Top Banner

of 17

Kagiso Ext 13 Project Charter -Project Charter 02.09.2014

Oct 05, 2015

Download

Documents

Michael Benhura

project charter
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • PREPARED FOR: WATER AND SANITATION, MOGALE CITY LOCAL MUNICIPALITY PO BOX 94 KRUGERSDORP, 1740 TEL: +27 (0)11 668 0724 FAX: +27 (086) 6922903

    PREPARED BY: MORAD CONSULTING (PTY) LTD 274 VOORTREKKER ROAD NOORDHEUWEL, 1739 TEL: +27 (0) 11 954 3835 FAX: +27 (0) 11 954 6565

    MOGALE CITY LOCAL MUNICIPALITY

    KAGISO EXT 13 WATER PIPELINE REPLACEMENT, 22KM,75MM, UPVC PROJECT

    PROJECT CHARTER/SCOPE BRIEF/BUSINESS PLAN

    I (W&S) 04/2015

    AUGUST 2014

    GAUTENG PROVINCE

  • Page 2 of 17

    Contents

    1. EXECUTIVE SUMMARY ........................................................................................................................ 4

    2. BACKGROUND AND PROBLEM STATEMENT .............................................................................. 5

    3. OUTLINE BUSINESS CASE ................................................................................................................. 5

    5. PROJECT SCOPE .................................................................................................................................. 6

    6. REGULATORY REQUIREMENTS ....................................................................................................... 7

    6.1 Environmental Impact Assessment .......................................................................................................... 7

    6.2 Geotechnical Studies ................................................................................................................................ 7

    7. CONSTRAINTS AND ASSUMPTIONS ............................................................................................... 7

    7.1 Physical Constraints .................................................................................................................................. 7

    7.2 Financial Constraints .......................................................................................................................... 8

    8. STAKEHOLDERS AND COMMUNICATION ..................................................................................... 8

    9. PROJECT MANAGEMENT TEAM STRUCTURE ............................................................................. 8

    10. TIME FRAME ....................................................................................................................................... 9

    11. PROJECT FINANCES ...................................................................................................................... 9

    11.1 Professional Fees .................................................................................................................................... 9

    11.2 Cost Estimate and Work Breakdown Structure .................................................................................... 11

    11.3 Cash Flow Projection ............................................................................................................................ 12

    12. PLACES OF WORK ......................................................................................................................... 12

    13. SITE CLEARANCE ........................................................................................................................... 12

    14. DELIVERABLES ............................................................................................................................... 13

    15. MILESTONES .................................................................................................................................... 13

    16. SUCCESS CRITERIA ....................................................................................................................... 14

    17. REPORTING REQUIREMENTS AND MEETING SCHEDULE ................................................. 14

    18. GUIDELINES AND STANDARDS .................................................................................................. 15

    19. QUALITY ASSURANCE AND CODE OF CONDUCT ................................................................ 15

    20. RISK MANAGEMENT ...................................................................................................................... 16

    20.1 Health and Safety Risks ........................................................................................................................ 16

    20.2 Financial Risks ....................................................................................................................................... 16

    21. PROJECT APPROVAL REQUIREMENTS ................................................................................... 16

    22. PROJECT SPONSOR ...................................................................................................................... 16

  • Page 3 of 17

    23. ACCEPTANCE .................................................................................................................................. 17

    Table of Tables

    Table 1: (Source: Extract from Mogale City Local Municipality Strategic Plan 2012-2017) ............................... 5

    Table 2: (Source: Extract from Mogale City Local Municipality Strategic Plan 2014-2018) ............................... 5

    Table 3: Project Management Team Structure .................................................................................................. 8

    Table 4: Time Frames Related to the Project ..................................................................................................... 9

    Table 5: Professional Fees ................................................................................................................................ 10

    Table 6: Cost Estimate and Work Breakdown Structure .................................................................................. 11

    Table 7: Cash Flow Projection .......................................................................................................................... 12

    Table 8: Reporting Deliverables ....................................................................................................................... 13

    ANNEXURE A: Appointment Letter

    ANNEXURE B: Project Inception Meeting Minutes

    ANNEXURE C: Fee Proposal

    ANNEXURE D: Project Program

    ANNEXURE E: Water Balance Results

    ANNEXURE F: Tables from MCLM Strategic Plan

  • Page 4 of 17

    1. EXECUTIVE SUMMARY

    MORAD Consulting Engineers was appointed by Mogale City Local Municipality for the

    Kagiso Ext 13 Water Pipeline Replacement Project. This Project Charter forms part

    the Consultants appointment and covers the strategy for the planning, designing,

    tender documentation and contract administration of the water pipelines replacement

    in Kagiso Ext 13 as per the subject project requirements.

    Mogale City Local Municipality is experiencing unaccounted for water losses in most of

    its areas including Kagiso Ext 13. Morad did a water balance exercise in Mogale City

    to establishing extend of water loses. The results showed losses of up to 28.8% for the

    year 2011. The Municipalitys 2012-2017 and 2014-2018 strategic plans also indicate

    water losses of 31% and 33% respectively. The ultimate goal of Municipality strategic

    plan is to curb water losses to 15% at most.

    To achieve these strategic goals, Mogale City Local Municipality assigned Morad

    Consulting the Kagiso Ext 13 water pipeline replacement project.

    The project comprises of the elimination of the 110mm, 90mm and 75mm diameter

    Asbestos mid-block lines and the installation of 2700m of 110mm uPVC pipe,

    7780m of 90mm uPVC pipe and 9120m of 75mm uPVC pipe on the Municipal

    servitude. The total project cost estimate including VAT is R26 459 720.39.

    The allocated budget for the project during this financial year is R7 652 1736.00, all

    inclusive. Therefore, we recommend that the project be executed in phases, with the

    first phase having 1400m of 90mm Dia uPVC and 1600m of 75mm uPVC pipes to be

    laid for 398 stands. The total project cost estimate for the construction of this phase

    would be R6 272 681.29 including contingencies and VAT. The professional fees

    would be R1, 377,391.14 including VAT. The duration of the construction will be 6

    months.

  • Page 5 of 17

    2. BACKGROUND AND PROBLEM STATEMENT

    Morad undertook a water balance exercise in Mogale City with the view of establishing

    the extend of water loses in the area. The water balance results showed high water

    loses of up to 28.8% for the year 2011. The Municipalitys 2012-2017 strategic plan

    also showed that for the year 2011/2013, the losses had increased to about 31%.

    Furthermore, the 2014-2018 strategic plan indicates that the losses have further

    increased to 33% at this point in time. The results of the water balance exercise and

    the tables extracted from the Municipality strategic plans are attached in appendix E

    and appendix F respectively.

    Amongst other mitigation measures that could be done, Morad recommended pipe

    replacement of the old class 9 AC pipes with class 12 uPVC pipes.

    3. OUTLINE BUSINESS CASE

    According to the Municipalitys 2014-2018 strategic plan on how to ensure quality

    service delivery, at this point in time, Mogale City water los is sitting at 33%. The

    previous year it was sitting on 31%. This shows a gradual increase in water losses.

    The MCLM Strategic Plan, strategic goals for 2012-2017 and 2014-2018 are as

    follows;

    Strategic Objective

    Performance Indicator

    Requirement

    Baseline/Current

    Target 12/13

    Target 13/14

    Target 14/15

    Target 15/16

    Target 16/17

    Water (Urban and peri-urban)

    Potable water loss(%) (norm 15)

    15 31 25 20 18 15 15

    Table 1: (Source: Extract from Mogale City Local Municipality Strategic Plan 2012-2017)

    Strategic Objective

    Performance

    Indicator

    Requirement

    Baseline/Current

    Target 13/14

    Revised Target 13/14

    Target 14/15

    Target 15/16

    Target 16/17

    Target 17/18

    Water (Urban and peri-urban)

    Potable water loss(%) (norm 15)

    15 33 20 30 25 20 15 15

    Table 2: (Source: Extract from Mogale City Local Municipality Strategic Plan 2014-2018)

  • Page 6 of 17

    To achieve these strategic goals, Mogale City Local Municipality assigned Morad

    Consulting the Kagiso Ext 13 water pipeline replacement project in-order to assist in

    coming up with an engineering sound solution to curbing these water losses.

    4. PROJECT OBJECTIVES AND DESIRED OUTCOME

    The major objective of this project is to reduce the unaccounted for water losses

    in the Municipality. The desire outcome is to have a new distribution network with

    class 12 uPVC pipes replacing the class 9 AC pipes which are rotten and prone

    to bursting.

    The Municipality intends the project to be ready for tender within the current financial

    year ending June 2014.

    5. PROJECT SCOPE

    The project scope with regard to design and tender documentation is as follows;

    Conduct feasibility studies

    Prepare concept design report and drawings for the project.

    Do preliminary design for the water pipeline replacement.

    Preparation of a preliminary cost estimate for the project.

    Provide technical support to the Municipality regarding relevant studies.

    Prepare detail design report and drawings.

    Prepare detail cost estimate

    Prepare tender documents and drawings and assist with procurement.

    Contract Administration and Inspection

    Prepare close our report.

    The project scope with regard to construction is as follows;

    Lay 1400m of 90mm Dia class 12 uPVC and 1600m of 75mm class 12

    uPVC pipes.

    Prepare concept design report and drawings for the project.

  • Page 7 of 17

    Install 65 isolation valves

    Install 19 pipe bends

    Install 20 reducers

    Install 21 fire hydrants

    Provide approximately 423 house connection and accessories

    Lay 21550m of 50mm dia HDPE stand pipes.

    6. REGULATORY REQUIREMENTS

    6.1 Environmental Impact Assessment

    The project comprises of the elimination of the 110mm, 90mm and 75mm diameter

    Asbestos mid-block lines and the installation of 2700m of 110mm uPVC pipe,

    7780m of 90mm uPVC pipe and 9120m of 75mm uPVC pipe on the Municipal

    servitude.

    This project is not listed under the Environmental Impact Assessment Regulations

    Listing Notice 1 of 2010, hence there is no need to conduct an EIA.

    6.2 Geotechnical Studies

    No Geotechnical studies will be required for this pipe replacement project.

    7. CONSTRAINTS AND ASSUMPTIONS

    7.1 Physical Constraints

    The constraints and assumptions pertaining to this project area;

    It is assumed that the roads that will be crossed during laying of the pipes

    are municipal roads and that permission to cross will be obtained.

    The existing distribution network was mid-block. As a result the stand

    connections points are on the side of the mid-block. With the new

    position of the pipes along the roads it means the stand connections are

    now on the opposite side of the stands. An extension pipe will have to be

    installed from the new connection point to the old connection point. This

    will take a huge portion of the project budget.

  • Page 8 of 17

    7.2 Financial Constraints

    The allocated budget for the project during this financial year is R7 652

    1736.00, all inclusive. With this budget, only 1400m of 90mm Dia uPVC and

    1600m of 75mm uPVC pipes can be laid for 398 stands, instead of the required

    2700m of 110mm uPVC pipe, 7780m of 90mm uPVC pipe and 9120m of

    75mm uPVC pipe. This means the project has to be done in phases with the

    first phase being funded by the R7, 652 173.00 available.

    8. STAKEHOLDERS AND COMMUNICATION

    The distribution network will be owned by Mogale City Local Municipality

    (MCLM) and will be used to supply potable water to the consumers in the

    Kagiso Ext 13 area. The reservoirs are owned by MCLM as well. Hence

    the stakeholders are the following:

    The community in the Kagiso Ext 13 area, represented by the Ward

    Counsellors of the wards that fall wholly or partially within the supply zone

    of the reservoir.

    Mogale City Local Municipality, represented by the Municipal Manager,

    Mr Dan Mashitisho.

    9. PROJECT MANAGEMENT TEAM STRUCTURE

    Project Team Role Project Team

    Member(s) Organization Email

    Executive Manager: Infrastructure Services

    Mpako Dennis Mokotedi

    Mogale City Local Municipality

    Manager: Water & Sanitation

    Sandile Mbanjwa

    Mogale City Local Municipality

    [email protected]

    Project Executive Collin Radebe Morad Consulting [email protected]

    Project Engineer Michael Benhura

    Morad Consulting [email protected]

    Table 3: Project Management Team Structure

  • Page 9 of 17

    Additional team members will be introduced as required for the successful completion

    of the project. Only skilled and experienced staff, professionally registered where

    appropriate, will be assigned to the project.

    10. TIME FRAME

    The following time frames will apply to the project;

    Activitie

    s

    July 2014 Aug 2014 Sep 2014 Oct 2014 Nov 2014 Dec 2014 Jan 2015 Feb 2015 Mar 2015 Arp 2015

    Inceptio

    n

    Concept

    and

    Viabilit

    y

    Design

    develop

    ment

    Docume

    ntation

    and

    Procure

    ment

    Workin

    g

    drawing

    s

    Constru

    ction

    Stage

    Close

    Out

    Table 4: Time Frames Related to the Project

    Legend:

    Planned Tasks

    Completed Tasks

    11. PROJECT FINANCES

    11.1 Professional Fees

    As per Mogale City Local Municipality appointment letter to Morad Consulting

    Engineers, the appointment is in line with Morads existing Contract

    COO(PMU)01/2011 with Mogale City Local Municipality.

    Fees will be calculated according to the fee scales agreed in the above contract, for

  • Page 10 of 17

    the following stages as defined in the Engineering Professions Act (Act 46 of 2000):

    MOGALE CITY LOCAL MUNICIPALITY

    (B) PROFESSIONAL SERVICES PROVISION FEES - KAGISO EXT 13 ZONE 28

    1.0 PROFESSIONAL FEES

    ITEM DESCRIPTION % AMOUNT

    1.1 Inception 5 R 43,157.27

    1.2 Concept and Viability 25 R 215,786.34

    1.3 Design Development 25 R 215,786.34

    1.4 Documentation and Procurement 15 R 129,471.80

    1.5 Contract Administration and Inspection 25 R 215,786.34

    1.6 Close Out Report 5 R 43,157.27

    Sub-Total Excl. VAT (Professional Fees) 100 R 863,145.34

    2.0 ADDITIONAL FEES

    ITEM DESCRIPTION RATE QTY AMOUNT

    2.1 Survey R - 1 R -

    2.2 Geotechnical Investigation R - 1 R -

    2.2 Full Time Resident Engineer R 15,000.00 6 R 90,000.00

    Sub-Total Excl. VAT (Additional Fees) R 90,000.00

    3.0 DISBURSEMENTS

    ITEM DESCRIPTION RATE QTY AMOUNT

    3.1 Travelling R 5.72 3000 R 17,160.00

    3.2 Reporting R 1,500.00 8 R 12,000.00

    3.3 Health and Safety R 30,000.00 6 R 180,000.00

    3.4 Copies and Printing

    3.4.1. A4 Black and White R 0.93 8000 R 7,440.00

    3.4.2 A4 Colour Pages R 12.71 500 R 6,355.00

    3.4.3 A4 Typing R 47.67 500 R 23,835.00

    3.4.4 A3 Black and White R 1.79 20 R 35.80

    3.4.5 A3 Colour R 16.46 20 R 329.20

    3.4.6 A3 Typing R 47.67 10 R 476.70

    3.4.7. A4 Binding R 27.32 20 R 546.40

    3.4.8 A1 Printing R 86.43 80 R 6,914.40

    Sub-Total Excl. VAT (Disbursements) R 255,092.50

    TOTAL (Excl. 14% VAT) R 1,208,237.84

    Add 14% VAT R 169,153.30

    TOTAL (Incl. 14% VAT) R 1,377,391.14

    Table 5: Professional Fees

  • Page 11 of 17

    11.2 Cost Estimate and Work Breakdown Structure

    Description Cost

    Site Clearance R 235 500.20 Trench excavation

    R 1 242 280,00

    Provision for Pipe Bedding R 594 400.00 Supply and construction of 1600 meters long 75 mm uPVC pipelines and accessories.

    R 160 000.00

    Supply and construction of 1400 meters long 110 mm uPVC pipelines and accessories.

