Laois Sawmills Ltd .1 Annual Environmental report 2011 LAOIS SAWMILLS LTD. IPC Licence P0322-01 ANNUAL ENVIRONMENTAL REPORT 2011
Laois Sawmills Ltd .1 Annual Environmental report 2011
LAOIS SAWMILLS LTD.
IPC Licence P0322-01
ANNUAL ENVIRONMENTAL REPORT 2011
Laois Sawmills Ltd .2 Annual Environmental report 2011
CONTENTS
Introduction
Site Location
Company Background
Site Activities
Emissions data -Summary
Consumption Figures
Spending on environmental protection
Laois Sawmills Ltd., Objectives and Targets.
Environmental Management Programme 2011
Report on 2011 Environmental Management Programme
Environmental Management Programme 2012
Laois Sawmills Ltd .3 Annual Environmental report 2011
Laois Sawmills Ltd : IPC license register number 322-01
Location of the site: Ballymacken, Portlaoise, Co. Laois
General Manager: Rory Roberts
Introduction
Site Location
The Laois sawmills site is located approximately 2km from Portlaoise on the main Portlaoise –Carlow road.
Company Background
This sawmill has been operation since 1984 .The company currently employs 48 persons. Mr. Jim McNamara is the Managing Director. Rory Roberts is the general manager and main contact person in relation to EPA license compliance.
Site Activities
Laois Sawmills are engaged in the manufacture of pallet timber and fencing material for the Irish and English market.
In June 2009 a new wood pellet processing plant was commissioned on site which has the which is now producing 20,000 tonnes of wood pellets per annum. This fuel a clean green energy for the Irish Market assisting Ireland meet its target for 30% renewable energy by 2020. In 2011, we installed a new hammer mill to break down wood bark from the sawmill so it can be processed into wood pellets. This development has It has allowed us to increase our pellet production by 15% using waste bark. Wood pellets are produced from indigenous timber certified by the Forest Stewardship Council. Heat for this facility is provided by wood chip boiler using a renewable energy source In 2011 the company processed 84,000 tonnes of timber raw material (logs), with 4,000 tonnes of sawn timber treated with Tanalith E. The sawmill operates on a five day week and is open 8.00 hrs to 17.30 hrs Monday to Friday. The plant is closed on Saturday except for maintenance.
Laois Sawmills Ltd .4 Annual Environmental report 2011
Emissions data -Summary
Odours No complaints have been received. Aqueous based preservative is used.
Dust As per condition 5.2 of the Laois Sawmills IPC licence which requires that “The Licensee shall ensure that all operations on site shall be carried out in a manner such that air emissions do not result in significant impairment of, or significant interference with amenities or the environment beyond the site boundary. Dust is collected and housed in a purpose built collection area.
Waste management Waste sawdust and a waste wood chip is reprocessed in the new pellet process. This has had a significant positive environmental impact as transportation of wood chip and sawdust offsite has been eliminated. Now waste sawdust and a waste wood chip is reprocessed into a green fuel for sale offsite.
Solid Waste Produced 2011
Waste Material EWC Code
Amount Destination
Metal Waste 20 01 40 5.0 T Midland scrap metal, General Waste 20 03 01 2.5 T AES Waste oil 13 02 08 0.0 T Enva Ireland Ltd.,
Portlaoise Treatment Plant Sludge 03 02 04 0. T * Cardboard 20 01 01 10 Bales AES Plastic 20 01 39 20 Bales AES
Laois Sawmills Ltd .5 Annual Environmental report 2011
Consumption Figures
Energy usage; Electricity consumption for 2011 was 7,500,000 kWhr
This increase on consumption on previous years is due activities in the new Pellet Production Plant.
Water usage; Water is abstracted on-site from a well and is used for sanitary purposes. Consumption of water for the Tanalith E treatment process is estimated at 10m3/day. Rainwater is used for this process.
Oil usage; The total amount of diesel oil used for the kiln boiler in 2011 was 4 tonnes. An additional 24 tonnes was consumed by on site vehicles. 8 tonnes of lubricant oil were consumed.
Tanalith (Wood Preservative) The wood treatment plant consumed 22.5 tonnes of Tanalith E in 2011.
Bunding The new treatment plant is enclosed in a fully bunded structure and certificates of bund integrity have been provided to the EPA.
Environmental incidents; Laois Sawmills is committed to reporting all incidents to the EPA in accordance with condition 4 of the IPC licence. No incidents were reported in 2011.
