PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
Provided by
www.pm-exam-simulator.com
This presentation showcases a free sample
questions to help you study for the PMP exam
You are using Microsoft Project as a tool to
manage the project. All the activities have been
recorded and the Work Breakdown Structure has
been prepared. Your project team wants to use
different units of work for different resources.
Which document establishes the information
regarding units of measurement for resources on
a project?
A. Enterprise Environmental Factors
B. Cost Management Plan
C. Project Charter
D. Performance Measurement
Documents
Units of measurement are contained in one
of the Project Management Plan's
subsidiary plans.
B. Cost Management Plan
The Cost Management Plan establishes
units of measurement such as staff hours,
staff days, and staff weeks.
Maintaining a realistic project
schedule is very important for the
successful execution of a project.
When you develop a schedule, which
of the following items from the Project
Scope Statement will impact the
schedule?
A. Work Packages
B. Activity List
C. Assumptions and Constraints
D. Activity Attributes
Think about different parts of the
Project Scope Statement.
C. Assumptions and Constraints
Assumptions and constraints are very
important items that impact the schedule.
The Project Scope Statement contains this
information.
You collected several hundred ideas for
requirements for your current project during
brainstorming sessions. These have been
consolidated into a single visual representation
to reflect commonality and differences in
understanding. This method of requirements
depiction is known as?
A. Delphi Technique
B. Brainstorming
C. Affinity Diagram
D. Idea/Mind Mapping
This method is one of the group
creativity techniques where you map
the ideas.
D. Idea/Mind Mapping
This technique is called Idea/Mind
Mapping. This is a technique in which
ideas created through individual
brainstorming sessions are consolidated
into a single map to reflect commonality
and differences in understanding, and
generate new ideas.