7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
1/12
INSTRUMENT & CONTROL SYSTEMS DESIGN PRIMER - PROJECT ESTIMATE
SCOPE OF THIS ESTIMATE :
1) Add a new Feed Water System in the North forty
ASSUMPTIONS:1) Water Supply is handy2) Reference driawings are correct.
NOTES AND COMMENTS:1)
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
2/12
INSTRUMENT CONTROLS DESIGN PRIMER
EXECUTIVE SUMMARY WORKSHEET
Customer: ADDISON PLASTICS Charge No: 332211
Project: FEED WATER SYS Design Team I&C#2
CP No. 999444 Revision: A
WBS No. 001 Date: 2-15-02
Location: BOONIESVILLE, TX By: ZZZ
Engineering 102 $90 9,190$
Design 104 $70 7,304$
CADD & Clerical 158 $50 7,884$
Engineering 609 $90 54,783$
Design 540 $70 37,798$
CADD & Clerical 843 $50 42,145$
Engineering 90 $90 8,096$
Design 209 $70 14,613$CADD & Clerical 94 $50 4,713$
2,749 186,525$
AVG RATE COST 1 Meetings
NA 186,525$ 1 Events$38 85,956$ 1 DaysNA 344,800$ 8 DrawingsNA $25,628 1 Task
1 Each
1 Each
108 Records
211 I/O PointsItem Total: 124
317 RecordsInstrument Cost: 344,800$ 1 DrawingsInstallation Hardware Cost: 5,280$ 1 Drawings
2 Tasks
COUNT 124 Each
AI 0 12 Each
AO 0 4 DrawingsAI 60 4 DrawingsAO 19 77 Drawings
TCK 0 6 DrawingsTCJ 0 4 Drawings
TC_ 0 4 DrawingsCU 0 1 Drawings
PL 3 4 DrawingsDI 81 4 DrawingsDO 48 1 DrawingsDI 0 3 TasksDO 0 1 Each
Total: 211 248 Documents
134,727$
27,421$
Phase
One
Projection
Phase
Two
Projection
Phase
ThreeProjection
24,378$
24vdc Discrete
110vac Discrete
P&ID Dwgs [3]:Control System Spec [5]:
Analog mv I/O
Analog mA I/O
Thermocouples
RTD's
I/O TYPE
I/O SUMMARY
INSTRUMENT SUMMARY
PHASE 1 DELIVERABLES SUMMARY
Project Kickoff Meeting(s)
Travel Time:
PROJECT COST SUMMARY
CATEGORY
ENGINEERING
CONSTRUCTION
INSTRUMENTS
MATERIAL
Instrument Plan Dwgs [15]:Power Distribution Dwgs [17]:
Site Plan [15]:Control Network Single-Line [16]:
Preliminary Bill of Material [21,22]:
Site Walkdown / Investigation
Phase 2 Project Estimate [6]:
Phase 2 Project Schedule [6]:
Project Drawing List [7]:
Final Bill of Material [21,22]:
arshalling Panel Arrangements [18]:
ENGINEERING COST SUMMARY
PROJECT COST SUMMARY SHEET
Instrument Loop Sheets [17]:
Control Elementaries [17]:Control Panel Arrangements [18]:
ld Junction Box Arrangements [18]:
Instrument Specifications [14]:
Instrument Calculations [14]:
PROJECTED COST: 642,908$
Design Package Squad Check [23]:
Issue for Construction [24]:
Develop I/O Configuration [12]:
Instrument Database [13]:
PHASE 2 DELIVERABLES SUMMARY
Instrument Installation Details [19]:ield Junction Box Wiring Dwgs [20]:Marshalling Panel Connections[20]:
7/6/2012 1:27 AM
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
3/12
INSTRUMENTATION CONTROLSDESIGN PRIMER INSTRUMENT TAKEOFF WORKSHE
INSTRUMENT & CONTROL SYSTEMS DESIGN PRIMER - PROJECT ESTIMATE
AI AO AI AO TCK TCJ TC_ CU PL DI DO
12 EA Analyzer 5,000$ 60,000$ 50$ 600$ 1 1
3 EA Analyzer, Oxygen 14,000$ 42,000$ 50$ 150$ 1
6 EA Anal zer, H 2,000$ 12,000$ 50$ 300$ 12 EA Arrestor, Flame 15,000$ 30,000$ -$ 16 EA Assembly, Bubbler Well Pipe 900$ 14,400$ 25$ 400$