    R 182 000.00

    Installation of 65 isolation valves R 139 000.00

    Installation of 19 bends R 7 635.00

    Installation of 30 tees R 29 300.00

    Installation of 20 reducers

    R 11 200.00

    Installation of 21 fire hydrants within the town, Installation of thrust blocks

    R 161 140.00

    R2 240.oo

    Provide approximately 423 house connections and accessories, R 501 960.00 Provide 21 550m of 50mm dia HDPE pipe, R 754 250.00 Provision of connection to existing network, R 20 000.00

    Provisional amounts. R 625 500.00

    Preliminary & Generals R 605 955.75

    Sub-Total 1 Cost Estimate for Construction Works R 5 272 540.75

    Allow for Contract Price Escalation to be claimed in accordance with the GCC 2010 (2nd Edition) Including Contingencies @5%

    R 263,6272.04

    Total Cost Estimate for Construction Works (Excl. VAT) R 5 536 167.79

    Professional Fees Estimate, including Survey, Geo-tech, etc. R 1,208,237.84

    Total Project Cost Estimate (Excl. VAT) R6,744,405,63

    VAT R 738,155.71

    Total Project Cost Estimate (Incl. VAT) R 7,651,714.63

    Table 6: Cost Estimate and Work Breakdown Structure

  • Page 12 of 17

    11.3 Cash Flow Projection

    Period Payment Cumulative Total

    July 2014 R 172,197.50 R 172,197.50

    Aug 2014 R 319,795.35 R 491,992.85

    Sep 2014 R 196,797.14 R 688,789.98

    Oct 2014 R 734,045.16 R 1,422,835.15

    Nov 2014 R 756,845.16 R 2,179,680.31

    Dec 2014 R 1,132,566.98 R 3,312,247.29

    Jan 2014 R 1,171,070.65 R 4,483,317.94

    Feb 2014 R 1,018,566.98 R 5,501,884.92

    Mar 2014 R 1,189,088.79 R 6,690,973.71

    Arp 2014 R 961,199.28 R 7,652,173.00

    Table 7: Cash Flow Projection

    12. PLACES OF WORK

    The planning, designing, tender document and preparation for the new business

    plan will be primarily carried out at the Morad Consulting Offices, at 274

    Voortrekker Road, Noordheuwel. Site visits will be done to the existing

    distribution network sites in Kagiso as necessary. Attendance of scheduled

    meetings will be done at the offices of MCLM. Meetings with relevant

    stakeholders like Rand Water and Johannesburg Water will be held at their

    respective offices.

    13. SITE CLEARANCE

    Clearance to proceed with construction will only be given when all required approvals

    and authorization have been obtained and all applicable environmental requirements

    have been satisfied. Land ownership and Surveyor-General boundaries will be

    confirmed where necessary.

    .

  • Page 13 of 17

    14. DELIVERABLES

    The project deliverables for this pipe replacement project are as follows;

    Laying of 1400m of 90mm Dia class 12 uPVC and 1600m of 75mm class

    12 uPVC pipes.

    Installation of 65 isolation valves

    Installation of 19 pipe bends

    Installation of 20 reducers

    Installation of 21 fire hydrants

    Providing approximately 423 house connection and accessories

    Laying of 21550m of 50mm dia HDPE stand pipes.

    Reporting as follows;

    Deliverable Status Importance

    Project Charter Finished Required

    Concept Design Report and Drawings Finished Required

    Preliminary Design Report and Drawings Finished Required

    Detail Design Report and Drawings Started Required

    Tender Documents and Drawings Started Required

    Contract Administration, Inspection & Monthly Progress Reports Required

    Close-out report Required

    Table 8: Reporting Deliverables

    15. MILESTONES

    The main project milestone is the to complete the pipe replacement of the

    existing AC pipes with 1400m of 90mm Dia class 12 uPVC and 1600m of 75mm

    class 12 uPVC pipes by the end of this current financial year with the allocated

    budget of R7 652 1736.00.

  • Page 14 of 17

    16. SUCCESS CRITERIA

    The success of the project will be measured in terms of the following criteria:

    Submission of a complete design, including design report, tender drawings and

    cost estimate.

