MESA and PUMA Status of deployment, User support and warranty
Monitoring for Environment and Security in Africa (MESA)
11
Présentation © 2016 – Telespazio France
IMAGINE… A SPACE APPLICATION
REVOLUTION…
IMAGINE… A SPACE APPLICATION
REVOLUTION…
Philippe RIERA
12th EUMETSAT User forum - 13/09/2016 - Kigali
Page 2
Supply Contract highlights
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
22
Présentation © 2016 – Telespazio France
Page 3
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
� Telespazio France:
� Supply Contract Management
� System Design & Validation
� Hardware integration & PHST (Logistics)
� Installation management and monitoring
� Thales Alenia Space:
Supply Contract highlights
33
Présentation © 2016 – Telespazio France
� Thales Alenia Space:
� System Design
� eStation2 integration (from JRC)
� Meteo France International:
� Synergie upgrade & integration
� Deployment Teams:
� On-site deployments
� On-site training
Page 4
Deployment teams
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
� ECOWAS : Etienne KENNE (Cameroon)
� IGAD : Peter MUTAI (Kenya)
� SADC : Abay ASSEFA (Ethiopia)
Supply Contract highlights
44
Présentation © 2016 – Telespazio France
� SADC : Abay ASSEFA (Ethiopia)
� CEMAC : Freddy FALANGA (DR Congo)
� IOC : Telespazio France
Page 5
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Figures and challenges:
• 178 stations: 116 MESA (full & partial) and 58 PUMA + 4 training centres
• 600 PCs to integrate, configure and test
Supply Contract highlights
55
Présentation © 2016 – Telespazio France
• 600 PCs to integrate, configure and test
• 50 tons of equipment to pack and ship
• 49 countries meaning 49 different situations in terms of administrative processes, shipment, packing, export control, customs, transit agent, etc.
Page 6
Supply Contract highlights
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
MESA Supply Contract (2015)
STATIONS UPGRADE NEW STATIONS
66
Présentation © 2016 – Telespazio France
PUMA2010 to PUMA2015
49 stations
AMESD to MESA
55 stations
PUMA2015
9 stations
MESA
61 stations
PUMA/MESA Training
Centres
4 centres
Page 7
Supply Contract highlights
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Project Milestones
Name Duration Scheduled DateReal
DateDetail
T0 13/05/2015 13/05/2015 Contract signature
KOM 3 weeks 03/06/2015 18/06/2015Review of activity, infrastructure
documentation, function and specification
Design validation and starting of
77
Présentation © 2016 – Telespazio France
FAT 4 months 1/2 27/09/2015 11/12/2015Design validation and starting of
deploiement of 7 references station
VGF start 8 months 13/01/2016 20/06/2016Starting of validation of 7 references
station with ISO 1.0,.3 version
VGF end 1 month 13/02/2016 20/07/2016End validation of 7 references station and
sending of the VGF report
FPA 18 months 13/11/2016 Full Provisionall Aceptance
End SW
warrantly30 months 13/11/2017 End of software warrantly
End HW
warrantly36 months 13/11/2019 End of hardware warrantly
Page 8
Deployment status - TULEAP
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
88
Présentation © 2016 – Telespazio France
Page 9
Pending issues
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
� Tax exemption and Customs clearance:
� Average time = 40 days
99
Présentation © 2016 – Telespazio France
� Average time = 40 days
� Niger, Angola, Benin, South Africa…
Page 10
Pending issues
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
� Site surveys : 13 % missing
RIC RETURNED PENDING TOTAL % Completed
MOI 11 2 13 85%
1010
Présentation © 2016 – Telespazio France
MOI 11 2 13 85%
UoG 22 2 24 92%
ICPAC 26 4 30 87%
CICOS 18 3 21 86%
AGRHYMET 31 10 41 76%
BDMS-CSC 36 2 38 95%
ACMAD 4 0 4 100%
TOTAL 148 23 171 87%
Page 11
Pending issues
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
� Antenna slabs : 57 % not built !
RIC Slab ReadySlab Not
ReadyTOTAL % Completed
MOI 0 0 0 0%
UoG 11 8 19 58%
1111
Présentation © 2016 – Telespazio France
UoG 11 8 19 58%
ICPAC 2 7 9 22%
CICOS 2 5 7 29%
AGRHYMET 1 5 6 17%
BDMS-CSC 8 8 16 50%
ACMAD 2 1 3 67%
TOTAL 26 34 60 43%
Page 12
Status of Deployments
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
1212
Présentation © 2016 – Telespazio France
Page 13
Deployment Schedule vs initial planning
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
1313
Présentation © 2016 – Telespazio France
Page 14
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Deployment schedule : September
� Cameroon (continued)
� DRC (continued)
Schedule
�Rwanda�Sao Tomé�Sudan
1414
Présentation © 2016 – Telespazio France
� Equatorial Guinea
� Ethiopia (Continued)
� Gambia
� Ghana
� Guinée Conakry
� Kenya (continued)
� Namibia
�Sudan�Swaziland�Tanzania
Page 15
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Deployment schedule : October
� Benin
� Burkina Faso
� Chad
Schedule
�Mauritania�Nigeria�RCA
1515
Présentation © 2016 – Telespazio France
� Chad
� Comoros
� Djibouti
� Ivory Coast
� Lesotho
� Malawi
� Madagascar
�RCA�Senegal�South Africa�South Sudan�Zimbabwe�Sierra Leone �Guinee Bissau
Page 16
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Deployment schedule : November
� Angola
� Eritrea
� Gabon
� Liberia
Schedule
1616
Présentation © 2016 – Telespazio France
� Liberia
� Mozambique
� Seychelles
� Somalia
� Uganda
Page 17
Users support -Tuleap
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
� One single Point of Contact :
EUMETSAT Helpdesk by email at [email protected] or by phone at +49 6151 807 3660/3770
1717
Présentation © 2016 – Telespazio France
� One single source of information:
TULEAP at https://tuleap.telespazio.fr
Page 18
Users support -Tuleap
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Tuleap is an Open Source Suite for Application Lifecycle Management tailored to follow-up MESA status for :
�Documentation
1818
Présentation © 2016 – Telespazio France
�Anomalies
�MESA/PUMA2015 Stations status and configuration
�Deployment Schedule
Page 19
Users support -Tuleap
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Users Accounts :
Account Type Occurrences
EO Focal Point 58
Eumetsat 4
Government and Ministers 8
1919
Présentation © 2016 – Telespazio France
Government and Ministers 8
other 139
REC Focal Point 2
RIC Focal Point 16
STATION ADMIN 18
STATION FOCAL POINT 10
STATION USER 2
TA representative 7
TA Thematic Expert 44
Trainer 9
UA representative 36
Page 20
Users support -Tuleap
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
2020
Présentation © 2016 – Telespazio France
Follow and update Station information
Page 21
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Users support -Tuleap
2121
Présentation © 2016 – Telespazio France
Page 22
Users support -Tuleap
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
2222
Présentation © 2016 – Telespazio France
NCR creation and follow-up
Page 23
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Users support -Tuleap
2323
Présentation © 2016 – Telespazio France
Page 24
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
Users support -Tuleap
2424
Présentation © 2016 – Telespazio France
Page 25
Warranty
MESA AND PUMA STATUS OF DEPLOYMENT, USER SUPPORT AND WARRANTY
1 year Software warranty covering:
� Sending of security updates (dissemination)
� NCRs fixing
3 years Hardware warranty covering:
� Support to diagnostic
2525
Présentation © 2016 – Telespazio France
� Support to diagnostic
� Handling of local repair when feasible
� Replacement of failing device if local repair is not possible
Page 26