EA Controller, PID, Panel Mnt 1,500$ -$ 10$ -$
EA Glass, Flow 1,000$ -$ 10$ -$ EA Glass, Level 300$ -$ 10$ -$
EA Indicator, Digital 400$ -$ 10$ -$
EA Indicator, Gauge 75$ -$ 10$ -$
EA Meter, Purge 50$ -$ 10$ -$
EA Motor, Fixed Spd w/ HOA 100$ -$ 50$ -$
EA Motor, VSD w/ Tach & HOA 100$ -$ 50$ -$ 1 1
EA Orifice, Restriction 200$ -$ 10$ -$
EA Regulator, Pressure 650$ -$ 10$ -$
EA Relay 48$ -$ 10$ -$
EA Relay, Interposing 24$ -$ 10$ -$
EA Relay, Timer 120$ -$ 10$ -$
EA Rotameter 800$ -$ 10$ -$
EA RTD 300$ -$ 50$ -$ 1
EA Rupture Disk 100$ -$ 10$ -$
EA Switch, Flow 1,200$ -$ 50$ -$ EA Switch, Level, Capacitance 1,000$ -$ 50$ -$ 1
EA Switch, Level, Tuning Fork 750$ -$ 50$ -$ 1
EA Switch, Position 100$ -$ 50$ -$ 1
EA Switch, Pressure 500$ -$ 50$ -$ 1
EA Switch, Selector 150$ -$ 50$ -$ 1
EA Switch, Temp 500$ -$ 50$ -$ 1
EA Switch, Vibration 4,250$ -$ 50$ -$ 1
EA Totalizer 2,500$ -$ 10$ -$
EA Transmitter, Conductivity 800$ -$ 50$ -$ 1
EA Transmitter, Current 500$ -$ 50$ -$ 1
EA Transmitter, Flow (Mag) 2,000$ -$ 50$ -$ 1
EA Transmitter, Flow (Mass) 6,000$ -$ 50$ -$ 1
EA Transmitter, Level, DP Bubbler 1,500$ -$ 50$ -$ 1
EA Transmitter, Level, Usonic 2,000$ -$ 50$ -$ 1
5 EA Transmitter, Pressure 1,500$ 7,500$ 50$ 250$ 1
5 EA Transmitter, Pressure Diff 1,500$ 7,500$ 50$ 250$ 1
6 EA Transmitter, S eed 500$ 3,000$ 50$ 300$ 17 EA Transmitter, Temp 1,800$ 12,600$ 50$ 350$ 125 EA Valve, On/ Off W/ Limit Sw 2,500$ 62,500$ 50$ 1,250$ 2 12 EA Valve, Pressure Relief 3,300$ 6,600$ 10$ 20$ 12 EA Valve, Solenoid 100$ 1,200$ 15$ 180$ 1
14 EA Valve, Throttling 3,500$ 49,000$ 50$ 700$ 1
3 EA Vent, Conservation 3,500$ 10,500$ 10$ 30$ 2 EA Wei h Scale, Load Cell 8,000$ 16,000$ 50$ 100$ 12 EA Wei h Scale, Platform 5,000$ 10,000$ 50$ 100$ 12 EA Weigh Feeder System (Vendor) -$ -$ 150$ 300$ 2 1 1 4 2
124 Items 344,800$ 5,280$AI AO AI AO TCK TCJ TC_ CU PL DI DO
4-20Ma ThermocoupleTOTAL
PRICE
RTD 24vdc
QTY U/I DEVICE DESCRIPTION
DEVICE
PRICE
TOTAL
PRICE
HARDWARE
PRICE
mv
Page 3 of 12
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
4/12
INSTRUMENT CONTROLS DESIGN PRIMERESTIMATE WORKSHEET
11
4.0 Customer: ADDISON PLASTICS Charge No: 3322111.0 Project: FEED WATER SYS Design Team I&C#22.0 CP No. 999444 Revision: A
2 WBS No. 001 Date: 2-15-021.0 Location: BOONIESVILLE, TX By: ZZZ
25.025.0 NOTE: Numbers in brackets "[]" indicate Project Deliverables discussed in the Projects chapter
% Spare: 15% PID Loops: 2
Type
Raw
Points
Total
Points
Pts Per
Module
Module
Total
Module
Cost
Total
Cost
Modules
Per Elem.
Points
Per Elem.
Elem.
Dwgs
Points
Per Loop
Loop
Sheets
AI 0 0 8 0 1,200$ -$ 0 0 - 1 -AO 0 0 8 0 1,200$ -$ 0 0 - 1 -
AI 52 60 16 4 1,200$ 4,800$ 0 0 - 1 60.0AO 16 19 16 2 1,200$ 2,400$ 0 0 - 1 19.0TCK 0 0 16 0 500$ -$ 0 0 - 1 -TCJ 0 0 8 0 500$ -$ 0 0 - 1 -TC_ 0 0 8 0 500$ -$ 0 0 - 1 -
CU 0 0 8 0 800$ -$ 0 0 - 1 -PL 2 3 32 1 800$ 800$ 1 0 1.0 0 -DI 70 81 16 6 300$ 1,800$ 2 0 3.0 0 -DO 41 48 16 3 300$ 900$ 2 0 1.5 0 -
DI 0 0 8 0 300$ -$ 4 0 - 0 -DO 0 0 8 0 300$ -$ 4 0 - 0
211 16 10,700$ 5.5 77.0Total
Points
Total
Modules
Total
Module
Cost:
Total
Elem.
Dwgs
Total
Loop Sheets
Analog mA I/O
Thermocouples
ConnDwgs / Cabinet:
Racks / Cabinet:ArrngDwgs / Cabinet:
I/O CONFIGURATION WORKSHEET
Analog mv I/O
I/O COUNT / SCHEMATIC CALCULATION SHEET
RTD's
24vdc Discrete
110vac Discrete
Total Racks:
Total Cabinets:Points / P&ID:
Points / Plan Dwg:
Slots / Rack:
BACKGROUND DATA
7/6/2012 1:27 AM
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
5/12
INSTRUMENT CONTROLS DESIGN PRIMERESTIMATE WORKSHEET
Customer: ADDISON PLASTICS Char e No: 332211
Pro ect: FEED WATER SYS Desi n Team I&C#2CP No. 999444 Revision: A
WBS No. 001 Date: 2-15-02Location: BOONIESVILLE, TX B : ZZZ
NOTE: Numbers in brackets "[]" indicate Project Deliverables discussed in the Projects chapter
QTY UNITS MODIFIER ENGRG DESIGN CADD ENGRG DESIGN CADD
1 Meetings 2.0 2.0 2.0 2.0 2.0 2.0 6.0
1 Events 1.0 1.0 1.0 1.0 1.0 1.0 3.0
1 Days 8.0 8.0 - 8.0 8.0 - 16.0
8 Drawings 4.0 2.0 8.0 33.8 16.9 67.5 118.21 Task 8.0 2.0 - 8.0 2.0 - 10.01 Each 8.0 8.0 - 8.0 8.0 - 16.0
1 Each 8.0 8.0 - 8.0 8.0 - 16.0108 Records 0.0 0.1 0.2 1.1 10.8 21.5 33.3
211 I/O Points 0.01 0.05 0.00 2.1 10.6 - 12.7317 Records 1.5 0.01 0.01 0.10 3.2 3.2 31.7 38.0
1 Drawings 1.0 8.0 8.0 1.0 8.0 8.0 17.0
1 Drawings 8.0 8.0 8.0 8.0 8.0 8.0 24.02 Tasks 9.0 9.0 9.0 18.0 18.0 18.0 54.0
Total: 102.1 104.3 157.7 364.1
QTY UNITS MODIFIER ENGRG DESIGN CADD ENGRG DESIGN CADD
124 Each 2.00 - - 248.0 - - 248.0
12 Each 2.00 - - 24.0 - - 24.04 Drawings 2.00 17.00 25.00 8.0 68.0 100.0 176.0
4 Drawings 1.00 4.00 8.00 4.0 16.0 32.0 52.077 Drawings 0.50 2.00 2.00 38.5 154.0 154.0 346.56 Drawings 1.00 12.00 12.00 5.5 66.0 66.0 137.5
4 Drawings 1.00 8.00 16.00 4.0 32.0 64.0 100.0
4 Drawings 1.00 4.00 8.00 4.0 16.0 32.0 52.0
1 Drawings 1.00 8.00 16.00 1.0 8.0 16.0 25.04 Drawings 0.50 2.00 2.00 2.0 8.0 8.0 18.04 Drawings 1.00 8.00 16.00 4.0 32.0 64.0 100.01 Drawings 1.00 8.00 16.00 1.0 8.0 16.0 25.0
3 Tasks 1.00 16.00 24.00 3.0 48.0 72.0 123.0
1 Each 0.10 0.10 0.10 34.7 45.6 62.4 142.7
248 Documents 0.01 0.05 0.10 2.5 12.4 24.8 39.61 Task 40.00 8.00 8.00 40.0 8.0 8.0 56.0
Total: 424.2 522.0 719.2 1,665.3
QTY UNITS MODIFIER ENGRG DESIGN CADD ENGRG DESIGN CADD
1 Task 10% 166.5 - - 166.5
3 Trips 2.00 4.00 - 6.0 12.0 - 18.0248 Documents - - 0.50 - - 123.8 123.8
3 Meetings 2.00 2.00 - 6.0 6.0 - 12.03 Reports 2.00 - - 6.0 - - 6.0
Total: 184.5 18.0 123.8 326.3
QTY UNITS MODIFIER ENGRG DESIGN CADD ENGRG DESIGN CADD8 Weeks 4.00 8.00 2.00 32.0 64.0 16.0 112.0
1 Class 2.00 8.00 2.00 2.0 8.0 2.0 12.01 Class 2.00 8.00 2.00 2.0 8.0 2.0 12.0- Weeks 4.00 40.00 2.00 - - - -
7 Days 1.00 8.00 - 7.0 56.0 - 63.0
3 Days 12.00 12.00 - 36.0 36.0 - 72.0
3 Trips 2.00 4.00 - 6.0 12.0 - 18.0248 Document 10% 0.10 0.50 2.00 2.5 12.4 49.5 64.4248 Documents 0.01 0.05 0.10 2.5 12.4 24.8 39.6
Total: 90.0 208.8 94.3 393.0
QTY UNITS MODIFIER SUPV CRAFT CLERK ENGRG DESIGN CADD
2 Personnel 8.00 8.00 - 16.0 16.0 - 32.0
10 Days 8.00 16.00 2.00 80.0 160.0 20.0 260.015 Days 8.00 16.00 4.00 120.0 240.0 60.0 420.020 Days 8.00 24.00 2.00 160.0 480.0 40.0 680.0
7 Days 8.00 48.00 2.00 56.0 336.0 14.0 406.0
3 Task 8.00 48.00 2.00 24.0 144.0 6.0 174.0
- Trips 2.00 4.00 2.00 - - - -5 Days 8.00 48.00 2.00 40.0 240.0 10.0 290.0
- - - -
Total: 496.0 1,616.0 150.0 2,262.0
Kickoff Meeting
Craft 1Craft 2Craft 3
Checkout:Startup:
Travel Time (En-Route):Cleanup
Prepare Status Reports:
CONSTRUCTION LABOR - PHASE THREE
DESIGN DATA UNIT MANHOURS CALCULATED MANHOURSTOTAL
DESCRIPTION
Marshalling Panel Arrangements [18]:
Field Junction Box Wiring Dwgs [20]:
Control Panel Arrangements [18]:
Travel Time (En-Route):Document Control:
Attend Update Meetings:
DESIGN DATA UNIT MANHOURS CALCULATED MANHOURSTOTAL
DESCRIPTION
Final Bill of Material [21,22]:Marshalling Panel Connections[20]:
Instrument Loop Sheets [17]:Control Elementaries [17]:
Field Junction Box Arrangements [18]:
Site Plan [15]:
Control Network Single-Line [16]:
Develop I/O Configuration [12]:
Project Drawing List [7]:
P&ID Dwgs [3]:
DIRECT ENGINEERING LABOR - PHASE TWO (PRODUCTION)
DIRECT ENGINEERING LABOR - PHASE ONE (INVESTIGATION)
DESIGN DATATOTAL
CALCULATED MANHOURSUNIT MANHOURSDESCRIPTION
UNIT MANHOURS CALCULATED MANHOURSTOTAL
DESCRIPTION
Supervision & Proj Mgmt:
Project Kickoff Meeting(s)Travel Time:
Instrument Calculations [14]:
Power Distribution Dwgs [17]:
Site Walkdown / Investigation
DESIGN DATA UNIT MANHOURS CALCULATED MANHOURSTOTAL
DESCRIPTION
Issue for Construction [24]:O&M Manual:
ENGINEERING LABOR - PHASE THREE
INDIRECT ENGINEERING LABOR - PHASE TWO
DESIGN DATA
Travel Time (En-Route):
Packaging for 'Issue for Record'
Construction Support:
Construction Management:Checkout:
Startup:
Operations Training:Maintenance Training:
Construction "Red-Lines":
PROJECT LABOR CALCULATION SHEET
Design Package Squad Check [23]:
Control System Spec [5]:
Instrument Installation Details [19]:
Preliminary Bill of Material [21,22]:
Instrument Plan Dwgs [15]:
Instrument Specifications [14]:
Instrument Database [13]:
Phase 2 Project Schedule [6]:Phase 2 Project Estimate [6]:
Enter the percentage of drawingsthat are likely to require revisionsdue to construction changes ordesign modifications...
DATALINK=E56
DATALINK=E47
DATALINK=SUM(E33:E4
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
6/12
ARKANSAS ESTIMATE 7/6/2012 1:27 AM
COST SUMMARY
Customer: ADDISON PLASTICS Charge No: 332211 CABLE $2,303.43
Project: FEED WATER SYS Design Team I&C#2 CABINET $2,859.80
CP No. 999444 Revision: A CONDUIT $8,243.12
WBS No. 001 Date: 2-15-02 TUBING / DETAILS $5,280.00
Location: BOONIESVILLE, TX By: ZZZ INSTR. AIR PIPING $1,661.22
GRAND TOTAL: $20,347.57Are there hazardous areas? If so, what percentage of
the equipment will be in hazardous locations? 75%3696 Wiring Terminations
66 Tubing Terminations
101 Conduit Terminations
200 FT Avg Homerun Distan 50 FT Average Local Run Distance
13 100 FT $0.39 $39.00 3/C #18 AWG UNSHLD CA BLE, 300V
118 FT $0.35 $41.30 2/C #18 AWG SHLD CAB LE, 300V
600 FT $0.30 $180.00 2/C #16 AWG UNSH CABLE, 300V
500 FT $0.12 $60.00 1/c #16, 600V, Hookup Wire
463 FT $1.45 $670.63 24twpr #18, Unsh for Digital Ckt Homeruns
850 FT $1.25 $1,062.50 16twpr #18, Indiv Shld for Analog Ckt Homeruns
200 FT $1.25 $250.00 4-triad, Indiv Shld for RTD Ckt Homeruns
0 FT $1.00 $0.00 2/C Thermocouple Extension Wire
0 FT $0.60 $0.00 Network Communications Cable
$2,303
181 Electrical Devices 50% Percentage of Devices Needing Fuses 8 AverageTerminals per Device
91 EA $5.00 $905.00 Fuseblocks
