CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012 11-18-70 Construction 32944 Road Concreting at Brgy. Sallacapo 02/28/09 I 0.855 18 C 0.375 0.200 0.300 - - - 87.50 *87.50% Satisfactory 121 Construction Corporation (Formerly: 121 Construction) 21686 Const. of Two (2) Storey MPB at Brgy. Malamig 08/10/11 NCR 1.868 60 C 0.483 0.200 0.300 - - - 98.30 *98.30% Outstanding 121 Construction Corporation (Formerly: 121 Construction) 21686 Const. of 2-Storey, 2-Classroom Sch. Bldg. at Heritage ES, Loma de Gato 04/15/11 III 2.472 120 C 0.419 0.200 0.300 - - - 91.90 89.10% V. Satisfactory 121 Construction Corporation (Formerly: 121 Construction) 21686 Const. of MPB, Brgy. Mabini J. Rizal 06/02/10 NCR 9.315 180 C 0.475 0.200 0.300 - - - 97.50 91.97% V. Satisfactory 2H2L Construction 16293 Impv't. of Drainage & Stairpathwalk, Brgy. Sta. Cruz 08/04/11 IVA 0.947 60 C 0.493 0.133 0.300 - - - 92.60 *92.60% V. Satisfactory 2H2L Construction 16293 Const. of 2-Storey Sch. Bldg., Famy E/S 08/11/11 IVA 3.856 60 C 0.453 0.138 0.300 - - - 89.10 *89.10% V. Satisfactory 2H2L Construction 16293 Rehab. of 8th and 9th Streets, San Martin Subd., Brgy. San Isidro 08/04/11 IVA 1.789 90 C 0.440 0.133 0.300 - - - 87.30 *87.30% Satisfactory 2H2L Construction 16293 Const. of Two (2) Storey, Six (6) Classrooms Cainta E/S 04/15/11 IVA 7.848 150 C 0.389 0.200 0.300 - - - 88.90 85.75% Satisfactory 2H2L Construction 16293 Impvt. of Flood Control at So. Upper East Kamias & So. East Kamias 03/12/09 IVA 2.692 120 C 0.461 0.138 0.300 - - - 89.90 *89.90% V. Satisfactory 2H2L Construction 16293 Impvt. of Multi-Purpose Pavement at Brgy. Dela Paz & Brgy. San Isidro 03/12/09 IVA 3.748 150 C 0.479 0.133 0.300 - - - 91.20 *91.20% V. Satisfactory ESH RDR STATUS CPES VISIT RATING WMS MTL TIME FAC PROJECT DATE OF EVALUATION FINAL RATING/ QUALITATIVE DESCRIPTION AMOUNT (Php, M) DUR (C.D.) CONTRACT *IMPL. AGENCY NAME OF CONSTRUCTOR LICENSE NO. * 1st/Final * For DPWH, only the region and PMO office are listed 15th CPES Release Page1
728

CIAP-PDCB CONSTRUCTORS PERFORMANCE ... Report 15th...CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORT CPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

May 05, 2018

Download

Documents

dangthuy
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    11-18-70 Construction 32944 Road Concreting at Brgy. Sallacapo 02/28/09 I 0.855 18 C 0.375 0.200 0.300 - - - 87.50 *87.50%Satisfactory

    121 Construction Corporation (Formerly:

    121 Construction)21686 Const. of Two (2) Storey MPB at Brgy. Malamig 08/10/11 NCR 1.868 60 C 0.483 0.200 0.300 - - - 98.30

    *98.30% Outstanding

    121 Construction Corporation (Formerly:

    121 Construction)21686 Const. of 2-Storey, 2-Classroom Sch. Bldg. at Heritage ES, Loma de Gato 04/15/11 III 2.472 120 C 0.419 0.200 0.300 - - - 91.90

    89.10% V. Satisfactory

    121 Construction Corporation (Formerly:

    121 Construction)21686 Const. of MPB, Brgy. Mabini J. Rizal 06/02/10 NCR 9.315 180 C 0.475 0.200 0.300 - - - 97.50 91.97% V. Satisfactory

    2H2L Construction 16293 Impv't. of Drainage & Stairpathwalk, Brgy. Sta. Cruz 08/04/11 IVA 0.947 60 C 0.493 0.133 0.300 - - - 92.60*92.60%

    V. Satisfactory

    2H2L Construction 16293 Const. of 2-Storey Sch. Bldg., Famy E/S 08/11/11 IVA 3.856 60 C 0.453 0.138 0.300 - - - 89.10*89.10%

    V. Satisfactory

    2H2L Construction 16293 Rehab. of 8th and 9th Streets, San Martin Subd., Brgy. San Isidro 08/04/11 IVA 1.789 90 C 0.440 0.133 0.300 - - - 87.30*87.30%

    Satisfactory

    2H2L Construction 16293 Const. of Two (2) Storey, Six (6) Classrooms Cainta E/S 04/15/11 IVA 7.848 150 C 0.389 0.200 0.300 - - - 88.9085.75%

    Satisfactory

    2H2L Construction 16293 Impvt. of Flood Control at So. Upper East Kamias & So. East Kamias 03/12/09 IVA 2.692 120 C 0.461 0.138 0.300 - - - 89.90*89.90%

    V. Satisfactory

    2H2L Construction 16293 Impvt. of Multi-Purpose Pavement at Brgy. Dela Paz & Brgy. San Isidro 03/12/09 IVA 3.748 150 C 0.479 0.133 0.300 - - - 91.20*91.20%

    V. Satisfactory

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page1

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    2H2L Construction 16293Rehab./Reconst./Upgrading of

    Marikina-Victoria Valley-Antipolo Road

    08/26/09 IVA 19.222 180 C 0.475 0.200 0.300 - - - 97.50 91.86% V. Satisfactory

    2H2L Construction 16293Rehab./Reconst./Upgrading of

    Marikina-Victoria Valley-Antipolo Road

    05/18/09 IV-A 19.221 180 O 0.387 0.239 0.150 0.030 0.025 0.050 88.10 -

    2-R Construction & Supply 15304

    Const. of Additional Classroom @ Comprehensive Nat'l. H/S 05/21/09 I 2.417 120 C 0.496 0.072 0.300 - - - 86.80

    *86.80% Satisfactory

    3FS Construction 30464 Upgrading of Gov't. Center Road Network, Km.000+650-Km.000+843 08/25/11 VIII 3.690 110 O 0.390 0.240 0.150 0.030 0.030 0.033 87.30 -

    3FS Construction 30464Road Upgrading (Gravel to Paved) of

    Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara Road

    04/06/11 VIII 19.108 180 C 0.459 0.176 0.300 - - - 93.50 90.62% V. Satisfactory

    3FS Construction 30464 Const. of Coastal Road 04/08/11 VIII 18.895 150 C 0.421 0.133 0.300 - - - 85.40 *85.40% Satisfactory

    3FS Construction 30464 Upgrading of Bagahupi-Babatngon-Sta. Cruz, Barugo-Carigara Rd. 03/11/10 VIII 19.289 230 C 0.497 0.189 0.300 - - - 98.6091.07%

    V. Satisfactory

    3FS Construction 30464 Const. of Grouted Riprap @ Brgy. 90 03/18/09 VIII 0.962 70 C 0.381 0.200 0.300 - - - 88.10 *88.10% Satisfactory

    3K Builders 27277 Const. of MPB, Natividad NHS (formerly: Narciso Ramos NHS) 08/12/11 I 1.918 100 C 0.460 0.133 0.300 - - - 89.30*89.30%

    V. Satisfactory

    3K Builders 27277Repair/Rehab. of MNR, Km.174+000 -

    Km.175+000 w/ exception Villasis Section

    06/10/10 I 9.996 32 C 0.455 0.133 0.300 - - - 88.80 88.80% Satisfactory

    3K Rock Engineering 27908 Const. of Sch. Bldg. @ Diego Silang E/S 08/15/011 II 0.748 45 C 0.464 0.120 0.300 - - - 88.40*88.40%

    Satisfactory

    3K Rock Engineering 27908 Const. of One Unit Classroom School Building, San Antonio I/S 04/08/11 II 0.641 45 C 0.485 0.133 0.300 - - - 91.80*91.80%

    V. Satisfactory

    3K Rock Engineering 27908 Construction of Multi-Purpose Building, Magsaysay 09/03/09 II 0.572 45 C 0.407 0.200 0.300 - - - 90.70*90.70%

    V. Satisfactory

    3K Rock Engineering 27908 Const./Repair of Multi-Purpose Building 02/25/10 II 1.735 60 C 0.413 0.133 0.300 - - - 84.6084.60%

    Satisfactory

    3K Rock Engineering 27908 Const./Completion of MPB, Liwayway 06/05/10 II 1.445 60 C 0.441 0.133 0.300 - - - 87.4087.40%

    Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page2

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    3K Rock Engineering 27908 Completion of Multi-Purpose Building, Gundaway 03/06/09 II 1.783 60 C 0.458 0.200 0.300 - - - 95.80*95.80%

    V.Satisfactory

    3-L Construction 16745 Const. of 2 Storey Multi-Purpose Bldg. (Brgy. Hall), Brgy. San Gabriel 03/09/09 V 0.955 120 C 0.436 0.175 0.300 - - - 91.10*91.10%

    V. Satisfactory

    3-L Construction 16745 Road Upgrading (Gravel to Paved), Sipocot-Cabusao Road 09/09/09 V 6.555 150 C 0.418 0.200 0.300 - - - 91.8089.64%

    V. Satisfactory

    3RB Construction & Supply 19541

    Rehab./Reconst./Upgrading of Calamba-Sta. Cruz-Famy Road 08/09/11 IVA 8.125 75 C 0.393 0.133 0.300 - - - 82.60

    *82.60% Satisfactory

    3RB Construction & Supply 19541

    Road Upgrading of San Fernando North Road (San Jacinto Sect.) 08/11/11 V 19.100 165 C 0.391 0.133 0.300 - - - 82.40

    83.72% Satisfactory

    3RB Construction & Supply 19541 Const. of Sto. Cristo Seawall 05/28/10 V 2.876 150 C 0.458 0.133 0.300 - - - 89.10

    89.10% Satisfactory

    3RB Construction & Supply 19541

    Road Upgrading along DM Jct.-Leg.-Sto. Domingo-Tab.-Cam. Sur Bdry.,

    Tiwi-Tabaco Section02/24/09 V 19.233 150 C 0.488 0.133 0.300 - - - 92.10 84.30% Satisfactory

    3RB Construction & Supply 19541

    Impvt. of San Fernando North Road, San Jacinto Section 02/17/10 V 9.450 210 O 0.378 0.240 0.150 0.015 0.035 0.050 86.80 -

    3RB Construction & Supply 19541

    Road Conc. & Impvt. of Barangay Road 02/22/10 V 0.959 160 C 0.396 0.139 0.300 - - - 83.50

    86.38% Satisfactory

    3RB Construction & Supply/Ajan Jaeda, Inc.

    (JV) JV-08-209 Const. of Tagas-Divino Rostro Bridge 09/01/09 V 19.179 202 O 0.384 0.240 0.150 0.030 0.033 0.050 88.70 -

    3S Builders 18009 Repair and Rehab. of MPB (Municipal Hall) 04/09/11 VII 1.893 97 C 0.491 0.133 0.300 - - - 92.40*92.40%

    V. Satisfactory

    4 A's Construction 9446 Construction of 1-CL (7x9) Lupigue IS 09/05/09 II 1.108 45 C 0.454 0.133 0.300 - - - 88.70*88.70%

    Satisfactory

    4 A's Construction 9446 Const./Conc. of Road 02/23/10 II 4.822 330 C 0.413 0.133 0.300 - - - 84.60 84.60% Satisfactory

    4 A's Construction 9446 Asphalt Overlay of Daang Maharlika 03/03/09 II 1.929 30 C 0.464 0.133 0.300 - - - 89.70 *89.70% V.Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page3

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    4B Construction Corporation 23445

    Upgrading and Concreting of Subic-Philseco Road 03/03/09 III 41.616 180 C 0.407 0.163 0.300 - - - 87.00

    83.76% Satisfactory

    4B Construction Corporation 23445

    Rehab./Reconst./Upgrading of Damaged Paved National Road,

    Olongapo-Bugallon Road05/23/09 III 33.265 45 C 0.374 0.200 0.300 - - - 87.40 *87.40%Satisfactory

    4B Construction Corporation 23445

    Preventive Maint. along Roman Expressway (Bal Sect.)

    K0120+279.82-K0123+434.42; (Cupang-Alauli Sect.) K0123+434.42-

    K0 125+000

    08/06/11 III 28.532 53 C 0.437 0.003 0.300 - - - 74.00 *74.00% Poor

    4B Construction Corporation 23445

    Rehab./Reconst./Upgrading of Visayas Avenue (Km 164+236-

    Km.164+711 & Km. 164+872 - Km. 164+236

    08/06/11 III 14.802 24 C 0.453 0.135 0.300 - - - 88.80 *88.80% Satisfactory

    4B Construction Corporation 23445

    Widening/Conc. of Calamba-Sta. Cruz-Famy Jct. Road (4 Lanes) 08/10/11 IVA 45.081 120 O 0.323 0.240 0.011 0.030 0.050 0.050 70.40 -

    4B Construction Corporation 23445

    Rehab./Reconst./Upgrading of Damaged Paved National Roads at

    Subic-PHILSECO Rd.04/04/11 III 41.378 163 C 0.356 0.167 0.300 - - - 82.30 80.41% Unsatisfactory

    4B Construction Corporation 23445

    Repair/Rehab. of Paete-Famy Pob. Rd., Pangil-Siniloan Sect. Km.109+000 - Km.110+400

    05/25/10 IVA 9.608 20 C 0.472 0.133 0.300 - - - 90.50 90.50% V. Satisfactory

    5-1 Construction Corporation 33605

    Asset Preservation (Preventive Maintenance) of Ilocos Sur,

    Km.0011+519 to Km.0011+909 with exception

    08/11/11 NCR 1.908 30 C 0.462 0.200 0.300 - - - 96.20 *96.20% Outstanding

    525 Construction 28532 Rehab. of Sta. Rita-Biak na Bato via Pulong Bayabas Road 04/15/11 III 38.599 210 C 0.330 0.200 0.300 - - - 83.0089.66%

    V. Satisfactory

    525 Construction 28532 Rahab. of Sta. Rita-Biak na Bato via Pulong Bayabas Road 09/08/09 III 19.049 120 C 0.478 0.133 0.300 - - - 91.10*91.10%

    V. Satisfactory

    525 Construction / MGSCC (JV)

    JV-07-095/ SLI-SN-005104

    Rehabilitation/Improvement of Sta. Rita Biak na Bato Road 03/11/09 III 44.000 200 C 0.405 0.200 0.300 - - - 90.50

    *90.50% V.Satisfactory

    525 Construction/MGSCC Joint Venture JV-08-235

    Rehabilitation of Sta. Maria-Norzagaray Road 09/07/09 III 46.339 180 C 0.479 0.133 0.300 - - - 91.20

    86.64% Satisfactory

    5G Galvez Construction and Supply 34736

    Northern Samar First Engineering District Brgy. Dancalan 08/12/11 VIII 0.960 60 C 0.457 0.133 0.300 - - - 89.00

    *89.00% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page4

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    6 Jewels Construction 34737 Const. of Line Canal @ Inicbulan 08/17/11 IVA 0.496 45 C 0.484 0.133 0.300 - - - 91.70 *91.70% V. Satisfactory

    628 Construction Enterprises 30049

    Construction of Two Classroom School Building at Lokeb Norte 03/06/09 I 1.369 70 C 0.429 0.178 0.300 - - - 90.70

    *90.70%V. Satisfactory

    722 Construction 21923 Rehab./Reconst./Upgrading at Old Cagayan Valley Rd. (Baliuag Sect.) 06/10/10 III 9.547 80 C 0.460 0.133 0.300 - - - 89.3089.30%

    V. Satisfactory

    722 Construction 21923Rehab/Reconst./Upgrading of Old

    Cagayan Valley Road (Pulilan Section)

    05/28/09 III 9.543 45 C 0.359 0.200 0.300 - - - 85.90 *85.90%Satisfactory

    722 Construction 21923 Const. of Sch. Bldg., 2 Storey, 2 CL Banga E/S 03/10/09 III 2.290 100 C 0.472 0.133 0.300 - - - 90.5089.52%

    V.Satisfactory

    722 Construction 21923Const. of Multi-Purpose Bldg.

    Malinta E/S Lawang Bato E/S, Brgy. Lawang Bato & Natividad Homes

    03/03/09 NCR 1.882 90 C 0.405 0.136 0.300 - - - 84.10 *84.10% Satisfactory

    722 Construction 21923Rehab./Reconst./Upgrading of

    Damages Pavement along Mc Arthur Highway

    05/31/10 NCR 9.506 120 C 0.436 0.200 0.300 - - - 93.60 93.60% V. Satisfactory

    722 Construction 21923 Rehab./Reconst./Upgrading along Rizal Avenue Extension 05/27/09 NCR 9.494 120 C 0.380 0.200 0.300 - - - 88.00*88.00%

    Satisfactory

    722 Construction 10221 Const. of MPB (Day Care) at Brgy. Polo 09/16/09 NCR 1.901 75 C 0.486 0.133 0.300 - - - 91.90*91.90%

    V. Satisfactory

    722 Construction, Inc. (Formerly: 722 Construction)

    21923 Repair and Rehab. along MacArthur Highway Extension, Dalandanan 08/02/11 NCR 8.895 157 O 0.363 0.240 0.150 0.030 0.045 0.033 86.10 -

    722 Construction, Inc. (Formerly: 722 Construction)

    21923 Impvt./Rehab. of Road, Sumandig Road, Brgy. Sumandig 08/17/11 III 1.914 70 C 0.405 0.200 0.300 - - - 90.50*90.50%

    V. Satisfactory

    722 Construction, Inc. (Formerly: 722 Construction)

    21923 Preventive Maint.Daang Maharlika Road. Km.43+792-Km.44+478.32 08/11/11 III 8.283 18 C 0.428 0.135 0.300 - - - 86.30*86.30%

    Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page5

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    722 Construction, Inc. (Formerly: 722 Construction)

    21923

    Asphalt Overlay along NCR/Bulacan Bdry.-Bigte-Ipo Dam Road,

    Km.029+836-Km.029+(-149) w/ exception

    08/17/11 III 5.027 20 C 0.385 0.137 0.300 - - - 82.20 *82.20% Satisfactory

    739 Builders 31174 Const. of Ten (10) CL, Two (2) Storey Sch. Bldg. At Ilocos Sur NHS 03/31/11 I 8.068 240 C 0.351 0.142 0.300 - - - 79.3083.36%

    Satisfactory

    739 Builders 31174 Construction of School Building, Pila E/S, Brgy. Pila 09/07/09 I 0.950 60 C 0.454 0.154 0.300 - - - 90.80*90.80%

    V. Satisfactory

    739 Builders 31174 Const. of Drainage Canal, Brgy. VII 05/29/10 I 1.141 80 C 0.444 0.133 0.300 - - - 87.70 87.70% Satisfactory

    739 Builders 31174 Road Concreting, Brgy. Napo 02/28/09 I 0.950 20 C 0.364 0.200 0.300 - - - 86.40 *86.40%Satisfactory

    747 Builders & Trader 16892 Rehab./Impvt. of Manggahan Floodway Eastbank 03/12/09 IVA 14.367 170 C 0.473 0.133 0.300 - - - 90.6086.97%

    Satisfactory

    747 Builders & Trader 16892Proposed Rehab./Impvt. of Pres.

    Quirino Ave. West Bound (Singalong-Roxas Blvd.)

    05/24/10 NCR 14.475 20 C 0.442 0.200 0.300 - - - 94.20 94.20% V. Satisfactory

    747 Builders and Trader 16892 Rehab./Reconst./Upgrading of Antipolo Circumferential Road "A" 08/26/09 IVA 19.213 180 C 0.411 0.200 0.300 - - - 91.1088.70%

    Satisfactory

    811 Trading & Construction 21215

    Impv't. of Jct. Nat'l. Rds.-Osmea St.-Sitio Toong Road, Poblacion

    Carugay ARC08/09/11 IVB 20.482 160 C 0.448 0.133 0.300 - - - 88.10 *85.88% Satisfactory

    811 Trading & Construction 21215

    Impvt. of Jct. National Road-Osmea Street-Sitio Toong Road Pob.

    Caguray ARC04/08/11 IVB 20.482 160 O 0.354 0.212 0.150 0.030 0.048 0.050 84.40 -

    811 Trading & Construction 21215

    Repair/Rehab. of Multi-Purpose Building (Phase II) 02/26/09 IV-B 0.288 27 C 0.463 0.133 0.300 - - - 89.60

    *89.60% V.Satisfactory

    830 Builders & Developers Corp. 29781

    Const. of 1 CL 7m x 7m Sch. Bldg. at Lanatan Munting Tubig E/S 04/12/11 IVA 0.495 40 C 0.459 0.200 0.300 - - - 95.90

    *95.90% V. Satisfactory

    888 ACY Enterprises 32898Reconst. (Conc. Paving) of Jct. LIR., Buenavista-Carmen, Danao-Getafe

    Road, Poblacion, Danao Sect.08/18/11 VII 9.541 240 C 0.328 0.200 0.000 - - - 52.80 66.93% Poor

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page6

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    888 Acy Enterprises 32898Reconst. (Conc. Paving) of Loay

    Interior Rd., Trinidad & San Miguel Sect.

    03/31/11 VII 14.320 565 C 0.278 0.133 0.000 - - - 41.10 60.60% Poor

    920 Factors & Enterprises 20387

    Road Upgrading (Gravel to Conc.) Gurel-Bukod-Kabagan-Buguias-

    Abatan Road04/11/11 CAR 28.838 337 C 0.456 0.133 0.300 - - - 88.90 *88.90% Satisfactory

    A B Aponesto Construction, Parts &

    Supply22998

    Road Upgrading (Gravel to Paved) along Compostela-Cateel Road,

    Osmea Section04/09/11 XI 18.892 180 C 0.372 0.200 0.300 - - - 87.20 85.82% Satisfactory

    A C J Construction Resources 10635

    Concreting of Poblacion Magpet-Nowa-Basak Road (Basak Section) 05/30/09 R-XII 18.797 180 O 0.336 0.300 0.000 0.024 0.055 0.050 76.50 -

    A C O Construction 13105Rehab./Upgrading of Ipil-Liloy-

    Sindangan Road Km. 2007+240-Km. 2008+369

    08/11/11 IX 10.787 101 O 0.362 0.300 0.000 0.030 0.050 0.000 74.20 -

    A C O Construction 13105

    Const. of Rotonda along National Highway (Zamboanga Peninsula) Cross Rd. Upgrading Project @

    Poblacion Ipil

    02/25/10 IX 2.829 115 O 0.319 0.300 0.000 0.020 0.042 0.033 71.40 -

    A C O Construction 13105Zamboanga Peninsula Crossroads Upgrading Project (Completion of

    Roundabout) Sta.1801+231.50 06/05/10 IX 1.861 60 C 0.476 0.133 0.300 - - - 90.90 90.90% V. Satisfactory

    A C O Construction 13105

    Const. of Rotonda along National Highway (Zamboanga Peninsula Crossroad Upgrading Project) at

    Poblacion Ipil

    06/05/10 IX 2.829 115 C 0.456 0.133 0.000 - - - 58.90 66.40% Poor

    A C O Construction 13105 Conc. of Liloy-Zamboanga del Norte-Ipil-Zamboanga Sibugay Rd. Ph. I 03/05/09 IX 14.306 150 C 0.425 0.147 0.300 - - - 87.2086.90%

    Satisfactory

    A. De Guia Construction 18228

    Preventive Maintenance along Santiago-Tuguegarao Road @ A)

    KO368+620 - KO369+000, Aurora B) KO374+000 - KO375+500

    04/06/11 II 6.718 90 C 0.483 0.133 0.300 - - - 91.60 *91.60% V. Satisfactory

    A. De Guia Construction 18228 Restoration of Jones Revetment 04/11/11 II 4.825 90 C 0.450 0.133 0.300 - - - 88.30 *88.30% Satisfactory

    A. De Guia Construction 18228 Restoration of Brgy. I Revetment 04/11/11 II 4.825 90 C 0.425 0.133 0.300 - - - 85.80 *85.80% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page7

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A. De Guia Construction 18228 Repair/Restoration of Flood Control, Sta.000+000 - Sta.000+120 04/11/11 II 9.650 90 C 0.400 0.133 0.300 - - - 83.30*83.30%

    Satisfactory

    A. De Guia Construction 18228

    Rehab./Reconst./Upgrading of Santiago-Baluarte-Quirino Bdry.

    Road; KO328+100 - KO331+000 w/ exception

    04/10/11 II 18.623 150 C 0.428 0.133 0.000 - - - 56.10 70.44% Poor

    A. De Guia Construction 18228Rehab./Reconst./Upgrading of

    Santiago-Tuguegarao Rd. Burucboc Sect.

    04/06/11 II 9.647 133 C 0.456 0.133 0.000 - - - 58.90 67.42% Poor

    A. De Guia Construction 18228Rehab./Reconst./Upgrading of Santiago-Tuguegarao Road,

    KO333+500 - KO334+85004/10/11 II 17.123 149 C 0.335 0.200 0.000 - - - 53.50 65.26% Poor

    A. De Guia Construction 18228Rehab./Reconst./Upgrading of

    Naguilian-San Mariano Rd., Villapaz Section

    08/25/09 II 19.296 104 C 0.420 0.200 0.300 - - - 92.00 92.84% V. Satisfactory

    A. De Guia Construction 18228 Concreting of Junction National -Potia Road 08/27/09 II 7.043 110 C 0.410 0.200 0.300 - - - 91.0091.42%

    V. Satisfactory

    A. De Guia Construction 18228 Rehab./Reconst. of Daang Maharlika Road, KO309+300-KO309+878 08/27/09 II 18.811 130 C 0.411 0.200 0.300 - - - 91.1091.10%

    V. Satisfactory

    A. De Guia Construction 18228 Rehab./Reconst./Upgrading of Gamu-Roxas Road (Roxas Section) 02/23/10 II 19.293 240 C 0.402 0.133 0.300 - - - 83.5088.78%

    Satisfactory

    A. De Guia Construction 18228 Const./Completion/Continuation of Unfinished On-going Bridges 03/01/10 II 11.574 120 C 0.415 0.133 0.300 - - - 84.8086.78%

    Satisfactory

    A. De Guia Construction 18228

    Rehab./Reconst./Upgrading of Damaged Paved national Road,

    Daang Maharlika KO 320+000 - KO 321+000

    06/03/10 II 16.396 120 O 0.387 0.295 0.150 0.030 0.042 0.033 93.70 -

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page8

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A. De Guia Construction 18228

    Rehab./Reconst./Upgrading of Damaged Paved National Road

    Santiago-Baluarte-Quirino Bdry. Road KO326+(-)280 - KO328+000 w/

    exception

    08/27/10 II 15.432 149 C 0.292 0.200 0.300 - - - 79.20 87.24% Satisfactory

    A. De Guia Construction 18228

    Restoration of Road Slope & Slope Protection along Naguilian-San

    Mariano Road KO395+850 - KO401+800

    08/25/10 II 14.471 120 C 0.389 0.150 0.300 - - - 83.90 85.28% Satisfactory

    A. De Guia Construction 18228Road Upgrading (Gravel to Paved) of Jct. Ipil-Panang-Quirino Bdry. Road;

    KO366+058 - KO367+11808/27/10 II 17.373 149 C 0.403 0.146 0.300 - - - 84.90 84.90% Satisfactory

    A. E. Belleza Builders Pampolna Resettlement Project, Phase I 04/23-26/12 NHA 9.978 150 O 0.398 0.300 0.000 0.030 0.056 0.033 81.74 -

    A. Montalbo Trading and Construction 32684

    Const. of Multi-Purpose Building at Bigain 1st 03/01/10 IVA 1.135 30 C 0.450 0.200 0.300 - - - 95.00

    95.00% V. Satisfactory

    A.A De Vera Construction 6191 Rehab./Expansion of Waterworks System 09/02/09 VII 4.510 240 C 0.417 0.133 0.300 - - - 85.00*85.00%

    Satisfactory

    A.A De Vera Construction 6191 Const./Rehab. of School Bldg. at Cogon E/S 06/05/10 VII 0.591 35 C 0.415 0.200 0.000 - - - 61.5061.50% Poor

    A.A De Vera Construction 6191 Const. of Water System Development Project 08/25/10 VII 1.413 90 C 0.497 0.133 0.300 - - - 93.0093.00%

    V. Satisfactory

    A.A De Vera Construction 6191 Const./Repair & Completion of Instructional Classroom, Corella CES 06/10/09 VII 0.504 105 C 0.492 0.200 0.300 - - - 99.20*99.20%

    Outstanding

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page9

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.A De Vera Construction 6191Completion of Tagbilaran City

    Puericulture Center & Maternity House and Related Facilities

    06/10/09 VII 4.575 150 C 0.500 0.169 0.300 - - - 96.90 *96.90% Outstanding

    A.A De Vera Construction 6191 Const./Repair/Rehab. of Multi-Purpose Building 06/10/09 VII 0.460 105 C 0.483 0.154 0.300 - - - 93.7095.52%

    V. Satisfactory

    A.A De Vera Construction 6191 Completion of Multi-Purpose Building 03/04/09 VII 0.458 60 C 0.382 0.200 0.300 - - - 88.20*88.20%

    Satisfactory

    A.A. De Vera Construction 6191 Const. of MPB, Basak 08/24/11 VII 1.835 120 C 0.485 0.133 0.300 - - - 91.80

    *91.80% V. Satisfactory

    A.A. De Vera Construction 6191 Const. of MPB, Songculan 08/23/11 VII 0.958 120 C 0.460 0.133 0.300 - - - 89.30

    *89.30% V. Satisfactory

    A.A. De Vera Construction 6191

    Const. of Employees Quarters, DPWH Bohol I 03/29/11 VII 4.710 210 C 0.485 0.162 0.300 - - - 94.70

    *94.70% V. Satisfactory

    A.A. De Vera Construction 6191

    Const. of MPB (School Stage) Loon North CES 03/29/11 VII 1.318 110 C 0.469 0.133 0.300 - - - 90.20

    *90.20% V. Satisfactory

    A.B Aponesto Construction Parts &

    Supply22998

    Road Upgrading (Gravel to Paved) along Compostela-Cateel Rd.,

    Osmea Sect.06/04/10 XI 18.892 180 O 0.355 0.238 0.150 0.030 0.045 0.033 85.10 -

    A.B Aponesto Construction, Parts &

    Supply22998 Concreting of Montevista-DNAS Road 03/01/10 XI 32.748 300 C 0.353 0.200 0.300 - - - 85.30

    88.48% Satisfactory

    A.B Taylan Construction & Development 25273

    Const. of RCBC and Canal along Manila North Road (Km. 483+040) 02/22/10 I 4.816 65 C 0.329 0.133 0.300 - - - 76.20

    76.20% Unsatisfactory

    A.B. Taylan Construction & Development / Fiat

    Construction Services (JV)

    JV-09-106Road Opening/Const. of Missing

    Links of Nat'l Rd., Solsona-Kabugao Road, Phase VI, Ilocos Norte Side

    08/01/11 I 192.447 540 C 0.464 0.145 0.300 - - - 90.90 87.30% Satisfactory

    A.C Rivero Development Corporation 5122

    Rehab./Reconst./Upgrading of Bacolod South Road Km. 6+862-Km.

    8+350 w/ exception09/12/09 VI 26.470 280 O 0.331 0.282 0.150 0.030 0.045 0.033 87.10 -

    A.C Rivero Development Corporation 5122

    Const./Impvt. of Multi-Purpose Bldg. at Maasin City (Legislative Building) 03/06/09 VIII 0.934 75 C 0.500 0.133 0.300 - - - 93.30

    *93.30%V. Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page10

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.C Rivero Development Corporation (Formerly:

    A.C. Rivero Const.)5122

    Rehab./Reconst./Upgrading of Bacolod South Rd. Km. 6+862 to Km.

    8+350 with exceptions03/06/10 VI 26.337 280 C 0.393 0.200 0.300 - - - 89.30 87.98% Satisfactory

    A.C Soliven Construction & General Merchandise 19278

    Channel Impvt./Slope Protection @ San Roque Creek, Camias Creek &

    San Vicente Creek02/23/10 III 4.781 60 C 0.445 0.177 0.300 - - - 92.20 92.20% V. Satisfactory

    A.C Soliven Construction & General Merchandise 19278

    Construction of 2 CL S.B. at La Paz H/S 09/01/09 III 0.974 90 C 0.483 0.133 0.300 - - - 91.60

    *91.60% V. Satisfactory

    A.C. Rivero Development Corporation (Formerly:

    A.C. Rivero Const.)5122 Const. of Subang Daku Bridge Phase II 08/16/11 VIII 18.890 360 O 0.376 0.300 0.150 0.030 0.045 0.033 93.40 -

    A.C. Rivero Development Corporation (Formerly:

    A.C. Rivero Const.)5122 Const. of Subang Daku Bridge 08/16/11 VIII 18.890 518 C 0.486 0.200 0.300 - - - 98.60 91.60% V. Satisfactory

    A.C. Soliven Construction & General

    Merchandise19278 Repair/Rehab. Of FMR at Brgy. Dalumpinas 08/12/11 I 0.950 23 C 0.491 0.133 0.300 - - - 92.40

    *92.40% V. Satisfactory

    A.C. Soliven Construction & General

    Merchandise17278

    Upgrading of Capas-Botolan Rd. (Capas Sect.) K0124+805 to

    K0124+94708/05/11 III 1.843 30 C 0.377 0.200 0.300 - - - 87.70 *87.70% Satisfactory

    A.C. Soliven Construction & General

    Merchandise19278 Const. of Two (2) Cl. Sch. Bldg. @ Aranguren High School 04/06/11 III 0.925 90 C 0.456 0.178 0.300 - - - 93.40

    *93.40% V. Satisfactory

    A.D Construction 6946 Conc. of Line Canal along National Road, Concepcion 09/09/09 IVA 1.442 90 C 0.371 0.200 0.300 - - - 87.10*87.10%

    Satisfactory

    A.D. Construction 6946 Impvt./Rehab. of San Jose Elem. School, District II 08/18/11 NCR 0.838 45 C 0.458 0.200 0.300 - - - 95.80*95.80%

    V. Satisfactory

    A.D. Construction 6946 Partial Completion of Jose P. Laurel H/S 04/04/11 NCR 1.571 60 C 0.486 0.192 0.300 - - - 97.80*97.80%

    Outstanding

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page11

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.D.P Construction & Supply 3466

    Impvt./Conc. of Access Road, Tubalan Port, Tubalan 06/14/10 XI 58.261 320 O 0.338 0.300 0.000 0.030 0.040 0.033 74.10 -

    A.D.P Construction & Supply 3466

    Impv't./Conc. Of Mana-Ticulon-Lagumit-Little Baguio Rd. 08/25/10 XI 47.455 571 C 0.292 0.133 0.000 - - - 42.50

    42.50% Poor

    A.D.P Construction & Supply 3466

    Rehab./Reconst./Upgrading of Damaged Paved National Road,

    Roxas City Boundary-Panitan Road-Jct. Bailan Road, Capiz (KM.112+750-

    Km 122+705) with exception

    08/31/10 VI 53.673 225 O 0.364 0.240 0.150 0.030 0.051 0.050 88.50 -

    A.D.P Construction & Supply 3466 Reconst. of Dumaguete North Road 03/12/09 VII 18.881 230 C 0.442 0.200 0.300 - - - 94.20

    82.14%Satisfactory

    A.D.P. Const. & Supply 3466 Road Upgrading of Sara-Concepcion Road 04/13/11 VI 66.819 328 C 0.421 0.176 0.300 - - - 89.7087.84%

    Satisfactory

    A.D.P. Const. & Supply 3466 Conc. of Pototan-Tina-Lambunao Road 04/12/11 VI 9.419 178 C 0.410 0.133 0.300 - - - 84.3087.54%

    Satisfactory

    A.D.P. Const. & Supply 3466 Repair/Reconst./Upgrading of Roxas City Bdry.-Panitan Jct. Bailan Road 04/11/11 VI 53.673 225 C 0.409 0.134 0.300 - - - 84.3086.61%

    Satisfactory

    A.D.P. Const. & Supply 3466 Const. of Various Drainage System at Roxas City 04/11/11 VI 28.854 240 C 0.432 0.133 0.300 - - - 86.50*86.50%

    Satisfactory

    A.D.S San Juan Construction 12853

    Conc. of Dionisio Anore St., Brgy. Mambog 02/16/10 IVA 1.728 90 C 0.427 0.200 0.300 - - - 92.70

    92.70% V. Satisfactory

    A.F.G Construction & Construction Supply 17161

    Const. of MPB (Covered Court) at San Enrique NHS 03/10/10 VI 1.925 78 C 0.405 0.200 0.300 - - - 90.50

    87.08% Satisfactory

    A.F.G Construction & Construction Supply 17161

    Rehab. of Amerang Flood Control, Tigum River, Brgy. Amerang 09/05/10 VI 8.159 257 C 0.456 0.133 0.000 - - - 58.90

    69.28% Poor

    A.F.G Construction & Construction Supply 17161

    Rehab. of Bacolod South Rd. (Hingaran Section) 09/15/09 VI 14.221 222 C 0.398 0.133 0.300 - - - 83.10

    83.88% Satisfactory

    A.F.G. Construction and Construction Supply 17161

    Rehab./Reconst./Upgrading of Jct. National Road, Sagay-Bato-Dian-ay-Marcelo-Balea Jct. National Road,

    Bato Sect.

    03/31/11 VI 37.184 210 C 0.448 0.135 0.300 - - - 88.30 83.38% Satisfactory

    A.G Cosipag Construction 12700 Balogo CIS 06/1-6/09 NIA 2.144 150 C 0.421 0.126 0.300 - - - 84.68

    *84.68% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page12

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.G Herrera Construction Corp. 26307

    Construction of Multi-Purpose Building, Sto. Cristo 06/01/09 III 2.381 80 C 0.488 0.133 0.300 - - - 92.10

    90.42% V. Satisfactory

    A.I.P Construction 32458 Road Concreting at Pinget Barangay 03/13/09 CAR 1.872 45 C 0.386 0.200 0.300 - - - 88.60 *88.60% Satisfactory

    A.I.P Construction 32458 Rehab. of Ambasing-Balugang FMR 08/27/10 CAR 0.800 268 C 0.439 0.133 0.300 - - - 87.20 87.20% Satisfactory

    A.I.P. Construction 32458 Rehab. of Kin-iway-Tamboan FMR 04/10/11 CAR 1.000 250 C 0.436 0.147 0.300 - - - 88.30 85.42% Satisfactory

    A.I.P. Construction 32458Restoration of Road cuts along

    Bontoc Baguio Road Alab Section (Km.383+619 - Km.384+124)

    04/09/11 CAR 1.732 70 C 0.340 0.200 0.300 - - - 84.00 82.68% Satisfactory

    A.J Lava Builders 22265 Const. of the Makinabang Baliuag FMR 11/24/08 III 4.769 62 C 0.296 0.300 0.300 - - - 89.60*89.60%

    V. Satisfactory

    A.J Lava Builders 22265 Impvt./Rehab. of MPB, Brgy. San Antonio 09/14/09 NCR 2.021 90 C 0.412 0.133 0.300 - - - 84.50*84.50%

    Satisfactory

    A.J Lava Builders 22265 Impv't./Rehab. of MPB and Alley Fernandez St., Brgy. San Antonio 06/04/10 NCR 0.961 45 C 0.455 0.200 0.300 - - - 95.5095.50%

    V. Satisfactory

    A.J Taylan Construction Corporation 2336

    Road Opening/Const. of Missing Links of National Road, Solsona-Kabugao Road, Ilocos Norte Side

    09/09/09 I 48.199 300 O 0.379 0.250 0.150 0.030 0.050 0.033 89.20 -

    A.J. Lava Builders 22265Preventive Maintenance of San

    Mateo-Rodriguez Road, San Mateo-Rodriguez

    08/01/11 IVA 4.413 30 C 0.498 0.133 0.300 - - - 93.10 *93.10% V. Satisfactory

    A.L Dare Construction 11932Const./Repair/Rehab. of Slope Protection along Porac River,

    Mabical Sect.08/16/10 III 14.344 90 C 0.481 0.133 0.300 - - - 91.40 91.40% V. Satisfactory

    A.L Gantuangco Construction 30872

    Construction of the Diversion Works and Canal System of Libertad CIP -

    Phase 211/15-20/2010 NIA 16.060 202 O 0.373 0.264 0.150 0.023 0.038 0.050 89.69 -

    A.L Gantuangco Construction 30872 Benolho CIS 10/6-10/08 NIA 3.720 90 O 0.277 0.180 0.050 0.020 0.038 0.100 66.50 -

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page13

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.L. Dare Construction 11932 Impvt. along Kennon Road, Camp 4 04/14/11 CAR 7.177 150 C 0.388 0.200 0.300 - - - 88.80 85.98% Satisfactory

    A.L.R Construction Corporation 24110 Completion of MPB at Brgy. Zapote 05/27/10 IVA 0.959 30 C 0.458 0.075 0.300 - - - 83.30

    83.30% Satisfactory

    A.L.R Construction Corporation 24110

    Completion of Two (2) Storey 4-CL at Landayan E/S 08/23/10 IVA 2.302 225 C 0.407 0.165 0.300 - - - 87.20

    87.06% Satisfactory

    A.L.R Construction Corporation 24110 Conc.of Road, Inday Subdivision 03/13/09 IVA 0.958 90 C 0.461 0.133 0.300 - - - 89.40

    *89.40% V. Satisfactory

    A.L.R Construction Corporation 24110

    Const.of Multi Purpose Pavement with Perimeter Fence, Marcelino M.

    Santos NHS03/13/09 IVA 0.957 90 C 0.480 0.133 0.300 - - - 91.30 *91.30% V. Satisfactory

    A.L.R Construction Corporation 24110

    Const. of Pedestrian Overpass (Phase II) Brgy. Pagsawitan 09/01/09 IVA 2.882 35 C 0.484 0.185 0.300 - - - 96.90

    *96.90% Outstanding

    A.L.R Construction Corporation 24110

    Const. of Multi-Purpose Building at Brgy. Timugan 09/03/09 IVA 2.111 40 C 0.389 0.155 0.300 - - - 84.40

    *84.40% Satisfactory

    A.L.R Construction Corporation 24110 Conc. of Roads, Brgy. San Luis 02/15/10 IVA 3.358 90 C 0.455 0.200 0.300 - - - 95.50

    95.50% V. Satisfactory

    A.L.R Construction Corporation 24110

    Completion of 2-Storey 4-CL @ Landayan E/S 02/24/10 IVA 5.030 225 O 0.354 0.300 0.150 0.015 0.018 0.033 87.00 -

    A.L.R Construction Corporation 24110

    Construction of Overpass (Phase I), Pagsawitan 05/30/09 IV-A 3.849 129 C 0.482 0.133 0.300 - - - 91.50

    *91.50% V. Satisfactory

    A.L.R Construction Corporation 24110

    Const. of Pedestrian Overpass at Brgy. San Antonio and Bian-

    Carmona Road Intersection06/01/09 IV-A 19.203 241 C 0.466 0.133 0.300 - - - 89.90 90.86% V. Satisfactory

    A.L.R Construction Corporation 24110

    Road Upgrading (Gravel to Paved-HDM-4) of Jct. MWCR (Bagong

    Silang)-Cabacao Diversion Road, Brgy. Cabacao

    08/28/10 IVB 9.649 145 C 0.409 0.198 0.300 - - - 90.70 88.60% Satisfactory

    A.L.R. Construction Corporation 24110

    Const. of Pedestrian Overpass, Old Manila South Road, Km.34+520 04/06/11 IVA 9.632 202 C 0.395 0.111 0.300 - - - 80.60

    85.64% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page14

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.M Oreta & CO., Inc./IBC Int'l Builders Corp. (JV) JV-07-097

    Conc. of Iloilo-Caticlan Highway (Pototan-Passi-Capiz Bdry. Sect.) 05/31/10 VI 158.259 570 C 0.379 0.200 0.300 - - - 87.90

    87.82% Satisfactory

    A.M Oreta & CO., Inc./IBC Int'l Builders Corp. (JV) 7096

    Kalibo Airport Development Project (Asphalt Overlay of Runway,

    Extension of Apron and Construction of Drainage Canal)

    04/14/10 DOTC 283.188 360 C 0.449 0.200 0.300 - - - 94.90 92.40% V. Satisfactory

    A.M Robles Construction 28056 Construction of Water Supply @ Brgy. San Simon 03/02/09 I 0.530 40 C 0.415 0.184 0.300 - - - 89.90*89.90%

    V. Satisfactory

    A.M Robles Construction 28056 Completion of Multi-Purpose Building at Pinaglabanan 05/28/09 NCR 4.776 90 C 0.487 0.133 0.300 - - - 92.00*92.00%

    V. Satisfactory

    A.M. Oreta / IBC (JV) JV-09-227

    Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads, Iloilo-

    Capiz Rd. (Old Route) Cabatuan-Janiuay-Lambunao-Calinog Sect.

    08/23/11 VI 143.049 360 O 0.345 0.200 0.150 0.030 0.059 0.050 83.40 -

    A.M. Oreta / IBC (JV) JV-07-171Const. of CP-V, Pandan-Libertad-Antique Bdry. Rd., Sta.00+057 - Sta.27+762.66 with exception

    04/06/11 PJHL 409.901 707 C 0.418 0.200 0.300 - - - 91.80 *91.80% V. Satisfactory

    A.M. Oreta / IBC (JV) JV-09-227Rehab./Reconst./Upgrading of Iloilo-Capiz Road (Old Route) Cabatuan-Janiuay-Lambunao-Calinog Sect.

    04/10/11 VI 143.049 360 O 0.336 0.300 0.150 0.030 0.056 0.033 90.50 -

    A.M. Oreta / IBC International (JV) JV-08-261

    Pototan Bridge along Iloilo-Capiz, (New Route) including Access Road

    to the New Airport04/10/11 VI 308.770 676 C 0.447 0.133 0.300 - - - 88.00 83.50% Satisfactory

    A.P Consebido Construction & Trading 33616 Basey Irrigation Project 09/5-9/11 NIA 8.463 120 C 0.451 0.160 0.300 - - - 91.10

    91.07% V. Satisfactory

    A.P Consebido Construction and Trading 33616 Const. of MPB, Brgy. Alimanguan 08/20/10 IVB 0.974 114 C 0.447 0.200 0.300 - - - 94.70

    88.54% Satisfactory

    A.P Palacios Construction 29021 Const. of MPB, Brgy. Pingit 06/05/10 III 4.287 180 C 0.470 0.133 0.300 - - - 90.30

    90.30% V. Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page15

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.P Palacios Construction 29021 Rehab./Impvt. of Dikidit-Suguit FTMR 09/08/09 III 4.723 150 O 0.300 0.300 0.150 0.030 0.050 0.033 86.30 -

    A.P. Consebido Construction and Trading 33616 Const. of Seawall at Brgy. Rizal 08/05/11 IVB 0.665 40 C 0.459 0.133 0.300 - - - 89.20

    *89.20% V. Satisfactory

    A.P. Consebido Construction and Trading 33616

    Repair/Maint. Of Flood Control Structure of Tulariquen Bridge,

    Revetment08/05/11 IVB 0.880 48 C 0.448 0.133 0.300 - - - 88.10 *88.10% Satisfactory

    A.P. Palacios Construction / Wilper

    Const., Inc. (JV)

    Rehab./Reconst./Upgrading of Damage Pave (SLAMAC) 04/09/11 III 46.297 240 C 0.419 0.188 0.300 - - - 90.70

    *90.70% V. Satisfactory

    A.P.B Construction 17055Repair/Rehab. of Baguio-Bauang Road, Km. 296+050-Km. 297+050

    with exceptions08/29/10 CAR 4.891 47 C 0.456 0.176 0.300 - - - 93.20 93.40% V. Satisfactory

    A.P.B Construction 17055 Rehab. and Conc. of Road at Brgy. Balligi, Kias Barangay 03/03/10 CAR 1.248 60 C 0.384 0.158 0.300 - - - 84.2084.20%

    Satisfactory

    A.P.B. Construction 17055Rehab./Reconst./Upgrading of

    Damaged Paved National Road, PMA cut-off Road 2 K0+000-K0+360

    08/18/11 CAR 5.610 102 O 0.370 0.240 0.000 0.030 0.042 0.033 71.50 -

    A.P.O General Construction 7010

    Rehab./Reconst. of Dungon-Agat Section, Km. 216+648-Km. 217+723

    (V.S.) Camp 108/29/10 CAR 4.555 90 C 0.466 0.133 0.300 - - - 89.90 89.90% V. Satisfactory

    A.P.O. General Construction 7010

    Rehab./Reconst. along Gurel-Bokod-Kabayan-Buguias-Abatan Rd. 04/11/11 CAR 31.838 441 C 0.453 0.153 0.300 - - - 90.60

    *90.60% V. Satisfactory

    A.Q Loisaga Construction & General

    Services32691 Const. of 2 CL in Quillo-Quillo E/S 09/01/09 IVA 2.023 120 C 0.470 0.133 0.300 - - - 90.30 *90.30% V. Satisfactory

    A.R & Mark Builders 31673 Const. of @-CL Maramag CES 02/25/10 X 0.989 105 C 0.418 0.133 0.300 - - - 85.10 85.10% Satisfactory

    A.R Lustre Jr. Construction 7680

    Rehab./Reconst./Upgrading of Damaged Paved Nat'l. Rds. At Bigaa-Plaridel via Bulacan and Malolos Rd.

    08/27/10 III 14.352 90 C 0.367 0.185 0.300 - - - 85.20 85.20% Satisfactory

    A.R Lustre Jr. Construction 7680

    Conc. of Puerto-Princesa-Sabang Road 09/11/09 IVB 48.140 284 C 0.419 0.200 0.300 - - - 91.90

    90.61%V. Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page16

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.R Lustre Jr. Construction 7680

    Puerto Princesa Airport Development Project 8/13-14/09 DOTC 90.817 270 C 0.488 0.200 0.300 - - - 98.80

    98.80% Outstanding

    A.R Lustre Jr. Construction 7680

    Rehab/Reconst./Upgrading of Bigaa-Plaridel via Bulacan and Malolos

    Road05/28/09 III 13.077 75 C 0.449 0.196 0.300 - - - 94.50 *94.50%V. Satisfactory

    A.R Lustre Jr. Construction 7680

    Construction of Multi-Purpose Building 03/07/09 IV-B 0.383 90 C 0.481 0.107 0.300 - - - 88.80

    *88.80% Satisfactory

    A.R Lustre Jr. Construction 7680

    Repair/Rehab/Impvt. of Santiago-Syjuco E/S 09/17/09 NCR 0.482 45 C 0.482 0.000 0.300 - - - 78.20

    *78.20% Unsatisfactory

    A.R. Lustre Jr. Construction 7680

    Rehab./Reconst./Upgrading of Damaged Paved Nat'l Roads Pulilan

    & Calumpit08/12/11 III 21.726 113 O 0.313 0.300 0.136 0.030 0.060 0.033 87.20 -

    A.R. Lustre Jr. Construction 7680

    Conc. of Tapul-Bahile Road, Km.39+903.50-Km.40+560 08/09/11 IVB 9.214 75 O 0.375 0.237 0.150 0.023 0.054 0.050 88.90 -

    A.R. Lustre Jr. Construction 7680

    Conc. of Puerto Princesa South Road Phase 2 08/11/11 IVB 7.481 95 C 0.410 0.133 0.300 - - - 84.30

    87.06% Satisfactory

    A.R. Lustre Jr. Construction 7680

    Asphalt Overlay of Capitol-Canigaran Road, Km.1+950.6-Km.2+264 08/09/11 IVB 1.023 51 C 0.428 0.133 0.300 - - - 86.10

    *86.10% Satisfactory

    A.R. Lustre Jr. Construction 7680

    Conc. of Puerto Princesa South Road 03/31/11 IVB 38.600 217 C 0.441 0.133 0.300 - - - 87.40

    87.64% Satisfactory

    A.R. Lustre Jr. Construction 7680

    Const. of Puerto Princesa Airport Development Project (Building and

    Industrial Plant)05/25/11 DOTC 38.547 210 C 0.417 0.200 0.300 - - - 91.70 91.70% V. Satisfactory

    A.R. Lustre Jr. Construction 7680

    Const. of Peurto Princesa Airport Development Project (Building and

    Industrial Plant)05/26/11 DOTC 102.128 300 C 0.438 0.200 0.300 - - - 93.80 93.80% V. Satisfactory

    A.R.L Construction 27645 Repair/Rehab. of School Building BSU 03/03/10 III 0.989 18 C 0.454 0.148 0.300 - - - 90.2090.20%

    V. Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page17

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.R.L Construction 27645 Rehab/Impvt./Upgrading of Pulilan-Calumpit Road (Pulilan Section) 05/28/09 III 9.542 60 C 0.376 0.200 0.300 - - - 87.60*87.60%

    Satisfactory

    A.R.L Construction 27645Const. of Flood Control

    (Revetrment), Poblacion, San Sebastian, San Jose, Sta. Monica,

    09/04/09 III 6.697 80 C 0.400 0.133 0.300 - - - 83.30 *83.30% Satisfactory

    A.R.L Construction 27645 Upgrading/Conc. of Roads with Drainage Improvement 03/04/09 NCR 0.476 45 C 0.364 0.200 0.300 - - - 86.40*86.40%

    Satisfactory

    A.R.L Construction 27645Rehab./Reconst./Upgrading of

    Damaged Pavement along 7th Ave. East

    05/31/10 NCR 6.445 90 C 0.409 0.200 0.300 - - - 90.90 90.90% V. Satisfactory

    A.R.L. Construction 27645 Repair/Rehab. of MPB at Sta. Elena E/S 08/13/11 III 1.317 40 C 0.500 0.143 0.300 - - - 94.30*94.30%

    V. Satisfactory

    A.S.M Francisco Dev't and Construction Corp. 19098 Proposed Exterior Repainting Works 03/24/09 U.P. 1.368 120 C 0.400 0.200 0.300 - - - 90.00

    90.00% V. Satisfactory

    A.S.S Construction 31509 Completion of Alaremil Building II 03/2-3/10 DOST 9.607 250 C 0.496 0.200 0.300 - - - 99.60 97.64% Outstanding

    A.S.S. Construction 31509 Completion of ACA Building II 05/14-15/09 DOST 9.631 210 O 0.380 0.296 0.150 0.030 0.062 0.050 96.80 -

    A.S.S. Construction 31509 Construction of Sports Complex 05/14-15/09 DOST 3.159 90 C 0.391 0.295 0.300 - - - 98.60 98.60% Outstanding

    A.S.S. Construction 31509 Partial Completion of vast set, PCASTRD & PCIERD bldg. 07/08/09 DOST 7.479 135 C 0.483 0.200 0.300 - - - 98.30*98.30%

    Outstanding

    A.S.T. Builders 34104

    Rehab./Reconst./Upgrading of Damaged Paved Nat'l Rd., Cebu-Balamban Transcentral Highway

    (Km.0007+860-Km.0008+400)

    08/24/11 VII 4.516 10 C 0.455 0.200 0.300 - - - 95.50 *95.50% V. Satisfactory

    A.S.V Construction Supply and Services 13490

    Const. of FMR, Venegas St., Brgy. Layac-Sta.Isabel 05/26/10 III 0.473 60 C 0.444 0.133 0.300 - - - 87.70

    87.70% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page18

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    A.S.V. Construction Supply and Services 13490 Const./Impvt. of MPB 08/04/11 III 2.794 104 O 0.392 0.233 0.150 0.022 0.038 0.050 88.50 -

    A.S.V. Construction Supply and Services 13490

    Concrete Reblocking of Jct. Layac-Balanga-Mariveles Port Rd.,

    Km.106+151-Km.107+00008/04/11 III 4.778 109 O 0.383 0.225 0.150 0.030 0.048 0.033 86.90 -

    A.V. Bernal Construction & Trading Corp. 32999

    Asphalt Overlay along Tagaytay-Manila via Silang Road 08/18/11 IVA 4.468 14 C 0.481 0.133 0.300 - - - 91.40

    *91.40% V. Satisfactory

    A.Y.U. Engineering and Construction 25632

    Completion of MPB at Barangay Duterte 08/24/11 XI 1.473 120 C 0.448 0.133 0.300 - - - 88.10

    *88.10% Satisfactory

    A.Y.U. Engineering and Construction 25632

    Conc. of Roads @ Brgy. Sto. Nio, Tugbok District 03/28/11 XI 2.825 210 C 0.368 0.200 0.300 - - - 86.80

    *86.80% Satisfactory

    AB Aponesto Construction, Parts &

    Supply22998 Conc. of Lublub-Bolilac-Salad Road, Km.277+707.50-Km.278+711 09/05/10 VI 14.425 192 O 0.356 0.240 0.150 0.030 0.042 0.033 85.10 -

    Abesco Construction & Development Corp. 2934

    Construction of Multi-Purpose Building @ Cupang Elem. School 05/21/09 III 3.273 88 C 0.484 0.133 0.300 - - - 91.70

    90.23%V. Satisfactory

    Abu Construction 22313 Const. of MPB, Brgy. Caloocan 08/20/11 XII 2.657 105 C 0.497 0.125 0.300 - - - 92.20 *92.20% V. Satisfactory

    Abu Construction 22313 Const. of MPB, Brgy. Panay 08/20/11 XII 2.695 105 C 0.499 0.124 0.300 - - - 92.30 87.61% Satisfactory

    Abu Construction 22313 Rehab. of FTMR at Jct. Prv'l. Road Pob. Tamnag Lutayan-Mamali 08/19/11 XII 1.825 62 C 0.340 0.200 0.300 - - - 84.00*84.00%

    Satisfactory

    Abu Construction 22313 Rehab. of FTMR at Jct. Prv'l. Rd. at Blingkong, Lutayan-Bayasong 08/19/11 XII 1.781 62 C 0.330 0.200 0.300 - - - 83.00*83.00%

    Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page19

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Abu Construction 22313 Const. of Multi-Purpose Building 06/10/10 XII 1.926 126 C 0.494 0.133 0.300 - - - 92.70 92.70% V. Satisfactory

    Abu Construction 22313 Completion of MPB (Mini Gym) at Brgy. San Rafael 06/08/10 XII 1.897 65 C 0.386 0.133 0.300 - - - 81.9081.90%

    Unsatisfactory

    Abu Construction 22313 Completion of MPB (Gym) at Brgy. Baras 06/08/10 XII 0.764 65 C 0.339 0.133 0.300 - - - 77.2077.20%

    Unsatisfactory

    Abulug Construction Company, Inc. 5593

    Reblocking along Bangag-Allapacan-Magapit Road (BAMR), KO686+400-

    KO687+20009/08/09 II 7.999 150 C 0.406 0.200 0.300 - - - 90.60 *90.60% V. Satisfactory

    Abulug Construction Company, Inc. 5593

    Concrete Paving of Ballesteros Road (Washington & Luna St.,) 09/08/09 II 1.930 150 C 0.405 0.200 0.300 - - - 90.50

    88.94% Satisfactory

    Abulug Construction Company, Inc. 5593 Const. of Zitanga Brgy. Roads 02/17/10 II 9.648 132 C 0.370 0.200 0.300 - - - 87.00

    88.14% Satisfactory

    Abulug Construction Company, Inc. 5593

    Rehab. of Ballesteros Central School Building 02/17/10 II 0.192 60 C 0.437 0.133 0.300 - - - 87.00

    87.00% Satisfactory

    Abulug Construction Company, Inc. 5593 Construction of Deepwell 02/18/10 II 0.289 60 C 0.396 0.133 0.300 - - - 82.90

    82.90% Satisfactory

    Abulug Construction Company, Inc. 5593 Const. of Colony Road 11/13/08 II 2.894 120 O 0.329 0.240 0.100 0.030 0.033 0.100 83.20 -

    Abulug Construction Company, Inc. 5593

    Concreting of Jct. Claveria-Dibalio-Luzon Road 05/21/09 II 9.648 273 C 0.485 0.133 0.300 - - - 91.80

    88.95% Satisfactory

    Abulug Construction Company, Inc. 5593 Const. of Public Market (Phase II) 02/23/09 II 1.446 269 C 0.476 0.133 0.300 - - - 90.90

    87.40% Satisfactory

    Abulug Construction Company, Inc. 5593 Lucban River Control Project 02/29/09 II 3.858 347 C 0.417 0.133 0.300 - - - 85.00

    83.35% Satisfactory

    Abulug Developers & Builders Co., Inc. 2366 Conc. of Luna Street at Centro West 05/24/10 II 0.964 120 C 0.434 0.200 0.300 - - - 93.40

    93.40% V. Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page20

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Abulug Developers & Builders Co., Inc. 2366

    Emergency Restoration of Cadcadir Bridge #1 Approach KO 600+(-)595

    Phase I05/24/10 II 0.995 90 C 0.419 0.200 0.300 - - - 91.90 91.90% V. Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Restoration of Scoured Approaches & Eroded Bank of Cadcadir Bridge 2

    KO 602+723 Phase II05/24/10 II 0.771 90 C 0.408 0.200 0.300 - - - 90.80 90.80% V. Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Restoration of Scoured Approaches & Eroded Bank of Cadcadir Bridge 1

    Phase II, KO 600+ (-594)05/24/10 II 0.963 90 C 0.467 0.134 0.300 - - - 90.10 90.10% V. Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Reblocking along Manila North Road (Ballesteros-Abulug Section) 09/08/09 II 18.527 210 C 0.407 0.200 0.300 - - - 90.70

    89.38% V. Satisfactory

    Abulug Developers & Builders Co., Inc. 2366 Construction of 1-CL Bessang E/S 09/08/09 II 0.484 60 C 0.404 0.181 0.300 - - - 88.50

    *88.50% Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Emergency/Rehab. of Slope Protection KO 590+640, MNR 02/17/10 II 1.495 90 C 0.417 0.200 0.300 - - - 91.70

    91.70% V. Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Emergency/Rehab. of Slope Protection KO 590+340, MNR 02/17/10 II 0.995 90 C 0.467 0.133 0.300 - - - 90.00

    90.00% V. Satisfactory

    Abulug Developers & Builders Co., Inc. 2366 Concrete Paving of Jones Street 02/12/10 II 0.868 90 C 0.384 0.200 0.300 - - - 88.40

    88.40% Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Reblocking along Manila North Road (/Fugu Bdry. - Bangag Sect.) 02/17/10 II 19.299 234 C 0.394 0.200 0.300 - - - 89.40

    88.08% Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Rehab./Regravelling of Curva to Capallepaan Farm-to-Market Road 02/18/10 II 0.675 60 C 0.353 0.200 0.300 - - - 85.30

    85.30% Satisfactory

    Abulug Developers & Builders Co., Inc. 2366

    Road Opening of Pimpila Farm-to-Market Road 02/17/10 II 0.820 75 C 0.348 0.200 0.300 - - - 84.80

    84.80% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page21

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Abulug Developers & Builders Co., Inc. 2366

    Reblocking along Manila North Road (Fugu Bdry.-Bangag Section) 05/21/09 II 19.299 210 O 0.368 0.240 0.150 0.030 0.051 0.033 87.20 -

    Abulug Developers and Builders Co., Inc. 2366

    Rehab./Upgrading of Manila North Road 08/03/11 II 40.496 402 C 0.403 0.137 0.300 - - - 84.00

    86.46% Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Restoration of River Control Project along Goron & Langgangan River 03/31/11 II 12.542 179 C 0.445 0.133 0.300 - - - 87.8092.90%

    V. Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Conc. along Cadcadir-Kabugao Road 03/31/11 II 5.015 166 C 0.423 0.133 0.300 - - - 85.60 89.32% V. Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Const. of Namuac Bridge Protection Works 03/31/11 II 9.647 180 C 0.426 0.133 0.300 - - - 85.90*85.90%

    Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Rehab. of Pamplona Bridge, Phase 3 03/30/11 II 14.473 210 C 0.417 0.133 0.300 - - - 85.00 *85.00% Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Const. of Lucban Flood Control Project, (Ph-3) 03/30/11 II 17.368 240 C 0.407 0.133 0.300 - - - 84.00*84.00%

    Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Const. of Sto. Tomas Farm-to-Market Road 03/31/11 II 0.962 199 C 0.410 0.133 0.300 - - - 84.3084.00%

    Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Restoration of Slope Protection KO591+320 - KO591+353, MNR 08/19/10 II 1.928 120 C 0.434 0.200 0.300 - - - 93.4093.40%

    V. Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Const. of Slope Protection at KO673+000 - KO673+853 MNR 08/19/10 II 1.929 90 C 0.420 0.200 0.300 - - - 92.0092.00%

    V. Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page22

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366Emergency Rehab. of Slope

    Protection KO600+525 - KO602+200, MNR

    08/19/10 II 4.195 90 C 0.347 0.200 0.300 - - - 84.70 87.58% Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Conc. along Claveria Dibalio-Luzon-Cagayan Bdry. Road 08/19/10 II 2.938 153 C 0.374 0.200 0.300 - - - 87.4087.40%

    Satisfactory

    Abulug Developers and Builders Co., Inc.

    (Formerly: F. Vargas Construction)

    2366 Retrofitting of Pamplona Bridge, Manila North Road 02/24/09 II 10.290 180 C 0.386 0.200 0.300 - - - 88.6082.96%

    Satisfactory

    Aca Construction & Supply 10784

    Construction of Multi-Purpose Building, Bancagan 02/26/09 I 0.096 30 C 0.417 0.133 0.300 - - - 85.00

    *85.00%Satisfactory

    Aca Construction & Supply 10784 Construction of Water Supply 02/26/09 I 0.096 30 C 0.338 0.188 0.300 - - - 82.60

    *82.60%Satisfactory

    Aca Construction & Supply 10784 Repair of Farm-to-Market Road 02/26/09 I 0.480 30 C 0.343 0.200 0.300 - - - 84.30

    *84.30%Satisfactory

    Acer Industrial/Solid Rock Construction Joint

    Venture

    SLI-SN-005433/JV-

    08-217

    Rehabilitation of Libingan ng mga Bayani Road-MRT Road 05/27/09 NCR 4.694 75 C 0.396 0.133 0.300 - - - 82.90

    *82.90% Satisfactory

    ACJ Construction Resources 10635

    Road Upgrading of Nat'l Rd. (Gravel to Concrete) Nat'l Secondary Rd., Km.1628+584-Km.1630+803 along Kidapawan-Magpet-Pangao-an Rd.

    08/17/11 XII 24.178 180 O 0.342 0.300 0.000 0.030 0.045 0.033 75.00 -

    ACJ Construction Resources 10635

    Road Upgrading of Nat'l Rd. (Gravel to Concrete) Nat'l Secondary Rd.,

    Km.1629+(-124) - Km.1630+133 along Magpet-Nowa-Doroluman-Greenfield

    Rd.

    08/17/11 XII 22.850 200 O 0.350 0.278 0.000 0.030 0.040 0.033 73.10 -

    ACJ Construction Resources 10635

    Conc. of Magpet Binay-Noa-basak-Arakan Road (Noa-Bagumbayan

    Sect.)04/02/11 XII 18.363 224 C 0.410 0.140 0.300 - - - 85.00 *85.00% Satisfactory

    ACJ Construction Resources 10635

    Conc. Of Paco-Roxas-Arakan Valley Road, Luhong Section along Paco-

    Roxas-Arakan Valley Road04/02/11 XII 18.453 200 C 0.391 0.145 0.300 - - - 83.60 *83.60% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page23

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    ACJ Construction Resources 10635

    Conc. of Paco-Roxas-Arakan Road Kiyaab-Antipas Section (Km. 1648+300-Km.1649+385.63)

    09/05/09 XII 16.826 150 O 0.324 0.300 0.150 0.015 0.042 0.050 88.10 -

    ACJ Construction Resources 10635

    Conc. of Poblacion-Magpet-Nowa Road, Nowa-Basak Section w/

    exception09/05/09 XII 18.798 200 C 0.358 0.200 0.300 - - - 85.80 84.30% Satisfactory

    ACJ Construction Resources 10635

    Asphalt Overlay along Davao-Cotabato Rd., Saguing Section 03/01/10 XII 6.765 68 C 0.429 0.200 0.300 - - - 92.90

    92.90% V. Satisfactory

    ACJ Construction Resources 10635

    Const. of Kinamalig Bridge including Concrete Paving of Approach along

    Paco-Roxas-Arakan03/02/10 XII 12.815 202 C 0.384 0.142 0.300 - - - 82.60 86.08% Satisfactory

    ACJ Construction Resources 10635

    Conc. of Paco-Roxas-Arakan Road, Kiyab-Antipas Section, Km. 1648+300-Km. 1649+385.63

    03/02/10 XII 16.826 175 C 0.379 0.143 0.300 - - - 82.20 85.71% Satisfactory

    ACJ Construction Resources 10635

    Conc. of Paco-Roxas-Arakan Road, inclined Gap Ipuan Section, Km. 1640+374.10 - Km. 1646+794.28

    03/02/10 XII 13.144 189 C 0.394 0.145 0.300 - - - 83.90 83.90% Satisfactory

    ACJ Construction Resources 10635

    Rehab./Reconst. of Damaged Paved along Makilala-Allah Junction Road,

    La Esperanza Section06/05/10 XII 9.961 55 C 0.436 0.133 0.300 - - - 86.90 86.90% Satisfactory

    ACJ Construction Resources 10635

    Rehab./Reconst. of Damage Paved along Matalam-M'lang-Bagontapay

    Road06/05/10 XII 14.307 60 C 0.424 0.133 0.300 - - - 85.70 85.70% Satisfactory

    ACJ Construction Resources 10635

    Road Upgrading of Matalam-Mlang-Bagontapay Road, Additional Lane

    (Poblacion Section)08/27/10 XII 18.338 153 C 0.476 0.127 0.300 - - - 90.30 90.30% V. Satisfactory

    ACJ Construction Resources 10635

    Concreting of Paco-Roxas-Arakan Road (Luhong-Kiyaab Section) 05/30/09 R-XII 18.566 205 C 0.338 0.200 0.300 - - - 83.80

    88.42% Satisifactory

    ACJ Construction Resources 10635

    Concreting of Poblacion Magpet-Nowa Road (Nowa Basak Sect.) 03/10/09 XII 18.798 180 O 0.356 0.284 0.150 0.030 0.035 0.050 90.50 -

    Acme Builders Corp./MWJ Construction

    JV JV-08-243

    Conc. of Burauen-Albuena Road Km. 98+986.50-Km. 986+857.50 w/

    exceptions02/22/10 VIII 46.887 240 C 0.411 0.200 0.300 - - - 91.10 91.10% V. Satisactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page24

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Acme Builders Corporation 6442

    Const. Of Nijaga Bridge along Calbayog Diversion Road (Phase II) 08/17/11 VIII 37.279 300 O 0.383 0.182 0.150 0.030 0.055 0.033 83.30 -

    Acme Builders Corporation 6442

    Repair/Rehab. of Mainit Bridge along Palo-Carigara-Ormoc Road 08/24/11 VIII 14.198 120 C 0.481 0.174 0.300 - - - 95.50

    *95.50% V. Satisfactory

    Acme Builders Corporation 6442

    Const./Completion/Continuation/On-going of Nijaga Bridge along

    Calbayog Diversion Road, Brgy. Nijaga

    04/02/11 VIII 27.000 180 C 0.474 0.133 0.300 - - - 90.70 *90.70% V. Satisfactory

    Acme Builders Corporation 6442

    Const. of Palo-East-By-Pass Road (including Bridge) 03/28/11 VIII 28.783 125 C 0.447 0.133 0.300 - - - 88.00

    88.48% Satisfactory

    Acme Builders Corporation 6442

    Const. of Nijaga Bridge Along Calbayog Diversion Road (Phase II) 04/02/11 VIII 37.279 300 O 0.400 0.240 0.150 0.020 0.040 0.033 88.30 -

    Acme Builders Corporation 6442

    Rehab./Reconst./Upgrading of Daang Maharlika, Palo-Tolosa Road Sect.,

    Km.915+500 - Km.921+70004/06/11 VIII 24.050 200 C 0.423 0.133 0.300 - - - 85.60 87.04% Satisfactory

    Acme Builders Corporation 6442 Const. of Palo East By-Pass Road 03/11/10 VIII 19.260 240 C 0.436 0.200 0.300 - - - 93.60

    89.76% V. Satisfactory

    Acme Builders Corporation 6442

    Rehab./Reconst./Impvt./Upgrading of Damaged Pavement, Tacloban

    Baybay South Rd.06/17/10 VIII 34.600 150 O 0.366 0.300 0.150 0.030 0.032 0.033 91.10 -

    Acme Builders Corporation 6442

    Rehab./Reconst./Impvt./Upgrading of Damaged Pavement, Tacloban

    Baybay South Road09/08/10 VIII 33.358 150 C 0.398 0.133 0.300 - - - 83.10 87.90% Satisfactory

    Acme Builders Corporation 6442 Construction of Sinugbuhan Bridge 06/04/09 VI 33.384 676 C 0.441 0.133 0.300 - - - 87.40

    85.20% Satisfactory

    Acme Builders Corporation 6442

    Asphalt Overlay along Tigbao-Pulak-Sta. Fe Road, Km 925+370-Km

    926+37903/18/09 VIII 11.310 90 C 0.393 0.133 0.300 - - - 82.60 *82.60%Satisfactory

    Acme Builders Corporation 6442 Construction of Bagacay Bridge 03/02/09 VIII 39.122 332 O 0.319 0.288 0.000 0.030 0.023 0.050 71.00 -

    Acme Builders Corporation 6442 Rehabilitation of Mahayahay Creek 03/03/09 VIII 6.709 170 C 0.375 0.133 0.300 - - - 80.80

    84.10%Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page25

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Acme Builders Corporation / B. Vicencio

    ConstructionJV-07-066 Const. of Palo East By Pass Road (Const. of Bernard Reed II Bridge) 08/31/09 VIII 57.823 616 O 0.384 0.240 0.150 0.030 0.047 0.033 88.40 -

    Acme Builders Corporation / MWJ Construction (JV)

    JV-08-243 Const. of Albuera-Burauen Road including Bridges, Burauen Sect. 09/02/09 VIII 47.235 240 O 0.352 0.245 0.150 0.030 0.045 0.050 87.20 -

    ACV Construction & Surveying 10903

    Concreting of FMR @ Various Brgys., Urbiztondo and Mangatarem 03/09/09 I 3.838 60 C 0.353 0.200 0.300 - - - 85.30

    *85.30%Satisfactory

    ADB Dynamic Builders & Supply 33359

    Repair/Rehab. of St., Brgy. Dalupirit; Rehab. of San Roque St., Brgy.

    Vinisitahan; Rehab./Repair of St., Brgy. Pilar

    03/07/09 VIII 1.437 60 C 0.463 0.200 0.300 - - - 96.30 *96.30% Outstanding

    Adelfa & Charlie Enterprises 11569

    Construction of MPP Brgy. Hibulangan 03/11/09 VIII 0.142 30 C 0.433 0.133 0.300 - - - 86.60

    *86.60%Satisfactory

    Adfil Corporation 14437Rehab. of Magaboy and Lucena Bridge Approaches-Slope/Bank

    Protection06/13/10 XIII 4.709 105 C 0.450 0.200 0.300 - - - 95.00 95.00% V. Satisfactory

    Adfil Corporation 14437 Rehab. of River Dike 06/01/10 XIII 9.649 150 C 0.408 0.179 0.300 - - - 88.70 88.46% Satisfactory

    Adfil Corporation 14437Repair/Maintenance with Asphalt

    Overlay of Tabon-Tabon Slip along Agusan- Davao Road

    06/17/10 XIII 32.364 225 O 0.371 0.240 0.150 0.030 0.055 0.033 87.90 -

    Adfil Corporation 14437 Rehab. of Magsaysay Bridge along Iligan City 09/09/10 XIII 48.161 300 O 0.352 0.300 0.150 0.030 0.055 0.050 93.70 -

    Adfil Corporation 14437 Completion/Continuation of Libertad Bridge & Approaches 09/08/10 XIII 11.224 180 C 0.462 0.189 0.300 - - - 95.1092.58%

    V. Satisfactory

    Adfil Corporation 14437Rehab./Along Reconst. of Daang

    Maharlika (Agusan-Surigao Road) Ampayon-Taguibo Sect.

    09/09/10 XIII 35.253 270 C 0.400 0.200 0.300 - - - 90.00 90.54% V. Satisfactory

    Adfil Corporation 14437Repair/Maintenance with Asphalt

    Overlay of Tabon-Tabon Slip along Agusan-Davao Road

    09/06/10 XIII 32.398 225 C 0.440 0.133 0.300 - - - 87.30 87.66% Satisfactory

    Adfil Corporation 14437Rehab./Reconst. of Damaged Paved National Roads Gingoog-Calveria-

    Villanueva Road09/10/09 X 96.400 405 O 0.259 0.300 0.150 0.030 0.061 0.050 85.00 -

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page26

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Adfil Corporation 14437 Rehab./Reconst. of NRJ Bahbah-Talacogon Road 06/09/09 XIII 19.263 220 C 0.485 0.200 0.300 - - - 98.50*98.50%

    Outstanding

    Adfil Corporation 14437

    Repair/Rehab./Impvt. of Roads & Bridges along the National Highway Epoxy Sealing of Cracks in concrete girder, deck slab & conc. Pavement

    (injectable epoxy) along Bahbah, Talacogon Road

    06/09/09 XIII 9.429 180 C 0.464 0.200 0.300 - - - 96.40 *96.40% Outstanding

    Adfil Corporation 14437 Rehabilitation/Concreting of Tagcatong-Vinapor Road 05/25/09 XIII 9.629 210 C 0.489 0.133 0.300 - - - 92.20*92.20%

    V. Satisfactory

    Adfil Corporation 14437 Conc. of Dapa-Junction Cancohoy Road 03/07/09 XIII 28.451 241 C 0.414 0.200 0.300 - - - 91.4088.94%

    Satisfactory

    Adfil Corporation 14437Rehab./Reconst. of Damaged Paved

    National Road along Agusan-Misamis Road

    03/02/09 XIII 9.634 180 C 0.405 0.200 0.300 - - - 90.50 86.36% Satisfactory

    Adfil Corporation 14437Rehab./Reconst. of Damaged Paved

    National Road along Agusan-Surigao Road

    03/03/09 XIII 9.635 180 C 0.408 0.200 0.300 - - - 90.80 87.50% Satisfactory

    Adfil Corporation 14437Repair/Reconst. of Butuan City-

    Cagayan de Oro-Iligan Road (Agusan-Misamis Oriental Road) inc. Bridge

    03/18/09 XIII 19.198 210 C 0.402 0.200 0.300 - - - 90.20 89.06% V.Satisfactory

    Adfil Corporation 14437 Repair/Rehab. of NRJ Bahbah-Talacogon Road 03/20/09 XIII 9.633 188 C 0.431 0.200 0.300 - - - 93.1087.04%

    Satisfactory

    Adfil Corporation 14437

    Rehab./Reconst. of Damaged Paved National Rd. along Butuan City-CDO-Iligan Rd.,(Agusan-Misamis Oriental

    Sect.)Libertad-Bancasi Sect.

    09/16/09 XIII 54.954 285 O 0.371 0.300 0.150 0.030 0.055 0.050 95.60 -

    Adfil Corporation 14437Const./Completion/Continuation of Unfinished Bridge and Approaches,

    Brgy. Libertad09/16/09 XIII 23.830 195 O 0.364 0.300 0.150 0.030 0.055 0.050 94.90 -

    Adfil Corporation 14437 Rehab. of NRJ-Bahbah-Talacogon Rd. 09/13/09 XIII 14.427 210 C 0.416 0.194 0.300 - - - 91.0094.66%

    V.Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page27

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Adfil Corporation 14437 Concreting of NRJ-Bahbah-Talacogon Rd. 09/13/09 XIII 15.872 225 O 0.371 0.244 0.150 0.030 0.065 0.050 91.00 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc. of Butuan City-Pianing/Tandag Road 08/24/11 XIII 14.808 180 O 0.341 0.300 0.150 0.030 0.048 0.050 91.90 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437

    Widening/Conc. of Additional Lane Both Directions along Butuan City-

    Cagayan de Oro-Iligan Road, Ampayon-Baan Section

    08/24/11 XIII 26.233 240 O 0.338 0.300 0.150 0.030 0.048 0.050 91.60 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437Reconst. of Slip Sect. along Daang

    Maharlika (Agusan-Davao Road) Lapinigan Sect.

    08/22/11 XIII 17.326 220 O 0.378 0.263 0.150 0.030 0.043 0.050 91.40 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc. of Butuan City-Pianing/Tandag Road 08/24/11 XIII 9.021 105 C 0.474 0.133 0.300 - - - 90.7091.24%

    V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Const. of Hawaiian-Salug-Sinakungan Road 08/26/11 XIII 86.118 334 C 0.430 0.181 0.300 - - - 91.10*91.10%

    V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Rehab. of Wawa Bridge along Agusan-Davao Road 08/26/11 XIII 110.847 469 C 0.469 0.133 0.300 - - - 90.2090.68%

    V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437Repair of Taguibo Bridge and

    Approaches along Daang Maharlika (Surigao-Agusan Road)

    08/23/11 XIII 8.671 90 C 0.459 0.143 0.300 - - - 90.20 *90.20% V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437Completion of Bislig Bridge along

    Surigao-Davao Coastal Road (Demolition of Old Bridge-Phase I)

    08/17/11 XIII 13.043 285 O 0.334 - 0.200 0.050 0.062 0.250 89.60 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437Conc. of NRJ Cuevas-Bislig Road,

    Phase II, Sta. 1375+369-Sta. 1380+840

    08/22/11 XIII 26.309 245 O 0.349 0.271 0.150 0.030 0.043 0.050 89.30 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Overlay of Daang Maharlika (Surigao-Agusan Sect.) 08/09/11 XIII 11.604 75 C 0.438 0.133 0.300 - - - 87.10*87.10%

    Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page28

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Reconst. of Maglambing Bridge and Approaches 08/17/11 XIII 65.519 521 O 0.376 0.288 0.104 0.030 0.032 0.017 84.70 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Const. of Tubay-Lake Mainit Circ. Road, Tubay-Jabonga 08/09/11 XIII 96.417 438 C 0.445 0.026 0.300 - - - 77.1082.56%

    Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437Rehab. of Taguibo Steel Bridge

    along Daang Maharlika (Surigao-Agusan Road), Brgy. Taguibo

    04/11/11 XIII 9.601 180 C 0.500 0.133 0.300 - - - 93.30 *93.30% V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc. of Pulang Lupa-Sta. Josefa Road 04/01/11 XIII 19.249 195 C 0.439 0.200 0.300 - - - 93.9092.91%

    V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437Rehab. of Magsaysay Bridge along Iligan City-Cagayan de Oro-Butuan

    City Road04/13/11 XIII 48.161 300 C 0.476 0.134 0.300 - - - 91.00 92.62% V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc./Repair of Slip along NRJ-Cuevas-Sampaguita Rd. 04/01/11 XIII 47.951 470 C 0.478 0.133 0.300 - - - 91.1091.19%

    V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437Rehab./Reconst. of Butuan-Cagayan

    de Oro-Iligan Road inc. Bridges (Agusan-Mis. Or. Road)

    04/12/11 XIII 8.595 105 C 0.474 0.133 0.300 - - - 90.70 *90.70% V. Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Reconst. of Maglambing Bridge and Approaches 04/02/11 XIII 96.519 521 O 0.343 0.300 0.150 0.030 0.048 0.033 90.40 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc. of NRJ Cuevas-Bislig Road, Phase II 04/01/11 XIII 26.309 245 O 0.377 0.247 0.150 0.030 0.048 0.050 90.20 -

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc. of Butuan City-Pianing-Tandag Road 04/13/11 XIII 18.905 270 C 0.347 0.200 0.300 - - - 84.7088.96%

    Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc. of NRJ Cuevas-Sampaguita Road 04/01/11 XIII 60.039 270 C 0.367 0.200 0.300 - - - 86.7088.14%

    Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437Rehab. of Butuan City-Cagayan de Oro-Iligan Road (Agusan-Misamis

    Oriental Road)04/11/11 XIII 105.122 210 C 0.322 0.200 0.300 - - - 82.20 86.70% Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page29

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Const. of River Dike Protection, Brgy. Agao 03/10/10 XIII 9.556 90 C 0.485 0.133 0.300 - - - 91.8091.80%

    V.Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437Impv't./Rehab. of Iligan-Cagayan-

    Butuan Rd. (Agusan-Misamis Oriental Section)

    02/23/10 XIII 67.446 180 C 0.480 0.133 0.300 - - - 91.30 91.30% V.Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Const./Conc. of NRJ San Francisco-Bahi Rd. 03/07/10 XIII 28.892 330 C 0.431 0.133 0.300 - - - 86.4091.20%

    V.Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Upgrading/Conc. of NRJ Cuevas-Bislig Rd. 03/07/10 XIII 28.874 315 C 0.485 0.133 0.300 - - - 91.8090.66%

    V.Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Conc. of Dapa-Del Carmen (Sayak-Airport Rd.) 02/26/10 XIII 75.947 390 C 0.456 0.133 0.300 - - - 88.9088.90%

    Satisfactory

    Adfil Corporation (Formerly: Adfil Construction)

    14437 Rehab./Reconst. of Damaged Rd. Gingoog-Claveria-Villanueva Rd. 03/10/10 X 96.400 405 C 0.437 0.200 0.300 - - - 93.7089.71%

    V.Satisfactory

    Adfil Corporation/RID Corporation (JV) JV-06-022

    Repair/Rehab. of Patin-ay Bridge along Agusan-Davao Road, Patin-ay 06/08/09 XIII 23.749 658 C 0.458 0.200 0.300 - - - 95.80

    91.84% V. Satisfactory

    Adige Sta. Clara (JV) JV-06-032DPWH Component Project under the

    Help for Catubig Agricultural Advancement Proj.

    05/30/09 VIII 519.663 1,073 O 0.378 0.300 0.150 0.030 0.050 0.050 95.80 -

    Adige Sta. Clara (JV) JV-06-032DPWH Component Project under the

    HELP for Catubig Agricultural Project (HCAAP)

    08/25/08 VIII 448.581 734 O 0.377 0.300 0.070 0.030 0.050 0.067 89.40 -

    Adimre Construction 25534 Marilao Port Development Project 08/20/09 DOTC 2.862 60 C 0.451 0.200 0.300 - - - 95.10 *95.10% V. Satisfactory

    Adimre Construction 25534 Sta. Cruz Port Development Project 08/20/09 DOTC 0.960 30 C 0.460 0.200 0.300 - - - 96.00 96.00% V. