PROJECT CHARTER FOR
THE DETAIL DESIGNS, AND TENDER
DOCUMENTATION FOR
MUNSIEVILLE, ZONE
35, WATER PIPELINE
REPLACEMENT
PROJECT
Page 2 of 15
Contents
1. EXECUTIVE SUMMARY ............................................................................................................ 3
2. BACKGROUND AND PROBLEM STATEMENT ................................................................... 6
3. OUTLINE BUSINESS CASE ..................................................................................................... 6
4. PROJECT OBJECTIVES AND DESIRED OUTCOME ......................................................... 7
5. PROJECT SCOPE AND EXCLUSIONS .................................................................................. 7
6. CONSTRAINTS AND ASSUMPTIONS .................................................................................... 7
7. STAKEHOLDERS AND COMMUNICATION .......................................................................... 8
8. PROJECT MANAGEMENT TEAM STRUCTURE ................................................................. 8
9. TIME FRAME ................................................................................................................................ 9
10. PROJECT BUDGET ................................................................................................................ 9
11. PLACES OF WORK ................................................................................................................ 9
12. SITE CLEARANCE ............................................................................................................... 10
13. DELIVERABLES .................................................................................................................... 10
14. PROFESSIONAL FEES........................................................................................................ 10
15. MILESTONES ......................................................................................................................... 11
16. SUCCESS CRITERIA ........................................................................................................... 12
17. REPORTING REQUIREMENTS AND MEETING SCHEDULE...................................... 12
18. GUIDELINES AND STANDARDS ...................................................................................... 13
19. QUALITY ASSURANCE AND CODE OF CONDUCT ..................................................... 13
20. RISK MANAGEMENT ........................................................................................................... 14
21. PROJECT APPROVAL REQUIREMENTS ....................................................................... 14
22. PROJECT SPONSOR ........................................................................................................... 14
23. ACCEPTANCE ....................................................................................................................... 15
ANNEXURE A: Appointment Letter
ANNEXURE B: Project Inception Meeting Minutes
ANNEXURE C: Fee Proposal
ANNEXURE D: Project Program
Page 3 of 15
1. EXECUTIVE SUMMARY
MORAD Consulting Engineers was appointed by Mogale City Local Municipality
for the Munsieville, Zone 35 Water Pipeline Replacement Project. This Project
Charter forms part the Consultants’ appointment and covers the strategy for the
planning, designing and tender documentation of the water pipelines
replacement in Munsieville as per the subject project requirements.
Mogale City Local Municipality is experiencing unaccounted for water losses in
most of its areas including along the bulk water lines supplying Munsieville with
portable water. The existing bulk waterline comprises of rotten AC pipes, prone
to bursting. The infrastructure along the water pipelines is also now old.
This has made Mogale City Local Municipality assign Morad Consulting the
Munsieville bulk water pipeline replacement project in-order to assist in curbing
water losses.
The Water & Sanitation Department of MCLM has got funds in place for the
designing, tender documentation and implementation for the Munsieville, zone
35 bulk water pipeline replacement project during this current financial year.
The major objective of this project is to reduce the unaccounted for water
losses in the Municipality.
