Page 1: Construction Update September 2014 Madison Elementary School District.

Construction Update September 2014Construction Update September 2014

Madison Elementary School DistrictMadison Elementary School District

Page 2: Construction Update September 2014 Madison Elementary School District.

Summer Projects

Madison Park Action Lab Before

Page 3: Construction Update September 2014 Madison Elementary School District.

Summer Projects

Madison Park Action Lab After

Page 4: Construction Update September 2014 Madison Elementary School District.

Summer Projects

Madison Park Front Entry & Parking Lot

Page 5: Construction Update September 2014 Madison Elementary School District.

Summer Projects

Madison Park Exterior Lighting Replacement

Page 6: Construction Update September 2014 Madison Elementary School District.

Summer Projects

Madison Park Cooling Tower Replacement

Before

After

Page 7: Construction Update September 2014 Madison Elementary School District.

Summer Projects

Rose Lane Courtyard & Stage

Page 8: Construction Update September 2014 Madison Elementary School District.

Other Projects Completed

• Rose Lane- Landscaping• Park- Landscaping• Meadows- Sidewalk replacement• Madison #1- Interior painting• District- UV protection of rubberized play surface• Maintenance and Transportation- Lobby• Park- Remodel rooms J3 & J8• Madison #1- Remodel dance studio• Park- New marquee

Summer Projects

Page 9: Construction Update September 2014 Madison Elementary School District.

Upcoming Projects

• Heights- Student restroom remodel• Heights- Conference room remodel• Rose Lane- Restroom remodel• District Office- Fire alarm replacement (in-progress)

• M&T- Parking lot renovations• Energy Auditing and planning

Page 10: Construction Update September 2014 Madison Elementary School District.

Phase 2 Solar ProjectsMeadows & Madison Traditional Academy

Application and award of APS rebates..

System planning and design

Projects permitting process.

Construction and Operation.

Page 11: Construction Update September 2014 Madison Elementary School District.

Solar Construction Timeline

September

October

November

December

START

FINISH

Mobilization

Completion & Operation

Structural Steel

Solar Panel Set