FANSHAWE WALKWAY By Project Revolutions Sameer B. Michael W. Mandeep K. Bhushan C. Zohaib M.
8

FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

Feb 09, 2017

Download

Documents

Mandeep Kaur
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

FANSHAWE WALKWAY By Project Revolutions

• Sameer B.

• Michael W. Mandeep

K.• Bhushan C. • Zohaib M.

Page 2: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

Work Breakdown Structure

Page 3: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

PROJECT OVERVIEW REPORT

Page 4: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

PENDING WORK

Page 5: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

STATUS INDICATION

Parameters Status Indicator

Cost

Schedule

Scope

CriteriaCost / Schedule / Scope is not satisfiedFacing some problem / Delay in scheduleAll parameters are satisfied

Page 6: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

OVERALL STATUS• Cost Overrun of the project by CAD 180,220• Reasons behind cost overrun : -

- Change in project plan during execution phase. 33,698 CAD- Modified control phase of project, by implementing risk assessment and control

40,128 CAD

- Replaced all general workers by skilled construction workers.

26,570 CAD

- Increase number of manpower to speed up the activities.

68,236 CAD

- Minor expenses that includes daily expenses, transportation costs, material costs etc.

Around 16,000 to 18,000 CAD

Page 7: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)

ANY QUESTIONS

Page 8: FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)