NO 1 I PEKERJAAN PERSIAPAN 1 1 M' Pengukuran & pemasanga 0.0120 m3 0.0250 oh 0.0070 m3 0.1000 Oh 0.1000 Oh 0.0100 Oh 0.0050 Oh 2 1 M3 Membersihkan lapangan 0.1000 oh 0.0500 oh II PEKERJAAN TANAH 1 1 M3 Galian Tanah biasa sed 0.7500 oh 0.0250 oh 2 1 M3 Galian tanah biasa sed 0.9000 oh 0.0450 oh 3 1 M3 Galian tanah biasa sed 1.0500 oh 0.0670 oh 4 1 M3 Galian tanah keras se 1.0000 oh 0.0320 oh 5 1 M3 Galian tanah cadas sed 1.5000 oh 0.0600 oh
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
DAFTAR ANALISA PEKERJAAN
NO URAIAN
1 2
I PEKERJAAN PERSIAPAN1 1 M' Pengukuran & pemasangan bowplank
0.0120 m3 Kayu Usuk 5/7 0.0250 oh Paku Biasa 2"-5" 0.0070 m3 Kayu Papan 3/20 0.1000 Oh Pekerja 0.1000 Oh Tukang kayu 0.0100 Oh Kepala Tukang 0.0050 Oh Mandor
2 1 M3 Membersihkan lapangan dan peralatan 0.1000 oh Pekerja 0.0500 oh Mandor
II PEKERJAAN TANAH1 1 M3 Galian Tanah biasa sedalam 1 meter
0.7500 oh Pekerja 0.0250 oh Mandor
2 1 M3 Galian tanah biasa sedalam 2 meter 0.9000 oh Pekerja 0.0450 oh Mandor
3 1 M3 Galian tanah biasa sedalam 3 meter 1.0500 oh Pekerja 0.0670 oh Mandor
4 1 M3 Galian tanah keras sedalam 1 meter 1.0000 oh Pekerja 0.0320 oh Mandor
5 1 M3 Galian tanah cadas sedalam 1 meter 1.5000 oh Pekerja 0.0600 oh Mandor
6 1 M3 Galian tanah lumpur sedalam 1 meter 1.2000 oh Pekerja 0.0450 oh Mandor
13 1 M3 Urugan sirtu padat untuk peninggian lantai bangunan 1.2000 m3 sirtu 0.2500 oh Pekerja 0.0250 oh Mandor
III PEKERJAAN PONDASI1 1 M3 Pasang pondasi batu belah 1 Pc : 3 Ps
1.2000 m3 Batu belah 15/20 cm 136.0000 kg Semen portland 0.4850 m3 Pasir pasangan 1.5000 oh Pekerja 0.7500 oh Tukang Batu
0.0750 oh Kepala tukang 0.0750 oh Mandor
2 1 M3 Pasang pondasi batu belah 1 Pc : 4 Ps 1.2000 m3 Batu belah 15/20 cm 163.0000 kg Semen portland 0.5200 m3 Pasir pasangan 1.5000 oh Pekerja 0.7500 oh Tukang Batu 0.0750 oh Kepala tukang 0.0750 oh Mandor
3 1 M3 Pasang pondasi batu belah 1 Pc : 5 Ps 1.2000 m3 Batu belah 15/20 cm 136.0000 kg Semen Portland 0.5440 m3 Pasir pasangan 1.5000 oh Pekerja 0.7500 oh Tukang Batu 0.0750 oh Kepala Tukang 0.0750 oh Mandor
4 1 M3 Pasang pondasi batu belah 1 Pc : 6 Ps 1.2000 m3 Batu belah 15/20 cm 117.0000 kg Semen Portland 0.5610 m3 Pasir pasangan 1.5000 oh Pekerja 0.7500 oh Tukang Batu 0.0750 oh Kepala Tukang 0.0750 oh Mandor
5 1 M3 Pasang pondasi batu belah 1 Pc : 8 Ps 1.2000 m3 Batu belah 15/20 cm 91.0000 kg Semen Portland 0.5840 m3 Pasir pasangan 1.5000 oh Pekerja 0.7500 oh Tukang Batu 0.0750 oh Kepala Tukang 0.0750 oh Mandor
6 1 M3 Pasang pondasi batu kosong 1.2000 m3 Batu belah 15/20 cm 0.4320 m3 Pasir urug 1.5000 oh Pekerja
0.7500 oh Tukang Batu 0.0750 oh Kepala Tukang 0.0750 oh Mandor
IV PEKERJAAN BETON1 Pembesian 10 kg dengan besi polos / ulir
10.5000 kg Besi beton (polos/ulir) 0.1500 kg Kawat beton 0.0700 oh Pekerja 1.0500 oh Tukang Besi 0.0070 oh Kepala tukang 0.0040 oh Mandor
2 1 M2 Pasang bekisting untuk pondasi 0.0400 m3 Kayu kelas III 0.3000 kg Paku biasa 5' - 10' 0.1000 ltr Minyak bekisting 0.5200 oh Pekerja 0.2600 oh Tukang Kayu 0.0260 oh Kepala tukang 0.0260 oh Mandor
3 1 M2 Pasang bekisting untuk sloof 0.0450 m3 Kayu kelas III 0.3000 kg Paku biasa 5' - 10' 0.1000 ltr Minyak bekisting 0.5200 oh Pekerja 0.2600 oh Tukang Kayu 0.0260 oh Kepala tukang 0.0260 oh Mandor
4 1 M2 Pasang bekisting untuk kolom 0.0400 m3 Kayu kelas III 0.4000 kg Paku biasa 5' - 10' 0.2000 ltr Minyak bekisting 0.3500 lbr Plywood tebal 9 mm 0.6600 oh Pekerja 0.3300 oh Tukang Kayu 0.0330 oh Kepala tukang 0.0330 oh Mandor
5 1 M2 Pasang bekisting untuk balok
0.0400 m3 Kayu kelas III 0.4000 kg Paku biasa 5' - 10' 0.2000 ltr Minyak bekisting 0.3500 lbr Plywood tebal 9 mm 0.6600 oh Pekerja 0.3300 oh Tukang Kayu 0.0330 oh Kepala tukang 0.0330 oh Mandor
6 1 M2 Pasang bekisting untuk lantai 0.0400 m3 Kayu kelas III 0.4000 kg Paku biasa 5' - 10' 0.2000 ltr Minyak bekisting 0.3500 lbr Plywood tebal 9 mm 0.6600 oh Pekerja 0.3300 oh Tukang Kayu 0.0330 oh Kepala tukang 0.0330 oh Mandor
7 1 M2 Pasang bekisting untuk tangga 0.0300 m3 Kayu kelas III 0.4000 kg Paku biasa 5' - 10' 0.1500 ltr Minyak bekisting 0.3500 lbr Plywood tebal 9 mm 0.6600 oh Pekerja 0.3300 oh Tukang Kayu 0.0330 oh Kepala tukang 0.0330 oh Mandor
8 1 M2 Pasang jembatan untuk pengecoran beton 0.0264 m3 Kayu klas III (papan) 0.600 kg Paku biasa 5' - 12'
0.1500 oh Pekerja 0.0500 oh Tukang Kayu 0.0050 oh Kepala Tukang Kayu 0.0080 oh Mandor
9 1 M3 membuat pondasi beton 336.0000 Kg Semen portland
15 1 M' membuat ring balok beton bertulang (10 x 15) cm0.0300 m3 Kayu kelas III0.0200 Kg Paku biasa 5'-12'3.6000 kg Besi beton polos0.0500 kg Kawat beton5.5000 Kg Semen portland0.0090 m3 Pasir beton0.0150 m3 Koral beton0.2970 oh Pekerja0.0330 oh Tukang batu0.0330 oh Tukang kayu0.0330 oh Tukang besi0.0100 oh Kepala tukang0.0150 oh Mandor
16 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KR 218.0000 kg Semen Portland 0.5200 m3 Pasir Beton 0.8700 m3 Koral Beton 1.6500 oh Pekerja 0.2500 oh Tukang Batu 0.0250 oh Kepala Tukang Batu 0.0800 oh Mandor
V PEKERJAAN PENUTUP ATAP1
12.0000 bh Genteng Plentong 0.1500 oh Pekerja 0.0600 oh Tukang Kayu 0.0060 oh Kepala Tukang 0.0080 oh Mandor
0.2000 oh Tukang Kayu 0.0200 oh Kepala Tukang 0.0020 oh Mandor
VI PEKERJAAN LANGIT - LANGIT
1 0.3750 lbr Tripleks 0.0300 kg Paku biasa 1/2" - 1" 0.1000 oh Pekerja 0.1000 oh Tukang Kayu 0.0100 oh Kepala Tukang 0.0050 oh Mandor
2 1 M' PASANG LIST LANGIT-LANGIT KAYU PROFIL 1.0500 m' List Kayu Profil 0.1000 kg Paku lis 0.0500 oh Pekerja 0.0500 oh Tukang Kayu 0.0050 oh Kepala Tukang 0.0030 oh Mandor
VII PEKERJAAN SANITASI1 MEMASANG 1 BUAH KLOSET DUDUK/MONOBLOK
1.0000 bh Kloset jongkok 6 % x harga kloset Perlengkapan 3.3000 oh Pekerja 1.1000 oh Tukang batu 0.0010 oh Kepala Tukang 0.1600 oh Mandor
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN 1.0000 bh Kloset jongkok porselen 6.0000 kg Semen Portland 0.0100 Pasir Pasang 1.0000 oh Pekerja 1.5000 oh Tukang batu 1.5000 oh Kepala Tukang 0.1600 oh Mandor
3 MEMASANG 1 BUAH URINOIR KIA 1.0000 bh Urinoir 30% x harga Urin. Perlengkapan 6.0000 kg Semen Portland 0.0100 Pasir Pasang 1.0000 oh Pekerja 1.0000 oh Tukang batu 0.1000 oh Kepala Tukang 0.1000 oh Mandor
4 MEMASANG 1 BUAH WASTAFEL 1.0000 bh Wastafel 12% x harga wast Perlengkapan 6.0000 kg Semen Portland 0.0100 Pasir Pasang 1.2000 oh Pekerja 1.4500 oh Tukang batu 0.1500 oh Kepala Tukang 0.1000 oh Mandor
5 1.0000 bh Bak Fibreglass 18% x harga wast Perlengkapan 1.8000 oh Pekerja 2.7000 oh Tukang batu 0.5400 oh Kepala Tukang 0.1100 oh Mandor
6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 " 1.2000 m' Pipa galvanis 35% x harga pipa Perlengkapan 0.0540 oh Pekerja 0.0900 oh Tukang batu 0.0090 oh Kepala Tukang 0.0270 oh Mandor
7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3"
m3
m3
MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3
1.2000 M' Pipa galvanis 35% x harga pipa Perlengkapan 0.1080 Oh Pekerja 0.1800 Oh Tukang batu 0.0180 Oh Kepala Tukang 0.0054 Oh Mandor
8 1.2000 m' Pipa PVC 35% x harga pipa Perlengkapan 0.0360 oh Pekerja 0.0600 oh Tukang batu 0.0060 oh Kepala Tukang 0.0018 oh Mandor
9 1.2000 m' Pipa PVC 35% x harga pipa Perlengkapan 0.0540 oh Pekerja 0.0900 oh Tukang batu 0.0090 oh Kepala Tukang 0.0027 oh Mandor
10 1.2000 m1 Pipa PVC 35% x harga pipa Perlengkapan 0.0810 oh Pekerja 0.1350 oh Tukang batu 0.0135 oh Kepala Tukang 0.0041 oh Mandor
11 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5" 1.0000 bh Kran air 0.0250 bh Seal tape 0.0100 oh Pekerja 0.1000 oh Tukang batu 0.0100 oh Kepala Tukang 0.0050 oh Mandor
MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"
MEMASANG 1 M1 PIPA PVC TYPE AW f 2"
MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4"
VIII PEKERJAAN BESI DAN ALUMINIUM1 MEMASANG 1 KG BESI PROFIL
1.1500 kg Besi Profil 0.0600 oh Pekerja 0.0600 oh Tukang besi 0.0060 oh Kepala Tukang 0.0030 oh Mandor
2 1.0500 m' Seng plat 0.0150 bh Paku biasa 1 cm - 2,5 cm 0.0190 papan kayu klas II atau III 0.2000 oh Pekerja 0.4000 oh Tukang besi 0.0250 oh Kepala Tukang 0.0100 oh Mandor
IX PEKERJAAN KUNCI DAN KACA1 1 BH PASANG KUNCI TANAM BIASA
1.0000 bh Kunci tanam biasa 0.0100 oh Pekerja 0.5000 oh Tukang besi 0.0100 oh Kepala Tukang 0.0050 oh Mandor
2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS 70.0000 bh Bata Merah 5 x 11 x 22 cm 8.3200 kg Semen Portland 0.0490 m3 Pasir Pasang 0.3000 oh Pekerja 0.1000 oh Tukang Batu 0.0100 oh Kepala Tukang Batu 0.0150 oh Mandor
XIII PEKERJAAN PLESTERAN1 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM
10.2240 kg Semen Portland 0.0200 m3 Pasir Pasang 0.3000 oh Pekerja 0.1500 oh Tukang Batu 0.0150 oh Kepala Tukang Batu 0.0150 oh Mandor
2 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM 7.7760 kg Semen Portland 0.0230 m3 Pasir Pasang 0.3000 oh Pekerja 0.1500 oh Tukang Batu 0.0150 oh Kepala Tukang Batu 0.0150 oh Mandor
3 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM 4.4160 kg Semen Portland 0.0270 m3 Pasir Pasang 0.3000 oh Pekerja 0.1500 oh Tukang Batu 0.0150 oh Kepala Tukang Batu 0.1500 oh Mandor
4 Memasang 1 M2 finishing siap pasangan dinding bata merah (=20 m') 3.1080 kg Semen Portland 0.1500 oh Pekerja 0.0750 oh Tukang Batu 0.0080 oh Kepala Tukang Batu 0.0080 oh Mandor
5 1 M2 PEKERJAAN ACIAN DENGAN PC DAN MILL 3.2500 Kg Semen Portland 50 Kg 0.2000 Zak Mill 0.1000 oh Tukang Labur/Cat 0.0100 oh Kepala Tukang Labur/Cat 0.0100 oh Mandor
XIV PEKERJAAN KAYU1 1 M3 PASANG KUSEN PINTU DAN JENDELA KAYU KAMPER
1.2000 m3 Kayu Kamper balok 1.2500 kg Paku 10 cm 1.0000 kg Lem Kayu 6.0000 oh Pekerja 18.0000 oh Tukang Kayu 1.8000 oh Kepala Tukang Kayu 0.3000 oh Mandor
2 1 M3 PASANG PINTU KLAMP KAYU KAMPER 0.0400 m3 Kayu Kamper Papan 3/20 0.0500 kg Paku Biasa 2" - 5" 0.3500 oh Pekerja 1.0500 oh Tukang Kayu 0.1050 oh Kepala Tukang Kayu 0.0180 oh Mandor
3 1 M2 PASANG PINTU PANEL KAYU KAMPER 0.0400 m3 Kayu Kamper Papan 3/20 0.5000 kg Lem Kayu 1.0000 oh Pekerja 3.0000 oh Tukang Kayu 0.3000 oh Kepala Tukang Kayu 0.0500 oh Mandor
4 1 M2 PASANG PINTU DAN JENDELA KACA KAYU KAMPER 0.0240 m3 Kayu Kamper Papan 3/20 0.3000 kg Lem kayu 0.8000 oh Pekerja 2.4000 oh Tukang Kayu 0.2400 oh Kepala Tukang Kayu
0.0400 oh Mandor
5 1 M2 PEKERJAAN PINTU KAYU PLYWOOD RANGKAP KAMPER 0.0250 m3 Kayu Kamper Papan 3/20 0.0300 kg Paku Biasa 2" - 5" 0.5000 ltr Lem Kayu 1.0000 lbr Plywood 4' x 3' x 6 mm 0.7000 oh Pekerja 2.1000 oh Tukang Kayu 0.2100 oh Kepala Tukang Kayu 0.0350 oh Mandor
6 1 M2 PEKERJAAN PINTU KAYU TEAKWOOD RANGKAP KAMPER 0.0250 m3 Kayu Kamper Papan 3/20 0.0300 kg Paku Biasa 2" - 5" 0.3000 ltr Lem Kayu 1.0000 lbr Teakwood 4 mm 0.8000 oh Pekerja 2.4000 oh Tukang Kayu 0.2400 oh Kepala Tukang Kayu 0.0400 oh Mandor
7 1 M2 PASANG PINTU DAN JENDELA JALUSI KAYU KAMPER 0.0640 m3 Kayu Kamper Papan 3/20 0.5000 kg Lem kayu 1.0000 oh Pekerja 3.0000 oh Tukang Kayu 0.3000 oh Kepala Tukang Kayu 0.0500 oh Mandor
8 1 M2 PASANG KUSEN JALUSI KAYU KAMPER 0.0600 m3 Kayu Kamper Papan 3/20 0.1500 kg Paku 1 - 2,5 cm 0.6700 oh Pekerja 2.0000 oh Tukang Kayu 0.2000 oh Kepala Tukang Kayu 0.3350 oh Mandor
1.1000 m3 Kayu Kruing Balok 8/12 15.0000 kg Besi Strip tebal 5 cm 5.6000 kg Paku Biasa 2" - 5" 4.0000 oh Pekerja 12.0000 oh Tukang Kayu 1.2000 oh Kepala Tukang Kayu 0.2000 oh Mandor
10 1 M2 PEMASANGAN RANGKA ATAP GENTENG KERAMIK 0.0140 m3 Kayu Kruing 5/7 0.0036 m3 Kayu Reng Kamper
0.2500 kg Paku Biasa 2" - 5" 0.1000 oh Pekerja 0.1000 oh Tukang Kayu 0.0100 oh Kepala Tukang Kayu 0.0050 oh Mandor
11 1 M2 PEMASANGAN ATAP SIRAP 0.1650 m3 Kayu Kamper 0.2000 Kg Paku reng 5 sampai 10 cm 0.1200 or/hr Pekerja 0.1200 or/hr Tukang Kayu 0.0120 or/hr Kepala Tukang Kayu 0.0060 or/hr Mandor
12 1 M2 PAS. RANGKA LANGIT-LANGIT (50X100) 0.0154 m3 Kayu Kamper usuk 5 X 7 0.2000 Kg Paku Biasa 2" - 5" 0.1500 or/hr Pekerja 0.3000 or/hr Tukang Kayu 0.0300 or/hr Kepala Tukang Kayu 0.0750 or/hr Mandor
13 1 M2 PEKERJAAN RANGKA LANGIT - LANGIT (60 x 60), KAYU KAMPER 0.0163 m3 Kayu Kamper Usuk 4/6 0.2500 kg Paku Biasa 2" - 5" 0.2000 oh Pekerja 0.3000 oh Tukang Kayu 0.0300 oh Kepala Tukang Kayu
0.0100 oh Mandor
14 1 M1 PEKERJAAN LIST PLANK UKURAN 3 X 20 CM KAYU KAMPER 0.0108 m3 Kayu Kamper Papan 3/20 0.1000 kg Paku Biasa 2" - 5" 0.1000 oh Pekerja 0.2000 oh Tukang Kayu 0.0200 oh Kepala Tukang Kayu 0.0050 oh Mandor
15 1 M1 PEKERJAAN LIST PLANK UKURAN 3 X 30 CM KAYU KAMPER 0.0110 m3 Kayu Kamper Papan 3/20 0.0500 kg Paku Biasa 2" - 5" 0.2200 oh Pekerja 0.0220 oh Tukang Kayu 0.1100 oh Kepala Tukang Kayu 0.0050 oh Mandor
16 1 M2 PEK. DINDING PEMISAH TEAKWOOD RANGKAP RANGKA KAMFER 0.0280 m3 Kayu Kamper 6/12 cm 0.1500 kg Paku Biasa 2" - 5" 0.5600 ltr Lem Kayu 0.8600 lbr Teakwood 4 mm uk. 120 x 240 cm 0.4500 oh Tukang Kayu 0.0450 oh Kepala Tukang Kayu 0.1500 oh Pekerja 0.0080 oh Mandor