Environmental complaints; There were no environmental complaints from the public in 2011.
Training and awareness;
In 2011 employees received ongoing training waste segregation. Employees have also received training on the wood pellet plant and also on the new wood treatment plant.
The treatment plant operator has received certified training.
Laois Sawmills Ltd .6 Annual Environmental report 2011
Spending on environmental management 2010
Environmental consultants €24,000
General Waste Management €2,800
General waste €2,800
Company time devoted to environmental management ( monitoring, report preparation, installation of EMS, etc.)
€13,000
EPA fee €12,400
Total
€55,000
Laois Sawmills Ltd .7 Annual Environmental report 2011
Laois Sawmills Ltd. Objectives and Targets. 2012
1. Objective Continue to develop Environmental Management System for the Site
Target
Meet all IPC requirements
2. Objective Assess all operations and review all practicable options for the use of cleaner
technology, cleaner production and minimisation of waste. To initiate waste reduction projects where practicable.
Targets
Search for Cleaner Production opportunities and implement where feasible.
3. Objective Reduce/Eliminate emissions of pollutants to the environment to include fugitive
dust emissions.
Target
To assess where pollutants are emitted and have potential to be emitted from the plant. To take measures to reduce /eliminate these emissions.
4. Objective
To demonstrate that all bunded structures and tanks on-site are water tight and resistant to penetration by materials stored therein.
Target To carry out integrity tests on all tank and drum storage area and report finding to
EPA as required by IPC licence. 5. Objective To assess ground and groundwater contamination on the site.
Target
To ensure ground and groundwater are not impacted by site activities and to rehabilitate soil contaminated by past activities.
Laois Sawmills Ltd .8 Annual Environmental report 2011
2011 Environmental Management Programme
Project 1/11 To continue to develop an Environmental Management System (EMS).
Relationship to objectives and targets:
This is in line with Laois Sawmills Ltd. 2011 EMP objective number 1.
Reason for undertaking project:
The maintenance of an EMS is necessary to fulfil Conditions 2.1 to 2.7 of the Laois Sawmills Ltd. IPC licence. It is also company policy to operate an environmental management system.
Target: Continue to improve Environmental Management System.
Project Summary:
In 2011 there are a number of aspects to the development of the EMS. These will include; • Carry out internal environmental audits on a biannual basis. • Review training plan.
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame:
• Internal environmental audits will be carried out in June and December.
• Environmental Training Plan to be reviewed and updated by June 2011
Laois Sawmills Ltd .9 Annual Environmental report 2011
Project 2/11 Carry Out Feasibility Study to install Combined Heat and Power Plant (CHP) at wood pellet facility.
Relationship to objectives and targets:
This project is in line with Laois Sawmills Ltd. 2011 EMP objective number 2; Assess all operations and review all practicable options for the use of cleaner technology, cleaner production and minimisation of waste.
Reason for undertaking project:
To reduce CO2 emissions from the facility and improve the sustainability of the pellet plant operation.
Target: To determine the cost benefit / feasibility of installing a CHP on site provide CO2 neutral electricity and heat.
Project Summary:
Review biomass CHP plants available on the market which could provide LS facility with 1 MW of electricity and 2 MW of heat which could be used to dry pellets in the pellet plant facility. Carry out cost/ benefit analysis ( including the sourcing of grant where possible)
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame: Feasibility Study to be completed by December 2011
Laois Sawmills Ltd .10 Annual Environmental report 2011
Project 3/11 Continue to monitor ground water and soil for contamination levels
Relationship to objectives and targets:
This project is in line with Laois Sawmills Ltd. 2011 EMP objective number 3; Reduce/Eliminate emissions of pollutants to the environment.
Reason for undertaking project:
This project is required to ensure compliance with condition 8.1
Target: To meet all EPA recommendations for decontamination of soil from the site
Project Summary:
Monitor groundwater contamination at all monitoring wells and report groundwater analysis to EPA.
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame: Monitor groundwater as per agreed schedule and submit results to EPA.
Laois Sawmills Ltd .11 Annual Environmental report 2011
Project 4/11 Carry out soil investigation study at original wood treatment plant area.
Relationship to objectives and targets:
This project is in line with Laois Sawmills Ltd. 2011 EMP objective number 3; Reduce/Eliminate emissions of pollutants to the environment.
Reason for undertaking project:
This project is required to ensure compliance with condition 8.1
Target: To meet all EPA recommendations for decontamination of soil from the site
Project Summary: Environmental consultants URS will be employed to carry out a
detailed survey of soil contamination levels at the original wood treatment plant area.
Based on these findings Laois Sawmill may be required to take remediation measures.
Laois Sawmills will act on the findings of this survey following discussion with the EPA.
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame: Commission soil investigation study in April 2011. Report findings to EPA before December 2011
Laois Sawmills Ltd .12 Annual Environmental report 2011
2011 Environmental Management Programme Review
Project 1/11 To continue to develop an Environmental Management System (EMS). Progress: In the last year Laois Sawmills Ltd. endeavoured to meet all of its IPC requirements and to implement its environmental management programmes. EMS procedures have been reviewed and updated to reflect changes to the plant associated with the new wood chip/ pellet processing plant. Training needs have been assessed and training provided where required. Site inspections from the EPA have been positive.
Project 2/11 Carry Out Feasibility Study to install Combined Heat and Power Plant (CHP) at wood pellet facility.
Progress: This has been carried out and deemed feasible with the assistance of grant aid form SEAI. However, since then SEAI has stop grant aiding CHP and until this decision is reversed the project to install a CHP has been put on hold.
In 2012 Laois Sawmills will investigate the possibility of the plant joining the SEAI Large Industry Energy Network ‘LIEN’ .
Laois Sawmills Ltd .13 Annual Environmental report 2011
Project 3/11 Continue to monitor ground water and soil for contamination levels Progress: Laois Sawmills have continued to monitor groundwater contamination at all monitoring wells and report groundwater analysis to EPA.
Groundwater contamination remains an issue on the site and our consultants believe this may be associated with historical contamination beneath the old treatment plant bunds. Laois Sawmills recently submitted a ground remediation proposal and are awaiting EPA approval.
Project 4/11 Carry out soil investigation study at original wood treatment plant area.
Progress: Sawmills employed URS to carry out a soil investigation study in 2011. This has been presented to the EPA.
Laois Sawmills Ltd .14 Annual Environmental report 2011
2012 Environmental Management Programme
Project 1/12 To continue to develop an Environmental Management System (EMS).
Relationship to objectives and targets:
This is in line with Laois Sawmills Ltd. 2012 EMP objective number 1.
Reason for undertaking project:
The maintenance of an EMS is necessary to fulfil Conditions 2.1 to 2.7 of the Laois Sawmills Ltd. IPC licence. It is also company policy to operate an environmental management system.
Target: Continue to improve Environmental Management System.
Project Summary:
In 2012 there are a number of aspects to the development of the EMS. These will include; • Carry out internal environmental audits on a biannual basis. • Review training plan.
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame:
• Internal environmental audits will be carried out in June and December.
• Environmental Training Plan to be reviewed and updated by June 2012
Laois Sawmills Ltd .15 Annual Environmental report 2011
Project 2/12 Contact SEAI to investigate how they can assist in energy efficiency at plant. Consider joining SEAI Large Industry Energy Network ‘LIEN’.
Relationship to objectives and targets:
This project is in line with Laois Sawmills Ltd. 2011 EMP objective number 2; Assess all operations and review all practicable options for the use of cleaner technology, cleaner production and minimisation of waste.
Reason for undertaking project:
To gain support form the SEAI on management of energy consumed on site.
Target: Investigate opportunities for improving energy efficiency at the plant with the assistance of SEAI. To join LIEN and investigate what benefits can be received through the Network. To disseminate the lessons Laid Sawmills have learned in the area of renewable energy and waste to energy projects to other Large Energy users in Ireland.
Project Summary:
Make contact with SEAI regarding their services. Attend LIEN meetings in 2012.
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame: Report to EPA on outcome by December 2012
Laois Sawmills Ltd .16 Annual Environmental report 2011
Project 3/12 Continue to monitor ground water and soil for contamination levels
Relationship to objectives and targets:
This project is in line with Laois Sawmills Ltd. 2011 EMP objective number 3; Reduce/Eliminate emissions of pollutants to the environment.
Reason for undertaking project:
This project is required to ensure compliance with condition 8.1
Target: To meet all EPA recommendations for decontamination of soil from the site
Project Summary:
Monitor groundwater contamination at all monitoring wells and report groundwater analysis to EPA.
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame: Monitor groundwater as per agreed schedule and submit results to EPA.
