Page 1
Previous Issue: 23 August 2011 Next Planned Update: 23 August 2016
Revised paragraphs are indicated in the right margin Page 1 of 54
Primary contact: Anezi, Mohammed Ali on +966-13-8809528
Copyright©Saudi Aramco 2013. All rights reserved.
Engineering Procedure
SAEP-1662 28 October 2013
Cleaning of Heat Exchangers and Unfired Plant Equipment
Document Responsibility: Materials and Corrosion Control Standards Committee
Saudi Aramco DeskTop Standards
Table of Contents
1 Scope.................................................................... 2 2 References............................................................ 2 3 Purpose................................................................. 2 4 Responsibilities..................................................... 3 5 Introduction to Cleaning........................................ 5 6 Preparations for Chemical Cleaning..................... 5 7 Criteria For Cleaning............................................. 9 8 Chemical Cleaning Treatment Selection............... 9 9 Alkaline Treatments............................................ 13 10 Acid Cleaning and Neutralization........................ 19 11 Passivation.......................................................... 30 12 Evaluating Cleaning Performance by Inspection... 31 13 Equipment Lay-Up.............................................. 31
Appendix 1 – Definition of Terms..................................... 31 Appendix 2 – Contractor Submittals................................. 32 Appendix 3 – List of Approved Inhibitors and Manufacturers.................................. 34 Appendix 4 – Chemical Cleaning Log Sheet.................... 35 Appendix 5 – High Pressure Water Jetting (HPJ)……..... 36 Appendix 6 – Onstream Cleaning of Heat Exchangers… 38 Appendix 7 – Cleaning of Twisted Tube Heat Exchangers.............................. 43 Appendix 8 – Heat Transfer Coefficients and Fouling Factor.................................. 45 Appendix 9 – Economic Evaluation TFRE Concept............ 47 Appendix 10 – Safety Hazards with Chemical Cleaning….. 50 Appendix 11 – Cleaning Chemical Compatibility Chart for Materials................................ 54
Page 2
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 2 of 54
1 Scope
This procedure defines the responsibilities of the various departments involved in the
pre commission and operational cleaning. It outlines methods to determine the need for
cleaning, the criteria for selecting specific cleaning procedures, and steps involved in
various cleaning procedure alternatives.
The use of high pressure water jetting is covered in Appendix 5 and on-stream cleaning
in Appendix 6. Advice is available from Materials Engineering & Corrosion
Operations Division /Consulting Services Department (ME&COD/CSD) to draft
detailed procedures for cleaning specific equipment.
The procedures listed herein are applicable to clean undesirable deposits in heat
exchangers and other unfired plant equipment such as piping, columns, vessels,
Multiple Effect Distillation (MED) units, etc.
For twisted tube heat exchangers, see Appendix 7.
For evaluation and recommendation of alternative cleaning procedures not listed herein
contact ME&COD/CSD.
2 References
The following documents apply as referenced in this procedure.
Saudi Aramco Engineering Procedure
SAEP-327 Disposal of Wastewater from Cleaning, Flushing,
and Dewatering Pipelines and Vessels
Saudi Aramco Engineering Standard
SAES-B-069 Emergency Eyewashes and Showers
Saudi Aramco Manual
SAER-2365 Saudi Aramco Mothball Manual
3 Purpose
It is necessary to clean a new equipment initially and periodically thereafter for its
efficient operation, corrosion control and prevention of fouling related failures.
This scope includes, but not limited to, coolers and condensers, DEA, MEA, MDEA,
DGA and any other amine systems, TEG, refrigerant systems, vessels, columns, towers,
storage tanks, and piping. Cleaning is accomplished by a combination of (not
necessarily in the sequence listed):
Page 3
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 3 of 54
Mechanical cleaning
High pressure water jetting (HPJ)
Hot alkaline treatment
Acid cleaning and Neutralization
Passivation
Cleaning with Solvents
For some equipment it may not be necessary to use all of the above steps since the degree
of contamination will vary from unit to unit. Scale severity, and its analysis, tube failures,
inspection and consultation with the various departments outlined in Section 4 will
determine the exact procedure to be used. This procedure does not override an equipment
manufacturer's cleaning recommendations, especially where warranty rights are involved.
Differences shall be questioned and resolved by the proponent.
4 Responsibilities
4.1 The Project Construction Agency is responsible for cleaning new equipment.
4.2 The Facility Operating Department is responsible for cleaning commissioned
equipment.
4.2.1 Maintenance
Prepares the equipment mechanically.
