Top Banner
A Practical Summer Training Report On Construction of class A type of school building and 9 unit staff qtrs for kendriya vidyalya at karauli. In CENTRAL PUBLIC WORKS DEPARTMENT(CPWD),JAIPUR Submitted as a Partial fulfillment of the B.Tech program In CIVIL ENGINEERING of Rajasthan Technical University,Kota SESSION 2012-13 SUBMITTED TO :- SUBMITTEDBY :- PROF.(DR.) SUDHIR KUMAR PAWAN KUMAR MEENA HEAD OF DEPT.CIVIL ENGINEERING B.TECH 4 th year(CIVIL) ROLL NO.= 09EVVCE033 _________________________________________________________________________________________________ __________________ 1
43

Civil Tranning Report

Oct 27, 2014

Download

Documents

Abhishek Meena
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Civil Tranning Report

A Practical Summer Training Report

On

Construction of class A type of school building and 9 unit staff qtrs for kendriya vidyalya at karauli.

In

CENTRAL PUBLIC WORKS DEPARTMENT(CPWD),JAIPUR

Submitted as a Partial fulfillment of the B.Tech program

In CIVIL ENGINEERING of

Rajasthan Technical University,Kota

SESSION 2012-13SUBMITTED TO :- SUBMITTEDBY :-

PROF.(DR.) SUDHIR KUMAR PAWAN KUMAR MEENA

HEAD OF DEPT.CIVIL ENGINEERING B.TECH 4thyear(CIVIL) ROLL NO.= 09EVVCE033

___________________________________________________________________________________________________________________

VIVEKANANDA INSTITUTE OF TECHNOLOGY(EAST), JAIPUR

ACKNOWLEDGEMENT

1

Page 2: Civil Tranning Report

I am extremely thankful to Mr. KELASH RAM MEENA(JEN) and all the staff, site managementof CENTRAL PUBLIC WORKS DEPARTMENT(CPWD) For my great knowledgeful

practical summer training at the construction site, laboratory, and testing plant site and also at office work formalities.

I am greatful to Mr. KELASH RAM MEENA and other staff of CPWD as well as security guards etc. who given the guidance and extend their support during my summer training

I am also thankful to all who helped me to complete my training successfully.

I am thankful to respected Principal sir Mr. M. Raisinghani, Ms. LatikaDhuria (Head Training & Placement),Mr.(dr.) sudhir kumar (head civil), Mr. NarianMeghnani, Mr. Yuvraaj Singh (Head

Training & Placement-CIVIL )and other faculties and staff of college for their support and guidance.

I am also thankful to my mother and father who has encouraged from time to time for the same.

PREFACE

2

Page 3: Civil Tranning Report

Project give an opportunity to implement the principles and knowledge practically. The experience that one gets wonderful because what one studies in books is different from what one fact in the field.

A Project helps a student in getting acquainted with the manner in which his knowledge is being practically used and this is normally different from what one has learnt from books. Hence, when one switches from the process of learning to that of implementation his knowledge, he finds an abrupt change. This is exactly why project during the B.Tech. Curriculum becomes all the more important.

Imagine large drives used in Site, they are really effective and helpful. Also imagine of we could control different machine and equipment at site or industry by using another device. My training included these basic and some important engineering needs in an industry.

This report is detail describe of OVERVIEW OF CENTRAL PUBLIC WORKS DEPARTMENT(CPWD)

TABLE OF CONTENTS

3

Page 4: Civil Tranning Report

S. No. PARTICULARS PAGE No.

1. Introduction About the Company 52. Intro. About Project and site data 63. materials 7-104. Authority and responciblities 115. Seafty tranning 126. Site plan 137. Introduction about building 14-178. Test in Laboratory 18-319. Reinforcement Work 32-3510. Conclusion 36

INTRODUCTION ABOUT THE COMPANY

4

Page 5: Civil Tranning Report

ABOUT THE PROJECT-

5

Page 6: Civil Tranning Report

1. SITE DATA:- PROJECT NAME : KENDRIYA VIDHYALYA KARULI

PROJECT LOCATION : - AT HINDON CITY KARULI (RAJ)

COMPANY :- CPWD, JAIPUR

STRUCTRAL : - MR. KELASH RAM MEENA (J.E)

CONSULTANT

TOTAL AREA : - 4000 SQR.FT

TOTAL COST : - 1.5 CRORES

EARTHQUAKE ZONE : -IV

TYPE OF FOUNDATION: - RAFT FOUNDATION 60cm (16 mm steel bar provided)

CONCRETE GRADE: - .There are used READY MIX CONCRETE (RMC) .

P.C.C :- M10

FOUNDATION : - M30

SLAB : - M3O

COLUMN : - M40

BEAM : - M30

RETAINING WALL : - M25

2 .MATERIALS:-

6

Page 7: Civil Tranning Report

STEEL REINFORCEMENT BARS:-

There are different types of steel reinforcement bars are used as like

12mm to 25mm different for beam and column and slab according to load bearing capacity

The steel reinforcement bars are used HYSD Fe-500 TMT of “SAIL STEEL “company.

CEMENT:-

Portland cement is composed of calcium silicates and aluminates and aluminoferrite It is obtained by

blending predetermined proportions limestone clay and other minerals in small quantities which is

pulverized and heated at high temperature – around 1500 deg centigrade to produce ‘clinker’. The

7

Page 8: Civil Tranning Report

clinker is then ground with small quantities of gypsum to produce a fine powder called Ordinary

Portland Cement (OPC). When mixed with water, sand and stone, it combines slowly with the water to

form a hard mass called concrete. Cement is a hygroscopic material meaning that it absorbs moisture In

presence of moisture it undergoes chemical reaction termed as hydration. Therefore cement remains in

good condition as long as it does not come in contact with moisture. If cement is more than three

months old then it should be tested for its strength before being taken into use.

The Bureau of Indian Standards (BIS) has classified OPC in three different grades The classification is

mainly based on the compressive strength of cement-sand mortar cubes of face area 50 cm2 composed

of 1 part of cement to 3 parts of standard sand by weight with a water-cement ratio arrived at by a

specified procedure. The grades are

(i) 33 grade

(ii) 43 grade

(iii) 53 grade

The grade number indicates the minimum compressive strength of cement sand mortar in N/mm2 at 28

days, as tested by above mentioned procedure.

Only Portland pozololona cement complying with the requirements of IS 1489 shall be used otherwise as mentioned in the work. The cement shall be obtained directly from the manufacturers by the owner and issued to contractor.

The cement shall be delivered to the site in the thoroughly dry condition in sealed bags. The cement shall be unloaded under cover by the contractor at his cost and shall be stored in the perfectly water tight and well ventilated godown accommodating sufficient cement at any time to ensure continuity of work. The flooring of the godown shall be raised not less than 150mm from the surrounding ground. Each consignment shall be recorded by the contractor and stacked separately there in to permit easy access for inspection. The cement shall be utilized from the store in the same order in which it is received at the site. The cement temporarily stacked for day to day work near the concrete mixers adjacent to actual place of pour shall also be adequately protected with tarpaulin over a raised platform and to the satisfaction of the owner.

8

Page 9: Civil Tranning Report

The cement is used of 53 grade of “J.K SUPER” company.

9

Page 10: Civil Tranning Report

BRICKS:-

The bricks are used of first class.

ADMIXTURES:-

The admixture is used of “SIKA COMPANY”.

WATER:- Drinking water is used. Water is used which has pH 6.5 to 8.0.

10

Page 11: Civil Tranning Report

3.AUTHORITY AND RESPONSIBLITIES :-

SITE ENGINEER:-

To perform all site related activities in accordance with guideline provided project manager.

SUPERVISORS:-

To supervise and carry out the entire site related construction activities as per the instruction given by the project manager and site engineer.

CLIENT:-

Client is the authority witch regular check the quality of construction and takes the samples of material which are used.

SAFETY ENGINEER:-

Which gives the instruction to all the workers and engineers from physical safety point of view.