Page 4 of 15
The project deliverables under this appointment are as follows:
Deliverable Status Importance
Project Charter Finished Required
Fee Proposal Finished Required
Concept Design Report and Drawings
Finished Required
Preliminary Design Report and Drawings
Finished Required
Preliminary Cost Estimate Finished Required
Detail Design Report and Drawings
Started Required
Detail Cost Estimate Started Required
Tender Documents and Drawings
Started Required
Contract Administration, Inspection & Monthly Progress Reports
Required
Project Program Started Required
Cash Flow Projection Started Required
Close-out report Required
The project deliverables listed above lead to the projects milestones and they will
be submitted in line with the project stages as follows:
Deliverable Submission Category Status Importance
Project Charter Inception Stage Finished Required
Fee Proposal Inception Stage Finished Required
Concept Design Report and Drawings
Concept and Viability Stage
Finished Required
Preliminary Design Report and Drawings
Concept and Viability Stage
Finished Required
Preliminary Cost Estimate Concept and Viability Stage
Finished Required
Detail Design Report and Drawings
Design Development Stage
Started Required
Detail Cost Estimate Design Development Started Required
Page 5 of 15
Stage
Tender Documents and Drawings
Documentation and Procurement Stage
Started Required
Contract Administration, Inspection & Monthly Progress Reports
Contract Administration and Inspection Stage
Required
Project Program Concept and Viability Stage
Started Required
Cash Flow Projection Design Development Stage
Started Required
Close-out Report Close-out Stage Required
The completion of the assignment shall be constituted by submission and
acceptance of the close out report.
Page 6 of 15
2. BACKGROUND AND PROBLEM STATEMENT
Mogale City Local Municipality is experiencing unaccounted for water losses in
most of its areas including along the bulk water lines supplying Munsieville with
portable water. The existing bulk waterline comprises of rotten AC pipes, prone
to bursting. The infrastructure along the water pipelines is also now old.
In a letter dated 19 November 2013, Mogale City Local Municipality appointed
Morad Consulting to develop a solution to the problem. The appointment is for
the “Preparation of Detail Designs and Tender Documents so that the project is
ready for tender within the current financial year ending June 2014.”
3. OUTLINE BUSINESS CASE
Mogale City as the local Water Services Authority, one of its main responsibility
is to ensure effective, efficient, affordable and sustainable access to water
services with minimum or no losses within the distribution network As a result
Mogale City has to meet its service delivery mandate in Munsieville
where they are experiencing numerous unaccounted for water losses. This has
motivated the need to come up with a water pipeline replacement project to
eradicate these water losses being caused by problems stated under the
problem statement above.
With the implementation of the project, unaccounted for water losses will
be curbed in Munsieville, resulting in the Municipality saving money.
The implementation of this project will also ensure:
To achieve these goals, MOGALE CITY APPOINTED Morad Consulting
to design an appropriate solution based on current best engineering
practice and at a cost and within a time frame that is acceptable to MCLM.
Page 7 of 15
4. PROJECT OBJECTIVES AND DESIRED OUTCOME
The major objective of this project is to reduce the unaccounted for water
losses in the Municipality.
The Municipality intends the project to be ready for tender within the current
financial year ending June 2014.”
5. PROJECT SCOPE AND EXCLUSIONS
The Scope is as follows;
Prepare concept design report and drawings for the project.
Do preliminary design for the water pipeline replacement.
Preparation of a preliminary cost estimate for the project.
Provide technical support to the Municipality regarding relevant
studies.
Prepare detail design report and drawings.
Prepare detail cost estimate
Prepare tender documents and drawings and assist with
procurement.
Contract Administration and Inspection
Prepare close our report.
Exclusions
EIA
6. CONSTRAINTS AND ASSUMPTIONS
The constraints and assumptions pertaining to this project area;
It is assumed that the roads that will be crossed during laying of the
pipes are municipal roads and that permission to cross will be
obtained.
The other constraint is the unavailability of a survey along the strip
of the bulk waterline.
Page 8 of 15
7. STAKEHOLDERS AND COMMUNICATION
The bulk water line is owned by Mogale City Local Municipality
(MCLM) and will be used to supply potable water to the consumers
in the Munsieville area. The reservoirs are owned by MCLM as well.
Hence the stakeholders are the following:
The community in the Munsieville, zone 35 areas, represented by
the Ward Counsellors of the wards that fall wholly or partially within
the supply zone of the reservoir.
Mogale City Local Municipality, represented by the Municipal
Manager, Mr Dan Mashitisho.
Rand Water
Johannesburg Water
8. PROJECT MANAGEMENT TEAM STRUCTURE
Project Team Role
Project Team
Member(s) Organization Email
Manager: Water & Sanitation
Sandile Mbanjwa
Mogale City Local Municipality
Specialist: Water & Sanitation
Johann van Eck
Mogale City Local Municipality
Engineering Technician: Water & Sanitation
Org Viljoen Mogale City Local Municipality
Project Executive
Collin Radebe
Morad Consulting
Project Manager
Anna Viljoen
Morad Consulting
Project Engineer
Michael Benhura
Morad Consulting
Additional team members will be introduced as required for the successful
completion of the project. Only skilled and experienced staff, professionally
Page 9 of 15
registered where appropriate, will be assigned to the project. Mrs Anna Viljoen
will act as Project Manager for Morad Consulting and will be responsible for the
delivery of the project in terms of the defined scope. Mrs Viljoen’s authority in
terms of the execution of the project will be in accordance with the provisions of
the management of Morad Consulting.
9. TIME FRAME
The following time frames will apply to the project;
All planning, designing and tender document preparation to be done
so that the project is ready for the advertising within the current
financial year ending June 2014.
10. PROJECT BUDGET
The project budget for the planning, design, tender documentation and
implementation of the project is about R7, 652,173.00. The professional fees
are also included in the budget.
11. PLACES OF WORK
The planning, designing, tender document and preparation for the new
business plan will be primarily carried out at the Morad Consulting Offices,
at 274 Voortrekker Road, Noordheuwel. Site visits will be done to the
existing distribution network sites in Munsieville as necessary. Attendance
of scheduled meetings will be done at the offices of MCLM. Meetings with
relevant stakeholders like Rand Water and Johannesburg Water will be
held at their respective offices.
Page 10 of 15
12. SITE CLEARANCE
Clearance to proceed with construction will only be given when all required
approvals and authorization have been obtained and all applicable
environmental requirements have been satisfied. Land ownership and Surveyor-
General boundaries will be confirmed where necessary.
.
13. DELIVERABLES
Deliverable Status Importance
Project Charter Finished Required
Fee Proposal Finished Required
Concept Design Report and Drawings Finished Required
Preliminary Design Report and Drawings Finished Required
Preliminary Cost Estimate Finished Required
Detail Design Report and Drawings Started Required
Detail Cost Estimate Started Required
Tender Documents and Drawings Started Required
Contract Administration, Inspection & Monthly Progress Reports
Required
Project Program Started Required
Cash Flow Projection Started Required
Close-out report Required
14. PROFESSIONAL FEES
As per Mogale City Local Municipality appointment letter to Morad Consulting
Engineers, the appointment is in line with Morad’s existing Contract
COO(PMU)01/2011 with Mogale City Local Municipality.
Fees will be calculated according to the fee scales agreed in the above contract,
Page 11 of 15
for the following stages as defined in the Engineering Professions Act (Act 46 of
2000):
Inception
Concept and Viability
Design Development
Documentation and Procurement
Contract Administration and Inspection
Close-out
15. MILESTONES
The project deliverables listed above lead to the projects milestones and they will
be submitted in line with the project stages as follows:
Deliverable Submission Category Status Importance
Project Charter Inception Stage Finished Required
Fee Proposal Inception Stage Finished Required
Concept Design Report and Drawings
Concept and Viability Stage
Finished Required
Preliminary Design Report and Drawings
Concept and Viability Stage
Finished Required
Preliminary Cost Estimate Concept and Viability Stage
Finished Required
Detail Design Report and Drawings
Design Development Stage
Started Required
Detail Cost Estimate Design Development Stage
Started Required
Tender Documents and Drawings
Documentation and Procurement Stage
Started Required
Contract Administration, Inspection & Monthly Progress Reports
Contract Administration and Inspection Stage
Required
Project Program Concept and Viability Stage
Started Required
Cash Flow Projection Design Development Stage
Started Required
Close-out Report Close-out Stage Required
Page 12 of 15
The completion of the assignment shall be constituted by submission and
acceptance of the final tender documents and tender drawings.
16. SUCCESS CRITERIA
The success of the project will be measured in terms of the following criteria:
Submission of a complete design, including design report, tender
drawings and cost estimate.
Submission of complete tender documents and drawings, based on a
draft submitted to MCLM for comment.
Submission of a Close Out Report
17. REPORTING REQUIREMENTS AND MEETING SCHEDULE
During the execution of the project, regular progress meetings shall be held
between MCLM and Morad, to discuss progress and to ensure that the
development of options and solutions remains aligned with the ultimate vision of
MCLM for the water supply system as a whole.
The provisional meeting schedule allows for the following meetings:
One monthly meeting with the Executive Manager: Infrastructure Services
and the Manager: Water & Sanitation.
A biweekly meeting with the Manager: Water & Sanitation.
Other staff shall attend the meeting when required by the Manager: Water &
Sanitation.
During the execution of the project, the following reports will be prepared and
submitted
Concept Design Report
Preliminary Design Report
Detail Design Report
Page 13 of 15
Monthly Technical Project Report
Close-out Report
18. GUIDELINES AND STANDARDS
The design criteria, materials and methods of shall be based on the
following guidelines and standards:
The National Housing Board's: "GUIDELINES FOR THE PROVISION
OF ENGINEERING SERVICES FOR RESIDENTIAL TOWNSHIPS" –
Redbook
All materials and methods of not specifically listed in these guidelines
shall be in accordance with general methods of building as set out in
the "SABS STANDARD SPECIFICATIONS, STANDARDISED
SPECIFICATIONS and CODES OF PRACTICE" as applicable.
The criteria and guidelines will be from “GUIDELINES FOR HUMAN
AND SETTLEMENT PLANNING AND DESIGN” and “DWAF
GUIDELINES”. The discussions will be based on actual field
investigations, review of criteria related to the project and current
design and technical manuals.
Department of Water Affairs and Forestry’s: “TECHNICAL GUIDELINES
FOR THE DEVELOPMENT OF WATER AND SANITATION
INFRASTRUCTURE”
Gauteng Department of Agriculture and Rural Development “GDARD
GUIDELINES”.
Additional guidelines and standards will be consulted where required. In such
cases Morad will ensure that only recognized local and international documents
are used as the basis for any analysis or design.
19. QUALITY ASSURANCE AND CODE OF CONDUCT
Morad’s ISO 9001-accredited Quality Assurance procedures will be adhered to
Page 14 of 15
during the execution of the project.
Morad project team members will at all times conduct themselves in a
professional manner and act in accordance with the provisions of the
Engineering Services Act (Act 46 of 2000).
20. RISK MANAGEMENT
A risk is something that may happen and if it does, will have a positive or
negative impact on the project. Risk management serves to identify sources of
risk and uncertainty, determine their impact, and developing appropriate
management Reponses to minimise their impact on the project.
During the execution of this project the following four stages to risk
management planning will be observed:
Risk Identification
Risks Quantification
Risk Response
Risk Monitoring and Control
21. PROJECT APPROVAL REQUIREMENTS
All deliverables under this appointment will be submitted to the Manager: Water
& Sanitation for approval.
Each stage of the project shall be approved by the Manager: Water & Sanitation
before the next stage is commenced.
22. PROJECT SPONSOR
The project sponsor is the Mogale City Municipality, represented by the
Executive Manager: Infrastructure Services, Mr Mpako Dennis Mokotedi.
Page 15 of 15
23. ACCEPTANCE
This Project Charter prepared by Morad Consulting is based on the content of
the appointment letter dated 19 November 2013 and the discussion during the
Project Inception Meeting held on 08 August 2014 at 15H00 at the Mogale City
Local Municipality offices in President Street, Krugersdorp.