17 1 M2 PEKERJAAN DINDING PEMISAH PLAYWOOD RANGKAP RANGKA KAMFER 0.0280 m3 Kayu Kamper 6/12 cm 0.1500 kg Paku Biasa 2" - 5" 0.5600 ltr Lem Kayu 0.8600 lbr Teakwood 4 mm uk. 120 x 240 cm 0.6000 oh Tukang Kayu 0.0600 oh Kepala Tukang Kayu 0.2000 oh Pekerja 0.0100 oh Mandor
35% x harga pipa Perlengkapan 0.0540 oh Pekerja 0.0900 oh Tukang batu 0.0090 oh Kepala Tukang 0.0270 oh Mandor
19 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3" 1.2000 M' Pipa galvanis 35% x harga pipa Perlengkapan 0.1080 Oh Pekerja 0.1800 Oh Tukang batu 0.0180 Oh Kepala Tukang 0.0054 Oh Mandor
20 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" 1.2000 m1 Pipa PVC 35% x harga pipa Perlengkapan 0.0360 oh Pekerja 0.0600 oh Tukang batu 0.0060 oh Kepala Tukang 0.0018 oh Mandor
21 MEMASANG 1 M1 PIPA PVC TYPE AW f 2" 1.2000 m1 Pipa PVC 35% x harga pipa Perlengkapan 0.0540 oh Pekerja 0.0900 oh Tukang batu 0.0090 oh Kepala Tukang 0.0027 oh Mandor
22 MEMASANG 1 M1 PIPA PVC TYPE AW f 3" - 4" 1.2000 m1 Pipa PVC 35% x harga pipa Perlengkapan 0.0810 oh Pekerja 0.1350 oh Tukang batu 0.0135 oh Kepala Tukang 0.0041 oh Mandor
23 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5" 1.0000 bh Kran air 0.0250 bh Seal tape 0.0100 oh Pekerja 0.1000 oh Tukang batu 0.0100 oh Kepala Tukang 0.0050 oh Mandor
XV PEKERJAAN BESI DAN ALUMINIUM1 1 KG PASANG RANGKA ATAP BAJA
1.1000 kg Besi Profil WF 0.0800 kg Meni besi 0.0060 oh Pekerja 0.0600 oh Tukang besi 0.0060 oh Kepala Tukang 0.0003 oh Mandor
2 1 M1 PASANG TALANG MIRING, SENG BJLS 28 0.5000 lbr Seng plat 3' x 6' BJLS 28 0.0150 kg Paku biasa 0,5" - 1" 0.0190 m3 Kayu papan kamper 0.3000 kg Meni besi 0.0400 oh Pekerja 0.4000 oh Tukang besi 0.0250 oh Kepala Tukang 0.0013 oh Mandor
XVI PEKERJAAN KUNCI DAN KACA1 1 BH PASANG KUNCI TANAM BIASA
1.0000 bh Kunci tanam biasa 0.0100 oh Pekerja 0.5000 oh Tukang besi 0.0100 oh Kepala Tukang 0.0050 oh Mandor
0.1000 kg Plamir 0.1000 kg Cat dasar 0.2600 kg Cat Penutup 2x 0.0200 oh Pekerja 0.0630 oh Tukang cat 0.0063 oh Kepala Tukang 0.0025 oh Mandor
4 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 0.1200 kg Cat dasar 0.1800 kg Cat Penutup 2x 0.0280 oh Pekerja 0.0420 oh Tukang cat
0.0042 oh Kepala Tukang 0.0025 oh Mandor
5 1 M2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI 0.1000 kg Meni besi 0.0100 lbr Kuas 0.0200 oh Pekerja 0.2000 oh Tukang cat 0.0200 oh Kepala Tukang 0.0100 oh Mandor
6 1 M2 PENGECATAN PERMUKAAN BAJA, 1 LAPIS DENGAN CAT BESI 0.3000 kg Cat besi 0.0060 oh Pekerja 0.0600 oh Tukang cat 0.0120 oh Kepala Tukang 0.0060 oh Mandor
7 1 M2 PELABURAN BIDANG KAYU DENGAN POLITUR 0.2200 kg Wood filler 0.1600 kg Wood stain 0.1600 kg Sanding sealer 0.1600 ltr Politur Ultran top coat 0.7500 ltr Tinner A 1.2000 lbr Amplas 0.2000 oh Pekerja 0.0200 oh Tukang cat 0.0250 oh Kepala Tukang 0.0020 oh Mandor
8 1 M2 PASANGAN ORNAMEN PEPALIHAN PARAS KEROBOKAN 1 MUKA13.750 bj Paras kerobokan8.400 kg Semen Gresik2.000 or/hr Tukang style bali0.300 or/hr Kepala tukang style bali1.000 or/hr Pekerja0.010 or/hr Mandor
9 1 M2 PASANGAN WATER PROOFING 1.0000 kg Masterseal 440 0.4000 oh Pekerja 0.0400 oh Mandor
XIX PEKERJAAN ELEKTRIKAL1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN, DAN CEILING FAN
8.0000 m1 Kabel NYM 3x2.5 mm ex Supreme 3.0000 bt Pipa clipsal 20 mm hitam 2.0000 bh T dus clipsal 20 mm hitam 15.0000 bj Klem clipsal 20 mm hitam 3.0000 bj Sock clipsal 20 mm hitam 1.0000 bj Inbow dus plastik clipsal 1.0000 ttk Biaya pasang
2 1 TITIK INSTALASI AC 10.0000 m1 Kabel NYM 3x2.5 mm ex Supreme 3.0000 bt Pipa clipsal 20 mm hitam 1.0000 bh T dus clipsal 20 mm hitam 15.0000 bj Klem clipsal 20 mm hitam 4.0000 bj Sock clipsal 20 mm hitam 1.0000 bj Inbow dus plastik clipsal 1.0000 m1 Pipa flexible clipsal 20 mm hitam 1.0000 ttk Biaya pasang
XX PEKERJAAN STYLE BALI1 1 M2 PASANGAN ORNAMEN PEPALIHAN PARAS KEROBOKAN 1 MUKA
13.750 bj Paras kerobokan8.400 kg Semen Gresik2.000 or/hr Tukang style bali0.300 or/hr Kepala tukang style bali1.000 or/hr Pekerja0.010 or/hr Mandor
NO NAMA BARANG SATUAN HARGA 1 2 4 5 1 Amplas lbr 2,000 2 Bak Mandi Fiber bh 215,000 3 Bambu Besar bt 12,000 4 Bambu Kecil bt 9,500 5 Bambu Sedang bt 11,500 6 Batako Kualitas I bh 1,650 7 Batu Bata Gosok Klas I bh 1,600 8 Batu Bata Pasangan Kelas I bh 1,000 9 Batu Belah 15-30 cm/ batu kali m3 100,000 10 Batu Pecah 1 - 2 cm m3 150,000 11 Batu Pecah 2 - 3 cm (Manual, Mesin) m3 125,000 12 Batu Pecah 3 - 5 cm (Manual, Mesin) m3 120,000 13 Batu Pecah 5 - 7 cm (Manual) m3 100,000 14 Batu Pecah 7 - 10 cm m3 100,000 15 Bentala Paras bh 100,000 16 Besi Beton 4 mm btg 7,500 17 Besi Beton 8 mm btg 24,700 18 Besi Galvanised diameter 1,5" bt 250,000 19 Besi Galvanised diameter 2" bt 280,000 20 Besi Profil WF kg 8,350 21 Besi Strip kg 73,500 22 Cat Besi kg 37,500 23 Cat Dasar kg 18,000 24 Cat Kayu Emco kg 40,000 25 Cat Meni Besi kg 18,000 26 Cat Meni Kayu kg 18,000 27 Cat Tembok kg 21,000 28 Clear Gross kg 38,000 29 Closet Jongkok bh 70,000 30 Dempul kg 15,000 31 Engsel Kupu - Kupu ps 25,000 32 Engsel Nilon ps 9,000 33 Enternit Plapond Klas I lbr 13,500 34 Expagnolet bh 45,000 35 Floor drain plastik bh 8,000 36 Floor drain stainless bh 38,000 37 Gedeg kulit Klas I m2 17,000
38 Genteng Bubungan Lokal bj 4,000 39 Genteng Bubungan Plentong bj 5,000 40 Genteng lokal Plentong bj 1,400 41 Glass Block bj 18,500 42 Grendel Biasa bh 10,000 43 Grendel Hanaro bh 22,000 44 Gypsum board standard lbr 54,000 45 Hard Board MDF lbr 115,000 46 Ijuk kg 20,000 47 ikut celedu kg 100,000 48 Jaro bh 3,500 49 Kabel NYM 2 mm m1 5,500 50 Kabel NYM 4 mm m1 5,200 51 Kaca Bening 5 MM m2 72,500 52 Kait angin biasa ps 8,000 53 Kalsiboard 4.5 mm lbr 17,500 54 Kawat Baja Bendrat kg 12,500 55 Kawat Beton RRT kg 12,000 56 Kawat las kg 16,500 57 Kayu Bingkirai Balok m3 6,400,000 58 Kayu Bingkirai Papan / Usuk / Reng m3 7,800,000 59 Kayu Dolken (Pekerjaan Sementara) btg 23,000 60 Kayu Jati Balok m3 15,500,000 61 Kayu Jati Papan m3 21,000,000 62 Kayu Kamper Balok 8/12 m3 6,200,000 63 Kayu Kamper Usuk 5/7 m3 4,300,000 64 Kayu Kruing Balok 8/12 m3 4,800,000 65 Kayu Kruing Usuk 5/7 m3 3,900,000 66 Kayu Meranti papan 3/20 m3 3,000,000 67 Kayu Meranti Usuk 5/7 m3 1,800,000 68 Kayu Meranti balok 6/12 m3 1,800,000 69 Kayu Merbau Papan m3 12,500,000 70 Kayu Perancah / Begesting m3 1,850,000 71 Kayu Profil m1 60,000 72 List kayu 2/5 m1 14,000 73 Keramik 30x30 cm (warna tua) bh 6,400 74 Keramik 20x20 cm (warna muda) bh 2,600 75 Kran Air biasa bh 20,000 76 Kerikil Beton m3 100,000 77 Kuas bh 10,000 78 Kunci Slot bh 72,000