11

Page 13: Civil Tranning Report

SITE PLAN

Some important points which are important to us:-

1. Boundary of plot.

2. Shape of size :( as square, triangular, rectangular).

3. Exterior house dimension.

4. Set back leave and front back leave.

5. Name and width of existing street.

6. Elevation of center line.

7. Elevation of corners of plot.

8. No of plots, block and name of adjusting property.

9. Direction of traveling winds and north direction.

10. Generally we take the north direction because the pole star are existing in the north direction.

11. Size and location detail of gas line underground draining water main, ventilating pipes.

12. Location of fire hydrain should be mark.

13

Page 14: Civil Tranning Report

5. INTRODUCTION ABOUT BUILDING:-

CLASSIFICATION OF BUILDING

1. According to their occupancy.2. According to type of construction.

ACCORDING TO THEIR OCCUPANCY

According to N.B.C of India 1970, Buildings are classified as:

1. RESIDENTIAL BUILDINGS.2. EDUCATIONAL BUILDINGS.3. INSTITUTIONAL BUILDINGS.4. ASSEMBLY BUILDINGS.5. BUSINISS BUILDINGS.6. MERCENTILE BUILDINGS.7. INDUSTRIAL BUILDINGS.8. STORAGE BUILDINGS.9. HAZARDEOUS BUILDINGS.

1) GROUP A: RESIDENTIAL BUILDINGS

14

Page 15: Civil Tranning Report

These are those buildings in which sleeping accommodation is provided for normal residential purposes, with or without cooking or dining or both facilities. It is further sub divided into 5 groups viz A-1 to A-5.

2) GROUP B: EDUCTIONAL BUILDINGS

All those buildings, which are meant for education room, a Nursery schools to University for more than 8 hours per week. These buildings provide facilities like classrooms, staff cabins, laboratories, administrative blocks, library, and play fields.

3) GROUP C: INSTITUTIONAL BUILDINGS

These Groups include any buildings or part there of, which is used for the purposes such as medical, health, recovering health after illness, care of infant or aged persons etc. These buildings normally provide sleeping accommodation for the occupants. These buildings are further subdivided into three groups viz C-1 Hospitals and Sanitories; C-2 Custodians Institutes (example:- Homes for aged) and C-3: Panel institution (example:- Jails, Mental hospitals etc)

4) GROUP D: ASSEMBLY BUILDINGS

These include any building or part of building where group of people gather for amusements, recreations, social, religious, patriotic, civil, travel & similar purposes.

Ex- Theaters, assembly halls, auditoriums, museums, restaurant, places of worship, clubs, aero drums etc. Buildings under these groups are further subdivided into three groups i.e. D-1 to D-5 in descending order of accommodation and facilities.

15

Page 16: Civil Tranning Report

5) GROUP E: BUSINESS BUILDINGS

These include any building or part of building, which is used for the transaction of business, for keeping accounts, doctors & barber shop, beauty parlors etc.

6) GROUP F: MERCANTILE BUILDINGS

These groups include any building or part of buildings, which is used for shops, stores, markets for sale and display of products for wholesale or retail.

7) GROUP G: INSDUSTRIAL BUILDING

This group includes any building or part of a building or structure in which products of different kinds and properties are fabricated and assembled or processed. For example assembly plants, power plants laboratories, gas plants, refineries, dairies etc.

8) GROUP H: STORAGE BUILDING

This group includes those buildings, which are primarily used for storage of goods, wares, (not highly combustible), warehouses, cold storages, garages etc.

9) GROUP I: HAZARDOUS BUILDING

This group includes those building structures which are used for storage, handling, and manufacture or processing of materials which are liable to burn with extreme rapidity and prove hazardous to health, building contents. Ex- buildings used for storage of highly flammable liquids or explosives etc. included in this groups.

16

Page 17: Civil Tranning Report

ACCORDING TO TYPE OF CONSTRUCTIONS

1) LOAD BEARING STRUCTURES

In this system the load bearing walls of stone or brick are constructed on a continuous foundation and they are designed to support the entire load including their own load. Hence in this type of structures, the beams, trusses etc are always made to rest on lode bearing walls.

2) FRAMED STRUCTURES

In this system the numbers of piers or columns are erected on their own independent foundations and they are braced together by beams and slabs. In this way the whole structure is erected and the gaps between the piers or columns are filled with partition walls. The function of partition walls is simply to support their own weight and to serve as a screen for privacy. The entire load of structure is carried out by the frame.

3) COMPOSITE STRUCTURES

This structure is combinations of load bearing structure. In this type, the order wall consists of bearing wall. Where as the frame of columns and beams consist with one end on bearing walls and other end on inner columns with thin partitions between the bearing walls.

17

Page 18: Civil Tranning Report

TESTS IN LABORATORYIntroduction of Concrete testing lab-

1. Compression Testing Machine(CTM)2. Flexural Test of Concrete for Beam3. Soundness Test of Cement(Expansion of Cement, ”Le Chatteres

Principal”)4. Aggregate Abrasion Test5. Workability or Slump test on Concrete6. Air Content Test on Concrete7. Flakielongation Test8. Sieve analysis of coarse aggregate9. Sieve analysis of fine aggregate10. Sand present in aggregate

18

Page 19: Civil Tranning Report

CONCRETE TESTING LAB

Experiment-1

Compression Testing Machine

USE- Compressive strength test on concrete remove before 24hrs. Whenever cube is coated.

NOTE:- Load in UTM=140 Kg/cm 2 .

Size of Cube Mould=15x15x15 cm.

PROCEDURE-

1. Remove the specimen from curing tank.2. Place the specimen in Compression Testing Machine (CTM), Capacity-

3000KN.3. Place the cube so that caste face shall not be at top or bottom.4. In case so that cast face shall not be capped using Sulphur Capping.

“Sulphur Capping is for the finishing of cube layer.”5. Align the axis of specimen with center of thrust of spherically seated platen6. Apply the load till specimen break or crack.7. Record the max load applied.8. Calculate compressive strength.

Compressive Strength = Load/Area.

Unit-N/mm2

Note- Taping bar is used for cube is 25 times and 35 times.

TAPING BAR- 16mm Diameter & 700mm Long

19

Page 20: Civil Tranning Report

CONCRETE TESTING LAB

Experiment-2

Flexural Test of Concrete for Beam

1. Specimen shall be 700x150x150mm concrete beam.2. Specimen shall be cured by submerging in clean water upto time of

testing.3. Bearing surface of the supporting and loading rollers shall be wiped clean,

any loose sand or other material removed from surface of specimen.4. The specimen shall be wiped clean, any loose sand or other material

removed from the surface of specimen.5. The specimen shall then be placed in the machine in such a manner that

the load shall be applied to uppermost surface as caste in mould, along two lines spaced 200mm apart. The axis of specimen shall be carefully aligned with axis of loading device.

6. The fiber stresses increases at application 7Kg/sq./min that is at the rate of loading 4KN/min for the 150 mm specimen.

7. The load shall be increased until the specimen fails, and the maximum load applied during the test.

The flexural strength of specimen shall be expressed as modulus of rupture fb.

fb= Pl/bd2

P=Load (N), l=Length of specimen (mm), b=width of specimen (mm), d=depth of specimen (mm).

20

Page 21: Civil Tranning Report

CONCRETE TESTING LAB

Experiment-3

Soundness test of Cement (Expansion of cement)

Initial reading Final reading

(Specific Gravity of Cement)-

Le-Chatelier flask-Standard Le-Chatelier flask conforming to IS 4301, shall be used.

Analytical balance-Electronic balance of accuracy (± 0.1g) shall be used.

Procedure-

1. Kerosene, free of water having a specific gravity not less than 0.731 shall be used in specific gravity determination.

2. The flask shall be filled with kerosene to a point on the stem between the 0 and 1-ml mark.

3. Inside the flask above the level of the liquid shall be dried.4. First reading shall be recorded.5. A weighted quantity of cement (about 65g for Portland cement) shall then

be introduced in small amount at the same temp. as the liquid.6. Care shall be taken to avoid splashing and has been introduced, the stopper

has been introduced.

21

Page 22: Civil Tranning Report

7. The stopper shall be placed in the flask and the flask rolled in inclined position or gently whirled in the horizontal circle, so as to free the cement from air until no further air bubbles rise to surface of the liquid.

8. If proper amount of cement has been added the level of liquid will be in its final position at some point of upper series of graduations.

9. The final reading shall be taken.10.The flask shall be kept in constant temperature room for sufficient interval

before making either of the reading so as to avoid variation greater than 0.2°C in temperature of the liquid in the flask.

11.The difference between the first and final reading represent the volume of liquid displace by the mass of cement used in test.

The Specific Gravity shall be calculated as-

Mass of cement in (gms)= --------------------------------

Displaced volume in cm3

22

Page 23: Civil Tranning Report

CONCRETE TESTING LAB

Experiment-4

Workability/Slump test on cement

1. Collect the sample onnon absorbent metal plate or tray and mix it thoroughly.

2. Clean the internal surface of cone slump.3. Fix the cone firmly to its base plate with help of clamping screw and place it

at horizontal surface.4. Fill the mould with concrete sample in four layers each layer approximately

¼ cone height.5. Compact each layer with 25 strokes by tamping rod.6. Release the clamping screw and lift the cone slowly and carefully in vertical

direction from the concrete.7. Place the cone inverted at the side of concrete.8. Measure the difference of height between top of cone top of plastic

concrete.9. Record the value as slump of concrete in mm.

23

Page 24: Civil Tranning Report

CONCRETE TESTING LAB

Experiment-5

Air Content test on Concrete

1. Collect the sample on nonabsorbent metal plate and mix it thoroughly.2. Fill the container in three equal layers and compact each layer with 25

strokes by tamping rod.3. Close main air valve of air receive of top LID open both the pet clocks of top

LID.4. Place LID on container and close the four toggle clamp.5. Pour water into funnel until water comes out of petcock.6. Close both the petcock and air bleeder valve.7. Gently pump air into receiver until gauge needle comes in line marked on

gauge.

24

Page 25: Civil Tranning Report

8. Top gauge gently and open main air valve.9. Allow the needle to come to rest and take the reading.10.Report this reading is present of air entered in concrete.

CONCRETE TESTING LAB

Experiment-6

Aggregate Abrasion Test

The test sample shall consist of clean aggregate which has been dried in an oven at 105°C to 110°C to substantially constant weight and shall confirm to one of the grading shown.

25

Page 26: Civil Tranning Report

Table: 1- Grading of test sample

Sieve Size (Square Hole) Weight in gm. Of Test Sample for Grade

Passing Retained on

A B C D E F G

80 63 - - - - 2500* - -63 50 - - - - 2500* - -50 40 - - - - 5000* 5000* -40 25 1250 - - - - 5000 500025 20 1250 - - - - - 5000*20 12.5 1250 2500 - - - - -

12.5 10 1250 2500 - - - - -10 6.3 - - 2500 - - - -6.3 4.75 - - 2500 - - - -

4.75 2.36 - - - 5000 - - -

Table: 2- No. of Abrasive Charges

Grading No. of Spheres Wt. of Charges gms.A 12 5000±25B 11 4584±25C 8 3330±20D 6 2500±15E 12 5000±25F 12 5000±25G 12 5000±25

26

Page 27: Civil Tranning Report

For grading A,B,C,D the machine shall be rotated for 500 revolution.

For grading E,F,G it revolve 100 revolutions. After completion test the machine shall be discharge and sample passes through 1.10 mm sieve. The finger portion shall than be sieved on a 1.70mm IS sieve sample.

The ratio of the weight of fine formed the total sample weight is expressed in % for each test.

Aggregate Abrasion Value = (B/A)*100

B = Weight fraction 1.7mm IS Sieve.

A = Weight of oven dried sample.

CONCRETE TESTING LAB

Experiment-7

27

Page 28: Civil Tranning Report

Flakieness of Aggregate Test

1. Take aggregate sample, so that minimum no. of 200 pieces of each fraction is available.

2.40 mm down aggregate-50Kg.

20 mm down aggregate-20Kg.3. Sieve the sample on IS sieve 40, 31.5, 25, 20, 16, 12.5, 10, 6.3 mm.4. Calculate % retain on each sieve.5. Count aggregate retain on each sieve as (Ni).6. Gauge each fraction for thickness on the standard metal thickness gauge.7. Aggregate passing the gauge for each fraction shall be separately counted

(N1i).

Calculate Flakiness index (F.I.) = (Σ N1i / Σ Ni)*C3i (%)

28

Page 29: Civil Tranning Report

CONCRETE TESTING LAB

Experiment-8

Sieve Analysis of Coarse Aggregate

1. Prepare sample using sample divider for different of aggregate as per table below-

Max. Size of Aggregate(mm)

Min. Wt. of Sample(Kg.) Min. Wt. of Sieve Analysis(Kg.)

40 50 20 20 25 12 10 6 3

2. Make the sample dry by heating at 100 to 110°C.3. Take the weight of sample and sieve it successfully on following sieve-

50mm, 40mm, 20mm, 10mm, and 4.75mm.4. Shake each sieve separately until not more than a trace passes but not less

than 2 min.5. Take weight of material retained on each sieve.6. Calculate % retained, and cumulative % retained on each sieve.7. Calculate corresponding % passing.

%retained = (Wt. of retained on sieve/Total Wt. of sample)*100

29

Page 30: Civil Tranning Report

CONCRETE TESTING LAB

Experiment-9

Sieve Analysis of Fine Aggregate

1. Sieve Analysis of Fine Aggregate

Max. Size of aggregate(mm)

Min. Wt. of Sample(Kg) Min. Wt. of Sieve Analysis(Kg)

10 6 3 4.75 3 1

Following using Sieve-

4.75mm, 2.36mm, 1.18mm, 600micron, 300micron, 150micron.

2. Make the sample dry by heating at 100 to 110°C.3. Take the weight of sample and sieve it successfully on following sieve-

50mm, 40mm, 20mm, 10mm, and 4.75mm.4. Shake each sieve separately until not more than a trace passes but not less

than 2 min.5. Take weight of material retained on each sieve.6. Calculate % retained, and cumulative % retained on each sieve.7. Calculate corresponding % passing.

%retained = (Wt. of retained on sieve/Total Wt. of sample)*100

NOTE: - Sieve shaker with 20 & 45 cm. frame.

30

Page 31: Civil Tranning Report

Reinforcement Work

31

Page 32: Civil Tranning Report

Material- HYSD bar and TMT bar Fe 500 to IS 1786.

In Fe 500 steel elongation not more than 14.5% ultimate tensile strength of bar 15% more than actual 0.2% proof stress/yield stress.

Storage-Reinforcement steel shall not keep direct contact with ground; it is kept on timber sleepers or concrete pedestal.

Bending of Reinforcement-The reinforcement bar shall be cold bent at appropriate radius of minimum 6D using “Bar Bending Machine” with proper mandrill. Load shall be applied gradually on bar.

Lying of Reinforcement- The bars are placed as according to reinforcement diagram. Chair/ Spacer made up of reinforcement steel bar shall be provided to keep the bars in position. The radius of bent is less than 6 times the diameter for HYSD TMT bars.

Reinforcement shall be tied with each other 16 gauge where the spacing of re-bars is greater than 300mm both ways. If spacing of the bars is less than 300mm, only alternate joint shall be tied both ways.

Spacing- R*Ø 36 mm Ø bar is used for reinforcement of grade Fe 500in construction of

Reactor Building.

32

Page 33: Civil Tranning Report

Q. Why we use Fe 500 bar, not use Fe 415 bar in construction of Reactor Building?Ans. Because the strength of Fe500 is more than Fe 415 bar.

Types of Bars used in construction of Reactor Building:-

S.No. Name of Bar Diameter of Bar

Shape of Bar Type of Bar

1. Straight Bar 8mm TMTFe 500

2. Straight Bar 10mm TMTFe 500

3. Straight Bar 18mm TMTFe 500

4. Straight Bar 20mm TMTFe 500

5. Straight Bar 32mm TMTFe 500

6. Straight Bar 36mm TMTFe 500

33

Page 34: Civil Tranning Report

7. Chair Bar 36mm TMTFe 500

8. Lap Bar 36mm TMTFe 500

9. Radial Bar 32mm TMTFe 500

Bending of Bars-

Stirrup and Links used in bars-

Tying of Reinforcement-

34

Page 35: Civil Tranning Report

CONCLUSION

On concluding the training report , I would like to say that I got a good overview of central public works department (cpwd). I learn about the practical knowledge at site. I learnt about many instrument at the site. I think this training will come good in future use. Apart from my area of project I also got an idea that “ How to do work at construction site”, which is important in my future.

35