Madison Elementary School District Bond Project Update August 2013
10

Madison Elementary School District

Jan 10, 2016

Download

Documents

Peyton

Madison Elementary School District. Mr. Calvin. Bond Project Update August 2013. Solar Update Madison #1. Solar Update Rose Lane Elementary. Solar Update Park Elementary. Solar - Schedule of Completion. Structural and panel set- 8/22/13 - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Madison Elementary School District

Madison Elementary School DistrictBond Project Update August 2013

Page 2: Madison Elementary School District

Solar Update Madison #1

Page 3: Madison Elementary School District

Solar Update Rose Lane Elementary

Page 4: Madison Elementary School District

Solar Update Park Elementary

Page 5: Madison Elementary School District

Solar - Schedule of Completion

• Structural and panel set- 8/22/13• Broken sidewalk replacement- 8/26/13• Installation of turf and DG- 9/16/13• Substantial completion- 9/23/13• First day of generation- 9/26/13• Final Completion- 10/14/13

Page 6: Madison Elementary School District

The Next Step in Solar

Site evaluations later this weekPreliminary design by 8/29Submitting applications to APS for rebates by 8/30

Page 7: Madison Elementary School District

Rose Lane Café Remodel

Page 8: Madison Elementary School District

Madison Heights Café Remodel

Page 9: Madison Elementary School District

Madison Meadows Site Work

Page 10: Madison Elementary School District

Upcoming Projects

• Madison Heights kitchen remodel• Madison Meadows front office remodel• Non-skid surfacing on exterior stairs• Roof replacement at Heights• Daylighting in dining areas at Heights, Park and Rose Lane

Questions: