds and methods of procurement are explained in this section of the PIP. Prior Review Thresholds. All goods contracts estimated to cost USD 150,000 or more and the first contract under NCB will be subject to IDA review of bidding documents prior to inviting for bids and bid evaluation reports prior to contract award. Single source selection irrespective of value will be subject to IDA prior review. Consultancy contracts with firms with estimated value of USD 100,000 or more, and consultancy contracts with individuals estimated value of USD 50,000 or more and the first contract will be subject to prior review by the Bank in accordance with the procedures in Appendix I of the Consultants Gu idelines. Terms of References for all consultancy services will be subject to prior review. Contracts, which are not subject to prior review, will be selectively reviewed by the Bank during program implementation and will be governed by the procedures set forth in paragraph 4 of Appendix I to the relevant Guidelines. Eligible Expenditure Categories. The following paragraphs describe the various eligible expenditure categories for funding by the IDA credit proceeds for PSCAP.

§ Goods and Equipment. Procurement of goods is expected to include office equipment,

production of manuals and guides, printing training materials, etc. § Consultancy Services. Recruitment of consultants will be mainly for assignments

pertaining to planning and budgeting, sectoral planning and management, national assessments, technical assistance for capacity building, and production of training materials for use by the federal and regional authorities.

§ Training, Workshops and Seminars. Training activities are expected to comprise

developing training materials and conducting training, support for training activities through task forces and other in-house or external providers. Training is also expected to cover activities that involve local and foreign workshops, seminars, attachments and study tours across subprograms at the federal and regional level;

§ Audits. It is expected that several audits will be carried out during the life of the program

for the audit of Special and Project Accounts under PSCAP. Cost of audit is eligible for funding when the Office of the Auditor General (OAG) engages private external auditors to audit PSCAP related accounts.

§ Incremental Operating Costs. Incremental operating costs comprise operating costs

associated with the implementation of national assessments, lobbying of line ministries, orientation activities, sundries, vehicle and equipment operation and maintenance, and program utility costs.

Page 58: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 51 -

Section 7. Monitoring & Evaluation

7.1 Purpose and Objectives of the PSCAP M&E System

The flexible framework and performance-orientation (as opposed to an unconditional entitlement to subsidies), enshrined in the PSCAP design places premium on timely availability, use and publication of public sector performance monitoring and evaluation information. The purpose of PSCAP’s M&E system is therefore to:

§ Provide information for timely decision-making at all levels; § Ensure that subprogram and PSCAP outputs are being achieved timely and in a robust

manner, and contributing towards achieving PSCAP outcomes; § Improve the overall institutional quality and enhance continuous institutional learning for

all stakeholders of PSCAP; § Promote accountability and transparency of PSCAP to stakeholders; and § Develop professional and institutional capacity for M&E.

In developing an M&E framework that achieves these ends, the Government plans to build upon existing systems and capacities for data collection, reporting and analysis; and has been envisaged as a phased development process, with deployment of intermediary instruments for data collection and development of M&E capacities, over the program period.

7.2 PSCAP Activities, Outputs and Outcomes

7.2.1 Defining “Activities, Outputs, and Outcomes”

For the purposes of monitoring progress and evaluating the results of the Program, three types of indicators have been identified from the Government’s SDPRP matrix. These indicators are capacity building activities, outputs , and outcomes , and are further explained below.

Activities. Activities in PSCAP are a set of restructuring and capacity building tasks to achieve subprogram level and PSCAP outputs. Examples of activities in PSCAP are: the conduct of assessment exercises, data collection and studies; drafting/development of documents, those pertaining to setting up new systems and procedures; training and capacity building, and management actions such as six-monthly and annual performance reviews and reallocation, and monitoring and evaluation, etc.

Outputs. PSCAP ultimately seeks to achieved a series of policy and institutional reforms across tiers of government and sectors. These outputs can be (i) one-time decisions taken, (ii) events denoting a result or reaching a state or stage (e.g. proclamation of a law, organization restructured), or (iii) other time bound, verifiable change processes (e.g. performance based management being practiced by majority of institutions, or increasing tax collection or reducing staff turnover). Outputs are a cumulative result of a set of activities implemented - although completing of those activities itself may not necessarily result in the output being produced. Therefore, it will be important that institutions at all levels focus on achieving outputs as the end product of capacity building activities.

Outputs, defined above, are to achieved by subprograms at the federal and regional level. These immediate subprogram level outputs from are indicated in the respective subprogram action plans. Examples are adoption or implementation or roll out of a particular system that has been developed; important proclamations made, public decisions or approval accorded; completed establishment of new or restructuring of existing institutions. Whereas each of the subprograms may have such specific outputs, all the subprograms need to individually and jointly, strive for the achievement of program level or PSCAP level policy and institutional

Page 59: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 52 -

reforms at the federal, regional and local levels. Therefore a subset of subprogram level outputs have been identified as overall program level outputs and are reflected in the PSCAP logframe which is attached as Annex 2. Specifically, these program level outputs which cut across the six subprograms can be organized as follows.

§ strengthened legal and policy framework § restructuring and performance improvements § reforms of expenditure management systems reforms § improved personnel management systems § intergovernmental fiscal and revenue mobilization mechanisms in place § vertical accountability mechanisms established § horizontal accountability mechanisms (or checks and balances) established

Outcomes. PSCAP outcomes are defined as the improvements in the quality of public institutions that should result from achievement of the above PSCAP outputs. These PSCAP outcomes are the Key Performance Indicators (KPIs) reflected in Section 1 of this PIP and represent the actual qualitative and quantitative improvements that are expected from this Program.

§ increased predictability and adequacy of financial resources flows (in-year, across years); § greater inclusiveness and transparency of planning and prioritization processes; § enhanced fiscal autonomy and improved revenue administration at all levels; § enhanced incentive environment for public servants (gender disaggregated); § improved quality and efficiency of operations of the public sector; and § improved transparency and accountability.

7.2.2 Participation and Performance Agreements

Under the PSCAP system, federal and regional Executing Agencies (EAs) would make formal annual and semi-annual commitments to achieve capacity building outputs through the mechanism of annual Participation and Performance Agreements (PPAs). Activities to be carried out in a given year by a region or a federal EA would be driven by the outputs or results committed in the form of the PPAs. A Sample Agreement, which include matrices detailing annual and semi-annual output commitments, are included in Volume 2 of this PIP. Commitments made in PPAs should be approved by both the cabinets at the regional and federal level and submitted to respective legislatures with approved budgets.

7.3 M&E Building Blocks

Measuring progress along the lines described above requires a variety of instruments that should form building blocks within the overall M&E system for PSCAP.

Program Activity Monitoring: seeks to track ongoing progress of activities and thereby help program management at each level take immediate corrective steps so that activities are timely and are able to achieve the planned outputs. The monitoring function will be an integral part of management information systems (MIS) at each level, and shall rapidly resolve issues that may constrain the timely achievement of outputs. Activity information will be periodically combined with financial and procurement information available from SOEs and FMRs (as explained in Section 5 of this document, and the accompanying Financial Reporting Guidelines).

Quality Assessments : Quality Assessments will periodically confirm the achievement of outputs (for example, the achievement of a critical state/stage of institutional reforms) and measure the degree to which certain significant change processes have been accomplished against output commitments. The additional subjects of assessments will be whether the process of achieving

Page 60: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 53 -

the outputs followed a robust procedure (hence “Quality” Assessments), the emerging results and learning, and treatment of cross cutting issues. Periodic summaries of financial management and procurement information will be also be reviewed and linked with the achievement of outputs.

Quality Assessments will be conducted periodically for all regions (at least annually) as also for federal subprograms (initially very six-months and reduced frequency and scope over PSCAP). Organised by Federal PPD M&E Team, under the guidance of (and participation) of the Federal Technical Team, and comprising representatives of regional and subprogram personnel, consultants, academic/research institutions and NGOs, the Quality Assessment visits will analyse monitoring information, conduct discussions with and assess progress with implementing agencies, and consult institutional and primary stakeholders.

Where feasible, assessments should be consolidated and streamlined. An important streamlined mechanism that will serve the purposes of Quality Assessments as well as evaluation reports is the woreda and municipal benchmarking survey, which surveys public officials at the local level on various aspects of public management. The survey will be repeated on a regular basis and should serve as a key pillar for outputs and outcome evaluation under PSCAP.

They will summarize and record the actual performance of the region or the subprogram against those committed to by them, in their respective Participation and Performance Agreements with the MCB, and provide the rating of performance (which will in turn form the basis for mid-year and across -year reallocation of drawing rights for regions). The scope and timing of Quality Assessments will be timed and structured to serve as the MCB’s quality assurance mechanism and will feed into the agreed Joint Review Semi-Annual and Annual Review Missions.

Specially Commissioned Studies: Special studies and surveys will be commissioned to examine specific themes and achievements as also supplement information requirements for Quality Assessments. This will be a method of closely weaving learning into implementation and since

Figure 7.1 : PSCAP M&E Framework: Building Blocks

ACTIVITY MONITORINGCollect, analyze activity data

and use for program management at federal, regional, local levels

à Early information for planning & managementà Analyze and use at the level collectedà Share summary of achievements with PSCAP program support agenciesà Program support agencies provide feedback to agencies

QUALITY ASSESSMENTPeriodic collection and analysis of data on achievement of outputs at federal, regional, and local levels

• Periodic Assessments in Regions and local levels

• Periodic Review Missions at Federal Level• Special Studies to collect data on outputs

à Confirms achievement of Performance Agreement commitmentsà Informs mid and across- year resource allocationsàShare summary with parliaments and public à FTT/RTT feedback to implementing agencies

EVALUATION& LEARNING

Periodic Evaluations and Special Studies to carry out output to

PSCAP outcome measurements

• Planned Evaluations in years 3 and 5

à Informs strategic level planning and management corrections àShare summary with parliaments at all levels, public and partners

§ Evaluation & Knowledge Creation through special studies§ Lesson learning and sharing forums for learning about PSCAP impacts

Page 61: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 54 -

many if not most of these commissioned studies will have some evaluative import as well, they shall serve learning and knowledge development needs (see Evaluation and Learning below). Finally, these studies will capture information on and highlight the achievements of PSCAP early in its implementation and lend credibility to PSCAP.

A number of studies have already been initiated or planned as a part of PSCAP including benchmarking and tracking surveys (e.g. those being carried out for CSRP and DLDP); surveys of and group discussions with public officials, private firms and enterprises; participatory exercises with community groups in rural and urban areas; Citizens’ Report Card Surveys, and other thematic and specialized institutional studies. A number of other initiatives are also underway (e.g. Report Card Study by EEA/EEPRI), which will be reviewed and wherever possible, linkages made with PSCAP M&E. A set of such studies has been recommended whereas others will be decided during six-monthly and annual reviews.

Evaluation and Learning: Activities will systematically and objectively assess progress towards and the achievement of the program output-to-outcome linkages and the underlying (constraining and accelerating) factors. Learning events like workshops and meetings with public officials and primary consultations with communities will be utilised initially to help clarify PSCAP, later document the emerging lessons from PSCAP and help in improving the program strategies and management mechanisms including the M&E system. Periodic evaluation exercises will produce evaluative learning and feedback for program management at the strategic and operational levels, as also provide the basis for sharing of lessons between regions, across levels, and potentially across other programs under the SDPRP. Apart from annual learning workshops, a mid-Term Evaluation will be conducted in year 3, and an Impact Assessment Study in year 5 (end of the program). Subprograms and Regions will commission their own evaluations to assess achievement of outputs and outcomes, and learn lessons. Other MCB and donor-supported studies and exercises are also proposed for strategic learning and knowledge creation about public sector transformation.

Development of the M&E System. Since the current systems and capacities for M&E are not fully developed and variable across regions, the above building blocks will depend on a mix of review and supervision team visits, institution of new or development of existing data collection and reporting systems during PSCAP, consultancy assistance, specially commissioned monitoring and evaluation studies, and public-official and community-based exercises to develop and adapt the tool-kit and systems of M&E at local levels. In the federal subprograms and advanced regions thus, the initial years will witness the consolidation, building on their existing systems for collecting and analysing data on activities and outputs whereas in the emerging regions, the initial period will witness the institution of simple M&E systems and ensuring their compliance and functionality, and further development of content and sophistication in later years. The exact mix of in-house administrative systems of data collection and analysis, and in -sourced resources (consultants, academic and management institutions, NGOs, etc.) will be reviewed annually.

7.4 Institutional Arrangements for M&E

The inst itutional arrangements for M&E of PSCAP will follow the arrangements established for the implementation of PSCAP, as presented in Section III of this document. At each level, the effort is on collecting and utilizing monitoring and evaluation information at the respective levels. It will be important that, key findings of the M&E system, and the follow-up action proposed are regularly communicated to stakeholders and the public, to promote accountability of the program and mobilize popular support for ins titutional transformations.

At the Woreda/ ULGA/ Kebele levels, the development of structured participatory M&E processes will need early attention. This may be accomplished early under the DLDP subprogram (say, as a part of preparing sample Woreda pla ns). Over time, it is envisaged that these participatory processes will form the core of the PSCAP M&E system at the local levels. In the

Page 62: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 55 -

interim, Quality Assessment Missions and commissioned studies will be key instruments for M&E data collection. Due to the nature of the subprograms, the Federal and Regional PPDs will need to work closely with DLDP and UMCB, to ensuring the development of M&E methods, capacity and systems at the local levels.

Reporting and information flows have been proposed in keeping with the above institutional arrangements. The first category of M&E information collected and shared is for operational management of the program – this is in turn made up of vertical and horizontal sharing of information, and feedback information and action received in return. The use of information for periodic re-allocations is a contribution to program management. The second category of information is summarized and disseminated to elected bodies and the public at large.

7.4 PSCAP Indicators for M&E

Development of indicators of PSCAP outputs and outcomes, draws heavily upon the work done during the preparation of Ethiopia’s SDPRP 2002, followed by preparatory steps for PSCAP involving iterations of action planning for the subprograms and regions that detailed the subprogram objectives and outputs; and the specification and scheduling of subprogram components and activities planned to achieve the above outputs. The design of the M&E System for PSCAP, attempted to draw out the linkages between ac hievement of subprogram and PSCAP outputs and their impacting the PSCAP outcomes or KPIs; and set out measures and indicators to measure activity-output-outcome linkages.

7.4.1 Indicators for PSCAP activities and outputs

Activity indicators have been detailed in the regional and subprogram action plans, and are simple and robust for use. These indicators need to be tracked regularly by executing agencies as a part of their routine management systems, although at differing levels of detail.

Output indicators will measure the extent and quality of reaching an important stage (result indicators), including say, the extent of complying with a system or a law, or institutionalisation of certain policies and practices. The other set of (process) indicators will measure the extent of “making a significant process change”. The methods of tracking indicators will use simple measures like coverage or institutionalisation, count, percentage, etc. and must be tracked by the subprogram agencies at the relevant lo cal levels of implementation. Output indicators will also have an aggregative character in that federal offices may concern themselves more with the summary of progress on outputs achieved at local and regional levels.

When measuring outputs, additional dimensions to measure are quality in terms of a) whether a due process was followed in reaching the output; and b) what factors are constraining or supporting the output in improving the institution’s ability (emerging results i.e.) to manage its physical, human, financial and knowledge resources. These cannot be objective quantitative measurements but will depend initially on qualitative measures and a mix of assessment methods.

Finally, whereas each of the subprograms may have such specific outputs as above, all the subprograms will need to individually and jointly, seek to strive for the achievement of the specified wider set of policy and institutional reforms at the federal, regional and local levels . These reforms cut across and go beyond individual subprogram outputs and hence are the outputs that PSCAP seeks to achieve. Therefore, there are two sets of outputs and relevant indicators: subprogram outputs and indicators, as well as program level or PSCAP level outputs and indicators, as presente d in Annex 1a and 1b respectively. Methods of data collection are also proposed along with suggestions on process, and improvements where appropriate.

Page 63: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 56 -

Outcome indicators under PSCAP are those reflected in the Key Performance Indicators in Section 1. A series of legal and policy changes for example is expected to provide the framework of new direction and changes to be in structures and capacities of public sector. The achievement of PSCAP outputs is a necessary but not sufficient condition for achieving the impacts on institutional quality of the public sector. This is because the latter depends on a number of factors outside the control of the program (and government actions), and the relationship between outputs and outcomes is difficult to precisely state. In order to aid the appreciation of the linkages of outputs to outcomes and enable their measurement, the key performance indicators as presented in Section 1 along with the key contributing subprograms and outputs.

7.4.2 Available Data and Strategy for PSCAP M&E Data Collection

Ethiopia has a strong base of data collection and analysis systems within the administration although these are not geared yet to measure institutional changes. Therefore, the strategy for PSCAP will be to utilize the limited existing data sources as much as possible, and to develop systems for generating data for measurement of the program outputs and outcomes. The available systems of data collection in institutions at the federal, regional and local levels especially on financial and human resources aspects (typically, data on stocks and flows of resources through the system) will be reviewed to examine what improvements are possible to serve PSCAP M&E requirements. Further, systems to generate new data sets will be developed under PSCAP to monitor performance and progress of organizational (individual agencies) and institutional (whole set of government institutions at each level) transformations, as they are manifest both as indicators of state/stage or rate of internal change, and most importantly of course, the results they bring about on the constituents of the governed including sub-groups of households, communities, and private sector.

Trade-offs have had to be made in selecting the indicators since a) data collection systems and information are limited in case of many indicators that are valid; b) capacities and experience with measuring institutional change is nascent; and c) causal links between outputs and

Box 7.1: Choice of indicators Experience of M&E experts and practitioners in public sector reform as well as other areas suggests that the following criteria should be used for selecting indicators for PSCAP. § Validity: Does the indicator accurately measure what is to be measured? § Objectivity and lack of ambiguity: Does the indicator measure one dimension fully is there any

ambiguity about its interpretation? § Reliability : Does the measurement of the indicator suffer from problems of data collection

methodology (in relation to the robustness required for the use that the findings will be put to)? § Comprehensiveness: Do the group of indicators together provide a complete picture? § Credibility : Does the indicator suffer from incentives of the collecting/reporting agency wanting

to influence the data? § Economy and Practicability including the following considerations:

- Whether the indicators change across the time-period they are meant to be tracked? - Are the indicators simple and easy to understand by stakeholders (including institutions, collecting agencies and users of the information including the public at large)? - Are the indicators economical and value-for-money to collect? - Is partial data on indicators easily available from existing administrative sources? - Will the indicators be comparable across regions and subprograms? - Will collection of disaggregated data (by region, sex, etc.) result in a better appreciation of dimensions of institutional change?

Page 64: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 57 -

outcomes are not precisely known. Higher importance has been accorded to validity, reliability, and practical considerations (especially simplicity and ease of data collection, and economy to some extent). These indicators currently score low on the criteria of objectivity, credibility and comprehensiveness. With development of better data collection and M&E capacity within the government as a result of relevant PSCAP activities, and the development/crafting of new methodologies for data collection on institutional benchmarking and change, the choice of indicators will have better rating on the latter criteria.

7.5 Challenges and Recommendations for PSCAP M&E

A Strategy and plan for capacity building for M&E teams at the federal and regional subprogram agencies as also the program support agencies, has been detailed in the M&E Report. A number of actions are recommended to grow the existing capacities and systems for M&E including sourcing in of expertise from private sector and academic and research institutions in Ethiopia. A phased development of M&E systems for PSCAP will also imply interim commissioning of studies and periodic reviews of the system itself as also of indicators and commitments of regions and federal subprograms. Regular disclosure of the results of M&E data collection, will be a key mechanism of building credibility of PSCAP amongst the parliament, public at large, public institutions themselves as also donor partners. The opportunity of introducing elements of public service delivery indicators in the survey systems of the Govt. (e.g. WMS and HICE Surveys, as also sectoral data collection mechanisms), may be discussed immediately with relevant departments and agencies whereas additional resources may be deployed and partnerships explored (e.g with AAU and EEA, etc.) to help in developing better systems of data collection and analysis on public sector transformation in Ethiopia. Setting up M&E systems in regions need to be incorporated in minimum mandatory capacity building commitments. Finally, it is recommended that Technical assistance from NGOs and consultants be utilized in developing participatory approaches for involving and consulting community groups for M&E data collection.

Page 65: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 58 -

Section 8. Information, Education, & Communication (IEC)

8.1 Purpose of IEC

The purpose of IEC is to create awareness, share knowledge and information, encourage feedback among the diverse group of implementers and stakeholders involved in PSCAP. among target audiences on PSCAP priority issues. A key cross-cutting objective of IEC is also to target program related risks such as potential loss of political commitment for reform or lack of consensus on resource allocation activities related to the management of this performance oriented transfers. To achieve this immediate goal, sustained approach to message development, dissemination, utilization and monitoring and evaluation is deemed necessary.

IEC activities at both the federal and regional levels will consequently focus on creating and sustaining a symmetrical information environment that will enhance the potential for democratic decentralization, good governance, transparency and accountability. In the interest of sustainability, they will seek to build a strategic development partnership between government officials, NGOs, communities and the private sector by empowering the rural and urban populations in their interactions with the institutions that partner with them in the development process in a decentralized environment. The emphasis will be on using IEC to create space for continuing, non-confrontational negotiations between stakeholders.

8.2 Guidelines for IEC under PSCAP

The following guidelines will apply for all IEC activities to be undertaken for PSCAP at the federal, regional, and local levels. They will also provide the basis for monitoring and evaluation of IEC.

Targeting Risks. An overarching priority in designing and implementing IEC activities is to target critical risks that can be mitigated through the sharing of information and knowledge and development of effective feedback mechanisms. Key risks that IEC could help mitigate include lack of transparency in the management of the rules of the game for resource allocation and reallocation, lack of knowledge among citizens on anticipated changes in state and society relations.

Delegating to Mandated Institutions. The PSCAP IEC activities will follow a delegated approach at the federal level as well as a decentralized approach in regions to ensure that institutions (for example, federal EAs with a mandate for a certain set of reforms take the primary responsibility for prioritizing and sequencing IEC activities). Regions will be responsible for implementing the IEC initiative at their level with the Federal Technical Team playing the role of a clearing house.

Scaling Up. While the accommodation of institution/region specific issues is recognized in PSCAP IEC messages/materials development, it is also important to seek economies of scale. Generic materials such as brochures and leaflets will be produced in large cost-effective runs for utilization. In the production of high quality educating and entertaining serial radio or television drama that address common issues of interest to all partners, it will be useful to bring the efforts of PSCAP IEC implementing institution together. The Ministry of Capacity Building will take the overall coordination responsibility.

Quality Control and Assurance. In PSCAP, IEC message/material development and production, quality of the output is given great importance because it promotes cost effectiveness. As a basis, quality production of messages/material require operational research, involvement of specialist in the production of messages/materials and pre-testing with relevant audiences before dissemination to

Page 66: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 59 -

target audiences. To this effect, institutions implementing PSCAP program will ensure production of quality messages/materials. The Federal Technical Team and Regional Technical Teams will have the role of assuring the quality of materials and serve as clearing houses for all IEC materials before dissemination and PPD will facilitate these communications.

Public Disclosure. Public information disclosure promotes broad public understanding of the Government’s overall capacity building agenda. It enhances participation and local ownership of the program for greater effectiveness and better results for the country. To this end, Government will regularly publish and disclose data generated from various survey instruments used under PSCAP so that the public is made aware of the progress and impact of public sector reforms.

8.3 Roles and Responsibilities at the Federal and Regional Level

At the federal level, the Ministry of Capacity Building through its Planning and Programming Directorate (PPD) will be the overall coordinator of the PSCAP IEC Strategy implementation. The PPD shall ensure that the Federal Technical Team (FTT) and the Public Relations Office, housed in MCB, endorse the IEC messages; support the recruitment of communication experts (either firms or individuals); and monitor the implementation and impact of IEC activities. At the regional level, roles and responsibilities for the implementation of PSCAP IEC Strategy will replicate the federal setup. The Bureau of Capacity Building (BCB) through the RPPD will be responsible for overall coordination at regional level. The Regional Technical Team (RTT) of BCB will endorse the IEC message; support the recruitment of communication experts (either firms or individuals); and through the PPD will get the approval from the Federal Technical Team before dissemination. Within the context of this strategy, inter-ministerial and inter-bureau coordination at federal and regional levels is essential to ensure effective implementation of PSCAP IEC activities. For maximum impact and quality of outputs, strengthening of networks and collaboration is needed among institutions in the executive, legislative, and judicial branches; representatives of civil society and the private sector; and representatives of communities, as needed. To this effect, media organizations should have a significant role in the development and dissemination PSCAP IEC programmes.

8.4 The IEC Cycle —From Issue Identification to Feedback

Given the scale of reforms and capacity building activities envisaged under PSCAP, it is critical that IEC activities follow a realistic sequence of steps to ensure effective outreach, comprehension, and feedback. A typical sequence for IEC that on any given area (for example, performance management under CSRP) should involve: (1) identification of objectives, issues, and messages, (2) selection of target audiences, (3) testing and refinement of messages, (4) deployment of communication channels with feedback mechanisms, (5) identifying indicators, (6) implementation, and (7) solicitation of feedback. These are detailed below and should be undertaken by Executing Agencies in close coordination with the PRO or equivalent, and the PPD or equivalent at federal and regional levels. Annex 3 provides examples of how to develop a full cycle approach to IEC in line with the principles noted above.

8.4.1 Identifying Priority Issues and Selecting Messages

IEC interventions shall focus on creating awareness and increasing knowledge of target audiences. Designed messages have to be need based and audience-specific . For instance, for any

Page 67: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 60 -

single issue, messages to be addressed to different categories of audiences may vary. Indeed different groups within the same audience category may require different messages. The content around key messages should be identified for critical aspects of capacity building subprograms under the guidance of subprogram directors or their regional equivalents.

8.4.2 Selecting and Segmenting Audiences

PSCAP IEC interventions shall be design to reach target audiences directly. In segmenting audiences, special focus should be given to women because of their low social and economic and political status and lack of access to information in the society. In the context of IEC for PSCAP, audiences are classified in to four major parts. These are policy makers, implementers, beneficiaries and others. Messages will be customized for various audiences to achieve the desired goal.

8.4.3 Deploying Communication Channels with Feedback Mechanisms

A broad range of communication channels will be employed to reach various IEC audiences. Federal and regional EAs should fully exploited a range of modern and traditional media including radio, TV, posters, brochures, leaflets, newspapers, and local cultural vehicles (folk drama, songs, etc.) to disseminate information to communities and stimulate demand for PSCAP-related services.

8.4.4 Identifying Output and Outcome Indicators

Based on identified objectives, experts working on IEC should identify output and outcome indicators for IEC activities in broad consultation with PPDs or equivalents, PROs or equivalents, Techincal Teams, and a sampling of clients.

Figure 8.1: Implementing the IEC Cycle

1. Identifying Priority Issues and Selecting

Messages

2. Segmenting Audiences

3. Deploying Communication Channels with

Feedback Mechanisms

4. Identifying Output and

Outcome Indicators

5. Implementing

6. Soliciting Feedback and

Evaluating Results

Page 68: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 61 -

8.4.5 Implementing

Critical to effective implementation is the need not only to use in-house expertise at the federal and regional levels, but also to contract in expertise from the market when required and to partner with a broad array of private, non-profit, traditional and civic institutions to effectively reach diverse audiences. It is worth noting that the IEC requirements of a program this complex typically goes beyond the traditional roles and responsibilities of public relations offices in single ministries or bureaus. A “rapid results” approach should be considered particularly in getting IEC messages out to remote areas and diverse communities.

8.4.6 Soliciting Feedback and Evaluating Results

At the heart of PSCAP’s approach is the need to go beyond a purely top-down approach to management or a one-way channel of communication. In establishing lines of communication with implementers, clients, citizens, and providers (for example, of training), responsible bodies should ensure that communication is two-way. A range of IEC mechanisms such as focus groups, client report cards, workshops and seminars shall be held on a regular basis to ensure that stakeholders are able to provide feedback on implementation of PSCAP activities. Such feedback is critical in ensuring that stakeholders can signal potential implementation problems, contribute to learning by doing, and also contribute to the overall credibility of the PSCAP system.

Page 69: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 62 -

Annex 1 (a): PSCAP Program Level Outcomes and Outputs (Consolidated from Subprograms) Program Development Objective: Outcome / Impact Indicators: Project reports: (from Objective to Goal)

1. 1 Enhanced predictability of financial resource flows in-year and across years - Budget variance - Federal-regional fiscal gap; regional-local fiscal gap

1.1.1 Annual Budget Reviews 1.1.2 Intergovernmental Fiduciary Assessments (IFAs) 1.1.3 Annual review mission reports

1.2 Greater inclusiveness and transparency of planning and prioritization processes

- Established practice of participatory budgeting and public reporting on budgets and performance at all levels - Regular involvement of civil society in planning, policymaking, budgeting, and review processes

1.2.1 Annual Budget Reviews 1.2.2 IFAs 1.2.3 Annual review mission reports 1.2.4 Annual Progress Report process

1.3 Improved quality and efficiency of government operations in priority sectors

- Improved service levels in terms of access, responsiveness, and cost efficiency - Reduced unit costs and processing time

1.3.1 Annual Budget Reviews 1.3.2 IFAs 1.3.3 Annual review mission reports

1.4 Improved incentive environment for public servants (gender disaggregated)

- Average civil service salary as percentage of living wage - Private-public wage ratios at each level - Wage decompression at each level

1.4.1 IFAs 1.4.2 Annual review mission reports

1.5 Enhanced revenue performance and fiscal autonomy

- Improved tax effort at all levels - Increased own revenues and unconditional transfers as a share of total expenditures at sub-national levels

1.5.1 Annual Budget Reviews 1.5.2 IFAs 1.5.3 Annual review mission reports

1. To improve the scale, efficiency, and responsiveness of public service delivery at the federal, regional, and local level; empower citizens to participate more effectively in shaping their own development; and promote good governance and accountability, by scaling up ongoing institutional transformation efforts under the Government’s Public Sector Capacity Building Program, and specifically in six priority areas: (i) Civil Service Reform; (ii) District-Level Decentralization; (iii) Urban Management Capacity Building; (iv) Tax Systems Reform; (v) Justice Systems Reform; (vi) Information and Communications Technology.

1.6 Improved transparency and accountability - Reduced incidence of corruption and arbitrariness in rule enforcement (as judged by economic agents) - Increased access to justice, recourse and redress - Enhanced independence of the judiciary - Improved access to government information

1.6.1 Public official and firm level surveys 1.6.2 IFAs 1.6.3 Annual review mission reports

1. Government sustains focus and continuity of state transformation agenda despite much larger, ambitious SDPRP agenda. 2. Federal and regional level governments effectively use the PSCAP design to coordinate efforts across subprograms and ensure consistency of public sector reform programs across regions. 3. Federal and regional level leadership maintain frontline service delivery focus of PSCAP rather than overemphasizing process. 4. Sufficient demand-side pressures are forthcoming on the part of citizens, civil society, and the private sector for improve public sector performance. 5. Woredas and municipalities access fiscal support for their recurrent and investment needs in order to leverage capacities towards specific service delivery goals.

Page 70: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 63 -

Output from each Component: Output Indicators: Project reports: (from Outputs to Objective) 1. Legal and policy framework across sectors strengthened

1.1 Law reform and revision undertaken and adopted at federal level 1.2 No. of regions adopting enabling legislation for local authorities 1.3 No. of regions adopting various tax proclamations (income, excise, TOT)

1.1 Negarit Gazetta and other relevant Government circulars and legislation 1.2 Financial Management Reports 1.3 IFAs 1.4 IGR 1.5 Annual review mission reports

2. Restructuring and performance improvement

2.1 Percentage of MABs (at federal and in each region) initiating restructuring and performance improvement 2.2 Percentage of woredas and municipalities undergoing restructuring 2.3 Percentage of courts at each level initiating performance improvement 2.4 No. of regions adopting sector-specific automated IT solutions

2.1 Quarterly progress reports 2.2 Financial Management Reports (or FMRs) 2.3 IFAs 2.4 IGR 2.5 Annual review mission reports

3. Expenditure management systems reform

3.1 Percentage of budgetary institutions at each level implementing medium term and strategic planning 3.2 No. of regions adopting new budget structure at all levels 3.3 No. of regions adopting of double entry, modified cash systems at all levels 3.4 Percentage of budgetary institutions each level adopting cash management directives 3.5 Percentage of budgetary institutions at each level rolling out automated financial systems 3.6 Procurement legislation adopted and directives issued 3.7 Accounts and audits backlog reduced at federal, regional levels 3.8 Percentage of budgetary institutions preparing standardized internal audit reports

3.1 Quarterly progress reports 3.2 Financial Management Reports (or FMRs) 3.3 IFAs 3.4 IGR 3.5 Annual review mission reports

Page 71: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 64 -

Project Development Objective: Outcome / Impact Indicators: Project reports: (from Objective to Goal) 4. Personnel management systems reform and roll-out

4.1 Medium-term remuneration policy developed, adopted at all levels 4.2 Results-Oriented Performance Evaluation rolled out at all levels HR guidelines in woredas and municipalities developed, adopted 4.3 Percentage of budgetary institutions at each level implementing IT based HRM systems

4.1 Quarterly progress reports 4.2 Financial Management Reports 4.3 IFAs 4.4 IGR 4.5 Annual review mission reports

5. Intergovernmental fiscal and revenue mobilization mechanisms

5.1 No. of regions adopting fiscal decentralization strategy including capital funding mechanisms 5.2 No. of regions implementing TIN 5.3 Guidelines developed and implemented for implementing withholding taxes, assessing presumptive tax bases 5.4 Strengthening and performance improvement of FIRA and Customs

2.1 Quarterly progress reports 2.2 Financial Management Reports 2.3 IFAs 2.4 IGR 2.5 Annual review mission reports

6. Vertical accountability mechanisms established

6.1 Service standards for urban and other essential services developed and established at all levels

2.1 Quarterly progress reports 2.2 Financial Management Reports 2.3 IFAs 2.4 IGR 2.5 Annual review mission reports

7. Horizontal accountability mechanisms or checks and balances established

7.1 No. of regions implementing guidelines for citizen participation at the woreda and municipal levels 7.2 Percentage of courts at each level undergoing performance improvement 7.3 Enhanced independence and efficiency of judiciary 7.4 Judges and lawyers trained

2.1 Quarterly progress reports 2.2 Financial Management Reports 2.3 IFAs 2.4 IGR 2.5 Legal and judicial assessment 2.6 Annual review mission reports

Page 72: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 65 -

Annex 1(b): PSCAP Subprogram Level Output Indicators (To Be Consolidated at Program Level)

TABLE (x.a): OUTPUT INDICATORS: CIVIL SERVICE REFORM PROGRAM No. Areas/Components Key Subprogram Output

Indicators Contributes to PSCAP Output Methods & Tools of Data

Collection Remarks/Recommendation

1 Strengthening the Capacity of CSR Coordinating Structures

1. CSR Coordinating structures in place and functioning (at federal, regional and local levels); 2.Structure and software include gender mainstreaming strategy, gender training, strategies for addressing gender equality at workplace; 3. HIV/Aids strategies and material ready as a part of IEC material

-NA- 1. CSRP Reports; 2. CSR Baseline and tracking studies; 3. Quality Assessments

*Recommend that gender disaggregated baseline studies, issues contributing to the inefficiency of the CS be available, barriers to the mainstreaming of gender in the civil service be identified including setting gender-disaggregated CS milestones, and involvement of civil society organisations working in the area of gender be encouraged.

2 Improving Governance of Financial Resources Management and Control

1. Compliance (%) of federal, regional and local institutions with new Financial Management Proclamation –medium term & strategic planning; 2. Compliance (%) of regions with new budget structure 3. Compliance (%) of regions with adoption of double entry, modified cash systems 4. Compliance (%) of budgetary institutions at each level adopting cash management directives 5. Compliance (%) of budgetary institutions at each level adopting automated financial systems 6. Procurement legislation adopted and directives issued at federal and regions (%) 7. Accounts and audits backlog reduced at federal, regional levels (% of budgetary institutions) 8. Budgetary institutions (%) preparing standardized internal audit reports 9. Timely publication of budget and standardized internal audit reports 10. Gender disaggregated budgeting

Expenditure Management Systems Reform

1. MoFED/BoFED Reports; 2. CSRP Reports; 3. Quality Assessments 4. Budget and Audit Reports 5. Financial Management Reports (FMR) 6. Intergovernmental Fiduciary Assessments (IFA) 7. IGR

* Baseline studies to establish current situation in respect of all these parameters is required. * Gender budgeting is recommended for piloting and development

Page 73: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 66 -

TABLE (x.a): OUTPUT INDICATORS: CIVIL SERVICE REFORM PROGRAM No. Areas/Components Key Subprogram Output

Indicators Contributes to PSCAP Output Methods & Tools of Data

Collection Remarks/Recommendation

framework proto-typed 3 Improving Governance

of Human Resources Management and Control

1. Medium-term remuneration policy developed, adopted at all levels 2. Results-Oriented Performance Evaluation rolled out at all levels 3. Implementation of HRM policy, rules and regulations (work, job grading, remuneration, cadre management, payroll etc 4. HR guidelines in woredas and municipalities developed and adopted 4. Percentage of budgetary institutions at each level implementing IT based HRM systems 5. Proportion of civil servants trained (%) (training in gender, HIV/Aids included) 7. Gender responsive recruitment mechanisms, women friendly working environment created in (%) of agencies at all levels

Personnel Management Systems Reform

1. CSRP Reports; 2. Quality Assessments; 3. Public officials' Surveys; 4. Tracking in comparison to baseline surveys; 5. IGR studies

* Recommended that all program and civil service data collection be disaggregated by sex

4 Improving Performance and Public Service Delivery

1. Performance and service delivery baseline and target standards for a) core government functions and b) key services compiled and publicised at federal, regional and local levels; 2. Strategic plans for performance and services improvements prepared; 3. Performance appraisal systems developed to link personnel performance to service delivery standards in services institutions 4. Reduced turnaround time for government-citizen interface routine and service delivery functions

Vertical Accountability Mechanisms Established

1. CSRP Reports; 2. Quality Assessments; 3. Citizens’ Report Card Surveys; 4. Tracking in comparison to baseline surveys

* Baseline studies to establish current situation in respect of service delivery parameters too. * Recommended that participatory consultations with stakeholders form the key to determining service standards - baseline and service standard studies to supplement. * CSR to identify key govt. functions and service delivery institutions at federal, regional and local levels and plan studies and actions over PSCAP (coordinate with UMCB, DLDP, TSRP, JSRP)

5 Improving 1. Annual public audit reporting to Horizontal and Vertical 1. Public Expenditure * Identification of critical departments

Page 74: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 67 -

TABLE (x.a): OUTPUT INDICATORS: CIVIL SERVICE REFORM PROGRAM No. Areas/Components Key Subprogram Output

Indicators Contributes to PSCAP Output Methods & Tools of Data

Collection Remarks/Recommendation

Accountability and Transparency

parliaments (% of regions); 2. Annual disclosure of accounting and performance information to public (through OFAG); 3. Ethics and anti-corruption law and systems strengthened at federal and regional levels; 4. Citizens' Charters publicised by institutions; 5. M&E Techniques (for tracking accountability and transparency) developed for federal and regional levels 6. Institute/Board of accountants and auditors established at Federal level

Accountability Mechanisms established

tracking surveys; 2. Studies of cost of service delivery 3. Citizens’ Report Cards 4. Annual Reports of participating institutions; 5. Public Audit Reports.

for public audit reports is important so that early on, public credibility of process is established. These could be one of the PSCAP-related departments or identified high-risk departments (this needs to be developed by CSRP in consultation with OFAG)

6 Strengthening Top Management Systems

1. Top Management Systems curriculum, handbooks and material prepared (must include gender, HIV/Aids and public accountability training); 2. Proportion of top managers (including public representatives) trained every year (gender disaggregated)

Restructuring and Performance Improvement; and Personnel Management Systems Reform

1. CSRP Reports; 2. Training Reports; 3. Annual Agency Reports.

* Recommend high priority to training on gender, public accountability and HIV/Aids

7 Building the Policy and Institutional Capacities of Emerging Regions (such as Afar, Somalia, Benishangul-Gumuz and Gambella)

1. Status and constraints assessed for emerging regions; 2. Governance improvements identified and legislations drafted; 3. Alternate approaches to Civil Service development implemented

Legal and policy framework developed; Restructuring and Performance Improvement

1. CSRP Reports; 2. Quality Assessments; 3. Special studies commissioned by MFA (DLDP/UMCB)

* Opportunity to introduce public accountability, gender and HIV/Aids related strategies and systems early in policies and institutional development * Mentoring and monitoring of key leaders and officers, recommended.

Page 75: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 68 -

TABLE (x.b): OUTPUT INDICATORS: DISTRICT LEVEL DECENTRALISATION PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

1 CB on institutional/ organizational Arrangement

1. Legislations promulgated; 2. Executive orders and manuals for compliance to executive orders implemented; 3. Assignment of expenditure and revenue in Woreda restructuring

Legal and Policy Framework 1. DLDP Subprogram and Regions’ Report 2. Legislations and manuals; 3. Quality Assessment

2 Manning and training

1. Personnel transferred (% to required) and in place at Woredas; 2. HRD Plans and % training coverage of Woreda staff (men and women)

Restructuring and performance improvement; Personnel Management Systems

1. DLDP Subprogram Report; 2. Regional Reports; 3. Quality Assessments

* Recommend that quota for the minimum participation of women in decision making at woreda level should be established/strengthened

3 Grass root participation

1. Participatory structures (planning; monitoring, review) in place in pilot woredas; 2. Increased awareness amongst communities (Kebele and sub-kebele) about PSCAP (resources transfer, changed systems, etc.); 3. Receipt of demands from community groups (especially women and remote groups) for inclusion in Woreda plans; 4. Woreda plans and operations reflect change toward community's demands 5. Quality of process indicators (key participation events specified, inclusion of poorest); 6. Participation level of women in Woreda meetings and other events

Horizontal Accountability Mechanisms 1. Quality Assessments; 2. Commissioned Special studies for development of participatory processes; 3. Woreda meeting notes and plans 4. IGR to contribute

* Participation strategy development at Woreda levels recommended to be a participatory exercise (rather than development of "manuals") * Real role and participation (as opposed to physical presence only) of women and special socio-economic groups, will need special strategies to be developed * All Quality Assessments and Evaluation exercises must cover representative spectrum of Woredas * NGOs must be involved in development of participatory framework and implementation at Woredas

4 Program Development

1. Decentralisation strategy documents from regions; 2. Woreda benchmarking tool in use in regions; 3. Training and capacity building measures implemented on administrative and financial decentralization

Restructuring and performance improvement

1. DLDP Subprogram Reports; 2. Quality Assessments 3. Woreda benchmarking studies

* All data collected should be gender disaggregated

Page 76: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 69 -

TABLE (x.b): OUTPUT INDICATORS: DISTRICT LEVEL DECENTRALISATION PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

5 Woreda fiscal transfer and own revenue enhancement

1. Woreda fiscal transfer framework improved in regions; 2. Actual budget allocations demonstrate increases (which is linked to above)

Intergovernmental fiscal and revenue mobilization mechanisms

1. DLDP Subprogram Reports; 2. Regional budget allocation laws/executive instructions on fiscal transfer

* Regional budget allocation guidelines to include instructions for gender budgeting at regional and woreda level

6 Woreda (local) planning and financial control

1. Woreda level exercise on medium term expenditure framework; 2. Capital funding becomes more prominent 3. Annual Accounts Published/ displayed at Woreda and Kebeles

Expenditure Management Systems Reform, Intergovernmental and fiscal revenue mobilization mechanisms

1. DLDP Subprogram Reports; 2. Regional Reports 3. IGR/Woreda Fin Mgt Assessments to provide key data and analysis for multi-year planning and financial management

Provision for gender budgeting to be made in regional budget allocation laws

7 Minimum standard service performance mechanisms

1. Service delivery study 2. Minimum standards for each service - charters consulted with kebeles and displayed; 3. Cost and performance tracking statistics displayed; 4. Reduced turnaround time for service provision

Vertical Accountability Mechanism 1. Service delivery and cost studies; 2. Citizens Report Cards Surveys 3. Service Charters 4. Woreda Complaints books

* Gender disaggregated data to be collected

8 Office equipment 1. Woreda offices equipped and improved operations

Page 77: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 70 -

TABLE (x.c): OUTPUT INDICATORS: JUSTICE SYSTEMS REFORM PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

1 Strengthening the Judiciary

1. Increase in % of men and women judges trained; 2. Increase in % of supporting staff trained; 3. Increase in courts equipped with modern equipments; 4. Modern case management and recording system implemented in courts

Horizontal Accountability Mechanisms, Restructuring and performance improvement

1. JSRP Subprogram Report; 2. Training Reports; 3. Court records; 4. Quality assessments

*Recommend a quota for a minimum number of women trainees in the training institutes; and a minimum number of women judges at each court

2 Law Revision and Law Reform

1. Number of laws drafted and enacted (civil, commercial, human rights, etc.); 2. Number of distributed compiled laws; 3. Completion of studies

Strengthened Legal and Policy Framework

1. Copies of draft and final laws in public media and to parliament; 2. Specially commissioned legal and judicial assessment studies; 3. JSRP Subprogram Report

* Recommend systems for increased legal access for poor and women e.g. special courts, family divisions/section within courts, easier rules of access, closed sessions for special cases like rape etc. *Recommend role for Women's Affairs Departments and Legal Aid Collectives and NGOs (in carrying out periodic studies)

3 Law Enforcement Organ capacity enhancement

1. Community policing system in place; 2. Crime prevention & prosecution policy in place; 3. Police Institutions Management Systems documented and implemented; 4. Police forensic service improved & new regional centres established; 5.Penitentiary institutions management standards improved; 6. Certain functions of law enforcement organs automated.

Strengthened Legal and Policy Framework, Restructuring and Performance Improvements, Horizontal Accountability Mechanisms

1. JSRP Subprogram Report; 2. Specially commissioned legal and judicial assessment studies; 3. Citizens’ Report Card Surveys

* See above also recommend inclusion of training on the gender aspects of the law as a component of all training to be conducted to law enforcement bodies, role for NGOs working on women's rights areas, gender disaggregated data on all crimes of violence committed against women.

4 Legislative organ 1.Increase in the number of trained members of standing committees federal & regional law making bodies; 2. Increase in the number of

Restructuring and Performance Improvements, Horizontal Accountability Mechanisms

1. JSRP Subprogram Report; 2. Proclamations and Executive Orders

Page 78: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 71 -

TABLE (x.c): OUTPUT INDICATORS: JUSTICE SYSTEMS REFORM PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

professional staff of the legislative body trained in legal drafting; 3. New law making procedures introduced; 4. Increase in number of law making organs equipped with modern materials

Page 79: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 72 -

TABLE (x.d): OUTPUT INDICATORS: URBAN MANAGEMENT CAPACITY BUILDING PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

1 Federal and Regional Urban Management Policy

1. Policies and strategies (urban development, housing, land, etc.) drafted; 2. Model Municipal legal framework and code drafted; 3. Regional and National Municipal associations functioning 4. Model Municipal Manuals prepared; 5. Fiscal transfer framework to ULGAs agreed by regions

Strengthened Legal and Policy Framework, Intergovernmental and fiscal revenue mobilization mechanisms

1. Policy documents; 2. Manuals; 3. UMCB Subprogram Reports; 4. Regional Report; 5. Quality Assessments

* Need for prioritisation of strategies, policies and laws (e.g. urban development policy could be the umbrella policy whereas others could be subsidiary legislation); * Participatory consultations must be used for determining policies and strategies * Manual preparation recommended to be based on studies in regions * Laws and manuals to reflect specific provisions for women and socio-economically disadvantaged groups

2 Deepening the Process of Decentralization

1. Establishing and strengthening urban-related institutions and organisational structure of ULGAs in the regions and CAs; 2. Manuals adapted to regions and CAs and in use by x (of 80) ULGAs; 3. Studies (e.g. revenue collection, financial and human resources management systems) completed; 4. Subsidiary urban laws, procedures and systems in use by ULGAs; 5. Urban information and communication systems established and in use; 6. Public participatory framework developed; 7. Establishing x and strengthening y physical planning units; 8. Provision of bulk training to federal, regional and CA staff

Restructuring and performance improvement, Strengthened Legal and Policy Framework, Horizontal Accountability Mechanisms

1. UMCB and CSRP Reports; Legislation documents; 2. Published policies and strategies; 3. ULGA annual reports; 5. Quality Assessments; 6. Specially commissioned studies; 8. IGR studies to supplement

* See above. Detailed listing, sequencing and prioritisation of activities (hence, outputs and outcomes) will be key to successful implementation (and monitoring). * Studies suggested on public service-citizens interface

3 Local Government Restructuring and Capacity Building

1. New organisational structures in ULGAs; 2. Improved service delivery systems

Restructuring and performance improvement, Strengthened Legal and Policy Framework, Vertical and

1. ULGA annual reports; 2. Subprogram reports; 3. Quality Assessments;

* Priority municipal baseline/ benchmarking studies proposed for year 1 may be advanced to