1448 EA $1.35 $1,954.80 Terminals
0 EA $400 $0.00 Digital Junction box
0 EA $400 $0.00 Analog Junction Box
0 EA $1,200 $0.00 PLC Cabinet
0 EA $1,200 $0.00 24VDC Power Supply
0 EA $500 $0.00 Power Supply components
0 EA $1,000 $0.00 Power Supply Cabinet
0 EA $1,000 $0.00 Cabinet Air Condistioner
$2,860
66 Instrument Air Users 10 Ft. (Average length of drop Per U ser)
660 FT $2.20 $1,452 1/2" Pipe, Stl, Galv, Sch 40
132 EA $0.40 $53 1/2" NPT, TE E, Iron, Galv, 150#
66 EA $0.50 $33 1/2" NPT, P lug, Iron, Galv, 150#
66 EA $0.58 $38 Hanger, Pipe, A dj.Clevis, 1/2", Grinnel Fig.260
66 FT $0.15 $10 Rod, con't. Thd, Stl, Zinc-Coated
66 EA $0.35 $23 1/2" NPT, Elbow, 90 Deg, Iron, Galv, 150#
132 EA $0.02 $3 Nut, heavy Hex, Stl
33 EA $0.50 $17 Clamp, Adj. Beam, 3/8"
66 EA $0.50 $33 Bushing, Pipe, Iron, Galv, Scr, 150#, 1" x 1/2"
$1,661
BULK MATERIAL TAKEOFF WORKSHEET
WIRE & CABLE CALCULATION TABLE
TERMINATIONS, JUNCTION BOXES & CABINETS
I&C PROJECT ESTIMATE - INSTRUMENT AIR PIPING
Page 6 Of 12 102658848.xls.ms_office, Bulk Matl
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
7/12
ARKANSAS ESTIMATE 7/6/2012 1:27 AM
25.0% 101 Conduit Drops 10 Ft. (Avg drop Per User)
FT $0.45 $113.63 3/4" ,RIGID STL CONDUIT
3 EA $11.60 $34.80 3/4" ,OUTLET BODY, TYPE C27
3 EA $12.60 $37.80 3/4" ,OUTLET BODY, TYPE T27
3 EA $11.60 $34.80 3/4" ,OUTLET BODY, TYPE L27
3 EA $4.25 $12.75 3/4" ,UNION,
9 EA $1.00 $9.00 COVERS & GASKETS
26 EA $0.97 $25.22 CONDUIT CLAMP, TYPE RC-3/4
FT $0.63 $79.54 1" ,RIGID STL CO NDUIT
1 EA $14.76 $18.63 1" ,OUTLET BODY, TYPE C37
1 EA $15.52 $19.59 1" ,OUTLET BODY, TYPE T37
1 EA $14.76 $18.63 1" ,OUTLET BODY, TYPE L37
1 EA $7.62 $9.62 1" ,UNION,
4 EA $1.00 $3.79 COVERS & GASKETS
13 EA $1.07 $13.51 CONDUIT CLAMP, TYPE RC-1
FT $0.93 $58.71 11/2",RIGID STL CO NDUIT
1 EA $49.55 $31.28 11/2",OUTLET BODY TYPE GUAC59
1 EA $54.37 $34.32 11/2",OUTLET BODY TYPE GUAT59
1 EA $49.55 $31.28 11/2",OUTLET BODY TYPE GUAN59
1 EA $12.60 $7.95 11/2",UNION,EXPLOSION PROOF ,UNF505
2 EA $1.00 $1.89 COVERS & GASKETS
6 EA $11.60 $73.23 CONDUIT CLAMP, TYPE RC-1-1/2
EA $61.80 $6,241.80 FLEX CONDUIT, ECLK115
0 ft $12.00 $0.00 CABLE TRAY
$6,912
75.0% 101 Conduit Drops 10 Ft. (Avg drop Per User)
FT $0.45 $340.88 3/4" ,RIGID STL CONDUIT
8 EA $11.60 $92.80 3/4" ,OUTLET BODY, TYPE GUAC26
8 EA $12.60 $100.80 3/4" ,OUTLET BODY, TYPE GUAT26
8 EA $11.60 $92.80 3/4" ,OUTLET BODY, TYPE GUAN26
8 EA $4.25 $34.00 3/4" ,UNION,EXPLOSION PROOF U NF205
4 EA $8.00 $32.00 CONDUIT SEAL TYPE EYS21 3/4"
76 EA $0.97 $73.72 CONDUIT CLAMP, TYPE RC-3/4
FT $0.63 $238.61 1" ,RIGID STL CO NDUIT
4 EA $14.76 $55.90 1" ,OUTLET BODY, TYPE GUAC36
4 EA $15.52 $58.78 1" ,OUTLET BODY, TYPE GUAT37
4 EA $14.76 $55.90 1" ,OUTLET BODY, TYPE GUAN36
4 EA $7.62 $28.86 1" ,UNION,EXPLOSION PROOF UNF305
38 EA $1.07 $40.53 CONDUIT CLAMP, TYPE RC-1
2 EA $10.00 $18.94 CONDUIT SEAL TYPE EYS21 1"
FT $0.93 $176.12 11/2",RIGID STL CO NDUIT
2 EA $49.55 $93.84 11/2",OUTLET BODY TYPE GUAC59
2 EA $54.37 $102.96 11/2",OUTLET BODY TYPE GUAT59
2 EA $49.55 $93.84 11/2",OUTLET BODY TYPE GUAN59
2 EA $12.60 $23.86 11/2",UNION,EXPLOSION PROOF ,UNF505
19 EA $11.60 $219.68 CONDUIT CLAMP, TYPE RC-1-1/2
1 EA $28.00 $26.51 CONDUIT SEAL TYPE EYS21 11/2"
EA $61.80 $6,241.80 FLEX CONDUIT, ECLK115
0 ft $12.00 $0.00 CABLE TRAY
$8,243
Multiplier
CONDUIT & FITTINGS - CLASS I DIV II
CONDUIT & FITTINGS - GENERAL PURPOSE
Multiplier
Page 7 Of 12 102658848.xls.ms_office, Bulk Matl
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
8/12
Task Budget Spread Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 WeekProject Kickoff Meeting(s) 6.0 0.0 6
Travel Time: 3.0 0.0 3
Site Walkdown / Investigation 16.0 0.0 16
P&ID Dwgs [3]: 118.2 6.2 24 40 40 8
Control System Spec [5]: 10.0 0.0 8 2
Phase 2 Project Estimate [6]: 16.0 0.0 16
Phase 2 Project Schedule [6]: 16.0 0.0 16
Project Drawing List [7]: 33.3 5.3 16 12
Develop I/O Configuration [12]: 12.7 0.7 12
Instrument Database [13]: 38.0 0.0 24 2 12
Site Plan [15]: 17.0 1.0 16
Control Network Single-Line [16]: 24.0 0.0 8 16
Preliminary Bill of Material [21,22]: 54.0 2.0 4 24 24
Total Phase 1Manhours: 364 15 81 88 86 94 0 0 0 0 0 0 0PHASE TWO MANPOWER: 2.0 2.2 2.2 2.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Task Budget Spread Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week
Instrument Specifications [14]: 248.0 0.0 80 80 40 40
Instrument Calculations [14]: 24.0 0.0 16 8
Instrument Plan Dwgs [15]: 176.0 0.0 16 40 40 40 40
Power Distribution Dwgs [17]: 52.0 0.0 40
Instrument Loop Sheets [17]: 346.5 33.7 40 40 40 40 40 40
Control Elementaries [17]: 137.5 0.0 16 40 40 40
Control Panel Arrangements [18]: 100.0 0.0 24 40 32
Field Junction Box Arrangements [18]: 52.0 0.0 24 24
Marshalling Panel Arrangements [18]: 25.0 0.0 24Instrument Installation Details [19]: 18.0 0.0
Field Junction Box Wiring Dwgs [20]: 100.0 0.0 40
Marshalling Panel Connections[20]: 25.0 0.0
Final Bill of Material [21,22]: 123.0 0.0 40 40
Design Package Squad Check [23]: 142.7 2.7
Issue for Construction [24]: 39.6 -0.4
O&M Manual: 56.0 0.0
Total Phase 2 Manhours: 1665 36 0 0 0 0 80 176 176 168 184 208 152 1
Phase 2 Engrg Manpower: 0.0 0.0 0.0 0.0 2.0 4.4 4.4 4.2 4.6 5.2 3.8
Task Budget Spread Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week
Construction Support: 112.0 4.0
Operations Training: 12.0 0.0
Maintenance Training: 12.0 0.0
Construction Management: 0.0 0.0
Checkout: 63.0 0.0
Startup: 72.0 0.0
Travel Time (En-Route): 18.0 0.0
Construction "Red-Lines": 64.4 2.3
Packaging for 'Issue for Record' 39.6 1.6
Total Phase 3 Engrg Manhours: 393 8 0 0 0 0 0 0 0 0 0 0 0
Phase 3 Engrg Manpower: 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Kickoff Meeting 32.0 0.0
Craft 1 260.0 20.0
Craft 2 420.0 60.0
Craft 3 680.0 0.0Checkout: 406.0 14.0
Startup: 174.0 0.0
Travel Time (En-Route): 0.0 0.0
Cleanup 290.0 0.0
Total Phase 3 Construction Manhours: 2262 94 0 0 0 0 0 0 0 0 0 0 0
Phase 3 Construction Manpower: 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Staff Allocation:
Staff Allocation:
Staff Allocation:
PROJECT ENGINEERING SCHEDULE - PHASE ONE
PROJECT ENGINEERING SCHEDULE - PHASE TWO
PROJECT SCHEDULE - PHASE THREE
Staff Allocation:
P1 P1 P2
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
9/12
Manhours per Unit of Time: 40 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Wee
Task Budget Start Finish Duration Resource 1 2 3 4 5 6 7 8 9
Project Kickoff Meeting(s) 6.0 1 1 1 0.2 1
Travel Time: 3.0 1 1 1 0.1 1
Site Walkdown / Investigation 16.0 1 1 1 0.4 1
P&ID Dwgs [3]: 118.2 1 4 4 0.7 1 2 3 4
Control System Spec [5]: 10.0 2 4 3 0.1 2 4
Phase 2 Project Estimate [6]: 16.0 4 4 1 0.4 4Phase 2 Project Schedule [6]: 16.0 4 4 1 0.4 4
Project Drawing List [7] : 33.3 1 2 2 0.4 1 2
Develop I/O Configuration [12]: 12.7 3 3 1 0.3 3
Instrument Database [13]: 38.0 2 4 3 0.3 2 3 4
Site Plan [15]: 17.0 1 1 1 0.4 1
Control Network Single-Line [16]: 24.0 3 4 2 0.3 3 4
Preliminary Bill of Material [21,22]: 54.0 2 4 3 0.5 2 3 4
Task Budget Start Finish Duration Resource 1 2 3 4 5 6 7 8 9
Instrument Specifications [14]: 248.0 5 8 4 1.6 5 6 7 8
Instrument Calculat ions [14]: 24.0 7 8 2 0.3 7 8
Instrument Plan Dwgs [15]: 176.0 6 10 5 0.9 6 7 8 9
Power Distribut ion Dwgs [17]: 52.0 9 14 6 0.2 9
Instrument Loop Sheets [17]: 346.5 6 14 9 1.0 6 7 8 9
Control Elementaries [17]: 137.5 6 14 9 0.4 6 7 8 9
Control Panel Arrangements [18]: 100.0 9 14 6 0.4 9
Field Junction Box Arrangements [18]: 52.0 15 14 6
Marshalling Panel Arrangements [18]: 25.0 0 0 - -
Instrument Installation Details [19]: 18.0 - -
Field Junction Box Wiring Dwgs [20]: 100.0 11 13 3 0.8
Marshalling Panel Connections[20]: 25.0 12 14 3 0.2
Final Bill of Material [21,22]: 123.0 10 14 5 0.6
Design Package Squad Check [23]: 142.7 13 14 2 1.8
Issue for Construction [24]: 39.6 14 14 1 1.0
O&M Manual: 56.0 14 14 1 1.4
Task Budget Start Finish Duration Resource 1 2 3 4 5 6 7 8 9
Construct ion Support: 112.0 14 22 9 0.3
Operations Training: 12.0 19 19 1 0.3
Maintenance Training: 12.0 19 19 1 0.3
Construction Management: 0.0 - -
Checkout: 63.0 20 20 1 1.6
Startup: 72.0 21 21 1 1.8
Travel Time (En-Route) : 18.0 20 21 2 0.2
Construction "Red-Lines": 64.4 22 22 1 1.6
Packaging for 'Issue for Record' 39.6 22 22 1 1.0
Kickoff Meeting 32.0 15 15 1 0.8
Craft 1 260.0 16 17 2 3.3
Craft 2 420.0 17 19 3 3.5
Craft 3 680.0 17 21 5 3.4
Checkout: 406.0 20 20 1 10.2
Startup: 174.0 21 21 1 4.4
Travel Time (En-Route): 0.0 - -
Cleanup 290.0 22 22 1 7.3
PROJECT ENGINEERING SCHEDULE - P
PROJECT ENGINEERING SCHEDULE - P
PROJECT SCHEDULE - PHASE TH
Units from "Schedule" Worksheeet:
P1 P1 P2
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
10/12
0
100
200
300
400
500
600
700
Week1
Week2
Week3
Week4
Week5
Week6
Week7
Week8
Week9
Week10
Week11
Week12
Week13
Week14
Week15
Week16
Week17
Week18
MANHOURS
WEEKS
PROJECT MANHOUR LOADING CHART
Phase 1 Engr Phase 2 Engr Phase 3 Engr Phase 3 C
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
11/12
Week19
Week20
Week21
Week22
onstr
7/31/2019 File 1B AddisonPlasticsEstimate&Schedule
12/12
Period
%Comp
1.0%
Member#1
Member#2
Member#3
Member#4
Member#5
Member#6
Member#7
Member#8
M e m b e r # 9
Task Budget Spent Remain Week 1 40.0 14.0 - 17.0 2.5 - - -
Project Kickoff Meeting(s) 6.0 3.3 2.7 3.3 3.3 0.8 - - - 2.5 - - -
Travel Time: 3.0 0.8 2.2 0.8 0.8 0.8 - - - - - - -Site Walkdown / Investigation 16.0 4.0 12.0 4.0 4.0 4.0 - - - - - - -
P&ID Dwgs [3]: 118.2 18.3 99.9 18.3 18.3 4.0 12.6 - 1.7 - - - -
Control System Spec [5]: 10.0 4.0 6.0 4.0 4.0 4.0 - - - - - - -
Phase 2 Project Estimate [6]: 16.0 4.0 12.0 4.0 4.0 4.0 - - - - - - -
Phase 2 Project Schedule [6]: 16.0 4.0 12.0 4.0 4.0 4.0 - - - - - - -