79 Kunci Pintu ex Union bh 110,000 80 Kunci Pintu ex Yale bh 120,000 81 Kunci Tanam Biasa bh 72,000 82 Kabel NYM 3x2.5 mm ex Supreme m1 10,000 83 Klem clipsal 20 mm hitam bj 700 84 Lampu SL 18 Watt bh 35,000 85 Lampu TL 20 Watt bh 28,500 86 Lem Aibond kg 18,000 87 Lem Kayu ltr 11,000 88 Limestone m3 125,000 89 List Gypsum Stdr m1 14,500 90 Mild zak 15,000 91 Minyak Bekisting ltr 12,000 92 Minyak Cat ltr 18,000 93 Multiplek 6 MM ltr 85,000 94 Multiplek 9 MM ltr 120,000 95 Multiplek 12 MM ltr 175,000 96 Multiplek 18 MM ltr 210,000 97 Mur Baut bh 3,500 98 Murda bh 70,000 99 Paku 2" - 5" (reng/usuk) kg 15,000 100 Paku List kg 16,000 101 Paku Skrup 2" kg 11,000 102 Paras Kerobokan 50 x 20 x 12 bj 4,000 103 Pasir Beton m3 85,000 104 Pasir Pasang m3 100,000 105 Pasir Urug m3 85,000 106 Pipa Galvanis 1/2" m1 90,250 107 Pipa Galvanis 3/4" m1 130,000 108 Pipa Galvanis 1 1/4" m1 236,550 109 Pipa Galvanis 1 1/2" m1 285,000 110 Pipa Galvanis 1" m1 17,500 111 Pipa Galvanis 1,5 BSA m1 46,500 112 Pipa Galvanis 2" m1 345,000 113 Pipa Galvanis 3" m1 47,500 114 Pipa PVC tipe AW Ø 0,5" P = 4 m bt 21,000 115 Pipa PVC tipe AW Ø 0,75" P = 4 m bt 24,000 116 Pipa PVC tipe AW Ø 1" P = 4 m bt 28,500 117 Pipa PVC tipe AW Ø 1,5" P = 4 m bt 52,250 118 Pipa PVC tipe AW Ø 2" P = 4 m bt 77,900 119 Pipa PVC tipe AW Ø 2.5" P = 4 m bt 109,250
120 Pipa PVC tipe AW Ø 3" P = 4 m bt 142,500 121 Pipa PVC tipe AW Ø 4" P = 4 m bt 220,000 122 Pipa clipsal 20 mm hitam bt 18,000 123 Pipa flexible clipsal 20 mm hitam m1 10,000 124 Plamir Tembok kg 12,500 125 Plywood 12 MM lbr 140,000 126 Plywood 3 MM lbr 60,000 127 Plywood 4 MM lbr 42,500 128 Plywood 6 MM lbr 53,000 129 Plywood 9MM lbr 95,000 130 Plywood Alluminium lbr 115,000 131 Politur kg 42,000 132 Politur Ultra kg 42,000 133 Rangka aluminium/holow m1 100,000 134 Sock clipsal 20 mm hitam m1 800 135 Sanding sealer kg 32,000 136 Seal tape bh 2,000 137 Semen PC 50 Kg gresik kg 1,000 138 Semen warna/semen grouting kg 4,000 139 Seng Gelombang 3" x 5" BJLS 28 lbr 47,500 140 Sirtu m3 90,000 141 Seng Bjls 0,25 lbr 47,500 142 Seng Bjls 0,32 lbr 52,500 143 Seng plat 3" x 6" BJLS 28 lbr 40,000 144 Stop Kontak bj 23,750 145 Tanah Urug m3 70,000 146 Teak Oll ltr 22,000 147 Teakwood 3 MM lbr 61,500 148 Teakwood 4 MM lbr 221,000 149 Tinner A ltr 18,000 150 Triplex 3 Mm lbr 59,000 151 T dus clipsal 20 mm hitam bh 2,500 152 Vernis kg 42,000 153 Washtafel KIA Standar bh 253,000 154 Wood Filer kg 22,000 155 Wood stain kg 40,000 156 Water proofing Masterseal 440 kg 32,000 157 Urinoir bh 265,000 158 Cat Penutup 2x kg 18,000 159 Kayu Kamper Papan m3 6,500,000 160 Lem kayu kg 11,500
161 kayu Kamper Reng ikat 240,000 162 Inbow dus plastik clipsal bj 2,300 163 Overspaning NYM ls 151,000 164 Penangkal Petir tbk 2,700,000
DAFTAR HARGA SATUAN UPAH
NO NAMA BARANG SATUAN HARGA(Rp.)
1 2 3 4
1 Mandor Hari 60,0002 Kepala Tukang Hari 60,0003 Tukang Politur Hari 45,0004 Tukang Batu Hari 45,0005 Tukang kayu Hari 55,000 6 Tukang Besi Hari 60,0007 Tukang cat Hari 45,0008 Tukang gali Hari 35,0009 Tukang Listrik Hari 45,000
10 Tukang Pipa/ Tukang Ledeng Hari 45,00012 Tukang Aspal Hari 40,00013 Tukang masak Aspal Hari 40,00014 Pekerja Hari 30,00015 Tukang Ukir Hari 75,000
Catatan :1. Harga - harga belum termasuk PPn 10 %;2. Harga - harga hanya sebagai pedoman / pendukung
dalam perhitungan konstruksi ( tidak mengikat ).
RENCANA ANGGARAN BIAYA (RAB) SMP NEGERI 4 KUTA SELATAN
1 Dengan rasio manfaat biaya (RMB)(benefit cost ratio = BCR)
PmoRMB = > 1
Pbo
Dimana :Pmo = Nilai kontrak = Rp. 1,150,709,482 Pbo = Nilai biaya pelaksana = Rp. 1,035,638,533
Maka : 1,150,709,482
RMB = = 1.11 1,035,638,533
RMB = 1.11 > 1 Investasi layak!
2 Dengan Net Present Value (NPV)
NPV = PWB - PWCPWB = Rp 460,283,793 + Rp 575,354,740 (P/F,10%,2) +
+ Rp 345,212,844 (P/F,10%,4) +
Dimana := Rp 460,283,793 + Rp 575,354,740 0,8264 +
+ Rp 345,212,844 0,6839 += Rp 1,525,541,208.00
PWC = Rp (308,827,411.00) (P/F,10%,1) - Rp 378,111,629 Rp 293,603,524.00 (P/F,10%,3) - Rp 195,000 Rp 64,002,461.00 (P/F,10%,4) - Rp 195,000 Rp 150,000,000.00 (P/F,10%,4)
= Rp (308,827,411.00) 0,9091 - Rp 378,111,629 Rp 293,603,524.00 0,7313 - Rp 195,000 Rp 64,002,461.00 0,6839 - Rp 195,000 Rp 150,000,000.00 0,6839
= Rp 952,069,452.00
Maka :NPV = PWB - PWCNPV = Rp 573,471,756 - Rp - NPV = Rp 573,471,756 > Investasi layak!
3 Dengan laju pemulangan internal(internal rate of return = IRR)
Dimana :
Investasi (I) = nilai kontrak 1,150,709,482 Annual benefit (Ab) = Rp 335,916,353 Suku bunga (i) = 10% per tahunRencana umur investasi (n) = 7 tahun
IRR ³ MARR
MARR = i = 12 % NPV = 0
Maka :
1 Untuk i = 12 %
NPV = - I + Ab ( P/A, I, n )
NPV = -Rp1,150,709,482 + Rp 335,916,353 4.5638 NPV = Rp382,330,971
2 Untuk i = 15 %
NPV = - I + Ab ( P/A, I, n )
NPV = -Rp1,150,709,482 + Rp 335,916,353 4.1604 = Rp246,843,542
Untuk mendapatkan IRR diinterpolasikan antara I = 12% dan i = 15%
IRR = + NPV+
=12%
+ Rp382,330,971Rp382,330,971 + -Rp246,843,542
= 12% + 0.0847 %
= 12.0847 %
Karena IRR = 12.0847% >>> MARR = 12%, maka Investasi layak!
iNPV+ NPV+ NPV-
ANALISA INVESTASI
Investasi layak!
Rp 150,000,000 (P/F,10%,2) Rp 335,916,353 (P/F,10%,4)