Provides maintenance support during the cleaning operation.
Coordinates cleaning and obtains approved contractor services.
Commentary:
Contact ME&COD/CSD for Saudi Aramco’s approved list of chemical cleaning contractors.
4.2.2 Operations Engineering
Prepares necessary operation procedures, advises the foreman of the
plant during the chemical cleaning of the equipment.
Acts as a technical representative to facility operator during the
chemical cleaning.
Ensures adequate safety procedures and precautions are taken.
Notifies Loss Prevention Department to review safety during
cleaning.
Page 4
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 4 of 54
Coordinates and obtains the approval of chemical cleaning
procedures and formulations from the ME&COD/CSD and the
Research and Development Center (R&DC).
Requests the presence of specialist personnel from ME&COD/CSD
if this service is desired.
4.2.3 Operations Inspection
Has the responsibility for inspection before and after cleaning.
Is responsible to get and keep the corrosion monitoring records from
the contractor.
Maintains history of equipment chemical cleaning. Incorporates
relevant reports and data into permanent plant records.
4.3 Loss Prevention Department
Audits cleaning operations and permits
Advises on field safety precautions on request.
4.4 Research and Development Center (R&DC)
Evaluates new chemical cleaning products and new corrosion inhibitors.
Provides specialist/consultant advice on request.
4.5 Regional Laboratories
Perform scale density, solubility, and chemical analysis, inhibitor
effectiveness testing and analyses during actual cleaning operations on
request.
Verify the purity of acids and chemicals used for chemical cleaning on
request.
4.6 Chemical Cleaning Contractor
The chemical cleaning contractor is selected from the Consulting Service
Department's approved list of chemical cleaning contractors. Contractor
responsibilities are stated in the contract. Usually this includes: submittal of
procedures and documents per Appendix 2; supply of all chemicals, inhibitors
per Appendix 3, auxiliary pumping and heating equipment as required, and the
necessary personnel for chemical cleaning, including a qualified chemist for
chemical analysis during the chemical cleaning; on line monitoring and control
of corrosion rates; disposal of all waste water and chemical solutions as
Page 5
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 5 of 54
provided in SAEP-327; and cleaning the equipment to meet or exceed the
acceptance criteria outlined in Section 12.
4.7 ME&COD/CSD
Reviews and approves the cleaning procedures and subsequent changes
necessitated by the field conditions.
Provides specialist/consultant advice on request.
Witnesses the cleaning operation on request.
5 Introduction to Cleaning
The cleaning process may involve a combination of several stages. Plan the stages of
cleaning in advance.
5.1 Mechanically remove, using power brushes or reamers as much of the deposits
as possible from the equipment.
5.2 Remove deposits if access is available with high-pressure water jetting.
See Appendix 5 for details.
5.3 Clean on-stream with acid slugging. See Appendix 6.
5.4 Remove oil, grease, and organic deposits and to neutralize pyrophoric material
with hot permanganate, alkaline treatment, or surfactants.
5.5 Removal of tarry and polymerized deposits by cleaning with organic solvents
such as heavy aromatic naphtha (HAN), kerosene, diesel, gas oil, or proprietary
solvents.
5.6 Acid clean to chemically remove, mill scale, mineral deposits from water,
process side deposits and corrosion products.
5.7 Neutralize acids and passivate to form a strongly adherent protective oxide layer
on the wetted metal surface.
6 Preparations for Chemical Cleaning
6.1 General
1. Install all necessary temporary piping, sacrificial valves and pressure,
temperature and level instruments. Do not connect equipment with
dissimilar metals into one system for circulation of acids.
2. Isolate the equipment from the process side by blinds. Install vents and
Page 6
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 6 of 54
adequately sized temporary valves to permit draining acids within
30 minutes. Use temporary plugs or slip blinds to isolate sections that do
not require cleaning.
3. Store all chemicals needed for the procedure on-site prior to commencing
cleaning, including emergency neutralizing agents and nitrogen as well as
wet lay-up chemicals.
4. Ensure that an adequate supply of water is available for flushing and
cleaning.
5. Ensure that instrument connections (except those temporarily installed) are
disconnected before acid cleaning stage.
6. Install fittings for liquid sampling, flow elements, temperature probes, pipe
spools with on-line access fittings for corrosion monitoring probes.
7. Provide adequate lighting at all operating points.
8. Plan for the disposal of wastewater and spent chemical solutions per
SAEP-327.
9. Perform checks on valve lineups as required for flushing and reversing
circulation.
10. Notify ME&COD/CSD and the Regional Laboratories of intention to
chemically clean. Request the presence of ME&COD/CSD personnel
during any stage of chemical cleaning for consultations as necessary.
11. Ensure utility water is available, or provide a temporary supply
connection.
12. Ensure sufficient supply of nitrogen at 80 psig to quickly drain using
nitrogen pressure any acid in the equipment.
13. Check and ensure that the flow design includes: flow reversal manifold
and valves, control valves and bypass to control circulation within
specified limits, blend filling of corrosive chemicals (acids and chelants)
without exposure to the atmosphere.
14. Test the cleaning circuit hydrostatically at 1.25 times the dead head
discharge pressure of the circulating pump, after installation of all
temporary piping and connections, prior to chemical cleaning.
15. Ensure that an external heat source is available to maintain the cleaning
fluid temperature, within the limits specified.
16. Ensure spare pumps are available in case of a pump failure to maintain
Page 7
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 7 of 54
circulation, and nitrogen pressure connection to drain the acid within
fifteen minutes in case of an emergency. Ensure sufficient holding tank
capacity is available for draining and neutralizing cleaning solutions if
necessary.
17. Ensure, using standard samples, that on-site chemical analytical
procedures and laboratory analytical procedures yield results within ±10%.
18. Ensure inhibitor is selected from Appendix 3.
19. Determine the volume of the equipment by filling with water and draining
it through a flow meter.
20. Be aware of the safety hazards (see Appendix 10) associated with chemical
cleaning and take adequate safety measures.
21. Ensure chemical feed lines are a minimum of 1/12th
the diameter of the
vessel or exchanger; drains and vents are clear.
22. Ensure that the chemical cleaning contractor is on-site with mixing tanks,
chemicals, flow meter, corrosion monitoring equipment, pH and
temperature probes, and pumping equipment to blend fill and circulate
chemicals.
23. Flush the equipment with water until it runs clear to remove all loose and
soluble deposits.
24. Use commercial grade quality for all chemicals except where austenitic
materials are present in the equipment to be cleaned. In this case, the total
chlorides of all the chemicals in the mixture must not yield a final solution
containing greater than 50 mg/L as chloride.
25. Install at least one corrosion probe in the circulating loop for on line
monitoring and control of corrosion rates.
6.2 Cleaning Record
1. Cleaning temperatures, time, dates of cleaning process, chemical additions,
and results of chemical cleaning analysis are recorded in a logbook by
Operations Engineering.
2. Typical log sheets include what is shown in Appendix 4, contractor's log
sheets and the on line corrosion monitoring results.
3. Operations Inspection Unit is to collect and keep as permanent plant
records, these log sheets on completion of the cleaning operation.
Page 8
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 8 of 54
6.3 Safety Precautions
1. Close all instrument connections and disconnect to protect instruments
from exposure to corrosive solutions.
2. Keep operational and tested, permanent or temporary eye wash fountains
and safety showers per SAES-B-069, within 15 meters and accessible in
10 to 15 seconds of the work site, prior to initiation of chemical cleaning.
3. Adhere to the work permit procedures. Vent flammable gases when
corrosive chemicals are used in the cleaning operation. A “Release of
Flammable Gas” Work Permit will be required. Therefore, do not permit
welding, burning, or running of welding machines or generator sets within
a 5 meter radius from the vents of the systems being cleaned. A hot work
permit will be required to operate pumps. Nitrogen is a non-toxic gas that
will not support life. Entrance by personnel into the equipment will be in
accordance with the requirements in the CONFINED SPACE ENTRY
permit procedures including oxygen tests, combustible gas tests, use of
lifelines if required, etc.
4. Keep hoses connected to an operable water supply adjacent to the
equipment being cleaned to dilute any chemical spills.
5. Rope off the area where the blending and heating of chemical solutions is
performed and post “DANGER” signs. Do not let unauthorized personnel
enter the roped off area.
6. Keep at cleaning site chemical hazard bulletins on various chemicals or
materials from the Environmental Protection Department. These bulletins
provide information on storage, handling, and protective measures for
these chemicals.
7. Ensure all nitrogen cylinders if in use, have individual regulators and are
adequately secured. Also, ensure the nitrogen manifold has a safety relief
valve attached.
8. Ensure all personnel handling chemicals wear protection equipment
required by the chemical hazard bulletins of the materials involved.
9. Ensure the contractor is equipped with adequate portable fire extinguishers
for its equipment.
10. Be aware and prepared for safety hazards with equipment deposits, noted
in Appendix 10.
Page 9
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 9 of 54
7 Criteria for Cleaning
Use any one of the following criteria to determine when to schedule cleaning.
1. Inspection: On every T & I, check inside the tubes and shell for corrosion and
scale. Note down the location and amount of scale buildup and check tube ends
for pits, and deposit. Scrape off deposits to determine its composition. Low flow
rate areas, boots, drains are particularly susceptible to heavy deposit buildup.
Visual inspection will indicate the condition of the equipment and will be one of
the primary factors in determining the need for cleaning. Inspect tubes inside and
on shell side for total blockage. Blocked tubes cannot be chemically cleaned until
a flow path is made for chemical circulation.
2. Clean whenever the actual heat transfer coefficient (Uactual) drops to 60% of the
Udesign at heat exchanger design operating conditions. (See Appendix 8).
3. Clean when the ten-day average Rf reaches twice of Rfdesign value. Rf is
independent of the fluctuations in the flow rates during the service period.
(See Appendix 8).
4. Clean when the total fouling related expenditure (TFRE) is at the minimum.
(See Appendix 9).
5. Clean whenever the drop in heat duty is unacceptable to Plant Operations.
6. Clean during T&I or unplanned shutdown to take advantage of down time.
7. Using scale monitoring or based on recorded rate of scale or corrosion products
build up, schedule cleaning before fluid flow is obstructed inside or outside the
tubes.
8 Chemical Cleaning Treatment Selection
8.1 General Criteria
8.1.1 Primarily select chemicals that: a) are safe to use, b) are compatible with
the materials of construction (see Appendix 11), c) will remove > 70% of
the undesired deposits, d) will achieve the desired degree cleaning.
8.1.2 With these criteria satisfied, make the final selection, with due reference
to other constraints including cost, environmental restriction on disposal
of waste solutions, and cleaning time available. Responsibility for the
final procedure of the treatment(s) is defined in Section 4. For on stream
cleaning see Appendix 6. Off stream chemical cleaning will involve one
or more of the following steps: Hot alkaline degreasing (see Section 9),
acid cleaning (see Section 10), followed by neutralization and
Page 10
Document Responsibility: Materials and Corrosion Control Standards Committee SAEP-1662
Issue Date: 28 October 2013
Next Planned Update: 23 August 2016 Cleaning of Heat Exchangers and Unfired Plant Equipment
Page 10 of 54
passivation treatment (see Section 11). Laboratory analyses of deposit
samples will determine the above sequence.
8.1.3 High pressure water jetting (HPJ) may precede or follow to remove
loosened scale (see Appendix 5). HPJ is very effective to remove most
brittle deposits. The use of HPJ is recommended alone, or before
chemical cleaning.
8.2 Analysis of Scale
8.2.1 General - Fouling composition, quantity, and distribution, will vary
considerably between one equipment and another, or even within the
same equipment at various time intervals during its life. It is therefore
necessary in each case, to select a specific treatment, or series of
treatments, which will be most effective in achieving thorough and safe
cleaning, to restore its operational efficiency. Determine the
composition of the scale or deposit and the suitable acids or organic
solvents to remove them before any chemical cleaning. Take a sample
or samples carefully representative of the deposit.
8.2.2 Solubility in Dilute HCl - This figure represents the weight percent of the
deposit, which will dissolve in boiling 7.5% wt., inhibited hydrochloric
acid.
8.2.3 Loss on Ignition - This figure represents the weight percentage of the
deposit that can be removed by heating the insoluble residue from 8.2.1
above to 315°C in a laboratory furnace. The result is indicative of the
organic content of the deposit in the forms of oil, grease, degraded
polymers and carbon. If the figure is high (greater than 10%) further
definition of the organic content can be determined by refluxing the
sample with a suitable organic solvent, which will indicate the relative
proportions of oil and grease, and carbon. These proportions assist in the
selection of a suitable hot alkaline or permanganate treatment.
8.2.4 Insoluble Residue - This figure represents the insoluble complexes of
other cations and, if the quantity is significant (i.e., greater than 2%)
further treatments with more concentrated hydrochloric acid may be
required to render the material soluble.
8.2.5 Metals - The metal ions present in the deposit, are analyzed for iron (Fe),
copper (Cu), calcium (Ca), magnesium (Mg), nickel (Ni), zinc (Zn),
manganese (Mn) and sodium (Na). These results are useful to determine
the number of cleaning stages that are likely to remove all the deposits
from the system.