    Submission of complete tender documents and drawings, based on a draft

    submitted to MCLM for comment.

    Submission of a Close Out Report

    17. REPORTING REQUIREMENTS AND MEETING SCHEDULE

    During the execution of the project, regular progress meetings shall be held between

    MCLM and Morad, to discuss progress and to ensure that the development of options

    and solutions remains aligned with the ultimate vision of MCLM for the water supply

    system as a whole.

    The provisional meeting schedule allows for the following meetings:

    One monthly meeting with the Executive Manager: Infrastructure Services and

    the Manager: Water & Sanitation.

    A biweekly meeting with the Manager: Water & Sanitation.

    Other staff shall attend the meeting when required by the Manager: Water & Sanitation.

    During the execution of the project, the following reports will be prepared and submitted

    Concept Design Report

    Preliminary Design Report

    Detail Design Report

    Monthly Technical Project Report

    Close-out Report

  • Page 15 of 17

    18. GUIDELINES AND STANDARDS

    The design criteria, materials and methods of shall be based on the following

    guidelines and standards:

    The National Housing Board's: "GUIDELINES FOR THE PROVISION OF

    ENGINEERING SERVICES FOR RESIDENTIAL TOWNSHIPS" Redbook

    All materials and methods of not specifically listed in these guidelines shall

    be in accordance with general methods of building as set out in the "SABS

    STANDARD SPECIFICATIONS, STANDARDISED SPECIFICATIONS and

    CODES OF PRACTICE" as applicable.

    The criteria and guidelines will be from GUIDELINES FOR HUMAN AND

    SETTLEMENT PLANNING AND DESIGN and DWAF GUIDELINES. The

    discussions will be based on actual field investigations, review of criteria

    related to the project and current design and technical manuals.

    Department of Water Affairs and Forestrys: TECHNICAL GUIDELINES FOR THE

    DEVELOPMENT OF WATER AND SANITATION INFRASTRUCTURE

    Gauteng Department of Agriculture and Rural Development GDARD

    GUIDELINES.

    Additional guidelines and standards will be consulted where required. In such cases

    Morad will ensure that only recognized local and international documents are used as

    the basis for any analysis or design.

    19. QUALITY ASSURANCE AND CODE OF CONDUCT

    Morads ISO 9001-accredited Quality Assurance procedures will be adhered to during

    the execution of the project.

    Morad project team members will at all times conduct themselves in a professional

    manner and act in accordance with the provisions of the Engineering Services Act (Act

    46 of 2000).

  • Page 16 of 17

    20. RISK MANAGEMENT

    20.1 Health and Safety Risks

    Since the construction will be taking place in a built up residential area, there are

    safety risks due to the presents of plant and other equipment. The contract needs to

    take serious safety measures so as to avoid causing any damage to property or

    people in the neighborhood.

    20.2 Financial Risks

    There is risk that the project might not get sufficient funding in the next financial year

    and this can prohibit the completion of the next phases after phase 1.

    21. PROJECT APPROVAL REQUIREMENTS

    All deliverables under this appointment will be submitted to the Manager: Water &

    Sanitation for approval.

    Each stage of the project shall be approved by the Manager: Water & Sanitation

    before the next stage is commenced.

    22. PROJECT SPONSOR

    The project sponsor is the Mogale City Municipality, represented by the Executive

    Manager: Infrastructure Services, Mr Mpako Dennis Mokotedi.

  • Page 17 of 17

    23. ACCEPTANCE

    This Project Charter prepared by Morad Consulting is based on the content of the

    appointment letter dated 19 November 2013 and the discussion during the Project

    Specification Meeting held on 04 July 2014 at 14H00 at the Mogale City Local

    Municipality offices in President Street, Krugersdorp.

    The meeting was attended by the persons identified on the Attendance Register

    attached to the Minutes of the Project Inception Meeting, included in the Annexure B.

    Prepared by: Approved and accepted by:

    Collin Radebe, Pr. Eng. Mr Sandile Mbanjwa

    Project Manager Manager: Water & Sanitation

    Morad Consulting Mogale City Local Municipality