Entrega Project Update Entrega Project Update Wyoming Natural Gas Pipeline Authority – Wyoming Natural Gas Pipeline Authority – August 30, 2005 August 30, 2005 Entreg Entreg a a Gas Pipeline Gas Pipeline Inc. Inc. www.entregapipeline www.entregapipeline .com .com
Entrega Gas Pipeline Inc. www.entregapipeline.com. Entrega Project Update. Wyoming Natural Gas Pipeline Authority – August 30, 2005. Agenda. Entrega Project Update Project and Facilities Milestones and Schedule Interconnects and Capacity Access to Markets Wrap-up. - PowerPoint PPT Presentation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Entrega Project UpdateEntrega Project Update
Wyoming Natural Gas Pipeline Authority – August 30, 2005Wyoming Natural Gas Pipeline Authority – August 30, 2005
EntregEntregaaGas Pipeline Gas Pipeline Inc.Inc.
www.entregapipeline.comwww.entregapipeline.com
Agenda
Entrega Project Update
Project and Facilities
Milestones and Schedule
Interconnects and Capacity
Access to Markets
Wrap-up
Segment 1
Meeker to Wamsutter
136 miles of 36-inch pipe
Segment 2
Wamsutter to Cheyenne Hub
191 miles of 42-inch pipe
Big Hole Compressor Station
Wamsutter
Compressor Station
Meeker Compressor Station
Project Description
Entrega is a new open access natural gas pipeline developed to move Rocky Mountain gas production to Midwest markets
FERC regulated interstate pipeline; developed with cooperation of Bureau of Land Management and other Federal and State Agencies
Runs from Meeker Hub in Rio Blanco County, CO through Wamsutter, WY to the Cheyenne Hub near Rockport, CO
FERC certificate includes capacity of 1,500 MMcf/d, developed in 2 phases
– Phase 1 approximately 750 MMcf/d (free flow)
– Phase 2 incremental 750 MMcf/d (compression)
Description of Facilities
Project includes 136 miles of 36-inch pipeline and 191 miles of 42-inch pipeline
Maximum Allowable Operating Pressure (MAOP) of the system is 1,480 psig
Route chosen to minimize environmental impact; 94% is adjacent to existing pipeline and utility right-of-way
Phase 2 will include 3 compressor stations; Meeker (11,000 HP), Big Hole (22,000 HP), and Wamsutter (14,000 HP)
Eight delivery/receipt meter stations at interconnects with existing pipelines, two at Meeker, two at Wamsutter, and four at Cheyenne Hub
Recent Significant Milestones
FERC Certificate Granted – August 9, 2005
Construction contract awarded to US Pipeline Company
Operating contract awarded to Kinder Morgan NatGas Operator LLC
Agreement to interconnect with TransColorado
Project Concept
Developed
Timeline of Major Milestones Achieved
9/03 12/03 1/04 12/04 1/05
Pre-Filing Docket
Assigned3/19/04
Applied for FERC
Certificate9/17/04
Open Season
6/4/04 – 6/25/04
Agmt Signed with Pipeline
Operator6/2/05
Environmental Impact Stmt
Issued7/1/05
FERC Certificate Granted
8/9/05
FERC Certificate Accepted
8/12/05
Project Timeline (most recent update)
1/05 12/05 1/06 12/06 1/07
Phase 1 Segment 1
ConstructionSep 05 – Dec 05
Phase 2 Construction of FacilitiesApr 07 – Jun 07
Phase 1 Segment 2
ConstructionJul 06 – Nov 06
FERC Notice to Proceed
Expected 9/5/05
Note: All dates referenced above are approximate and differ from the FERC filing