2 Project Details 0 (J UCCB Oil and Gas Production Plan Application- REVISED January 20 I 8 p ;] g I: I 8
2 Project Details
0
(J
UCCB Oil and Gas Production Plan Application- REVISED
January 20 I 8
p ;] g I: I 8
2.1 Introduction
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The United California, California and Bradley ("UCCB") Energy Project consists of the
redevelopment and reactivation of previously active oil properties in the Cat Canyon Oil Field.
The +-28 acre project proposes 231 new oil, water/steam injection, and potable/non-potable water
wells located on 29 well pads, a centralized tank battery, stean1 generators, pipelines and ancillary
equipment. The entirety of the project is located on existing drill pads or currently disturbed
ground, and will use existing public and private roads for daily operations and transportation.
The Tank Battery will serve as the centralized processing facility for all proposed wells. It
will include tanks, loading racks, separators, heater treaters, a steam generator, offices and other
ancillary equipment. The wells will be cyclic steamed and produced fluids will be transported
from the wellpads via pipeline to the Tank Battery and then either trucked or transported via
pipeline to a refinery. No hydraulic fracturing is proposed as pa11 of the project.
The project is proposed to be developed in two phases: i) an Exploratory Phase and ii) a
Development Phase. The Exploratory Phase will ascertain the economic viability of the project
and current status of the oil producing reservoir and will be comprised of development of the Tank
Battery, one (1) 25 MMBtu steam generator, and drilling of up to 30 wells on Sites 0 and M.
Should the Exploratory Phase be successful, the project may enter into a Development Phase which
will include the drilling of the remaining wells and installation of the steam generators, remaining
equipment, offices, pipelines to pads and sales pipeline. The Exploratory Phase is expected to be
developed over a one to five year period, with full development expected over the following five
to twenty year period, and operations continuing thereafter until the resource is not capable of
economically producing or operations are deemed undesirable by the owner. Upon cessation of
operations, the wells will be plugged and abandoned according to State and local requirements,
equipment removed and the sites restored.
2.2 Location
The UCCB Energy Project is located in the unincorporated area of Santa Barbara County
in the Fifth Supervisorial District approximately 5 miles southeast of the City of Santa Maria and
p ;Jg c I 9
0
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
1.5 miles west of the town of Sisquoc. The project area covers portions of APN's 129-180-
018/037/038, 101-030-011 and 101-040-026. The properties cover portions of Sections 14 and
23, T9N, R33W, SBB&M. Access to the property from the south is from Dominion Road and
from the north via Orcutt-Gary Road.
Ni • I I I I I I I
Salit lA ' Wli
-~~~ ~ LOS~ PADRE S
·-- ~
" ..... N ATION.AL
Vicinity Map Figure I
(remainder of page blank)
FORE ST ~
z
8
Page 110
I'
UCCB EneraY Project
PetroRock, LLC Spring 2015
·.
EC~kAve
. .
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
#
I
e Foxonc..... ., ~rron~
..
Locality Map Figure 2
(remainder of page blank)
P age Ill
0 "'
'<l:,di" •• • ''• '11111\
0
UCCB Energy Project
PetroRock, LLC June 2015
I ~
UCCB Oil and Gas Production Plan Application- REVISED
January2018
Assessor Parcel Maps
129- 18
..... .
. ,Ll•- -w-t.- : ~ ~I
~
u. 1~t
, cl ® JI.) ~
, .. _ ,,.,. •ff>h
.t·-· :c .. ,I I ·~~,!"!
-·· . -·· I I " , , t
NOTICE ...... ~ .. fltt ............. ~91'\\t..wl*NCNllC-....,_ .-c•~ ........ ~e!a
• • - •~"<t•'
Assessor's Mop Bl<. 129-Pg, 18 Cou" ty of Sonto 8orboro, Co/if.
Figure 3-1
(remainder of page blank)
P a g c I 12
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
T 9 N,R. 32 '1® 33 w, s.aa -~-M~- 101-04 - ., .. - , .
!~
at> -~ '· n •Q,,, ffe . 11•At1...,
<:::: r;· ~~ ~~- --.•u=*' -·~' =-
~: t~!'.:c ;p._ ' .. ~ •. ~~-~
/ . \ .. .. ... '!. ·--
i I r-:;,
UCCB Energy Project
PetroRock, LLC Jwe 201S
POR. T9N RJJW SBB&M POR. RANCHO LOS ALAMOS
· ~ .
@ I 4!1. 12:tk.
k .
UCCB Energy Project
PetroRock, LLC June 201S
.. h @
' "'°''"A< I
.... 19
I ... _,, ~ ..
I.!! ..,~ ..
Assessor Parcel Maps
® 75.07 At.
@ JS.90 k .
23
@ 27J.li Ac.
Assessor Parcel Maps
I
.. -···· ~il~~' l
'i'• z-lf•~
··=t~ 5
Figure 3-2
101-03
, •• 1200 #aJ;;J; I
Figure 3-3
P <t g e I 13
2.3 Topography & Site Characteristics
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The project location covers approximately 710 gross acres and consists of rolling hills, oak
woodlands, riparian areas, chaparral, developed farmland (vineyards), wellpads and private
roadways. Bradley Canyon bisects the property in a northwest-southeast tangent (Figure 4). Grade
varies from flat to moderate slope and has been altered by prior and current farming and oil
operations. There are two intermittent blue-line creeks present in the project area. One is located
in Bradley Canyon and the other unnamed creek runs north-south along the western boundary. No
paii of the project lies within a flood hazard ai·ea.
The entirety of the property is fenced and gated. Access to the property can be from
Dominion Road from the South, or Orcutt-Garey Road from the North, ai1d then private roads
throughout the property.
(remainder of page blank)
P a g l' I 14
UCCB Energy Project
PetroRoclc, LLC June 201S
UCCB Oil and Gas Production Plan Application- REVISED
January 20 I 8
Topographic Map (USGS 1982) Figure 4
P n g c I JS
0
2.4 Lease Boundaries
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The project is made of three oil and gas leases, the United California, California Trust and
Bradley Leases. (Note: the lease boundaries do not correspond to County Assessor parcels.) Some
of the lands covered by the leases are split estates with distinct and separate ownership of the
minerals and surface. Copies of the leases and additional ownership information are provided in
Section 5.4 and Section 5.5 respectively. Two of the pads (the RM-1 and RM-2) are not located
on the leased lands, however will be drilled into the leased lands from an adjacent property.
9N, 33W
Ii
United California California Trust Parcel Parcel
15 ~4 13
I~ I
I
Bradley Parcel
22 23 24
.....
UCCB En•r&Y Projrcl I Lease Boundaries I Figure 5 Petro Roel; LLC I Jwc io 1' I
P a g c I 16
2.5 Historical Site Uses
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The UCCB Energy Project is a redevelopment and reactivation of a previously active oil
property, most recently operated by California Resources Production Corporation ("CRPC"). Oil
company activity on the property dates back to 1910, with majority of the +-249 wells drilled on
the lands between the 1960's and 1990's (Figures 6 and 7). The property was developed with
wellpads, wells, a Tank Battery, offices, roadways, pipelines and utilities. The primary production
method employed at the project site was cyclic steam and the field was productive through 2008.
Since 2008 the wells have predominantly been shut-in, the tank battery and pipelines dismantled
and an extensive remediation, plug and abandonment program executed by CRPC, who remains
responsible for abandonment and cleanup relating to previous operations. CRPC currently
maintains the roads and well pads for use during the ongoing dismantling of former operations.
Discussions with the surface owners and review of aerial photographs indicate that grazing
and farming operations have been conducted continuously on the property since at least 1960.
(remainder of page blank)
Pa ge 117
UCCB F.Dt>rg)o' ProJt'ct
UCCB Oil and Gas Production Plan Application- REVl SED
January 2018
Historical Photo (1994) Figure 6
Pa g ~· I 18
UCCU EDHl)0 l'rojttl
rccroRock, LLC J1mc 201'
UCCB Oil and Gas Production Plan Application- REVISED
January 20 I 8
DOGGRMap Figure 7
Pa g.: I 19
2.6 Current and Adjacent Uses
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Current uses of the property include a combination of grazing lands, developed fan11land,
ag facilities, oil field facilities, roadways and ranch residential. Ongoing plugging and
abandonment of wells, remediation and surface restoration activities are being conducted by
previous operators2, including a bioremediation at the proposed Tank Battery location. Of the
previous 249 historic wells, there are approximately 50 wells remaining to plug and abandon
according to DOGGR records. Photographs of each existing well pad, the tank battery location
and roads are provided in Section 5.2.
The western and southern portions of the property have active cattle and grazmg
operations. The eastern portion of the prope1iy has significant vineyard, farming and grazing
operations. There are two occupied residential structures and several unoccupied ag structures on
the eastern portion of the property. All proposed well pads and the Tank Battery are located greater
than 1,600' from the nearest residential structure.
There are active oil operations on surrounding the project. Adjacent North and West are
the Harbordt Lease and Security Fee operated by Greka. They are folly developed, active oil
properties with well pads, roads, pipelines and facilities. Adjacent Northeast, East and South are
the Cantin, Porter, GWP, UCB and Dominion oil leases operated by ERG. They are fully
developed, active oil properties with well pads, roads, pipelines and facilities. There is a planted
vineyard adjacent to the Southwest. Properties adjacent on all sides have zoning of AG-II- I 00.
(remainder <!fjJage blank)
2 Conducted under separate permit issued by County of Santa Barbara
Pag\~120
UCCB Enef1Y Project
PetroRocl:, llC June 201S
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Adjacent Uses Figure 8
Pa g c I 21
c
2.7 Zoning & Application Process
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The designated zoning on the property is AG-11-100. The proposed uses under this
application are allowed under Article 35.5 of the Santa Barbara County Land Use Code. The
applicant has submitted the project under the County's Oil and Gas Production Plan process.
Planning& ® Development_::;
General Zoning __ .. ....... ..... ~~ ___ ... ""~ ... ,
............ .... , Tr• r.partt'kl'I Corldot
Ot. Jliris!C'ia\
- C-•I Zone l a.mdlty
-· &..PM- N11M fo-.1hrwfrr
--"'" ......... ... ..- . · ... a.--• •" .... ---.. o J lit' cl .. Ct\ a C<I • .. -.. -· -... -....... -..
Sc:llo: 1:2, ,000 (#'.-..-..- .iw"l:11
0 0.5 1 -=-=M•u ..,._,.Mt_°"""-.,.a.o..... ~-·• ut
UCCB Enerc Projtct
PetroRod<, LLC June 201~
D
Project Area
Z.Oning Map Figure 8
Pa g c I 22
2.8 Ag Preserve/Compatibility
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Parcels 129-180-03 7 /03 8 and 101-040-026 are under Williamson Act Contracts (87 AP005
& 71AP-4). The County Uniform Rules list oil development as a compatible use, and as the project
footprint on the parcels containing contracts is less than 1.0% the disruption to ongoing agriculture
operations is minimal.
The project does not contain any lands that are considered prime agricultural land.
Soils Classification Map Figure 9
P<J g c l23
2.9 Cat Canyon Oilfield
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The project is located in the north-central part of Cat Canyon, a State designated oilfield in
north Santa Barbara County located about I 0 miles southeast of the City of Santa Maria. It is the
largest oil field in the County at 8,970 acres, and as of 2010 is the 20th-largest in California by
cumulative production. It was discovered in 1908 and has been in continuous production since.
There are several operators active in the oilfield. Over the years the field has seen a resurgence
due to advancement of new technologies and higher oil prices making previously uneconomic
reserves obtainable. The process of cyclic steam proposed by the project has long been used in
Cat Canyon.
The field is regulated by District 3 of the Department of Conservation, Division of Oil, Gas
& Geothermal Resources out of the Santa Maria office.
(remainder of page blank)
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
310 _ _________ ,,, ______________________ _, ~·-------------·:.3 _1 0:.
,., Ij,,;:· I ~ .- .:. :.,
l -~ ;'" .
... · -·. ' . .,· ... . } 1:::::--s~~~:-·
-~--===:±:::::::=~ r- .... · .. ·.:
.;:::., ............. . -
r I
·· .. : .... :':::..t";.; :,- . :~r., ~·. :;. ~:..::: .. '; .':::. n~ :"
-· · 1
... 1.
. ... :· .:.- •,
'-' '· . -..... ·.·.lo,·,· . 1
l-· ~ L
~ 1 I .... I
~ .. . • !----.... _,.•: .. ~-~£-:_ . trtW O-- J-- l ' AW I
,. .... .. . :. ... 0
. . ~ -· :.
.·~ :.
·. T
.. · . . :. ··1 .. . . . ,
-· .... .: ... :· ... . . . . ......
• . .
·. " . '· ..... •
.... •
I ,. :. .
.: - ~·: ... :.. f;
.. ... ·.·' . . ·-;:·;::·:. · .. . ' , ,<·, ' ~ .. . .. .... ~ ...... ~ ---::. ,.·
· -· :.: ;'.·i ":\f 5}~: ~~:.:r~~t;.0 •. ,_,/ , ...,..
- -:·, .... ~· - 7: ~~ ::;,_~-~ ~ -.. :.· ::. }-: -~\
-~ -· ; :..
·--' •. .-.~~-:.~~~~ '\ .... ..: .. :·::,..
' ,.!.. .
· .. .. · : - . , ~
..
,.~
.,•
~ .. -: ·-
-::.
~·· ·.'' ... «;: .·
r '
__________________________ ,,.,,..~----------------=.::.... _ __:·:....:====--=== DIW I 310
UCCB Energy Project
PetroRock, LLC June 2015 Cat Canyon Oilfield Map Figure IO
pug c I 25
c
0
c
2.10 Target Formations
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The target geologic formations for the producing oil wells are the Sisquoc Sands and
Monterey Shale formations, with the target depth below 3,000 feet. The target geologic formations
for the water and gas injection wells are the Sisquoc and Monterey formations. Oil from the target
formations is generally heavy, with API gravity ranging from 9 to 16 degrees. Typical resources
recovered from the wells in from these formations include oil, gas and water.
500
Paso Robles 1000
Careaga 1500
2000 Foxen -~ .c 0. 2500 Cl)
Cl 3000
3500 Sisquoc
4000
4500
5000 Monterey
5500
UCCB r...-rs:r Projttt I Stl'lllicnpl1k Columa I F~rc 11 rsoanc.t u.c I SpTtt :01s I
Page I 26
2.11 Cyclic Steaming
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Cyclic steaming is a type of thermal enhanced oil recovery. It is a long-proven and well
developed method that has been employed in Santa Barbara County, and throughout California,
for decades. The process involves heating water into steam via a steam generator, then introducing
the steam through the well into the oil reservoir to reduce viscosity allowing the oil to flow more
freely into the well and to the surface.
The cyclic nature of the process is that a well goes through a steam cycle: typically 7-10
days of being steamed, then an additional 7-10 days ofletting the steam soak in the reservoir before
being produced. Production then continues until the production rate decreases to an uneconomic
level at whfoh point the well goes through an additional steam cycle.
The project proposes one (I) 25 MMBtu as part of the Exploratory Phase, and a total of five ( 5)
steam generators upon completion of the Development Phase including one (1) 85 MMBtu
stationary, one (1) 50.0 MMBtu stationary, and three (3) 25 MMBtu portable units. During the
Exploratory Phase, the steam generator will be located at the Tank Battery. During the
Development Phase the stationary steam generators will be located at the Tank Battery and Site Z
and the three (3) portable units will be moved amongst the remaining pads. At peak production,
the project may require up to 300 acre feet of water per year, the majority of which will be provided
from recycled, non-potable water obtained from operations and wells producing from non-potable
water aquifers. The non-potable water will be processed to operational specifications via an onsite
water recycling plant. Included in the 300 acre feet, up to 23 acre feet of fresh water may be
utilized annually by the project to be used for initial operations, domestic uses, drilling, dust control
and fire suppression, and will be provided by an existing onsite well, or additional wells that may
be drilled. Natural gas for the steam generators will be provided from oil operations.
2.12 Wellpads & Wells
The project consists of a total of twenty nine (29) wellpads, of which twenty eight (28) are
existing. One new pad will be developed in a location that is currently farmed and was chosen in
consultation with the farmer to limit disruptions to ag operations. A summary of the pads is shown
p ;Jg c I 27
0
()
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
below in Table 1 and detailed well site plans are included in Section 5 .1. The well pads range in
size from 0.22 to 4.6 acres (0.63 average), and have between 3 and 50 wells per pad3 which will
be directionally drilled to reach the downhole targets.
Table 1- Well Pads
Len 2th Width #of Current Distance to Lease Pad: (ft): (ft): Acres: Wells: Use: Condition: Boundarv (ft):
Site I 200 95 0.44 5 Production* Existing Pad 248
Site J 150 85 0.29 5 Production* Existing Pad 244
Site K 175 100 0.40 5 Production* Existing Pad 638
SiteL 175 100 0.40 5 Production* Existing Pad 930
SiteM 450 175 1.81 40 Production* Existing Pad 1320
SiteN 200 140 0.64 6 Production* Existing Pad 930
SiteO 550 175 2.21 40 Production* Existing Pad 2295
Site P 200 140 0.64 6 Production* Existing Pad 938
SiteQ 125 90 0.26 3 Production* Existing Pad 924
Site Ql 150 80 0.28 3 Production* Existing Pad 786
SiteR 180 85 0.35 3 Production• Existing Pad 895
Site RI 150 75 0.26 3 Production• Existing Pad 789
Site S 140 85 0.27 3 Production• Existing Pad 612
Site SI I40 85 0.27 3 Production* Existing Pad 293
SiteT 150 65 0.22 3 Production* Existing Pad 262
Site U 150 105 0.36 3 Production* Existing Pad 248
Site V 175 70 0.28 3 Production* Existing Pad 294
SiteW 150 65 0.22 4 Production* Existing Pad 268
SiteX 150 65 0.22 4 Production* Existing Pad 429
Site Y 250 65 0.37 8 Production* Existing Pad 883
SiteZ 470 430 3.23 50 Production* Farmed 325
Site AA 140 90 0.29 4 Production* Existing Pad 560
Site AB 150 65 0.22 4 Production* Existing Pad 317
Site B-I 185 80 0.34 3 Production* Existing Pad 140
Site B-2 185 80 0.34 3 Production* Existing Pad 81
Site B-3 1I5 70 0.18 3 Production* Existing Pad 63
Site RM-1 145 80 0.27 6 Production* Existing Pad 294
Site RM-2 200 85 0.39 3 Production* Existing Pad 235 Tank Oil Processing and
Battery NIA NIA 4.6 0" transportation Existing Pad 1611
3 The layout of wells on each pad have been designated, however the applicant is proposing wells may be relocated to other pads depending on geological and engineering discoveries during development. Neither the number of well pads or total wells would increase beyond those proposed. • Oil, water/gas injection, and/or water wells A May have water well(s) at this location
Pa g c I 28
Roads 23,760 15 8.2 0
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Roads Existing Varies
Tahle I .a- ll'ell De1ail
T:i::Qe of Well Number
Class II UIC Cyclic Steam Injection & Heavy Oil Production Wells 205
Class II UIC Water Injection Wells JO
Potable/Non-Potable Water Production Wells 16
TOTAL 231
(remainder of page blank)
p il g I: I 29
c
UCCB l:•tl'K)' Projr<I
P<troRo<k, UC J,_ 2015
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Aerial Overview with Well Pads
P a g c I 30
UCCB Energy Project
PcrroRock, LLC Spring 2015
UCCB Oil and Gas Production Plan Application- REVISED
January2018
UCAL Lease Well Pads Figure 13
P a g c 131
c
UCCB Energy Project
PctroRock, LLC June 2015
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Cal Lease Well Pads Figure 14
P a g c I 32
CB Energy Project
oR le, LLC une 2 S
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Bradley Lease Well Pads Figure 15
Total acreage of the well pads is approximately 20 acres, or 2.8% of the gross acreage of
the project area. Approximately five (5) miles of existing private roadways will be utilized as part
of the project. Three of the well pads (Sites 0, M, Z) are over 1.0 acre each, however each contains
Pa g c I 33
UCCB Oil and Gas Production Plan Application- REVISED
January 20 I 8
40, 40 and 50 wells respectively. By consolidating a greater number of wells onto a lesser number
oflarger well pads, the project has reduced its overall footprint by over 50 acres (a 70% reduction,
see Figure 16) over traditional 1 well: 1 pad vertical drilling. Additional project impact reductions
realized by consolidating wellpads through lower required number of pipelines, utility lines and
roadways.
Benefits of Directional Pad Drilling
Vmi<al \\"dk ~ Wdk 0..51iae pad• 2..Km: for four v."tlk l.Oacre pad• l..Js::II..for four .. m
UCCB Eatl'IY Projtcl Directional Drilling Figure 16
Three (3) of the well pads (0, M, Z) and the Tank Battery will require grading, estimated
at 50,000 CY, and grading is anticipated to balance onsite. Each well pad will include wells,
electric pumping units, power lines, pipelines, gas separator, and steam generator (either portable
or stationary depending on pad).
2.13 Tank Battery & Equipment
The Tank Battery is located on a 4.5 acre site that previously served as the epicenter of
previous oil operations and is currently the site of an extensive soil remediation project. The Tank
Battery will include oil storage tanks, water storage tanks, water recycling plant, fire suppression
system, heater treaters, boilers, gas separators, vapor recovery, loading racks, compressors, pumps,
flares and other ancillary equipment. Table 2a below includes a detailed list of equipment
associated with the Exploratory Phase and Table 2b for the Development Phase of the project4•
C 4 Table 2b includes the equipment listed in Table 2a
P a g c I 34
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
Individual site plans included in Section 5.1 denote more specific details regarding location of the
equipment.
The Tank Battery will also include a new two story 2,400 sf office, a 3,200 sf workshop
and 960 sf operator building. The buildings will require power and water (provided by onsite
water wells) and will be served by a septic system which will be developed concurrently with
construction. Detailed plans for the Tank Battery and buildings are included in Section 5.1.
Table 2a- Exploratory Phase £q11ip111e111 Lisi
Usage Data Max.Im um Optr•tlng Sc:hedul•
Equipment Category Description Size Units Capacity Units hr day qtr year
Tanks 3000 bbl Stock Tanks (2) 30.4 ' D x 24.583' H - 3000 bbl 1.0 24 2.190 8,760 1500 bbl Cone Tanks (2) 21 .5' D x24' H - 1500 bbl 1.0 24 2.190 8.760 3000 bbl Blend Oil Tank 30.4' D x 24.583' H - 3000 bbl 1.0 24 2.190 8,760 500 bbl Blend Oil Tank 30.4 'D x 24.583' H - 500 bbl 1.0 24 2.190 8,760 1500 bbl Produced Tanks (2) 182 sg. fl 1500 bbl 1.0 24 2,190 8,760
Crude Loading Rack Crude Loadlno Rack 100 bbl/hr - - 1.0 24 1,825 7,300
Fugitive Components Gas-Valves CateQOIV G 200 comp-lo - - 1.0 24 2,190 8,760 Gas- Flanges/Connections Category G 1667 comp-Ip - - 1.0 24 2,190 8,760 Gas- Comoressor Seals to Atm 4 comn-ln - - 1.0 24 2,190 8,760 Gas- PSV to VRS 4 comp-Ip - - 1.0 24 2,190 8,760 Oil- Valves CateQory G 200 comn-ln - - 1.0 24 2,190 8,760 Oil- Flanges/Comections Category G 1767 comp-Ip - - 1.0 24 2,190 8,760 Oil- PSV to VRS 4 comp-Ip - - 1.0 24 2,190 8,760 Oil- PumE Seals - Sl~le 75 come:IE - - 1.0 24 2,190 8,760
Combustion Equipment 25 MMBtu/hr Steam Generator 25 MM Btu/hr 25 MMBtu/hr 1.0 24 2.190 8,760 Boilers and Steam Gens. 5.4 MMBtu/hr Heater Treaters (2) 5 MM Btu/hr 5 MMBtu/hr 1.0 24 2,190 8,760
2 MMBtu/hr Boilers (2) 2 MM Btu/hr 2 MMBtu/hr 1.0 24 2,190 8,760 0.4 MMBtu/hr Line Heaters (3) 0 MM Btu/hr 0 MMBtu/hr 1.0 24 2,190 8,760
Combustion Eqijpment 17 MMBtu'hr Flare 17 MM Btu/hr 17 MMBtu/hr 1.0 24 2,190 8,760 Flares
Pa g c I 35
0
(j
Table 3b- Develop111e11/ Phase Eq11ip111e11/ List
Eaulpment Category Description
Tanks 3000 bbl Stock Tanks (4) 1500 bbl Cone Tanks (2) 3000 bbl Blend Oil Tank 500 bbl Blend Oil Tank 1500 bbl Produced Water Tanks (2)
Crude Loading Rack Crude Loading Racks (4)
Fugitive Components Gas- Valves Category G Gas- Flanoes/Connectjons Cateaorv G Gas- Comoressor Seals to Atm Gas- PSV to VRS Oil- Valves Cateaorv G Oil- Flanges/Connections Category G Oil- PSV to VRS 011- Pump Seals - Single
Combustion Equipment 85 MMBtulhr Steam Generator Boilers and Steam Gens. 25 MMBtulhr Steam Generators 131
50 MMBtu/hr Steam Generator 5.4 MMBtulhr Heater Treaters 161 2 MMBtulhr Boilers (6) 2 MMBtulhr Line Heaters (3) 0.4 MMBtulhr Line Heaters (21)
Combustion Equipment 17 MMBtulhr Flares (2) Flares
2.14 Pipelines and Utilities
UCCB Oil and Gas Production Plan Application- REVISED
January2018
Usage Data Maximum Operating Sc:h•dul•
Size Units Capacltv Units hr day atr year
30.4 'D x 24.583' H - 3000 bbl 1.0 24 2,190 8,760 21.5 'D x24' H - 1500 bbl 1.0 24 2,190 8,760
30.4' D x 24.583' H - 3000 bbl 1.0 24 2,190 8,760 30.4' D x 24.583' H - 500 bbl 1.0 24 2,190 8,760
182 SQ. ft. 1500 bbl 1.0 24 2,190 8,760
100 bbl/hr - - 1.0 24 1,095 4,380
600 comp-Ip - - 1.0 24 2,190 8,760 5000 comp-Ip - - 1.0 24 2,190 8,760 .
12 comp-lo - - 1.0 24 2,190 8,760 12 comp-Ip - - 1.0 24 2,190 8,760
600 comn-ln - - 1.0 24 2,190 8,760 5300 co mo-lo - - 1.0 24 2,190 8,760
8 comP-IP - - 1.0 24 2,190 8,760 224 comp-Ip - - 1.0 24 2,190 8,760
85 MM Btu/hr 85 MMBtulhr 1.0 24 2,190 8,760 25 MM Btu/hr 25 MMBtulhr 1.0 24 2,190 8,760 50 MM Btu/hr 50 MMBtulhr 1.0 24 2,190 8,760 5 MMBtulhr 5 MMBtu/hr 1.0 24 2,190 8,760 2 MMBtulhr 2 MMBtulhr 1.0 24 2,190 8,760 2 MM Btu/hr 2 MMBtlNhr 1.0 24 2,190 8,760 0 MMBtlNhr 0 MMBtlNhr 1.0 24 2,190 8,760
17 MMBtlNhr 17 MMBtulhr 1.0 24 2,190 8,760
Produced oil, water, gas and light crude oil will be transported to and from the well pads
and Tank Battery via pipelines. The pipelines range in size from 2" to 8" and shall predominantly
be located above ground on sleepers and follow alongside existing oilfield and ag roads. As part
of the Exploratory Phase, the pipeline route connecting Pads O/M to the tank battery will be
approximately 1,000 lineal feet. If required, installation of a dry gas line from SoCal gas main line
on Foxen Canyon Road to the tank battery (approximately 14,000 lineal feet (2.7 miles)) may be
installed. As part of the Development Phase, pipelines will traverse the intermittent blue-line creek
in Bradley Canyon either through trenches or a 200' pipeline suspension bridge to interconnect
Pads X, Y, Z, AA, and AB to the Tank Battery and the sales line. The footings for the bridge will
be from existing well pads located outside the top of banks of the creek resulting in no construction
Pa g c I 36
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
within the confines of the creek. Grading for the footings will be required, and is estimated at less
than I 00 cubic yards. The suspension bridge will include two high grade steel conduits which will
contain the pipelines. The bridge conduits and associated berms are designed to contain all fluids
in case of catastrophic pipeline failure to prevent spills into the creek. Pipelines to the adjacent
property north and east to allow for possible future connection to a DOT regulated sales pipeline
at Foxen Canyon Road will also be installed during the Development Phase. At full buildout, the
pipeline route for the entire project will be approximately 23,232 lineal feet.