Laois Sawmills Ltd .17 Annual Environmental report 2011
Project 4/12 Implement ground remediation programme
Relationship to objectives and targets:
This project is in line with Laois Sawmills Ltd. 2012 EMP objective number 3; Reduce/Eliminate emissions of pollutants to the environment.
Reason for undertaking project:
This project is required to ensure compliance with condition 8.1
Target: To meet all EPA recommendations or decontamination of soil from the site
Project Summary: Following approval from the EPA of the Ground remediation
Proposal submitted in 2011, Laois Sawmills will implement this remediation programme.
Consultants URS will oversee the implementation of this programme and report to the EPA on the success of this remediation programme.
Designation of Responsibility:
The General Manager is responsible for implementation of this project.
Time Frame: Implement Ground remediation proposal, when approved by EPA Report progress on the remediation Proposal to EPA as required.
| PRTR# : P0322 | Facility Name : Laois Sawmills Limited | Filename : Copy of
P0322_2011(1)(1).xls | Return Year : 2011 | 2415 03/07/2012 12:17
Guidance to completing the PRTR workbook
Version 1.1.13
REFERENCE YEAR 2011
1. FACILITY IDENTIFICATION
Parent Company Name Laois Sawmills Limited
Facility Name Laois Sawmills Limited
PRTR Identification Number P0322
Licence Number P0322-01
Waste or IPPC Classes of Activity
No. class_name
8.3
The treatment or protection of wood, involving the use of
preservatives, with a capacity exceeding 10 tonnes of wood per
day.
Address 1 Ballymacken
Address 2 Portlaoise
Address 3 Co. Laois
Address 4
Laois
Country Ireland
Coordinates of Location -7.25100 53.0313
River Basin District IESE
NACE Code 1610
Main Economic Activity Sawmilling and planing of wood
AER Returns Contact Name Rory Roberts
AER Returns Contact Email Address [email protected]
AER Returns Contact Position Environmental Officer
AER Returns Contact Telephone Number 0502 - 21075/087 2702269
AER Returns Contact Mobile Phone Number
AER Returns Contact Fax Number 0502 - 22892
Production Volume 84000.0
Production Volume Units tonnes of raw logs processed
Number of Installations 1
Number of Operating Hours in Year 2375
Number of Employees 48
User Feedback/Comments
Web Address
2. PRTR CLASS ACTIVITIES
Activity Number Activity Name
50.1 General
3. SOLVENTS REGULATIONS (S.I. No. 543 of 2002)
Is it applicable? No
Have you been granted an exemption ?
If applicable which activity class applies (as per
Schedule 2 of the regulations) ?
Is the reduction scheme compliance route being
used ?
AER Returns Workbook
4.1 RELEASES TO AIR Link to previous years emissions data | PRTR# : P0322 | Facility Name : Laois Sawmills Limited | Filename : Copy of P0322_2011(1)(1).xls | Return Year : 2011 | 03/07/2012 12:17
8 8 16 16 24 24 6 6 6 7 6 6 16
SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION B : REMAINING PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
Diesel Oil Boiler at Kiln pellet plant wood boiler
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 Emission Point 2 T (Total) KG/Year
A (Accidental)
KG/Year
F (Fugitive)
KG/Year
03 Carbon dioxide (CO2) E ESTIMATE 80.0 0.0 80.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION C : REMAINING POLLUTANT EMISSIONS (As required in your Licence)
Please enter all quantities in this section in KGs
QUANTITY
Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
Additional Data Requested from Landfill operators
Landfill: Laois Sawmills LimitedPlease enter summary data on the
quantities of methane flared and / or
utilised
additional_pollutant_no T (Total) kg/Year M/C/E Method Code
Designation or
Description
Facility Total Capacity
m3 per hour
Total estimated methane generation (as per
site model) 0.0 N/A
Methane flared 0.0 0.0 (Total Flaring Capacity)
Methane utilised in engine/s 0.0 0.0 (Total Utilising Capacity)
Net methane emission (as reported in Section
A above) 0.0 N/A
METHOD
POLLUTANT METHOD
Method Used
RELEASES TO AIR
POLLUTANT METHOD
Method Used
For the purposes of the National Inventory on Greenhouse Gases, landfill operators are requested to provide summary data on landfill gas (Methane)
flared or utilised on their facilities to accompany the figures for total methane generated. Operators should only report their Net methane (CH4) emission
to the environment under T(total) KG/yr for Section A: Sector specific PRTR pollutants above. Please complete the table below:
Method Used
Method Used
POLLUTANT
RELEASES TO AIR
RELEASES TO AIR
4.2 RELEASES TO WATERS Link to previous years emissions data | PRTR# : P0322 | Facility Name : Laois Sawmills Limited | Filename : Copy of P0322_2011(1)(1).xls | Return Year : 2011 | 03/07/2012 12:17
8 8 16 16 24 24 6 6 6 6 6 6
SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS Data on ambient monitoring of storm/surface water or groundwater, conducted as part of your licence requirements, should NOT be submitted under AER / PRTR Reporting as this only concerns Releases from your facility
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION B : REMAINING PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION C : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
Please enter all quantities in this section in KGs
QUANTITY
Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
RELEASES TO WATERS
Method Used
RELEASES TO WATERS
RELEASES TO WATERS
Method Used
POLLUTANT
Method Used
POLLUTANT
POLLUTANT
4.3 RELEASES TO WASTEWATER OR SEWER Link to previous years emissions data | PRTR# : P0322 | Facility Name : Laois Sawmills Limited | Filename : Copy of P0322_2011(1)(1).xls | Return Year : 2011 |03/07/2012 12:17
8 8 16 16 6 6 6 6
SECTION A : PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
Please enter all quantities in this section in KGs
QUANTITY
Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER
Method Used
Method Used
POLLUTANT METHOD
POLLUTANT METHOD
4.4 RELEASES TO LAND Link to previous years emissions data | PRTR# : P0322 | Facility Name : Laois Sawmills Limited | Filename : Copy of P0322_2011(1)(1).xls | Return Year : 2011 | 03/07/2012 12:17
8 8 16 16 6 6 6 6
SECTION A : PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year
0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
Please enter all quantities in this section in KGs
QUANTITY
Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year
0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
POLLUTANT METHOD
Method Used
RELEASES TO LAND
RELEASES TO LAND
POLLUTANT METHOD
Method Used
5. ONSITE TREATMENT & OFFSITE TRANSFERS OF WASTE | PRTR# : P0322 | Facility Name : Laois Sawmills Limited | Filename : Copy of P0322_2011(1)(1).xls | Return Year : 2011 | 03/07/2012 12:17
5 8 Please enter all quantities on this sheet in Tonnes 0
Quantity
(Tonnes per
Year)
Haz Waste : Name and
Licence/Permit No of Next
Destination Facility Non
Haz Waste: Name and
Licence/Permit No of
Recover/Disposer
Haz Waste : Address of Next
Destination Facility
Non Haz Waste: Address of
Recover/Disposer
Name and License / Permit No. and
Address of Final Recoverer /
Disposer (HAZARDOUS WASTE
ONLY)
Actual Address of Final Destination
i.e. Final Recovery / Disposal Site
(HAZARDOUS WASTE ONLY)
Transfer Destination
European Waste
Code Hazardous Quantity T/Year Description of Waste
Waste
Treatment
Operation M/C/E Method Used
Location of
Treatment Name and Licence / Permit No. of Recoverer / Disposer / Broker Address of Recoverer / Disposer / Broker Name and Address of Final Destination i.e. Final Recovery / Disposal Site (HAZARDOUS WASTE ONLY) Licence / Permit No. of Final Destination i.e. Final Recovery / Disposal Site (HAZARDOUS WASTE ONLY)
Within the Country 20 01 40 No 5.0 metals R4 M Weighed Offsite in Ireland
Midland Scrap
Metal,WMP005d
Harbour St,Mountmellick
,Co. Laois,.,Ireland
Within the Country 20 03 01 No 2.5 mixed municipal waste D1 E Volume Calculation Offsite in Ireland AES,W0194-01
Kyletalesha &
Kyleclonhobert,Portlaoise,C
o. Laois ,.,Ireland
Within the Country 20 01 01 No 1.0 paper and cardboard R3 E Weighed Offsite in Ireland AES,W0194-01
Kyletalesha &
Kyleclonhobert,Portlaoise,C
o. Laois ,.,Ireland
Within the Country 20 01 39 No 1.5 plastics R3 E Weighed Offsite in Ireland AES,W0194-01
Kyletalesha &
Kyleclonhobert,Portlaoise,C
o. Laois ,.,Ireland
* Select a row by double-clicking the Description of Waste then click the delete button
Link to previous years waste data
Link to previous years waste summary data & percentage change
Method Used