Page 80: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 73 -

TABLE (x.d): OUTPUT INDICATORS: URBAN MANAGEMENT CAPACITY BUILDING PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

implemented; 3. Specific local ULGA studies completed (master plan, roads, slums, markets, services networks, hazard protection, HIV/AIDS, poverty reduction, gender, etc.); 4. Standard manuals and operational procedures implemented in ULGAs

Horizontal Accountability Mechanisms, Intergovernmental and fiscal revenue mobilization mechanisms

4. CSRP reports; 5. Specially commissioned studies e.g. municipal benchmarking; 6. Citizens' report card surveys; 7. Public Officials' surveys

Q2; * Studies may be commissioned by Regional governments for specific needs, under federal guidance; * Restructuring must include gender, HIV/Aids and public accountability mechanisms

TABLE (x.e): OUTPUT INDICATORS: TAX SYSTEMS REFORM PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

1 Tax Policy and Legislation

1.Issue or adapt/adopt proclamations, regulations and directives (% of regions); 2. Agricultural income tax and land use fee proclamation issued 3. Revenue potential study of Regions and CAs completed (%)

Strengthened Legal and Policy Framework, Intergovernmental and fiscal revenue mobilization mechanisms

1. Proclamations and operational directives copies; 2. Increase in revenue and compliance from TSRP Subprogram Reports

* Stakeholder consultations may be planned for drafting key new tax laws and rules * Incidence analysis studies to pre-empt adverse impacts of key socio-economic groups

2 Tax Payer Identification Number (TIN)

1. TIN Coverage as a proportion of total tax base; at federal and regions; 2. Proportion of computerised TIN; 3. Third-party use of TIN (Customs and Financial Institutions)

Intergovernmental and fiscal revenue mobilization mechanisms, Restructuring and Performance Improvement

1. TIN computerised database; 2. Tax collections by federal and regions; 3. CSR and Citizens' surveys

3 Presumptive Taxation

1. Profitability rate directive issued; 2. New Tax-payers registered; 3. Increased tax revenue from businesses and hard-to-tax groups

Intergovernmental and fiscal revenue mobilization mechanisms

1. TIN database; 2. TSRP Subprogram Reports 3. Firms’ surveys

4 Value Added Tax (VAT)

1. No of registered VAT payers; 2. Increase in VAT collections

Intergovernmental and fiscal revenue mobilization mechanisms

1. Reports from Audit and Enforcement programs in operation; 2. TSRP Reports

5 Operational Programs Systems, Procedures and Manuals

1. Implementation of manual in tax offices in regions and CAs; 2. Tax file management system introduced 3. Improved tax-payer satisfaction;

Restructuring and Performance Improvement, Vertical Accountability Mechanisms

1. TSRP Subprogram Reports; 2. CSRP Reports; 3. Tax-payers' and firms’ surveys

* Stakeholder consultations recommended to finalise manual * Service Charter may be considered as a part of manual development

Page 81: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 74 -

TABLE (x.e): OUTPUT INDICATORS: TAX SYSTEMS REFORM PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

4.Integrated tax system customized & implemented.

6 Organisation and Tax Payers' Education

1. Reduced staff turnover; 2. Reduced corruption; 3. Reduced collection costs; 4. Autonomous Tax Authority set up

Restructuring and Performance Improvement, Horizontal Accountability Mechanisms

1. TSRP Subprogram Reports; 2. Collection costs to be computed internally; 3. Corruption, harassment and complaints reportage from tax payers surveys

1 Customs Automation

1. Reduced goods and passenger clearance time

Restructuring and Performance Improvement

1. TSRP Subprogram Reports 2. Firms’ surveys

* ECuA to be incorporated in the TSRP M&E System

2 Customs Organization and

Management

1. Reduced operational overheads costs; 2. Increased employee satisfaction

Restructuring and Performance Improvement, Personnel Management Systems

1. TSRP Subprogram Reports

* ECuA to incorporate (employee and customer, and business process) studies in their M&E System

TABLE (x.f): OUTPUT INDICATORS: INFORMATION & COMMUNICATIONS TECHNOLOGY PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

1 ICT Human Resource Development

1. No of (men and women) Civil Servants trained in ICT at all levels; 2. Hardware and software installed; 3. Regional training Centres established; 4.Trainng manuals and softwares developed in X no. of Local languages; 5. No of study documents produced

Restructuring and Performance Improvement

1. ICT Subprogram reports; 2. Quality assessment; 3. CSRP Reports

* Targets to be determined * ICT Offices to help client offices to track computer literacy and usage development amongst civil servants

2 ICT for Public Service Delivery and Good Governance

1. Regional Information Centres established and functioning; 2. Information portals launched; 3. Computerised information system for Woredas and ULGAs; 4. No. and type of customized and developed applications; 5. LAN and WAN developed; 6. Regional websites developed

Restructuring and Performance Improvement, Horizontal Accountability Mechanisms

1. ICT Subprogram reports; 2. Special Studies; 3. CSRP Reports; 4. Quality Assessment

* Targets for computerised service delivery counters to be planned

Page 82: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 75 -

TABLE (x.f): OUTPUT INDICATORS: INFORMATION & COMMUNICATIONS TECHNOLOGY PROGRAM

No. Areas/Components Key Subprogram Output Indicators

Contributes to PSCAP Output Methods & Tools of Data Collection

Remarks/Recommendation

3 ICT Applications for Sector Development

1. No of sectors with consolidated digital information at regional information centers; 2. Integrated information systems in x no of sectors and programs 3. public-domain sectoral information available to the public; 4. Inter-operable Local languages and graphic adaptation / development for sectoral information available; 5. All sectoral data disaggregated by gender; 6. No. of sector -specific content and applications developed; 7. No of developed or customized common administrative applications

Restructuring and Performance Improvement

1. ICT Subprogram reports; 2. Special Studies; 3. CSRP Reports; 4. Quality Assessment

* Plan of development and targets to be determined and monitored by M&E of subprogram

4 ICT for Community Based Information Systems and Services

1. Development of local communication content/software; 2. Community needs assessment for ICT services; 3. Broadcast through local media (including traditional media e.g. dagu)

Horizontal Accountability Mechanisms

1. ICT Subprogram reports; 2. Need Assessment Study Reports 3. Quality Assessments

* Community Needs assessment of ICT services may be planned * Local media availability to be assessed jointly with PSCAP IEC

Page 83: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 76 -

Annex 2. Thinking through the IEC Cycle IIss ss uueess aann dd RRiiss kk FFaacctt oorrss

RReellee vvaanntt IIEECC OO bbjjeeccttii vvee// IInn ddiicc aatt oorrss AAuu ddiiee nnccee CCoommmmuunniicc aattiioonn CChh aann nneell

RReess ppoonnss ii bbllee AAggeennccyy

RReeccoommmmee nn ddee dd AAccttiioonnss

Political commitment to institutional transformation may waver, or Government may not be able to sustain focus on PSCAP because of its ambitious development agenda

Objective: Increase knowledge to: sustain commitment to PSCAP allocate funds and personnel to

meet infrastructure and logistics requirements that are not financed by PSCAP

help them hold accountable the responsible bodies implementing PSCAP

Indicators: No. of regions that have confirmed

mechanisms to address the personnel, infrastructure and logistics requirement that are not finance by PSCAP

Ministries, bureaus and agencies implementing PSCAP related activities

No. of consensus building workshops involving federal and regional policymakers

Policy makers at federal and regional level Federal -Council of Ministers -Parliament Regional -Cabinet members -Regional councillors -Woreda councillors

Radio TV Brochures Progress report Workshops

Federal PPD Regional RPPD

PPD will produce one brochure on PSCAP-general to be disseminated to the audience (Time-frame)

BCBs ensure that BOFEDs include budgetary provisions for personnel, infrastructure and logistics requirements of PSCAP; and discuss budgetary implications with relevant legislators

The performance-based feature of PSCAP system – that is, the proposed mid-year and annual reallocation of drawing rights based on performance – poses an importance resource management challenge for the Government. If it is not managed clearly, fairly and transparently, it may undermine the credibility of the system.