High voltage power lines currently bisect the property. New above ground power lines
will be installed to c01mect to the high voltage system and power poles will be installed alongside
existing oilfield and ag roads to energize the tank battery and pumping units at each well pad.
Total lineal footage of the new power lines is approximately 25,000 feet. The poles will be set
approximately 200 ' apart, and are 40' tall.
Detailed plans for the pipelines and utility route are included in Section 5 .1.
2.15 Site Assessments
2.15.1 Biological
Garcia & Associates was engaged to conduct a Biological Assessment for the proposed project.
The property has a recent history of biological assessments related to previous and ongoing
remediation activities. Garcia & Associates has been involved in several of those previous reports,
and the applicant continued to use the firm given their understanding of the property. The report,
dated June 25, 2015, is included in Section 5.3.1. The report indicates the project may be feasible
if certain recommended measures are taken prior to, during and after construction activities.
An addendum Biological Assessment was conducted by Garcia & Associates dated April 2016
to evaluate previously excluded pads (Z, RM-I, RM-2) and pipeline routes and is included is
included in Section 5.3.1. A Biological Restoration Plan conducted by Garcia & Associates dated
April 2016 is included in Section 5 .3 .2.
I' <I g.: I 37
2.15.2 Archeological
UCCB Oil and Gas Production Plan Application- REVISED
January 20 I 8
Larry Spanne, M.A. was engaged to conduct a Phase I Archeological Investigation for the
proposed project. The report, dated April 20, 2015, is included in Section 5.3.3. The Executive
Summary from the report is included below:
'Two archaeological isolates (isolated artifacts) were identified in the project area during the record search and field survey for the UCCB Project in the Cat Canyon area near Sisguoc, California. Since both of these aiiifacts were located in disturbed soil contexts on existing facility pads, and because neither of them appears
to be linked to larger archaeological deposits, thev are not considered to be important or significant cultural resources under California Environmental Quality Act Guidelines. Based on these findings it is my professional opinion that the UCCB Project. as cuJTently configured, will have no discernible adverse impact on important or significant cultural resources. Consequently, my recommendation is that the project be allowed to proceed without additional cultural resource constraints, with the exception of the standard archaeological discoverv condition which should be incorporated in the project permit, as described below under conclusions and recommendations."
A subsequent Phase I to include previously excluded pads (Z, RM-!, RM-2) and
pipeline routes was conducted by Dudek in December 2015 and is included is included in
Section 5.3.3. The Dudek Phase I indicates an absence of cultural resources present and
potential for finding unknown resources to be low.
2.15.3 Air Quality Technical Report
Interact Environmental was engaged to conduct an Air Quality Technical Rep01i (AQTR)based
on emissions from the proposed project. The report has been updated as of December 2017 and is
included in Section 5.3.5.
2.15.4 HRA and AQIA
SCS Engineers were engaged to update the February 2016 UCCB Health Risk Assessment
(HRA) ai1d the March 2017 UCCB Air Quality Impact Analysis (AQIA) for the proposed project.
Pagcj38
UCCB Oil and Gas Production Plan Application- REVISED
January 2018
The reports will be submitted when completed. A HRA and AQIA protocol for which the updated
reports will be based is found as Figure 66 in the AQTR . .
2.15.5 Water Study
Katherman Exploration Co, LLC, was engaged to conduct a Water Source Study for the
proposed project. The purpose of the report was to identify and characterize the various water
aquifers (potable and non-potable) in the project area. The report, dated June 24, 2015 is included
in Section 5.3.6.
2.15.6 Traffic
Stantec Engineering was engaged to conduct a traffic review and assessment for the proposed
project. The report, dated June 25, 2015 is included in Section 5.3.4.
2.15.7 Fire
Jack Collings & Associates was engaged to review the proposed project and make
recommendations to address fire related concerns. The report letter, dated May 15, 2015, is
included in Section 5.3.7.
2.15.8 Noise & Visual
A noise assessment was not conducted as part of this application as the project is not located
closer than 1,600' to the nearest sensitive receptor. Portions of the property are visible from public
roads, however all visible aspects of the project are on existing well pads/developed areas. The
project is proposing visual mitigation where visual impacts may be realized from the public view
shed, including use of neutral paint colors and landscaping.
P ~ gr I 39
. l