The meeting was attended by the persons identified on the Attendance Register
attached to the Minutes of the Project Inception Meeting, included in the
Annexure B.
Prepared by: Approved and accepted by:
Collin Radebe, Pr. Eng. Mr Sandile Mbanjwa
Project Manager Manager: Water & Sanitation
Morad Consulting Mogale City Local Municipality
ANNEXURE A
Appointment Letter
ANNEXURE B
Inception Meeting Minutes
Prepared By: Morad Consulting Engineers
Minutes Meeting No1 - Inception Meeting:
Contract No. COO (PMU) 01/2011
Munsieville Waterline Replacement
IN
MOGALE CITY
14 August 2014
14H50
Mogale City Local Municipality – Muldersdrift Reservoir Page 2
MOGALE CITY LOCAL MUNICIPALITY
Munsieville Waterline Replacement
ATTENDANCE REGISTER
NAME REP TEL/CELL NO:
GENDER RACE DISABLED Job Category Level
Sandile Mbanjwa
Mogale City: W & S
0783480882 M B NONE NONE [email protected]
Org Viljoen Mogale City: W &S
0832802694 M W NONE NONE [email protected]
Johann Van Eck
Mogale City: W &S
0835225038 M W NONE NONE [email protected]
Rahel D. Shibesh
Morad 0745274773 F B NONE Civil & Structural Engineer
Michael Benhura
Morad 0605254873 M B NONE Civil Engineer
Thebe Montiane
Morad 0845526897 M B NONE Civil Engineering Technician
Mogale City Local Municipality – Muldersdrift Reservoir Page 3
AGENDA
ITEM
DESCRIPTION ATTENTION TO
1 OPENING AND INTRODUCTION :
Welcome from Mr Sandile Mbanjwa
ALL
2 PROJECT TEAM:
Mogale City : Sandile Mbanjwa – Project Manager Morad Consulting Engineering and Project Management: Collin Rahel Shibeshi – Civil & Structural Engineer, Michael Benhura – Civil Engineer Anna Viljoen – Project Manager
3 ATTENDANCE:
As per register attached
4 APOLOGIES :
C Radebe,
5 PURPOSE OF MEETING:
5.1 Mogale City explained that the meeting was for the clarification of
the assignment given to Morad Consulting by Mogale City on the proposed bulk waterline replacement in Munsieville.
5.2 The assignment is for Morad to do the planning, designing and
tender documentation for the proposed bulk waterline replacement in Munsieville.
MORAD MORAD
6 DETAILS OF THE SCOPE OF WORKS:
Mogale City Local Municipality – Muldersdrift Reservoir Page 4
The scope of works to include the following;
6.1 Conducting investigations around the existing pipeline and proposed route of the new pipeline.
MORAD
6.2 Do designs for the new proposed new bulk water pipeline.
MORAD
6.4 Prepare a design report for the new bulk water pipeline. MORAD
6.5 Provide technical support to the Municipality regarding the suitable land and the relevant studies, i.e., geotechnical studies, topo-survey, etc.
MORAD
6.6 Prepare a tender document
7
PROBLEM STATEMENT:
7.1 The bulk water line supplying the vast of the Krugersdorp west areas including Munsieville area with water from Rand Water is experiencing frequent bursts. This pipe is now old and is made up of Asbestos Cement in some portions and steel in some portions. The pipe size ranges from 600mm DIA to 400mm DIA. The pipe is approximately 2.5km long. As a result of the pipe busts, the Munsieville area and Krugersdorp West areas sit without water the majority of the time. This has necessitated the need to replace the whole pipeline.
MORAD
8
DELIVERABLES:
8.4 Morad to do preliminary designs for the bulk waterline replacement and come up with a preliminary design report for submission to Mogale by the 22
nd of August.
MORAD
8.6 Morad to produce monthly progress reports for the project and present them to Mogale City.
MORAD
8.7 Morad to prepare a project program.
MORAD
8.8 Morad to produce a cash flow projection for the program.
MORAD
8.9 Morad to produce a tender document for the project by
November 2014
MORAD
9
EXPECTED TIME FRAMES:
9.1 Project Preliminary Design to be submitted by Friday 22nd
of August 2014.
MORAD
MORAD
Mogale City Local Municipality – Muldersdrift Reservoir Page 5
9.2 All planning and designing should be finished by November 2014 so that the tendering process should start that time.
10 CLOSURE
10.1 Mogale City informed Morad that they now have the ticket to start working on the project.
MORAD
11 GENERAL:
11.1 Morad to collect information of the existing distribution network soon after the meeting from Mr Org Viljoen.
MORAD/MOGALE
11.2 For access to information on existing infrastructure, Morad to liaise with Mr Van Eck for access to information on existing infrastructure, Morad to liaise with Mr Van Eck.
MORAD/MOGALE
NEXT MEETING 22 August 2014 at 10h00 Meeting adjourned.
Signed on this ...........................day of..........................................................................20..................... At ..................................................................................................................................................................
..................................................... ...............................................
For Mogale City For Morad
ANNEXURE C
Fee Proposal
MOGALE CITY LOCAL MUNICIPALITY (B) PROFESSIONAL SERVICES PROVISION FEES - MUNSIEVILLE ZONE 35
1.0 PROFESSIONAL FEES
ITEM DESCRIPTION % AMOUNT
1.1 Inception 5 R 43,157.27
1.2 Concept and Viability 25 R 215,786.34
1.3 Design Development 25 R 215,786.34
1.4 Documentation and Procurement 15 R 129,471.80
1.5 Contract Administration and Inspection 25 R 215,786.34
1.6 Close Out Report 5 R 43,157.27
Sub-Total Excl. VAT (Professional Fees) 100 R 863,145.34
2.0 ADDITIONAL FEES
ITEM DESCRIPTION RATE QTY AMOUNT
2.1 Survey R - 1 R -
2.2 Geotechnical Investigation R - 1 R -
2.2 Full Time Resident Engineer R 15,000.00 6 R 90,000.00
Sub-Total Excl. VAT (Additional Fees) R 90,000.00
3.0 DISBURSEMENTS
ITEM DESCRIPTION RATE QTY AMOUNT
3.1 Travelling R 5.72 3000 R 17,160.00
3.2 Reporting R 1,500.00 8 R 12,000.00
3.3 Health and Safety R 30,000.00 6 R 180,000.00
3.4 Copies and Printing
3.4.1. A4 Black and White R 0.93 8000 R 7,440.00
3.4.2 A4 Colour Pages R 12.71 500 R 6,355.00
3.4.3 A4 Typing R 47.67 500 R 23,835.00
3.4.4 A3 Black and White R 1.79 20 R 35.80
3.4.5 A3 Colour R 16.46 20 R 329.20
3.4.6 A3 Typing R 47.67 10 R 476.70
3.4.7. A4 Binding R 27.32 20 R 546.40
3.4.8 A1 Printing R 86.43 80 R 6,914.40
Sub-Total Excl. VAT (Disbursements) R 255,092.50
TOTAL (Excl. 14% VAT) R 1,208,237.84
Add 14% VAT R 169,153.30
TOTAL (Incl. 14% VAT) R 1,377,391.14
ANNEXURE D
Project Program
PROJECT PROGRAMME
The proposed programme is shown in figure 1 below. (can be fast-tracked if necessary)
Activities/Milestones
July 2014 Aug 2014 Sep 2014 Oct 2014 Nov 2014 Dec 2014 Jan 2015 Feb 2015 Mar 2015 Arp 2015
Inception
Concept and Viability
Design development
Documentation and Procurement
Working drawings
Construction Stage
Close Out
Legend:
Planned Tasks Completed Tasks
Figure 1 – Proposed Programme (Munsieville, Zone 35)