Objective Increase knowledge for:

deeper understanding of rules of the game

deeper understanding of rights and responsibilities

Indicators Training conducted on the PIP Performance Report on the newsletter “Capacity” Development of website

Coordinators and implementers of PSCAP at Federal and Regional level will be the main audience. Federal -Federal Technical Team -MoFED staff responsible for PSCAP Regional -RPPD -Regional Technical Team -BoFED staff responsible for PSCAP

PIP Training workshop Newsletter “Capacity”

Federal Only PPD

Have a section on the PIP that clearly spells out the resource reallocation rules and procedures (Time-frame) Conduct training on the resource reallocation rules and procedures (Time-frame) Publish performance of regions on the newsletter “capacity” (Time-frame)

PPD may be too busy to sustain a continuous communication to help

Objective To create continuous communication with

Regional Coordinators and implementers will be the main audience

Review Meetings Regional Networks Website

Federal PPD

Institutionalize quarterly meeting with regions on implementation issues-if

Page 84: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 77 -

IIss ss uueess aann dd RRiiss kk FFaacctt oorrss

RReellee vvaanntt IIEECC OO bbjjeeccttii vvee// IInn ddiicc aatt oorrss AAuu ddiiee nnccee CCoommmmuunniicc aattiioonn CChh aann nneell

RReess ppoonnss ii bbllee AAggeennccyy

RReeccoommmmee nn ddee dd AAccttiioonnss

regions in resolving implementation issues

regions for smooth implementation To share good practices and lessons learned Indicators No. of review meeting with regions No. of Networking activities among regions

Regional -RPPD and lead sector bureaus

possible preceding the joint government-donor meeting (Time-frame) Create a PSCAP website where information can readily be available for regions (Time-frame) Create regional network to share good practices and lessons learned (Time-frame)

Primary beneficiaries will have very little knowledge about PSCAP thus can not demand their rights nor contribute to PSCAP.

Objective Create awareness of PSCAP to:

inform how the beneficiaries will benefit and also how they can contribute to PSCAP

help the beneficiaries hold

accountable executing agencies responsible for implementing PSCAP

to create a line of

communication with beneficiaries to inform them of progress and get feedback on perception of PSCAP

Indicators

Beneficiaries at Federal and Regional Level are the main audience. Federal - Sector ministries, agencies and commissions - Federal public, private and non-governmental training institutions Regional - Sector bureaus, agencies and Commissions at regional level -Woreda-level sector offices -Regional public, private and non-governmental training institutions

Workshops Progress Reports Brochures Review Meetings Survey Traditional Media

Federal -PPD and Program Directors' Offices Regional -RPPD

Directors of each of PSCAP sub-program will produce one brochure on their respective program for dissemination in collaboration with the PPD. (Time -frame). The Program Directors will conduct regular meeting with the beneficiaries (Time -frame) PPD and the Program Directors will conduct an awareness creation and consensus building workshop with the public, private and non-governmental training institutions

Page 85: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 78 -

IIss ss uueess aann dd RRiiss kk FFaacctt oorrss

RReellee vvaanntt IIEECC OO bbjjeeccttii vvee// IInn ddiicc aatt oorrss AAuu ddiiee nnccee CCoommmmuunniicc aattiioonn CChh aann nneell

RReess ppoonnss ii bbllee AAggeennccyy

RReeccoommmmee nn ddee dd AAccttiioonnss

No. of awareness creation workshops Meetings with training institutions on how they contribute to PSCAP Survey results on perception of beneficiaries

RPPD in collaboration with the relevant sector bureaus will produce one brochure on their respective program for dissemination (Time -frame). RPPD in collaboration with the relevant sector bureaus will conduct regular meeting with the beneficiaries at the regional level (Time-frame) RPPD and the relevant sector bureaus will conduct an awareness creation and consensus building workshop with the public, private and non-governmental training institutions at the regional level

Insufficient expressed demand on the part of citizens, civil society and the private sector for improved public sector performance in terms of service delivery, empowerment and good governance

Objective Create awareness among citizens to:

demand improved public sector performance

have voice in the

development agenda

hold accountable the executers of development policy

Citizens at Federal and Regional level Federal -civil society organizations -private sector -citizens at large Regional -civil society organizations -private sector -citizens at large

Radio TV Brochures Progress report Discussion Forum Workshops

Federal PPD Regional RPPD

Develop and disseminate messages on radio, TV and print on PSCAP

Page 86: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 79 -

IIss ss uueess aann dd RRiiss kk FFaacctt oorrss

RReellee vvaanntt IIEECC OO bbjjeeccttii vvee// IInn ddiicc aatt oorrss AAuu ddiiee nnccee CCoommmmuunniicc aattiioonn CChh aann nneell

RReess ppoonnss ii bbllee AAggeennccyy

RReeccoommmmee nn ddee dd AAccttiioonnss

Indicators No. of messages on radio, TV and print to create awareness.

PPD may be too busy to sustain a continuous communication to help regions in resolving implementation issues

Objective To create continuous communication with regions for smooth implementation To share good practices and lessons learned Indicators No. of review meeting with regions No. of Networking activities among regions

Regional Coordinators and implementers will be the main audience Regional -RPPD and lead sector bureaus

Review Meetings Regional Networks Website

Federal PPD

Institutionalize quarterly meeting with regions on implementation issues -if possible preceding the joint government-donor meeting (Time -frame) Create a PSCAP website where information can readily be available for regions (Time-frame) Create regional network to share good practices and lessons learned (Time-frame)

Primary beneficiaries will have very little knowledge about PSCAP thus can not demand their rights nor contribute to PSCAP.

Objective Create awareness of PSCAP to:

inform how the beneficiaries will benefit and also how they can contribute to PSCAP

Beneficiaries at Federal and Regional Level are the main audience. Federal - Sector ministries, agencies and commissions - Federal public, private and

Workshops Progress Reports Brochures Review Meetings Survey Traditional Media

Federal -PPD and Program Directors' Offices

Directors of each of PSCAP sub-program will produce one brochure on their respective program for dissemination in collaboration with the PPD. (Time -frame).

Page 87: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 80 -

IIss ss uueess aann dd RRiiss kk FFaacctt oorrss

RReellee vvaanntt IIEECC OO bbjjeeccttii vvee// IInn ddiicc aatt oorrss AAuu ddiiee nnccee CCoommmmuunniicc aattiioonn CChh aann nneell

RReess ppoonnss ii bbllee AAggeennccyy

RReeccoommmmee nn ddee dd AAccttiioonnss

help the beneficiaries hold accountable executing agencies responsible for implementing PSCAP

to create a line of

communication with beneficiaries to inform them of progress and get feedback on perception of PSCAP

Indicators No. of awareness creation workshops Meetings with training institutions on how they contribute to PSCAP Survey results on perception of beneficiaries

non-governmental training institutions Regional - Sector bureaus, agencies and Commissions at regional level -Woreda-level sector offices -Regional public, private and non-governmental training institutions

Regional -RPPD

The Program Directors will conduct regular meeting with the beneficiaries (Time -frame) PPD and the Program Directors will conduct an awareness creation and consensus building workshop with the public, private and non-governmental training institutions RPPD in collaboration with the relevant sector bureaus will produce one brochure on their respective program for dissemination (Time -frame). RPPD in collaboration with the relevant sector bureaus will conduct regular meeting with the beneficiaries at the regional level (Time-frame) RPPD and the relevant sector bureaus will conduct an awareness creation and consensus building workshop with the public, private and

Page 88: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section

- 81 -

IIss ss uueess aann dd RRiiss kk FFaacctt oorrss

RReellee vvaanntt IIEECC OO bbjjeeccttii vvee// IInn ddiicc aatt oorrss AAuu ddiiee nnccee CCoommmmuunniicc aattiioonn CChh aann nneell

RReess ppoonnss ii bbllee AAggeennccyy

RReeccoommmmee nn ddee dd AAccttiioonnss non-governmental training institutions at the regional level

Insufficient expressed demand on the part of citizens, civil society and the private sector for improved public sector performance in terms of service delivery, empowerment and good governance

Objective Create awareness among citizens to:

demand improved public sector performance

have voice in the

development agenda

hold accountable the executers of development policy

Indicators No. of messages on radio, TV and print to create awareness.

Citizens at Federal and Regional level Federal -civil society organizations -private sector -citizens at large Regional -civil society organizations -private sector -citizens at large

Radio TV Brochures Progress report Discussion Forum Workshops

Federal PPD Regional RPPD

Develop and disseminate messages on radio, TV and print on PSCAP

Page 89: PROGRAM IMPLEMENTATION PLAN - World Banksiteresources.worldbank.org/INTETHIOPIA/Resources/PSCAP/pip_vol_1… · - iii - 7.5 Challenges and Recommendations for PSCAP M&E.....57 Section