Project Drawing List [7]: 33.3 18.7 14.6 18.7 18.7 2.0 1.4 - 15.3 - - - -
Develop I/O Configuration [12]: 12.7 2.0 10.7 2.0 2.0 2.0 - - - - - - -
Instrument Database [13]: 38.0 2.0 36.0 2.0 2.0 2.0 - - - - - - -
Site Plan [15]: 17.0 2.0 15.0 2.0 2.0 2.0 - - - - - - -
Control Network Single-Line [16]: 24.0 2.0 22.0 2.0 2.0 2.0 - - - - - - -
Preliminary Bill of Material [21,22]: 54.0 2.4 51.6 2.4 2.4 2.4 - - - - - - -
Instrument Specifications [14]: 248.0 4.0 244.0 4.0 4.0 4.0 - - - - - - -
Instrument Calculations [14]: 24.0 2.0 22.0 2.0 2.0 2.0 - - - - - - -
Instrument Plan Dwgs [15]: 176.0 - 176.0 - 0.0 - - - - - - - -Power Distribution Dwgs [17]: 52.0 - 52.0 - 0.0 - - - - - - - -
Instrument Loop Sheets [17]: 346.5 - 346.5 - 0.0 - - - - - - - -
Control Elementaries [17]: 137.5 - 137.5 - 0.0 - - - - - - - -
Control Panel Arrangements [18]: 100.0 - 100.0 - 0.0 - - - - - - - -
Field Junction Box Arrangements [18]: 52.0 - 52.0 - 0.0 - - - - - - - -
Marshalling Panel Arrangements [18]: 25.0 - 25.0 - 0.0 - - - - - - - -
Instrument Installation Details [19]: 18.0 - 18.0 - 0.0 - - - - - - - -
Field Junction Box Wiring Dwgs [20]: 100.0 - 100.0 - 0.0 - - - - - - - -
Marshalling Panel Connections[20]: 25.0 - 25.0 - 0.0 - - - - - - - -
Final Bill of Material [21,22]: 123.0 - 123.0 - 0.0 - - - - - - - -
Design Package Squad Check [23]: 142.7 - 142.7 - 0.0 - - - - - - - -
Issue for Construction [24]: 39.6 - 39.6 - 0.0 - - - - - - - -
O&M Manual: 56.0 - 56.0 - 0.0 - - - - - - - -
Construction Support: 112.0 - 112.0 - 0.0 - - - - - - - -Operations Training: 12.0 - 12.0 - 0.0 - - - - - - - -
Maintenance Training: 12.0 - 12.0 - 0.0 - - - - - - - -
Construction Management: 0.0 - - - 0.0 - - - - - - - -
Checkout: 63.0 - 63.0 - 0.0 - - - - - - - -
Startup: 72.0 - 72.0 - 0.0 - - - - - - - -
Travel Time (En-Route): 18.0 - 18.0 - 0.0 - - - - - - - -
Construction "Red-Lines": 64.4 - 64.4 - 0.0 - - - - - - - -
Packaging for 'Issue for Record' 39.6 - 39.6 - 0.0 - - - - - - - -
Kickoff Meeting 32.0 - 32.0 - 0.0 - - - - - - - -
Craft 1 260.0 - 260.0 - 0.0 - - - - - - - -
Craft 2 420.0 - 420.0 - 0.0 - - - - - - - -
Craft 3 680.0 - 680.0 - 0.0 - - - - - - - -
Checkout: 406.0 - 406.0 - 0.0 - - - - - - - -
Startup: 174.0 - 174.0 - 0.0 - - - - - - - -
Travel Time (En-Route): 0.0 - - - 0.0 - - - - - - - -
Cleanup 290.0 - 290.0 - 0.0 - - - - - - - -
Total Hours: 4684.4 73.5 4610.9 73.5 # 73.5 40.0 14.0 0.0 17.0 2.5 0.0 0.0 0.0
47
74
27 Behind Schedule!
To capture each week's expenditures after the times have been
entered, simply insert a new column to the left of Column G. Then
"Select" the entire data range in the "Current" column "H". Once the
entire row is selected, press "Ctrl-C" to copy all the data. Then select
the top data cell in the new column. Once it is highlighted, with your
cursor over the highlighted cell, right-click the mouse and select "Paste
Special". Then select "Values". The current data will be copied as
data, not as links, and the current week's expenditures will thus be
saved.
Hours Deviation
"Earned" Hours:
"Actual" Hours:
"Deviation" Hours:
In Row 5, Enter the Number of Manhours Charged to the Project for this tim
Current
1.0%
Current
%Comp
DISCIPLINE TEAM WEEKLY MANHOURS - PHASE ONE