CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
11-18-70 Construction 32944 Road Concreting at Brgy. Sallacapo
02/28/09 I 0.855 18 C 0.375 0.200 0.300 - - - 87.50
*87.50%Satisfactory
121 Construction Corporation (Formerly:
121 Construction)21686 Const. of Two (2) Storey MPB at Brgy.
Malamig 08/10/11 NCR 1.868 60 C 0.483 0.200 0.300 - - - 98.30
*98.30% Outstanding
121 Construction Corporation (Formerly:
121 Construction)21686 Const. of 2-Storey, 2-Classroom Sch.
Bldg. at Heritage ES, Loma de Gato 04/15/11 III 2.472 120 C 0.419
0.200 0.300 - - - 91.90
89.10% V. Satisfactory
121 Construction Corporation (Formerly:
121 Construction)21686 Const. of MPB, Brgy. Mabini J. Rizal
06/02/10 NCR 9.315 180 C 0.475 0.200 0.300 - - - 97.50 91.97% V.
Satisfactory
2H2L Construction 16293 Impv't. of Drainage & Stairpathwalk,
Brgy. Sta. Cruz 08/04/11 IVA 0.947 60 C 0.493 0.133 0.300 - - -
92.60*92.60%
V. Satisfactory
2H2L Construction 16293 Const. of 2-Storey Sch. Bldg., Famy E/S
08/11/11 IVA 3.856 60 C 0.453 0.138 0.300 - - - 89.10*89.10%
V. Satisfactory
2H2L Construction 16293 Rehab. of 8th and 9th Streets, San
Martin Subd., Brgy. San Isidro 08/04/11 IVA 1.789 90 C 0.440 0.133
0.300 - - - 87.30*87.30%
Satisfactory
2H2L Construction 16293 Const. of Two (2) Storey, Six (6)
Classrooms Cainta E/S 04/15/11 IVA 7.848 150 C 0.389 0.200 0.300 -
- - 88.9085.75%
Satisfactory
2H2L Construction 16293 Impvt. of Flood Control at So. Upper
East Kamias & So. East Kamias 03/12/09 IVA 2.692 120 C 0.461
0.138 0.300 - - - 89.90*89.90%
V. Satisfactory
2H2L Construction 16293 Impvt. of Multi-Purpose Pavement at
Brgy. Dela Paz & Brgy. San Isidro 03/12/09 IVA 3.748 150 C
0.479 0.133 0.300 - - - 91.20*91.20%
V. Satisfactory
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page1
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
2H2L Construction 16293Rehab./Reconst./Upgrading of
Marikina-Victoria Valley-Antipolo Road
08/26/09 IVA 19.222 180 C 0.475 0.200 0.300 - - - 97.50 91.86%
V. Satisfactory
2H2L Construction 16293Rehab./Reconst./Upgrading of
Marikina-Victoria Valley-Antipolo Road
05/18/09 IV-A 19.221 180 O 0.387 0.239 0.150 0.030 0.025 0.050
88.10 -
2-R Construction & Supply 15304
Const. of Additional Classroom @ Comprehensive Nat'l. H/S
05/21/09 I 2.417 120 C 0.496 0.072 0.300 - - - 86.80
*86.80% Satisfactory
3FS Construction 30464 Upgrading of Gov't. Center Road Network,
Km.000+650-Km.000+843 08/25/11 VIII 3.690 110 O 0.390 0.240 0.150
0.030 0.030 0.033 87.30 -
3FS Construction 30464Road Upgrading (Gravel to Paved) of
Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara Road
04/06/11 VIII 19.108 180 C 0.459 0.176 0.300 - - - 93.50 90.62%
V. Satisfactory
3FS Construction 30464 Const. of Coastal Road 04/08/11 VIII
18.895 150 C 0.421 0.133 0.300 - - - 85.40 *85.40% Satisfactory
3FS Construction 30464 Upgrading of Bagahupi-Babatngon-Sta.
Cruz, Barugo-Carigara Rd. 03/11/10 VIII 19.289 230 C 0.497 0.189
0.300 - - - 98.6091.07%
V. Satisfactory
3FS Construction 30464 Const. of Grouted Riprap @ Brgy. 90
03/18/09 VIII 0.962 70 C 0.381 0.200 0.300 - - - 88.10 *88.10%
Satisfactory
3K Builders 27277 Const. of MPB, Natividad NHS (formerly:
Narciso Ramos NHS) 08/12/11 I 1.918 100 C 0.460 0.133 0.300 - - -
89.30*89.30%
V. Satisfactory
3K Builders 27277Repair/Rehab. of MNR, Km.174+000 -
Km.175+000 w/ exception Villasis Section
06/10/10 I 9.996 32 C 0.455 0.133 0.300 - - - 88.80 88.80%
Satisfactory
3K Rock Engineering 27908 Const. of Sch. Bldg. @ Diego Silang
E/S 08/15/011 II 0.748 45 C 0.464 0.120 0.300 - - -
88.40*88.40%
Satisfactory
3K Rock Engineering 27908 Const. of One Unit Classroom School
Building, San Antonio I/S 04/08/11 II 0.641 45 C 0.485 0.133 0.300
- - - 91.80*91.80%
V. Satisfactory
3K Rock Engineering 27908 Construction of Multi-Purpose
Building, Magsaysay 09/03/09 II 0.572 45 C 0.407 0.200 0.300 - - -
90.70*90.70%
V. Satisfactory
3K Rock Engineering 27908 Const./Repair of Multi-Purpose
Building 02/25/10 II 1.735 60 C 0.413 0.133 0.300 - - -
84.6084.60%
Satisfactory
3K Rock Engineering 27908 Const./Completion of MPB, Liwayway
06/05/10 II 1.445 60 C 0.441 0.133 0.300 - - - 87.4087.40%
Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page2
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
3K Rock Engineering 27908 Completion of Multi-Purpose Building,
Gundaway 03/06/09 II 1.783 60 C 0.458 0.200 0.300 - - -
95.80*95.80%
V.Satisfactory
3-L Construction 16745 Const. of 2 Storey Multi-Purpose Bldg.
(Brgy. Hall), Brgy. San Gabriel 03/09/09 V 0.955 120 C 0.436 0.175
0.300 - - - 91.10*91.10%
V. Satisfactory
3-L Construction 16745 Road Upgrading (Gravel to Paved),
Sipocot-Cabusao Road 09/09/09 V 6.555 150 C 0.418 0.200 0.300 - - -
91.8089.64%
V. Satisfactory
3RB Construction & Supply 19541
Rehab./Reconst./Upgrading of Calamba-Sta. Cruz-Famy Road
08/09/11 IVA 8.125 75 C 0.393 0.133 0.300 - - - 82.60
*82.60% Satisfactory
3RB Construction & Supply 19541
Road Upgrading of San Fernando North Road (San Jacinto Sect.)
08/11/11 V 19.100 165 C 0.391 0.133 0.300 - - - 82.40
83.72% Satisfactory
3RB Construction & Supply 19541 Const. of Sto. Cristo
Seawall 05/28/10 V 2.876 150 C 0.458 0.133 0.300 - - - 89.10
89.10% Satisfactory
3RB Construction & Supply 19541
Road Upgrading along DM Jct.-Leg.-Sto. Domingo-Tab.-Cam. Sur
Bdry.,
Tiwi-Tabaco Section02/24/09 V 19.233 150 C 0.488 0.133 0.300 - -
- 92.10 84.30% Satisfactory
3RB Construction & Supply 19541
Impvt. of San Fernando North Road, San Jacinto Section 02/17/10
V 9.450 210 O 0.378 0.240 0.150 0.015 0.035 0.050 86.80 -
3RB Construction & Supply 19541
Road Conc. & Impvt. of Barangay Road 02/22/10 V 0.959 160 C
0.396 0.139 0.300 - - - 83.50
86.38% Satisfactory
3RB Construction & Supply/Ajan Jaeda, Inc.
(JV) JV-08-209 Const. of Tagas-Divino Rostro Bridge 09/01/09 V
19.179 202 O 0.384 0.240 0.150 0.030 0.033 0.050 88.70 -
3S Builders 18009 Repair and Rehab. of MPB (Municipal Hall)
04/09/11 VII 1.893 97 C 0.491 0.133 0.300 - - - 92.40*92.40%
V. Satisfactory
4 A's Construction 9446 Construction of 1-CL (7x9) Lupigue IS
09/05/09 II 1.108 45 C 0.454 0.133 0.300 - - - 88.70*88.70%
Satisfactory
4 A's Construction 9446 Const./Conc. of Road 02/23/10 II 4.822
330 C 0.413 0.133 0.300 - - - 84.60 84.60% Satisfactory
4 A's Construction 9446 Asphalt Overlay of Daang Maharlika
03/03/09 II 1.929 30 C 0.464 0.133 0.300 - - - 89.70 *89.70%
V.Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page3
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
4B Construction Corporation 23445
Upgrading and Concreting of Subic-Philseco Road 03/03/09 III
41.616 180 C 0.407 0.163 0.300 - - - 87.00
83.76% Satisfactory
4B Construction Corporation 23445
Rehab./Reconst./Upgrading of Damaged Paved National Road,
Olongapo-Bugallon Road05/23/09 III 33.265 45 C 0.374 0.200 0.300
- - - 87.40 *87.40%Satisfactory
4B Construction Corporation 23445
Preventive Maint. along Roman Expressway (Bal Sect.)
K0120+279.82-K0123+434.42; (Cupang-Alauli Sect.)
K0123+434.42-
K0 125+000
08/06/11 III 28.532 53 C 0.437 0.003 0.300 - - - 74.00 *74.00%
Poor
4B Construction Corporation 23445
Rehab./Reconst./Upgrading of Visayas Avenue (Km 164+236-
Km.164+711 & Km. 164+872 - Km. 164+236
08/06/11 III 14.802 24 C 0.453 0.135 0.300 - - - 88.80 *88.80%
Satisfactory
4B Construction Corporation 23445
Widening/Conc. of Calamba-Sta. Cruz-Famy Jct. Road (4 Lanes)
08/10/11 IVA 45.081 120 O 0.323 0.240 0.011 0.030 0.050 0.050 70.40
-
4B Construction Corporation 23445
Rehab./Reconst./Upgrading of Damaged Paved National Roads at
Subic-PHILSECO Rd.04/04/11 III 41.378 163 C 0.356 0.167 0.300 -
- - 82.30 80.41% Unsatisfactory
4B Construction Corporation 23445
Repair/Rehab. of Paete-Famy Pob. Rd., Pangil-Siniloan Sect.
Km.109+000 - Km.110+400
05/25/10 IVA 9.608 20 C 0.472 0.133 0.300 - - - 90.50 90.50% V.
Satisfactory
5-1 Construction Corporation 33605
Asset Preservation (Preventive Maintenance) of Ilocos Sur,
Km.0011+519 to Km.0011+909 with exception
08/11/11 NCR 1.908 30 C 0.462 0.200 0.300 - - - 96.20 *96.20%
Outstanding
525 Construction 28532 Rehab. of Sta. Rita-Biak na Bato via
Pulong Bayabas Road 04/15/11 III 38.599 210 C 0.330 0.200 0.300 - -
- 83.0089.66%
V. Satisfactory
525 Construction 28532 Rahab. of Sta. Rita-Biak na Bato via
Pulong Bayabas Road 09/08/09 III 19.049 120 C 0.478 0.133 0.300 - -
- 91.10*91.10%
V. Satisfactory
525 Construction / MGSCC (JV)
JV-07-095/ SLI-SN-005104
Rehabilitation/Improvement of Sta. Rita Biak na Bato Road
03/11/09 III 44.000 200 C 0.405 0.200 0.300 - - - 90.50
*90.50% V.Satisfactory
525 Construction/MGSCC Joint Venture JV-08-235
Rehabilitation of Sta. Maria-Norzagaray Road 09/07/09 III 46.339
180 C 0.479 0.133 0.300 - - - 91.20
86.64% Satisfactory
5G Galvez Construction and Supply 34736
Northern Samar First Engineering District Brgy. Dancalan
08/12/11 VIII 0.960 60 C 0.457 0.133 0.300 - - - 89.00
*89.00% Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page4
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
6 Jewels Construction 34737 Const. of Line Canal @ Inicbulan
08/17/11 IVA 0.496 45 C 0.484 0.133 0.300 - - - 91.70 *91.70% V.
Satisfactory
628 Construction Enterprises 30049
Construction of Two Classroom School Building at Lokeb Norte
03/06/09 I 1.369 70 C 0.429 0.178 0.300 - - - 90.70
*90.70%V. Satisfactory
722 Construction 21923 Rehab./Reconst./Upgrading at Old Cagayan
Valley Rd. (Baliuag Sect.) 06/10/10 III 9.547 80 C 0.460 0.133
0.300 - - - 89.3089.30%
V. Satisfactory
722 Construction 21923Rehab/Reconst./Upgrading of Old
Cagayan Valley Road (Pulilan Section)
05/28/09 III 9.543 45 C 0.359 0.200 0.300 - - - 85.90
*85.90%Satisfactory
722 Construction 21923 Const. of Sch. Bldg., 2 Storey, 2 CL
Banga E/S 03/10/09 III 2.290 100 C 0.472 0.133 0.300 - - -
90.5089.52%
V.Satisfactory
722 Construction 21923Const. of Multi-Purpose Bldg.
Malinta E/S Lawang Bato E/S, Brgy. Lawang Bato & Natividad
Homes
03/03/09 NCR 1.882 90 C 0.405 0.136 0.300 - - - 84.10 *84.10%
Satisfactory
722 Construction 21923Rehab./Reconst./Upgrading of
Damages Pavement along Mc Arthur Highway
05/31/10 NCR 9.506 120 C 0.436 0.200 0.300 - - - 93.60 93.60% V.
Satisfactory
722 Construction 21923 Rehab./Reconst./Upgrading along Rizal
Avenue Extension 05/27/09 NCR 9.494 120 C 0.380 0.200 0.300 - - -
88.00*88.00%
Satisfactory
722 Construction 10221 Const. of MPB (Day Care) at Brgy. Polo
09/16/09 NCR 1.901 75 C 0.486 0.133 0.300 - - - 91.90*91.90%
V. Satisfactory
722 Construction, Inc. (Formerly: 722 Construction)
21923 Repair and Rehab. along MacArthur Highway Extension,
Dalandanan 08/02/11 NCR 8.895 157 O 0.363 0.240 0.150 0.030 0.045
0.033 86.10 -
722 Construction, Inc. (Formerly: 722 Construction)
21923 Impvt./Rehab. of Road, Sumandig Road, Brgy. Sumandig
08/17/11 III 1.914 70 C 0.405 0.200 0.300 - - - 90.50*90.50%
V. Satisfactory
722 Construction, Inc. (Formerly: 722 Construction)
21923 Preventive Maint.Daang Maharlika Road.
Km.43+792-Km.44+478.32 08/11/11 III 8.283 18 C 0.428 0.135 0.300 -
- - 86.30*86.30%
Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page5
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
722 Construction, Inc. (Formerly: 722 Construction)
21923
Asphalt Overlay along NCR/Bulacan Bdry.-Bigte-Ipo Dam Road,
Km.029+836-Km.029+(-149) w/ exception
08/17/11 III 5.027 20 C 0.385 0.137 0.300 - - - 82.20 *82.20%
Satisfactory
739 Builders 31174 Const. of Ten (10) CL, Two (2) Storey Sch.
Bldg. At Ilocos Sur NHS 03/31/11 I 8.068 240 C 0.351 0.142 0.300 -
- - 79.3083.36%
Satisfactory
739 Builders 31174 Construction of School Building, Pila E/S,
Brgy. Pila 09/07/09 I 0.950 60 C 0.454 0.154 0.300 - - -
90.80*90.80%
V. Satisfactory
739 Builders 31174 Const. of Drainage Canal, Brgy. VII 05/29/10
I 1.141 80 C 0.444 0.133 0.300 - - - 87.70 87.70% Satisfactory
739 Builders 31174 Road Concreting, Brgy. Napo 02/28/09 I 0.950
20 C 0.364 0.200 0.300 - - - 86.40 *86.40%Satisfactory
747 Builders & Trader 16892 Rehab./Impvt. of Manggahan
Floodway Eastbank 03/12/09 IVA 14.367 170 C 0.473 0.133 0.300 - - -
90.6086.97%
Satisfactory
747 Builders & Trader 16892Proposed Rehab./Impvt. of
Pres.
Quirino Ave. West Bound (Singalong-Roxas Blvd.)
05/24/10 NCR 14.475 20 C 0.442 0.200 0.300 - - - 94.20 94.20% V.
Satisfactory
747 Builders and Trader 16892 Rehab./Reconst./Upgrading of
Antipolo Circumferential Road "A" 08/26/09 IVA 19.213 180 C 0.411
0.200 0.300 - - - 91.1088.70%
Satisfactory
811 Trading & Construction 21215
Impv't. of Jct. Nat'l. Rds.-Osmea St.-Sitio Toong Road,
Poblacion
Carugay ARC08/09/11 IVB 20.482 160 C 0.448 0.133 0.300 - - -
88.10 *85.88% Satisfactory
811 Trading & Construction 21215
Impvt. of Jct. National Road-Osmea Street-Sitio Toong Road
Pob.
Caguray ARC04/08/11 IVB 20.482 160 O 0.354 0.212 0.150 0.030
0.048 0.050 84.40 -
811 Trading & Construction 21215
Repair/Rehab. of Multi-Purpose Building (Phase II) 02/26/09 IV-B
0.288 27 C 0.463 0.133 0.300 - - - 89.60
*89.60% V.Satisfactory
830 Builders & Developers Corp. 29781
Const. of 1 CL 7m x 7m Sch. Bldg. at Lanatan Munting Tubig E/S
04/12/11 IVA 0.495 40 C 0.459 0.200 0.300 - - - 95.90
*95.90% V. Satisfactory
888 ACY Enterprises 32898Reconst. (Conc. Paving) of Jct. LIR.,
Buenavista-Carmen, Danao-Getafe
Road, Poblacion, Danao Sect.08/18/11 VII 9.541 240 C 0.328 0.200
0.000 - - - 52.80 66.93% Poor
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page6
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
888 Acy Enterprises 32898Reconst. (Conc. Paving) of Loay
Interior Rd., Trinidad & San Miguel Sect.
03/31/11 VII 14.320 565 C 0.278 0.133 0.000 - - - 41.10 60.60%
Poor
920 Factors & Enterprises 20387
Road Upgrading (Gravel to Conc.)
Gurel-Bukod-Kabagan-Buguias-
Abatan Road04/11/11 CAR 28.838 337 C 0.456 0.133 0.300 - - -
88.90 *88.90% Satisfactory
A B Aponesto Construction, Parts &
Supply22998
Road Upgrading (Gravel to Paved) along Compostela-Cateel
Road,
Osmea Section04/09/11 XI 18.892 180 C 0.372 0.200 0.300 - - -
87.20 85.82% Satisfactory
A C J Construction Resources 10635
Concreting of Poblacion Magpet-Nowa-Basak Road (Basak Section)
05/30/09 R-XII 18.797 180 O 0.336 0.300 0.000 0.024 0.055 0.050
76.50 -
A C O Construction 13105Rehab./Upgrading of Ipil-Liloy-
Sindangan Road Km. 2007+240-Km. 2008+369
08/11/11 IX 10.787 101 O 0.362 0.300 0.000 0.030 0.050 0.000
74.20 -
A C O Construction 13105
Const. of Rotonda along National Highway (Zamboanga Peninsula)
Cross Rd. Upgrading Project @
Poblacion Ipil
02/25/10 IX 2.829 115 O 0.319 0.300 0.000 0.020 0.042 0.033
71.40 -
A C O Construction 13105Zamboanga Peninsula Crossroads Upgrading
Project (Completion of
Roundabout) Sta.1801+231.50 06/05/10 IX 1.861 60 C 0.476 0.133
0.300 - - - 90.90 90.90% V. Satisfactory
A C O Construction 13105
Const. of Rotonda along National Highway (Zamboanga Peninsula
Crossroad Upgrading Project) at
Poblacion Ipil
06/05/10 IX 2.829 115 C 0.456 0.133 0.000 - - - 58.90 66.40%
Poor
A C O Construction 13105 Conc. of Liloy-Zamboanga del
Norte-Ipil-Zamboanga Sibugay Rd. Ph. I 03/05/09 IX 14.306 150 C
0.425 0.147 0.300 - - - 87.2086.90%
Satisfactory
A. De Guia Construction 18228
Preventive Maintenance along Santiago-Tuguegarao Road @ A)
KO368+620 - KO369+000, Aurora B) KO374+000 - KO375+500
04/06/11 II 6.718 90 C 0.483 0.133 0.300 - - - 91.60 *91.60% V.
Satisfactory
A. De Guia Construction 18228 Restoration of Jones Revetment
04/11/11 II 4.825 90 C 0.450 0.133 0.300 - - - 88.30 *88.30%
Satisfactory
A. De Guia Construction 18228 Restoration of Brgy. I Revetment
04/11/11 II 4.825 90 C 0.425 0.133 0.300 - - - 85.80 *85.80%
Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page7
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A. De Guia Construction 18228 Repair/Restoration of Flood
Control, Sta.000+000 - Sta.000+120 04/11/11 II 9.650 90 C 0.400
0.133 0.300 - - - 83.30*83.30%
Satisfactory
A. De Guia Construction 18228
Rehab./Reconst./Upgrading of Santiago-Baluarte-Quirino Bdry.
Road; KO328+100 - KO331+000 w/ exception
04/10/11 II 18.623 150 C 0.428 0.133 0.000 - - - 56.10 70.44%
Poor
A. De Guia Construction 18228Rehab./Reconst./Upgrading of
Santiago-Tuguegarao Rd. Burucboc Sect.
04/06/11 II 9.647 133 C 0.456 0.133 0.000 - - - 58.90 67.42%
Poor
A. De Guia Construction 18228Rehab./Reconst./Upgrading of
Santiago-Tuguegarao Road,
KO333+500 - KO334+85004/10/11 II 17.123 149 C 0.335 0.200 0.000
- - - 53.50 65.26% Poor
A. De Guia Construction 18228Rehab./Reconst./Upgrading of
Naguilian-San Mariano Rd., Villapaz Section
08/25/09 II 19.296 104 C 0.420 0.200 0.300 - - - 92.00 92.84% V.
Satisfactory
A. De Guia Construction 18228 Concreting of Junction National
-Potia Road 08/27/09 II 7.043 110 C 0.410 0.200 0.300 - - -
91.0091.42%
V. Satisfactory
A. De Guia Construction 18228 Rehab./Reconst. of Daang Maharlika
Road, KO309+300-KO309+878 08/27/09 II 18.811 130 C 0.411 0.200
0.300 - - - 91.1091.10%
V. Satisfactory
A. De Guia Construction 18228 Rehab./Reconst./Upgrading of
Gamu-Roxas Road (Roxas Section) 02/23/10 II 19.293 240 C 0.402
0.133 0.300 - - - 83.5088.78%
Satisfactory
A. De Guia Construction 18228 Const./Completion/Continuation of
Unfinished On-going Bridges 03/01/10 II 11.574 120 C 0.415 0.133
0.300 - - - 84.8086.78%
Satisfactory
A. De Guia Construction 18228
Rehab./Reconst./Upgrading of Damaged Paved national Road,
Daang Maharlika KO 320+000 - KO 321+000
06/03/10 II 16.396 120 O 0.387 0.295 0.150 0.030 0.042 0.033
93.70 -
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page8
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A. De Guia Construction 18228
Rehab./Reconst./Upgrading of Damaged Paved National Road
Santiago-Baluarte-Quirino Bdry. Road KO326+(-)280 - KO328+000
w/
exception
08/27/10 II 15.432 149 C 0.292 0.200 0.300 - - - 79.20 87.24%
Satisfactory
A. De Guia Construction 18228
Restoration of Road Slope & Slope Protection along
Naguilian-San
Mariano Road KO395+850 - KO401+800
08/25/10 II 14.471 120 C 0.389 0.150 0.300 - - - 83.90 85.28%
Satisfactory
A. De Guia Construction 18228Road Upgrading (Gravel to Paved) of
Jct. Ipil-Panang-Quirino Bdry. Road;
KO366+058 - KO367+11808/27/10 II 17.373 149 C 0.403 0.146 0.300
- - - 84.90 84.90% Satisfactory
A. E. Belleza Builders Pampolna Resettlement Project, Phase I
04/23-26/12 NHA 9.978 150 O 0.398 0.300 0.000 0.030 0.056 0.033
81.74 -
A. Montalbo Trading and Construction 32684
Const. of Multi-Purpose Building at Bigain 1st 03/01/10 IVA
1.135 30 C 0.450 0.200 0.300 - - - 95.00
95.00% V. Satisfactory
A.A De Vera Construction 6191 Rehab./Expansion of Waterworks
System 09/02/09 VII 4.510 240 C 0.417 0.133 0.300 - - -
85.00*85.00%
Satisfactory
A.A De Vera Construction 6191 Const./Rehab. of School Bldg. at
Cogon E/S 06/05/10 VII 0.591 35 C 0.415 0.200 0.000 - - -
61.5061.50% Poor
A.A De Vera Construction 6191 Const. of Water System Development
Project 08/25/10 VII 1.413 90 C 0.497 0.133 0.300 - - -
93.0093.00%
V. Satisfactory
A.A De Vera Construction 6191 Const./Repair & Completion of
Instructional Classroom, Corella CES 06/10/09 VII 0.504 105 C 0.492
0.200 0.300 - - - 99.20*99.20%
Outstanding
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page9
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.A De Vera Construction 6191Completion of Tagbilaran City
Puericulture Center & Maternity House and Related
Facilities
06/10/09 VII 4.575 150 C 0.500 0.169 0.300 - - - 96.90 *96.90%
Outstanding
A.A De Vera Construction 6191 Const./Repair/Rehab. of
Multi-Purpose Building 06/10/09 VII 0.460 105 C 0.483 0.154 0.300 -
- - 93.7095.52%
V. Satisfactory
A.A De Vera Construction 6191 Completion of Multi-Purpose
Building 03/04/09 VII 0.458 60 C 0.382 0.200 0.300 - - -
88.20*88.20%
Satisfactory
A.A. De Vera Construction 6191 Const. of MPB, Basak 08/24/11 VII
1.835 120 C 0.485 0.133 0.300 - - - 91.80
*91.80% V. Satisfactory
A.A. De Vera Construction 6191 Const. of MPB, Songculan 08/23/11
VII 0.958 120 C 0.460 0.133 0.300 - - - 89.30
*89.30% V. Satisfactory
A.A. De Vera Construction 6191
Const. of Employees Quarters, DPWH Bohol I 03/29/11 VII 4.710
210 C 0.485 0.162 0.300 - - - 94.70
*94.70% V. Satisfactory
A.A. De Vera Construction 6191
Const. of MPB (School Stage) Loon North CES 03/29/11 VII 1.318
110 C 0.469 0.133 0.300 - - - 90.20
*90.20% V. Satisfactory
A.B Aponesto Construction Parts &
Supply22998
Road Upgrading (Gravel to Paved) along Compostela-Cateel
Rd.,
Osmea Sect.06/04/10 XI 18.892 180 O 0.355 0.238 0.150 0.030
0.045 0.033 85.10 -
A.B Aponesto Construction, Parts &
Supply22998 Concreting of Montevista-DNAS Road 03/01/10 XI
32.748 300 C 0.353 0.200 0.300 - - - 85.30
88.48% Satisfactory
A.B Taylan Construction & Development 25273
Const. of RCBC and Canal along Manila North Road (Km. 483+040)
02/22/10 I 4.816 65 C 0.329 0.133 0.300 - - - 76.20
76.20% Unsatisfactory
A.B. Taylan Construction & Development / Fiat
Construction Services (JV)
JV-09-106Road Opening/Const. of Missing
Links of Nat'l Rd., Solsona-Kabugao Road, Phase VI, Ilocos Norte
Side
08/01/11 I 192.447 540 C 0.464 0.145 0.300 - - - 90.90 87.30%
Satisfactory
A.C Rivero Development Corporation 5122
Rehab./Reconst./Upgrading of Bacolod South Road Km.
6+862-Km.
8+350 w/ exception09/12/09 VI 26.470 280 O 0.331 0.282 0.150
0.030 0.045 0.033 87.10 -
A.C Rivero Development Corporation 5122
Const./Impvt. of Multi-Purpose Bldg. at Maasin City (Legislative
Building) 03/06/09 VIII 0.934 75 C 0.500 0.133 0.300 - - -
93.30
*93.30%V. Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page10
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.C Rivero Development Corporation (Formerly:
A.C. Rivero Const.)5122
Rehab./Reconst./Upgrading of Bacolod South Rd. Km. 6+862 to
Km.
8+350 with exceptions03/06/10 VI 26.337 280 C 0.393 0.200 0.300
- - - 89.30 87.98% Satisfactory
A.C Soliven Construction & General Merchandise 19278
Channel Impvt./Slope Protection @ San Roque Creek, Camias Creek
&
San Vicente Creek02/23/10 III 4.781 60 C 0.445 0.177 0.300 - - -
92.20 92.20% V. Satisfactory
A.C Soliven Construction & General Merchandise 19278
Construction of 2 CL S.B. at La Paz H/S 09/01/09 III 0.974 90 C
0.483 0.133 0.300 - - - 91.60
*91.60% V. Satisfactory
A.C. Rivero Development Corporation (Formerly:
A.C. Rivero Const.)5122 Const. of Subang Daku Bridge Phase II
08/16/11 VIII 18.890 360 O 0.376 0.300 0.150 0.030 0.045 0.033
93.40 -
A.C. Rivero Development Corporation (Formerly:
A.C. Rivero Const.)5122 Const. of Subang Daku Bridge 08/16/11
VIII 18.890 518 C 0.486 0.200 0.300 - - - 98.60 91.60% V.
Satisfactory
A.C. Soliven Construction & General
Merchandise19278 Repair/Rehab. Of FMR at Brgy. Dalumpinas
08/12/11 I 0.950 23 C 0.491 0.133 0.300 - - - 92.40
*92.40% V. Satisfactory
A.C. Soliven Construction & General
Merchandise17278
Upgrading of Capas-Botolan Rd. (Capas Sect.) K0124+805 to
K0124+94708/05/11 III 1.843 30 C 0.377 0.200 0.300 - - - 87.70
*87.70% Satisfactory
A.C. Soliven Construction & General
Merchandise19278 Const. of Two (2) Cl. Sch. Bldg. @ Aranguren
High School 04/06/11 III 0.925 90 C 0.456 0.178 0.300 - - -
93.40
*93.40% V. Satisfactory
A.D Construction 6946 Conc. of Line Canal along National Road,
Concepcion 09/09/09 IVA 1.442 90 C 0.371 0.200 0.300 - - -
87.10*87.10%
Satisfactory
A.D. Construction 6946 Impvt./Rehab. of San Jose Elem. School,
District II 08/18/11 NCR 0.838 45 C 0.458 0.200 0.300 - - -
95.80*95.80%
V. Satisfactory
A.D. Construction 6946 Partial Completion of Jose P. Laurel H/S
04/04/11 NCR 1.571 60 C 0.486 0.192 0.300 - - - 97.80*97.80%
Outstanding
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page11
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.D.P Construction & Supply 3466
Impvt./Conc. of Access Road, Tubalan Port, Tubalan 06/14/10 XI
58.261 320 O 0.338 0.300 0.000 0.030 0.040 0.033 74.10 -
A.D.P Construction & Supply 3466
Impv't./Conc. Of Mana-Ticulon-Lagumit-Little Baguio Rd. 08/25/10
XI 47.455 571 C 0.292 0.133 0.000 - - - 42.50
42.50% Poor
A.D.P Construction & Supply 3466
Rehab./Reconst./Upgrading of Damaged Paved National Road,
Roxas City Boundary-Panitan Road-Jct. Bailan Road, Capiz
(KM.112+750-
Km 122+705) with exception
08/31/10 VI 53.673 225 O 0.364 0.240 0.150 0.030 0.051 0.050
88.50 -
A.D.P Construction & Supply 3466 Reconst. of Dumaguete North
Road 03/12/09 VII 18.881 230 C 0.442 0.200 0.300 - - - 94.20
82.14%Satisfactory
A.D.P. Const. & Supply 3466 Road Upgrading of
Sara-Concepcion Road 04/13/11 VI 66.819 328 C 0.421 0.176 0.300 - -
- 89.7087.84%
Satisfactory
A.D.P. Const. & Supply 3466 Conc. of Pototan-Tina-Lambunao
Road 04/12/11 VI 9.419 178 C 0.410 0.133 0.300 - - -
84.3087.54%
Satisfactory
A.D.P. Const. & Supply 3466 Repair/Reconst./Upgrading of
Roxas City Bdry.-Panitan Jct. Bailan Road 04/11/11 VI 53.673 225 C
0.409 0.134 0.300 - - - 84.3086.61%
Satisfactory
A.D.P. Const. & Supply 3466 Const. of Various Drainage
System at Roxas City 04/11/11 VI 28.854 240 C 0.432 0.133 0.300 - -
- 86.50*86.50%
Satisfactory
A.D.S San Juan Construction 12853
Conc. of Dionisio Anore St., Brgy. Mambog 02/16/10 IVA 1.728 90
C 0.427 0.200 0.300 - - - 92.70
92.70% V. Satisfactory
A.F.G Construction & Construction Supply 17161
Const. of MPB (Covered Court) at San Enrique NHS 03/10/10 VI
1.925 78 C 0.405 0.200 0.300 - - - 90.50
87.08% Satisfactory
A.F.G Construction & Construction Supply 17161
Rehab. of Amerang Flood Control, Tigum River, Brgy. Amerang
09/05/10 VI 8.159 257 C 0.456 0.133 0.000 - - - 58.90
69.28% Poor
A.F.G Construction & Construction Supply 17161
Rehab. of Bacolod South Rd. (Hingaran Section) 09/15/09 VI
14.221 222 C 0.398 0.133 0.300 - - - 83.10
83.88% Satisfactory
A.F.G. Construction and Construction Supply 17161
Rehab./Reconst./Upgrading of Jct. National Road,
Sagay-Bato-Dian-ay-Marcelo-Balea Jct. National Road,
Bato Sect.
03/31/11 VI 37.184 210 C 0.448 0.135 0.300 - - - 88.30 83.38%
Satisfactory
A.G Cosipag Construction 12700 Balogo CIS 06/1-6/09 NIA 2.144
150 C 0.421 0.126 0.300 - - - 84.68
*84.68% Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page12
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.G Herrera Construction Corp. 26307
Construction of Multi-Purpose Building, Sto. Cristo 06/01/09 III
2.381 80 C 0.488 0.133 0.300 - - - 92.10
90.42% V. Satisfactory
A.I.P Construction 32458 Road Concreting at Pinget Barangay
03/13/09 CAR 1.872 45 C 0.386 0.200 0.300 - - - 88.60 *88.60%
Satisfactory
A.I.P Construction 32458 Rehab. of Ambasing-Balugang FMR
08/27/10 CAR 0.800 268 C 0.439 0.133 0.300 - - - 87.20 87.20%
Satisfactory
A.I.P. Construction 32458 Rehab. of Kin-iway-Tamboan FMR
04/10/11 CAR 1.000 250 C 0.436 0.147 0.300 - - - 88.30 85.42%
Satisfactory
A.I.P. Construction 32458Restoration of Road cuts along
Bontoc Baguio Road Alab Section (Km.383+619 - Km.384+124)
04/09/11 CAR 1.732 70 C 0.340 0.200 0.300 - - - 84.00 82.68%
Satisfactory
A.J Lava Builders 22265 Const. of the Makinabang Baliuag FMR
11/24/08 III 4.769 62 C 0.296 0.300 0.300 - - - 89.60*89.60%
V. Satisfactory
A.J Lava Builders 22265 Impvt./Rehab. of MPB, Brgy. San Antonio
09/14/09 NCR 2.021 90 C 0.412 0.133 0.300 - - - 84.50*84.50%
Satisfactory
A.J Lava Builders 22265 Impv't./Rehab. of MPB and Alley
Fernandez St., Brgy. San Antonio 06/04/10 NCR 0.961 45 C 0.455
0.200 0.300 - - - 95.5095.50%
V. Satisfactory
A.J Taylan Construction Corporation 2336
Road Opening/Const. of Missing Links of National Road,
Solsona-Kabugao Road, Ilocos Norte Side
09/09/09 I 48.199 300 O 0.379 0.250 0.150 0.030 0.050 0.033
89.20 -
A.J. Lava Builders 22265Preventive Maintenance of San
Mateo-Rodriguez Road, San Mateo-Rodriguez
08/01/11 IVA 4.413 30 C 0.498 0.133 0.300 - - - 93.10 *93.10% V.
Satisfactory
A.L Dare Construction 11932Const./Repair/Rehab. of Slope
Protection along Porac River,
Mabical Sect.08/16/10 III 14.344 90 C 0.481 0.133 0.300 - - -
91.40 91.40% V. Satisfactory
A.L Gantuangco Construction 30872
Construction of the Diversion Works and Canal System of Libertad
CIP -
Phase 211/15-20/2010 NIA 16.060 202 O 0.373 0.264 0.150 0.023
0.038 0.050 89.69 -
A.L Gantuangco Construction 30872 Benolho CIS 10/6-10/08 NIA
3.720 90 O 0.277 0.180 0.050 0.020 0.038 0.100 66.50 -
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page13
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.L. Dare Construction 11932 Impvt. along Kennon Road, Camp 4
04/14/11 CAR 7.177 150 C 0.388 0.200 0.300 - - - 88.80 85.98%
Satisfactory
A.L.R Construction Corporation 24110 Completion of MPB at Brgy.
Zapote 05/27/10 IVA 0.959 30 C 0.458 0.075 0.300 - - - 83.30
83.30% Satisfactory
A.L.R Construction Corporation 24110
Completion of Two (2) Storey 4-CL at Landayan E/S 08/23/10 IVA
2.302 225 C 0.407 0.165 0.300 - - - 87.20
87.06% Satisfactory
A.L.R Construction Corporation 24110 Conc.of Road, Inday
Subdivision 03/13/09 IVA 0.958 90 C 0.461 0.133 0.300 - - -
89.40
*89.40% V. Satisfactory
A.L.R Construction Corporation 24110
Const.of Multi Purpose Pavement with Perimeter Fence, Marcelino
M.
Santos NHS03/13/09 IVA 0.957 90 C 0.480 0.133 0.300 - - - 91.30
*91.30% V. Satisfactory
A.L.R Construction Corporation 24110
Const. of Pedestrian Overpass (Phase II) Brgy. Pagsawitan
09/01/09 IVA 2.882 35 C 0.484 0.185 0.300 - - - 96.90
*96.90% Outstanding
A.L.R Construction Corporation 24110
Const. of Multi-Purpose Building at Brgy. Timugan 09/03/09 IVA
2.111 40 C 0.389 0.155 0.300 - - - 84.40
*84.40% Satisfactory
A.L.R Construction Corporation 24110 Conc. of Roads, Brgy. San
Luis 02/15/10 IVA 3.358 90 C 0.455 0.200 0.300 - - - 95.50
95.50% V. Satisfactory
A.L.R Construction Corporation 24110
Completion of 2-Storey 4-CL @ Landayan E/S 02/24/10 IVA 5.030
225 O 0.354 0.300 0.150 0.015 0.018 0.033 87.00 -
A.L.R Construction Corporation 24110
Construction of Overpass (Phase I), Pagsawitan 05/30/09 IV-A
3.849 129 C 0.482 0.133 0.300 - - - 91.50
*91.50% V. Satisfactory
A.L.R Construction Corporation 24110
Const. of Pedestrian Overpass at Brgy. San Antonio and Bian-
Carmona Road Intersection06/01/09 IV-A 19.203 241 C 0.466 0.133
0.300 - - - 89.90 90.86% V. Satisfactory
A.L.R Construction Corporation 24110
Road Upgrading (Gravel to Paved-HDM-4) of Jct. MWCR (Bagong
Silang)-Cabacao Diversion Road, Brgy. Cabacao
08/28/10 IVB 9.649 145 C 0.409 0.198 0.300 - - - 90.70 88.60%
Satisfactory
A.L.R. Construction Corporation 24110
Const. of Pedestrian Overpass, Old Manila South Road, Km.34+520
04/06/11 IVA 9.632 202 C 0.395 0.111 0.300 - - - 80.60
85.64% Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page14
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.M Oreta & CO., Inc./IBC Int'l Builders Corp. (JV)
JV-07-097
Conc. of Iloilo-Caticlan Highway (Pototan-Passi-Capiz Bdry.
Sect.) 05/31/10 VI 158.259 570 C 0.379 0.200 0.300 - - - 87.90
87.82% Satisfactory
A.M Oreta & CO., Inc./IBC Int'l Builders Corp. (JV) 7096
Kalibo Airport Development Project (Asphalt Overlay of
Runway,
Extension of Apron and Construction of Drainage Canal)
04/14/10 DOTC 283.188 360 C 0.449 0.200 0.300 - - - 94.90 92.40%
V. Satisfactory
A.M Robles Construction 28056 Construction of Water Supply @
Brgy. San Simon 03/02/09 I 0.530 40 C 0.415 0.184 0.300 - - -
89.90*89.90%
V. Satisfactory
A.M Robles Construction 28056 Completion of Multi-Purpose
Building at Pinaglabanan 05/28/09 NCR 4.776 90 C 0.487 0.133 0.300
- - - 92.00*92.00%
V. Satisfactory
A.M. Oreta / IBC (JV) JV-09-227
Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads,
Iloilo-
Capiz Rd. (Old Route) Cabatuan-Janiuay-Lambunao-Calinog
Sect.
08/23/11 VI 143.049 360 O 0.345 0.200 0.150 0.030 0.059 0.050
83.40 -
A.M. Oreta / IBC (JV) JV-07-171Const. of CP-V,
Pandan-Libertad-Antique Bdry. Rd., Sta.00+057 - Sta.27+762.66 with
exception
04/06/11 PJHL 409.901 707 C 0.418 0.200 0.300 - - - 91.80
*91.80% V. Satisfactory
A.M. Oreta / IBC (JV) JV-09-227Rehab./Reconst./Upgrading of
Iloilo-Capiz Road (Old Route) Cabatuan-Janiuay-Lambunao-Calinog
Sect.
04/10/11 VI 143.049 360 O 0.336 0.300 0.150 0.030 0.056 0.033
90.50 -
A.M. Oreta / IBC International (JV) JV-08-261
Pototan Bridge along Iloilo-Capiz, (New Route) including Access
Road
to the New Airport04/10/11 VI 308.770 676 C 0.447 0.133 0.300 -
- - 88.00 83.50% Satisfactory
A.P Consebido Construction & Trading 33616 Basey Irrigation
Project 09/5-9/11 NIA 8.463 120 C 0.451 0.160 0.300 - - - 91.10
91.07% V. Satisfactory
A.P Consebido Construction and Trading 33616 Const. of MPB,
Brgy. Alimanguan 08/20/10 IVB 0.974 114 C 0.447 0.200 0.300 - - -
94.70
88.54% Satisfactory
A.P Palacios Construction 29021 Const. of MPB, Brgy. Pingit
06/05/10 III 4.287 180 C 0.470 0.133 0.300 - - - 90.30
90.30% V. Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page15
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.P Palacios Construction 29021 Rehab./Impvt. of Dikidit-Suguit
FTMR 09/08/09 III 4.723 150 O 0.300 0.300 0.150 0.030 0.050 0.033
86.30 -
A.P. Consebido Construction and Trading 33616 Const. of Seawall
at Brgy. Rizal 08/05/11 IVB 0.665 40 C 0.459 0.133 0.300 - - -
89.20
*89.20% V. Satisfactory
A.P. Consebido Construction and Trading 33616
Repair/Maint. Of Flood Control Structure of Tulariquen
Bridge,
Revetment08/05/11 IVB 0.880 48 C 0.448 0.133 0.300 - - - 88.10
*88.10% Satisfactory
A.P. Palacios Construction / Wilper
Const., Inc. (JV)
Rehab./Reconst./Upgrading of Damage Pave (SLAMAC) 04/09/11 III
46.297 240 C 0.419 0.188 0.300 - - - 90.70
*90.70% V. Satisfactory
A.P.B Construction 17055Repair/Rehab. of Baguio-Bauang Road, Km.
296+050-Km. 297+050
with exceptions08/29/10 CAR 4.891 47 C 0.456 0.176 0.300 - - -
93.20 93.40% V. Satisfactory
A.P.B Construction 17055 Rehab. and Conc. of Road at Brgy.
Balligi, Kias Barangay 03/03/10 CAR 1.248 60 C 0.384 0.158 0.300 -
- - 84.2084.20%
Satisfactory
A.P.B. Construction 17055Rehab./Reconst./Upgrading of
Damaged Paved National Road, PMA cut-off Road 2
K0+000-K0+360
08/18/11 CAR 5.610 102 O 0.370 0.240 0.000 0.030 0.042 0.033
71.50 -
A.P.O General Construction 7010
Rehab./Reconst. of Dungon-Agat Section, Km. 216+648-Km.
217+723
(V.S.) Camp 108/29/10 CAR 4.555 90 C 0.466 0.133 0.300 - - -
89.90 89.90% V. Satisfactory
A.P.O. General Construction 7010
Rehab./Reconst. along Gurel-Bokod-Kabayan-Buguias-Abatan Rd.
04/11/11 CAR 31.838 441 C 0.453 0.153 0.300 - - - 90.60
*90.60% V. Satisfactory
A.Q Loisaga Construction & General
Services32691 Const. of 2 CL in Quillo-Quillo E/S 09/01/09 IVA
2.023 120 C 0.470 0.133 0.300 - - - 90.30 *90.30% V.
Satisfactory
A.R & Mark Builders 31673 Const. of @-CL Maramag CES
02/25/10 X 0.989 105 C 0.418 0.133 0.300 - - - 85.10 85.10%
Satisfactory
A.R Lustre Jr. Construction 7680
Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds. At
Bigaa-Plaridel via Bulacan and Malolos Rd.
08/27/10 III 14.352 90 C 0.367 0.185 0.300 - - - 85.20 85.20%
Satisfactory
A.R Lustre Jr. Construction 7680
Conc. of Puerto-Princesa-Sabang Road 09/11/09 IVB 48.140 284 C
0.419 0.200 0.300 - - - 91.90
90.61%V. Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page16
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.R Lustre Jr. Construction 7680
Puerto Princesa Airport Development Project 8/13-14/09 DOTC
90.817 270 C 0.488 0.200 0.300 - - - 98.80
98.80% Outstanding
A.R Lustre Jr. Construction 7680
Rehab/Reconst./Upgrading of Bigaa-Plaridel via Bulacan and
Malolos
Road05/28/09 III 13.077 75 C 0.449 0.196 0.300 - - - 94.50
*94.50%V. Satisfactory
A.R Lustre Jr. Construction 7680
Construction of Multi-Purpose Building 03/07/09 IV-B 0.383 90 C
0.481 0.107 0.300 - - - 88.80
*88.80% Satisfactory
A.R Lustre Jr. Construction 7680
Repair/Rehab/Impvt. of Santiago-Syjuco E/S 09/17/09 NCR 0.482 45
C 0.482 0.000 0.300 - - - 78.20
*78.20% Unsatisfactory
A.R. Lustre Jr. Construction 7680
Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads
Pulilan
& Calumpit08/12/11 III 21.726 113 O 0.313 0.300 0.136 0.030
0.060 0.033 87.20 -
A.R. Lustre Jr. Construction 7680
Conc. of Tapul-Bahile Road, Km.39+903.50-Km.40+560 08/09/11 IVB
9.214 75 O 0.375 0.237 0.150 0.023 0.054 0.050 88.90 -
A.R. Lustre Jr. Construction 7680
Conc. of Puerto Princesa South Road Phase 2 08/11/11 IVB 7.481
95 C 0.410 0.133 0.300 - - - 84.30
87.06% Satisfactory
A.R. Lustre Jr. Construction 7680
Asphalt Overlay of Capitol-Canigaran Road, Km.1+950.6-Km.2+264
08/09/11 IVB 1.023 51 C 0.428 0.133 0.300 - - - 86.10
*86.10% Satisfactory
A.R. Lustre Jr. Construction 7680
Conc. of Puerto Princesa South Road 03/31/11 IVB 38.600 217 C
0.441 0.133 0.300 - - - 87.40
87.64% Satisfactory
A.R. Lustre Jr. Construction 7680
Const. of Puerto Princesa Airport Development Project (Building
and
Industrial Plant)05/25/11 DOTC 38.547 210 C 0.417 0.200 0.300 -
- - 91.70 91.70% V. Satisfactory
A.R. Lustre Jr. Construction 7680
Const. of Peurto Princesa Airport Development Project (Building
and
Industrial Plant)05/26/11 DOTC 102.128 300 C 0.438 0.200 0.300 -
- - 93.80 93.80% V. Satisfactory
A.R.L Construction 27645 Repair/Rehab. of School Building BSU
03/03/10 III 0.989 18 C 0.454 0.148 0.300 - - - 90.2090.20%
V. Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page17
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.R.L Construction 27645 Rehab/Impvt./Upgrading of
Pulilan-Calumpit Road (Pulilan Section) 05/28/09 III 9.542 60 C
0.376 0.200 0.300 - - - 87.60*87.60%
Satisfactory
A.R.L Construction 27645Const. of Flood Control
(Revetrment), Poblacion, San Sebastian, San Jose, Sta.
Monica,
09/04/09 III 6.697 80 C 0.400 0.133 0.300 - - - 83.30 *83.30%
Satisfactory
A.R.L Construction 27645 Upgrading/Conc. of Roads with Drainage
Improvement 03/04/09 NCR 0.476 45 C 0.364 0.200 0.300 - - -
86.40*86.40%
Satisfactory
A.R.L Construction 27645Rehab./Reconst./Upgrading of
Damaged Pavement along 7th Ave. East
05/31/10 NCR 6.445 90 C 0.409 0.200 0.300 - - - 90.90 90.90% V.
Satisfactory
A.R.L. Construction 27645 Repair/Rehab. of MPB at Sta. Elena E/S
08/13/11 III 1.317 40 C 0.500 0.143 0.300 - - - 94.30*94.30%
V. Satisfactory
A.S.M Francisco Dev't and Construction Corp. 19098 Proposed
Exterior Repainting Works 03/24/09 U.P. 1.368 120 C 0.400 0.200
0.300 - - - 90.00
90.00% V. Satisfactory
A.S.S Construction 31509 Completion of Alaremil Building II
03/2-3/10 DOST 9.607 250 C 0.496 0.200 0.300 - - - 99.60 97.64%
Outstanding
A.S.S. Construction 31509 Completion of ACA Building II
05/14-15/09 DOST 9.631 210 O 0.380 0.296 0.150 0.030 0.062 0.050
96.80 -
A.S.S. Construction 31509 Construction of Sports Complex
05/14-15/09 DOST 3.159 90 C 0.391 0.295 0.300 - - - 98.60 98.60%
Outstanding
A.S.S. Construction 31509 Partial Completion of vast set,
PCASTRD & PCIERD bldg. 07/08/09 DOST 7.479 135 C 0.483 0.200
0.300 - - - 98.30*98.30%
Outstanding
A.S.T. Builders 34104
Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd.,
Cebu-Balamban Transcentral Highway
(Km.0007+860-Km.0008+400)
08/24/11 VII 4.516 10 C 0.455 0.200 0.300 - - - 95.50 *95.50% V.
Satisfactory
A.S.V Construction Supply and Services 13490
Const. of FMR, Venegas St., Brgy. Layac-Sta.Isabel 05/26/10 III
0.473 60 C 0.444 0.133 0.300 - - - 87.70
87.70% Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page18
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
A.S.V. Construction Supply and Services 13490 Const./Impvt. of
MPB 08/04/11 III 2.794 104 O 0.392 0.233 0.150 0.022 0.038 0.050
88.50 -
A.S.V. Construction Supply and Services 13490
Concrete Reblocking of Jct. Layac-Balanga-Mariveles Port
Rd.,
Km.106+151-Km.107+00008/04/11 III 4.778 109 O 0.383 0.225 0.150
0.030 0.048 0.033 86.90 -
A.V. Bernal Construction & Trading Corp. 32999
Asphalt Overlay along Tagaytay-Manila via Silang Road 08/18/11
IVA 4.468 14 C 0.481 0.133 0.300 - - - 91.40
*91.40% V. Satisfactory
A.Y.U. Engineering and Construction 25632
Completion of MPB at Barangay Duterte 08/24/11 XI 1.473 120 C
0.448 0.133 0.300 - - - 88.10
*88.10% Satisfactory
A.Y.U. Engineering and Construction 25632
Conc. of Roads @ Brgy. Sto. Nio, Tugbok District 03/28/11 XI
2.825 210 C 0.368 0.200 0.300 - - - 86.80
*86.80% Satisfactory
AB Aponesto Construction, Parts &
Supply22998 Conc. of Lublub-Bolilac-Salad Road,
Km.277+707.50-Km.278+711 09/05/10 VI 14.425 192 O 0.356 0.240 0.150
0.030 0.042 0.033 85.10 -
Abesco Construction & Development Corp. 2934
Construction of Multi-Purpose Building @ Cupang Elem. School
05/21/09 III 3.273 88 C 0.484 0.133 0.300 - - - 91.70
90.23%V. Satisfactory
Abu Construction 22313 Const. of MPB, Brgy. Caloocan 08/20/11
XII 2.657 105 C 0.497 0.125 0.300 - - - 92.20 *92.20% V.
Satisfactory
Abu Construction 22313 Const. of MPB, Brgy. Panay 08/20/11 XII
2.695 105 C 0.499 0.124 0.300 - - - 92.30 87.61% Satisfactory
Abu Construction 22313 Rehab. of FTMR at Jct. Prv'l. Road Pob.
Tamnag Lutayan-Mamali 08/19/11 XII 1.825 62 C 0.340 0.200 0.300 - -
- 84.00*84.00%
Satisfactory
Abu Construction 22313 Rehab. of FTMR at Jct. Prv'l. Rd. at
Blingkong, Lutayan-Bayasong 08/19/11 XII 1.781 62 C 0.330 0.200
0.300 - - - 83.00*83.00%
Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page19
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Abu Construction 22313 Const. of Multi-Purpose Building 06/10/10
XII 1.926 126 C 0.494 0.133 0.300 - - - 92.70 92.70% V.
Satisfactory
Abu Construction 22313 Completion of MPB (Mini Gym) at Brgy. San
Rafael 06/08/10 XII 1.897 65 C 0.386 0.133 0.300 - - -
81.9081.90%
Unsatisfactory
Abu Construction 22313 Completion of MPB (Gym) at Brgy. Baras
06/08/10 XII 0.764 65 C 0.339 0.133 0.300 - - - 77.2077.20%
Unsatisfactory
Abulug Construction Company, Inc. 5593
Reblocking along Bangag-Allapacan-Magapit Road (BAMR),
KO686+400-
KO687+20009/08/09 II 7.999 150 C 0.406 0.200 0.300 - - - 90.60
*90.60% V. Satisfactory
Abulug Construction Company, Inc. 5593
Concrete Paving of Ballesteros Road (Washington & Luna St.,)
09/08/09 II 1.930 150 C 0.405 0.200 0.300 - - - 90.50
88.94% Satisfactory
Abulug Construction Company, Inc. 5593 Const. of Zitanga Brgy.
Roads 02/17/10 II 9.648 132 C 0.370 0.200 0.300 - - - 87.00
88.14% Satisfactory
Abulug Construction Company, Inc. 5593
Rehab. of Ballesteros Central School Building 02/17/10 II 0.192
60 C 0.437 0.133 0.300 - - - 87.00
87.00% Satisfactory
Abulug Construction Company, Inc. 5593 Construction of Deepwell
02/18/10 II 0.289 60 C 0.396 0.133 0.300 - - - 82.90
82.90% Satisfactory
Abulug Construction Company, Inc. 5593 Const. of Colony Road
11/13/08 II 2.894 120 O 0.329 0.240 0.100 0.030 0.033 0.100 83.20
-
Abulug Construction Company, Inc. 5593
Concreting of Jct. Claveria-Dibalio-Luzon Road 05/21/09 II 9.648
273 C 0.485 0.133 0.300 - - - 91.80
88.95% Satisfactory
Abulug Construction Company, Inc. 5593 Const. of Public Market
(Phase II) 02/23/09 II 1.446 269 C 0.476 0.133 0.300 - - -
90.90
87.40% Satisfactory
Abulug Construction Company, Inc. 5593 Lucban River Control
Project 02/29/09 II 3.858 347 C 0.417 0.133 0.300 - - - 85.00
83.35% Satisfactory
Abulug Developers & Builders Co., Inc. 2366 Conc. of Luna
Street at Centro West 05/24/10 II 0.964 120 C 0.434 0.200 0.300 - -
- 93.40
93.40% V. Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page20
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Abulug Developers & Builders Co., Inc. 2366
Emergency Restoration of Cadcadir Bridge #1 Approach KO
600+(-)595
Phase I05/24/10 II 0.995 90 C 0.419 0.200 0.300 - - - 91.90
91.90% V. Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Restoration of Scoured Approaches & Eroded Bank of Cadcadir
Bridge 2
KO 602+723 Phase II05/24/10 II 0.771 90 C 0.408 0.200 0.300 - -
- 90.80 90.80% V. Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Restoration of Scoured Approaches & Eroded Bank of Cadcadir
Bridge 1
Phase II, KO 600+ (-594)05/24/10 II 0.963 90 C 0.467 0.134 0.300
- - - 90.10 90.10% V. Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Reblocking along Manila North Road (Ballesteros-Abulug Section)
09/08/09 II 18.527 210 C 0.407 0.200 0.300 - - - 90.70
89.38% V. Satisfactory
Abulug Developers & Builders Co., Inc. 2366 Construction of
1-CL Bessang E/S 09/08/09 II 0.484 60 C 0.404 0.181 0.300 - - -
88.50
*88.50% Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Emergency/Rehab. of Slope Protection KO 590+640, MNR 02/17/10 II
1.495 90 C 0.417 0.200 0.300 - - - 91.70
91.70% V. Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Emergency/Rehab. of Slope Protection KO 590+340, MNR 02/17/10 II
0.995 90 C 0.467 0.133 0.300 - - - 90.00
90.00% V. Satisfactory
Abulug Developers & Builders Co., Inc. 2366 Concrete Paving
of Jones Street 02/12/10 II 0.868 90 C 0.384 0.200 0.300 - - -
88.40
88.40% Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Reblocking along Manila North Road (/Fugu Bdry. - Bangag Sect.)
02/17/10 II 19.299 234 C 0.394 0.200 0.300 - - - 89.40
88.08% Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Rehab./Regravelling of Curva to Capallepaan Farm-to-Market Road
02/18/10 II 0.675 60 C 0.353 0.200 0.300 - - - 85.30
85.30% Satisfactory
Abulug Developers & Builders Co., Inc. 2366
Road Opening of Pimpila Farm-to-Market Road 02/17/10 II 0.820 75
C 0.348 0.200 0.300 - - - 84.80
84.80% Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page21
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Abulug Developers & Builders Co., Inc. 2366
Reblocking along Manila North Road (Fugu Bdry.-Bangag Section)
05/21/09 II 19.299 210 O 0.368 0.240 0.150 0.030 0.051 0.033 87.20
-
Abulug Developers and Builders Co., Inc. 2366
Rehab./Upgrading of Manila North Road 08/03/11 II 40.496 402 C
0.403 0.137 0.300 - - - 84.00
86.46% Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Restoration of River Control Project along Goron &
Langgangan River 03/31/11 II 12.542 179 C 0.445 0.133 0.300 - - -
87.8092.90%
V. Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Conc. along Cadcadir-Kabugao Road 03/31/11 II 5.015 166 C
0.423 0.133 0.300 - - - 85.60 89.32% V. Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Const. of Namuac Bridge Protection Works 03/31/11 II 9.647
180 C 0.426 0.133 0.300 - - - 85.90*85.90%
Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Rehab. of Pamplona Bridge, Phase 3 03/30/11 II 14.473 210 C
0.417 0.133 0.300 - - - 85.00 *85.00% Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Const. of Lucban Flood Control Project, (Ph-3) 03/30/11 II
17.368 240 C 0.407 0.133 0.300 - - - 84.00*84.00%
Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Const. of Sto. Tomas Farm-to-Market Road 03/31/11 II 0.962
199 C 0.410 0.133 0.300 - - - 84.3084.00%
Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Restoration of Slope Protection KO591+320 - KO591+353, MNR
08/19/10 II 1.928 120 C 0.434 0.200 0.300 - - - 93.4093.40%
V. Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Const. of Slope Protection at KO673+000 - KO673+853 MNR
08/19/10 II 1.929 90 C 0.420 0.200 0.300 - - - 92.0092.00%
V. Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page22
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366Emergency Rehab. of Slope
Protection KO600+525 - KO602+200, MNR
08/19/10 II 4.195 90 C 0.347 0.200 0.300 - - - 84.70 87.58%
Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Conc. along Claveria Dibalio-Luzon-Cagayan Bdry. Road
08/19/10 II 2.938 153 C 0.374 0.200 0.300 - - - 87.4087.40%
Satisfactory
Abulug Developers and Builders Co., Inc.
(Formerly: F. Vargas Construction)
2366 Retrofitting of Pamplona Bridge, Manila North Road 02/24/09
II 10.290 180 C 0.386 0.200 0.300 - - - 88.6082.96%
Satisfactory
Aca Construction & Supply 10784
Construction of Multi-Purpose Building, Bancagan 02/26/09 I
0.096 30 C 0.417 0.133 0.300 - - - 85.00
*85.00%Satisfactory
Aca Construction & Supply 10784 Construction of Water Supply
02/26/09 I 0.096 30 C 0.338 0.188 0.300 - - - 82.60
*82.60%Satisfactory
Aca Construction & Supply 10784 Repair of Farm-to-Market
Road 02/26/09 I 0.480 30 C 0.343 0.200 0.300 - - - 84.30
*84.30%Satisfactory
Acer Industrial/Solid Rock Construction Joint
Venture
SLI-SN-005433/JV-
08-217
Rehabilitation of Libingan ng mga Bayani Road-MRT Road 05/27/09
NCR 4.694 75 C 0.396 0.133 0.300 - - - 82.90
*82.90% Satisfactory
ACJ Construction Resources 10635
Road Upgrading of Nat'l Rd. (Gravel to Concrete) Nat'l Secondary
Rd., Km.1628+584-Km.1630+803 along Kidapawan-Magpet-Pangao-an
Rd.
08/17/11 XII 24.178 180 O 0.342 0.300 0.000 0.030 0.045 0.033
75.00 -
ACJ Construction Resources 10635
Road Upgrading of Nat'l Rd. (Gravel to Concrete) Nat'l Secondary
Rd.,
Km.1629+(-124) - Km.1630+133 along
Magpet-Nowa-Doroluman-Greenfield
Rd.
08/17/11 XII 22.850 200 O 0.350 0.278 0.000 0.030 0.040 0.033
73.10 -
ACJ Construction Resources 10635
Conc. of Magpet Binay-Noa-basak-Arakan Road (Noa-Bagumbayan
Sect.)04/02/11 XII 18.363 224 C 0.410 0.140 0.300 - - - 85.00
*85.00% Satisfactory
ACJ Construction Resources 10635
Conc. Of Paco-Roxas-Arakan Valley Road, Luhong Section along
Paco-
Roxas-Arakan Valley Road04/02/11 XII 18.453 200 C 0.391 0.145
0.300 - - - 83.60 *83.60% Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page23
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
ACJ Construction Resources 10635
Conc. of Paco-Roxas-Arakan Road Kiyaab-Antipas Section (Km.
1648+300-Km.1649+385.63)
09/05/09 XII 16.826 150 O 0.324 0.300 0.150 0.015 0.042 0.050
88.10 -
ACJ Construction Resources 10635
Conc. of Poblacion-Magpet-Nowa Road, Nowa-Basak Section w/
exception09/05/09 XII 18.798 200 C 0.358 0.200 0.300 - - - 85.80
84.30% Satisfactory
ACJ Construction Resources 10635
Asphalt Overlay along Davao-Cotabato Rd., Saguing Section
03/01/10 XII 6.765 68 C 0.429 0.200 0.300 - - - 92.90
92.90% V. Satisfactory
ACJ Construction Resources 10635
Const. of Kinamalig Bridge including Concrete Paving of Approach
along
Paco-Roxas-Arakan03/02/10 XII 12.815 202 C 0.384 0.142 0.300 - -
- 82.60 86.08% Satisfactory
ACJ Construction Resources 10635
Conc. of Paco-Roxas-Arakan Road, Kiyab-Antipas Section, Km.
1648+300-Km. 1649+385.63
03/02/10 XII 16.826 175 C 0.379 0.143 0.300 - - - 82.20 85.71%
Satisfactory
ACJ Construction Resources 10635
Conc. of Paco-Roxas-Arakan Road, inclined Gap Ipuan Section, Km.
1640+374.10 - Km. 1646+794.28
03/02/10 XII 13.144 189 C 0.394 0.145 0.300 - - - 83.90 83.90%
Satisfactory
ACJ Construction Resources 10635
Rehab./Reconst. of Damaged Paved along Makilala-Allah Junction
Road,
La Esperanza Section06/05/10 XII 9.961 55 C 0.436 0.133 0.300 -
- - 86.90 86.90% Satisfactory
ACJ Construction Resources 10635
Rehab./Reconst. of Damage Paved along
Matalam-M'lang-Bagontapay
Road06/05/10 XII 14.307 60 C 0.424 0.133 0.300 - - - 85.70
85.70% Satisfactory
ACJ Construction Resources 10635
Road Upgrading of Matalam-Mlang-Bagontapay Road, Additional
Lane
(Poblacion Section)08/27/10 XII 18.338 153 C 0.476 0.127 0.300 -
- - 90.30 90.30% V. Satisfactory
ACJ Construction Resources 10635
Concreting of Paco-Roxas-Arakan Road (Luhong-Kiyaab Section)
05/30/09 R-XII 18.566 205 C 0.338 0.200 0.300 - - - 83.80
88.42% Satisifactory
ACJ Construction Resources 10635
Concreting of Poblacion Magpet-Nowa Road (Nowa Basak Sect.)
03/10/09 XII 18.798 180 O 0.356 0.284 0.150 0.030 0.035 0.050 90.50
-
Acme Builders Corp./MWJ Construction
JV JV-08-243
Conc. of Burauen-Albuena Road Km. 98+986.50-Km. 986+857.50
w/
exceptions02/22/10 VIII 46.887 240 C 0.411 0.200 0.300 - - -
91.10 91.10% V. Satisactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page24
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Acme Builders Corporation 6442
Const. Of Nijaga Bridge along Calbayog Diversion Road (Phase II)
08/17/11 VIII 37.279 300 O 0.383 0.182 0.150 0.030 0.055 0.033
83.30 -
Acme Builders Corporation 6442
Repair/Rehab. of Mainit Bridge along Palo-Carigara-Ormoc Road
08/24/11 VIII 14.198 120 C 0.481 0.174 0.300 - - - 95.50
*95.50% V. Satisfactory
Acme Builders Corporation 6442
Const./Completion/Continuation/On-going of Nijaga Bridge
along
Calbayog Diversion Road, Brgy. Nijaga
04/02/11 VIII 27.000 180 C 0.474 0.133 0.300 - - - 90.70 *90.70%
V. Satisfactory
Acme Builders Corporation 6442
Const. of Palo-East-By-Pass Road (including Bridge) 03/28/11
VIII 28.783 125 C 0.447 0.133 0.300 - - - 88.00
88.48% Satisfactory
Acme Builders Corporation 6442
Const. of Nijaga Bridge Along Calbayog Diversion Road (Phase II)
04/02/11 VIII 37.279 300 O 0.400 0.240 0.150 0.020 0.040 0.033
88.30 -
Acme Builders Corporation 6442
Rehab./Reconst./Upgrading of Daang Maharlika, Palo-Tolosa Road
Sect.,
Km.915+500 - Km.921+70004/06/11 VIII 24.050 200 C 0.423 0.133
0.300 - - - 85.60 87.04% Satisfactory
Acme Builders Corporation 6442 Const. of Palo East By-Pass Road
03/11/10 VIII 19.260 240 C 0.436 0.200 0.300 - - - 93.60
89.76% V. Satisfactory
Acme Builders Corporation 6442
Rehab./Reconst./Impvt./Upgrading of Damaged Pavement,
Tacloban
Baybay South Rd.06/17/10 VIII 34.600 150 O 0.366 0.300 0.150
0.030 0.032 0.033 91.10 -
Acme Builders Corporation 6442
Rehab./Reconst./Impvt./Upgrading of Damaged Pavement,
Tacloban
Baybay South Road09/08/10 VIII 33.358 150 C 0.398 0.133 0.300 -
- - 83.10 87.90% Satisfactory
Acme Builders Corporation 6442 Construction of Sinugbuhan Bridge
06/04/09 VI 33.384 676 C 0.441 0.133 0.300 - - - 87.40
85.20% Satisfactory
Acme Builders Corporation 6442
Asphalt Overlay along Tigbao-Pulak-Sta. Fe Road, Km
925+370-Km
926+37903/18/09 VIII 11.310 90 C 0.393 0.133 0.300 - - - 82.60
*82.60%Satisfactory
Acme Builders Corporation 6442 Construction of Bagacay Bridge
03/02/09 VIII 39.122 332 O 0.319 0.288 0.000 0.030 0.023 0.050
71.00 -
Acme Builders Corporation 6442 Rehabilitation of Mahayahay Creek
03/03/09 VIII 6.709 170 C 0.375 0.133 0.300 - - - 80.80
84.10%Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page25
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Acme Builders Corporation / B. Vicencio
ConstructionJV-07-066 Const. of Palo East By Pass Road (Const.
of Bernard Reed II Bridge) 08/31/09 VIII 57.823 616 O 0.384 0.240
0.150 0.030 0.047 0.033 88.40 -
Acme Builders Corporation / MWJ Construction (JV)
JV-08-243 Const. of Albuera-Burauen Road including Bridges,
Burauen Sect. 09/02/09 VIII 47.235 240 O 0.352 0.245 0.150 0.030
0.045 0.050 87.20 -
ACV Construction & Surveying 10903
Concreting of FMR @ Various Brgys., Urbiztondo and Mangatarem
03/09/09 I 3.838 60 C 0.353 0.200 0.300 - - - 85.30
*85.30%Satisfactory
ADB Dynamic Builders & Supply 33359
Repair/Rehab. of St., Brgy. Dalupirit; Rehab. of San Roque St.,
Brgy.
Vinisitahan; Rehab./Repair of St., Brgy. Pilar
03/07/09 VIII 1.437 60 C 0.463 0.200 0.300 - - - 96.30 *96.30%
Outstanding
Adelfa & Charlie Enterprises 11569
Construction of MPP Brgy. Hibulangan 03/11/09 VIII 0.142 30 C
0.433 0.133 0.300 - - - 86.60
*86.60%Satisfactory
Adfil Corporation 14437Rehab. of Magaboy and Lucena Bridge
Approaches-Slope/Bank
Protection06/13/10 XIII 4.709 105 C 0.450 0.200 0.300 - - -
95.00 95.00% V. Satisfactory
Adfil Corporation 14437 Rehab. of River Dike 06/01/10 XIII 9.649
150 C 0.408 0.179 0.300 - - - 88.70 88.46% Satisfactory
Adfil Corporation 14437Repair/Maintenance with Asphalt
Overlay of Tabon-Tabon Slip along Agusan- Davao Road
06/17/10 XIII 32.364 225 O 0.371 0.240 0.150 0.030 0.055 0.033
87.90 -
Adfil Corporation 14437 Rehab. of Magsaysay Bridge along Iligan
City 09/09/10 XIII 48.161 300 O 0.352 0.300 0.150 0.030 0.055 0.050
93.70 -
Adfil Corporation 14437 Completion/Continuation of Libertad
Bridge & Approaches 09/08/10 XIII 11.224 180 C 0.462 0.189
0.300 - - - 95.1092.58%
V. Satisfactory
Adfil Corporation 14437Rehab./Along Reconst. of Daang
Maharlika (Agusan-Surigao Road) Ampayon-Taguibo Sect.
09/09/10 XIII 35.253 270 C 0.400 0.200 0.300 - - - 90.00 90.54%
V. Satisfactory
Adfil Corporation 14437Repair/Maintenance with Asphalt
Overlay of Tabon-Tabon Slip along Agusan-Davao Road
09/06/10 XIII 32.398 225 C 0.440 0.133 0.300 - - - 87.30 87.66%
Satisfactory
Adfil Corporation 14437Rehab./Reconst. of Damaged Paved National
Roads Gingoog-Calveria-
Villanueva Road09/10/09 X 96.400 405 O 0.259 0.300 0.150 0.030
0.061 0.050 85.00 -
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page26
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Adfil Corporation 14437 Rehab./Reconst. of NRJ Bahbah-Talacogon
Road 06/09/09 XIII 19.263 220 C 0.485 0.200 0.300 - - -
98.50*98.50%
Outstanding
Adfil Corporation 14437
Repair/Rehab./Impvt. of Roads & Bridges along the National
Highway Epoxy Sealing of Cracks in concrete girder, deck slab &
conc. Pavement
(injectable epoxy) along Bahbah, Talacogon Road
06/09/09 XIII 9.429 180 C 0.464 0.200 0.300 - - - 96.40 *96.40%
Outstanding
Adfil Corporation 14437 Rehabilitation/Concreting of
Tagcatong-Vinapor Road 05/25/09 XIII 9.629 210 C 0.489 0.133 0.300
- - - 92.20*92.20%
V. Satisfactory
Adfil Corporation 14437 Conc. of Dapa-Junction Cancohoy Road
03/07/09 XIII 28.451 241 C 0.414 0.200 0.300 - - - 91.4088.94%
Satisfactory
Adfil Corporation 14437Rehab./Reconst. of Damaged Paved
National Road along Agusan-Misamis Road
03/02/09 XIII 9.634 180 C 0.405 0.200 0.300 - - - 90.50 86.36%
Satisfactory
Adfil Corporation 14437Rehab./Reconst. of Damaged Paved
National Road along Agusan-Surigao Road
03/03/09 XIII 9.635 180 C 0.408 0.200 0.300 - - - 90.80 87.50%
Satisfactory
Adfil Corporation 14437Repair/Reconst. of Butuan City-
Cagayan de Oro-Iligan Road (Agusan-Misamis Oriental Road) inc.
Bridge
03/18/09 XIII 19.198 210 C 0.402 0.200 0.300 - - - 90.20 89.06%
V.Satisfactory
Adfil Corporation 14437 Repair/Rehab. of NRJ Bahbah-Talacogon
Road 03/20/09 XIII 9.633 188 C 0.431 0.200 0.300 - - -
93.1087.04%
Satisfactory
Adfil Corporation 14437
Rehab./Reconst. of Damaged Paved National Rd. along Butuan
City-CDO-Iligan Rd.,(Agusan-Misamis Oriental
Sect.)Libertad-Bancasi Sect.
09/16/09 XIII 54.954 285 O 0.371 0.300 0.150 0.030 0.055 0.050
95.60 -
Adfil Corporation 14437Const./Completion/Continuation of
Unfinished Bridge and Approaches,
Brgy. Libertad09/16/09 XIII 23.830 195 O 0.364 0.300 0.150 0.030
0.055 0.050 94.90 -
Adfil Corporation 14437 Rehab. of NRJ-Bahbah-Talacogon Rd.
09/13/09 XIII 14.427 210 C 0.416 0.194 0.300 - - - 91.0094.66%
V.Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page27
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Adfil Corporation 14437 Concreting of NRJ-Bahbah-Talacogon Rd.
09/13/09 XIII 15.872 225 O 0.371 0.244 0.150 0.030 0.065 0.050
91.00 -
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of Butuan City-Pianing/Tandag Road 08/24/11 XIII
14.808 180 O 0.341 0.300 0.150 0.030 0.048 0.050 91.90 -
Adfil Corporation (Formerly: Adfil Construction)
14437
Widening/Conc. of Additional Lane Both Directions along Butuan
City-
Cagayan de Oro-Iligan Road, Ampayon-Baan Section
08/24/11 XIII 26.233 240 O 0.338 0.300 0.150 0.030 0.048 0.050
91.60 -
Adfil Corporation (Formerly: Adfil Construction)
14437Reconst. of Slip Sect. along Daang
Maharlika (Agusan-Davao Road) Lapinigan Sect.
08/22/11 XIII 17.326 220 O 0.378 0.263 0.150 0.030 0.043 0.050
91.40 -
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of Butuan City-Pianing/Tandag Road 08/24/11 XIII
9.021 105 C 0.474 0.133 0.300 - - - 90.7091.24%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Const. of Hawaiian-Salug-Sinakungan Road 08/26/11 XIII
86.118 334 C 0.430 0.181 0.300 - - - 91.10*91.10%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Rehab. of Wawa Bridge along Agusan-Davao Road 08/26/11
XIII 110.847 469 C 0.469 0.133 0.300 - - - 90.2090.68%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437Repair of Taguibo Bridge and
Approaches along Daang Maharlika (Surigao-Agusan Road)
08/23/11 XIII 8.671 90 C 0.459 0.143 0.300 - - - 90.20 *90.20%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437Completion of Bislig Bridge along
Surigao-Davao Coastal Road (Demolition of Old Bridge-Phase
I)
08/17/11 XIII 13.043 285 O 0.334 - 0.200 0.050 0.062 0.250 89.60
-
Adfil Corporation (Formerly: Adfil Construction)
14437Conc. of NRJ Cuevas-Bislig Road,
Phase II, Sta. 1375+369-Sta. 1380+840
08/22/11 XIII 26.309 245 O 0.349 0.271 0.150 0.030 0.043 0.050
89.30 -
Adfil Corporation (Formerly: Adfil Construction)
14437 Overlay of Daang Maharlika (Surigao-Agusan Sect.) 08/09/11
XIII 11.604 75 C 0.438 0.133 0.300 - - - 87.10*87.10%
Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page28
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Adfil Corporation (Formerly: Adfil Construction)
14437 Reconst. of Maglambing Bridge and Approaches 08/17/11 XIII
65.519 521 O 0.376 0.288 0.104 0.030 0.032 0.017 84.70 -
Adfil Corporation (Formerly: Adfil Construction)
14437 Const. of Tubay-Lake Mainit Circ. Road, Tubay-Jabonga
08/09/11 XIII 96.417 438 C 0.445 0.026 0.300 - - - 77.1082.56%
Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437Rehab. of Taguibo Steel Bridge
along Daang Maharlika (Surigao-Agusan Road), Brgy. Taguibo
04/11/11 XIII 9.601 180 C 0.500 0.133 0.300 - - - 93.30 *93.30%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of Pulang Lupa-Sta. Josefa Road 04/01/11 XIII 19.249
195 C 0.439 0.200 0.300 - - - 93.9092.91%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437Rehab. of Magsaysay Bridge along Iligan City-Cagayan de
Oro-Butuan
City Road04/13/11 XIII 48.161 300 C 0.476 0.134 0.300 - - -
91.00 92.62% V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc./Repair of Slip along NRJ-Cuevas-Sampaguita Rd.
04/01/11 XIII 47.951 470 C 0.478 0.133 0.300 - - - 91.1091.19%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437Rehab./Reconst. of Butuan-Cagayan
de Oro-Iligan Road inc. Bridges (Agusan-Mis. Or. Road)
04/12/11 XIII 8.595 105 C 0.474 0.133 0.300 - - - 90.70 *90.70%
V. Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Reconst. of Maglambing Bridge and Approaches 04/02/11 XIII
96.519 521 O 0.343 0.300 0.150 0.030 0.048 0.033 90.40 -
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of NRJ Cuevas-Bislig Road, Phase II 04/01/11 XIII
26.309 245 O 0.377 0.247 0.150 0.030 0.048 0.050 90.20 -
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of Butuan City-Pianing-Tandag Road 04/13/11 XIII
18.905 270 C 0.347 0.200 0.300 - - - 84.7088.96%
Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of NRJ Cuevas-Sampaguita Road 04/01/11 XIII 60.039
270 C 0.367 0.200 0.300 - - - 86.7088.14%
Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437Rehab. of Butuan City-Cagayan de Oro-Iligan Road
(Agusan-Misamis
Oriental Road)04/11/11 XIII 105.122 210 C 0.322 0.200 0.300 - -
- 82.20 86.70% Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page29
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Adfil Corporation (Formerly: Adfil Construction)
14437 Const. of River Dike Protection, Brgy. Agao 03/10/10 XIII
9.556 90 C 0.485 0.133 0.300 - - - 91.8091.80%
V.Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437Impv't./Rehab. of Iligan-Cagayan-
Butuan Rd. (Agusan-Misamis Oriental Section)
02/23/10 XIII 67.446 180 C 0.480 0.133 0.300 - - - 91.30 91.30%
V.Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Const./Conc. of NRJ San Francisco-Bahi Rd. 03/07/10 XIII
28.892 330 C 0.431 0.133 0.300 - - - 86.4091.20%
V.Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Upgrading/Conc. of NRJ Cuevas-Bislig Rd. 03/07/10 XIII
28.874 315 C 0.485 0.133 0.300 - - - 91.8090.66%
V.Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Conc. of Dapa-Del Carmen (Sayak-Airport Rd.) 02/26/10 XIII
75.947 390 C 0.456 0.133 0.300 - - - 88.9088.90%
Satisfactory
Adfil Corporation (Formerly: Adfil Construction)
14437 Rehab./Reconst. of Damaged Rd. Gingoog-Claveria-Villanueva
Rd. 03/10/10 X 96.400 405 C 0.437 0.200 0.300 - - - 93.7089.71%
V.Satisfactory
Adfil Corporation/RID Corporation (JV) JV-06-022
Repair/Rehab. of Patin-ay Bridge along Agusan-Davao Road,
Patin-ay 06/08/09 XIII 23.749 658 C 0.458 0.200 0.300 - - -
95.80
91.84% V. Satisfactory
Adige Sta. Clara (JV) JV-06-032DPWH Component Project under
the
Help for Catubig Agricultural Advancement Proj.
05/30/09 VIII 519.663 1,073 O 0.378 0.300 0.150 0.030 0.050
0.050 95.80 -
Adige Sta. Clara (JV) JV-06-032DPWH Component Project under
the
HELP for Catubig Agricultural Project (HCAAP)
08/25/08 VIII 448.581 734 O 0.377 0.300 0.070 0.030 0.050 0.067
89.40 -
Adimre Construction 25534 Marilao Port Development Project
08/20/09 DOTC 2.862 60 C 0.451 0.200 0.300 - - - 95.10 *95.10% V.
Satisfactory
Adimre Construction 25534 Sta. Cruz Port Development Project
08/20/09 DOTC 0.960 30 C 0.460 0.200 0.300 - - - 96.00 96.00% V.
Satisfactory
Adimre Construction 25534 Sasmuan Port Development Project
08/20/09 DOTC 2.871 60 C 0.459 0.200 0.300 - - - 95.90 95.90% V.
Satisfactory
Adimre Construction 25534 Hagonoy Port Development Project
10/02/09 DOTC 0.949 30 C 0.460 0.200 0.300 - - - 96.00 96.00%
Outstanding
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page30
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
Adimre Construction 25534 Baguio Airport Development Project
04/04/09 DOTC 861.940 60 C 0.435 0.181 0.300 - - - 91.60 91.60% V.
Satisfactory
Adimre Construction 25534
Dumaguete Airport Dev't Project (Completion of Imprv't of
Terminal Building and Purchase/ Installation
of Bagage Conveyor)
01/21/10 DOTC 13.500 90 C 0.402 0.199 0.300 - - - 90.10 90.10%
V.Satisfactory
Adimre Construction 25534Tuguegarao Airport Dev't Project
(Continuation of Widening of Runway)
03/04/10 DOTC 9.588 90 C 0.452 0.200 0.300 - - - 95.20 95.20%
V.Satisfactory
Adimre Construction 25534
Tuguegarao Airport Dev't Project (Continuation of Widening
of
Runway and Improvement of Fire Station Building)
03/04/10 DOTC 12.490 90 C 0.458 0.200 0.300 - - - 95.80 95.80%
V.Satisfactory
Adimre Construction 25534
Laoag Airport Development Project (Upgrading of Radar Area,
Continuation of Perimeter Fence Construction of Drainage
System)
04/09/10 DOTC 9.604 120 C - 0.419 0.200 0.300 - - 91.90 91.90%
V. Satisfactory
Adimre Construction 25534Laoag Airport Development Project
(Improvement of Fire Station Building)
04/09/10 DOTC 4.821 120 C 0.464 0.200 0.300 - - - 96.40 96.40%
Outstanding
Adimre Construction 25534Laoag Airport Development Project
(Shoulder Grade Correction including Drainage System)
04/09/10 DOTC 4.793 75 C 0.410 0.200 0.300 - - - 91.00 91.00% V.
Satisfactory
Adimre Construction 25534Tuguegarao Airport Development Project
(Repair/Rehabilitation of
Terminal Building)09/10/10 DOTC 1.927 90 C 0.449 0.200 0.300 - -
- 94.90 94.90% V. Satisfactory
Adimre Construction 25534 Canalate Port Development Project
(Improvement of Port) 12/03/10 DOTC 1.919 60 C 0.458 0.200 0.300 -
- - 95.8095.80%
V. Satisfactory
Adimre Construction 25534Const. of Standard One Classroom
School Building (Modified) at GITMES
09/05/09 III 0.526 24 C 0.442 0.133 0.300 - - - 87.50 *87.50%
Satisfactory
Adimre Construction 25534
Camiguin Ports Cluster Project (Construction of Seawall
Enclosure
at Benoni Port and Repair of Causeway at Catarman Port)
02/17/11 DOTC 6.231 60 C 0.419 0.200 0.300 - - - 91.90 91.90% V.
Satisfactory
* 1st/Final* For DPWH, only the region and PMO office are listed
15th CPES Release Page31
-
CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES
Reports-On-going and Completed Projects from July 01, 2010 to June
30, 2012
ESH RDRSTATUSCPES VISIT
RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION
FINAL RATING/ QUALITATIVE DESCRIPTION
AMOUNT (Php, M) DUR (C.D.)
CONTRACT*IMPL.
AGENCYNAME OF
CONSTRUCTORLICENSE
NO.
ADP Const. & Supply 3466 Impvt./Conc. of Access Road,
Tubalan Port, Tubalan 04/01/11 XI 58.261 320 C 0.135 0.200 0.000 -
- - 33.5061.25% Poor
Adriot Construction 11169 Const. of Bridge, Brgy. Conversion
08/11/11 III 1.137 45 C 0.467 0.200 0.300 - - - 96.70 *96.70%
Outstanding
Adroit Construction 11169 Const. of 2-CL, Sta. Barbara E/S
04/08/11 III 1.324 60 C 0.45 0.048 0.300 - - - 79.80 *79.80%
Unsatisfactory
Adroit Construction 11169 Completion of Bridge, General Luna 2nd
Phase 03/02/09 III 3.026 30 C 0.332 0.200 0.300 - - -
83.20*83.20%
Satisfactory
Adroit Construction 11169 Concreting of Brgy. Maligaya Road
03/02/09 III 1.867 25 C 0.404 0.133 0.300 - - - 83.70
*83.70%Satisfactory
Advance Foundation Const. System Corp. /
Abulug Developer Builders Const. Inc. (JV)
JV-09-289 Const. of Gov. Edgar R. Lara Bridge along
Cagayan-Apayao Road 03/30/11 II 112.029 240 O 0.360 0.300 0.000
0.023 0.051 0.017 75.10 -
Advanced Foundation - IBC (JV) JV-09-265
Replacement of E. Marcos Bridge, Km.28+310 along
Maasin-Cabatuan
Roa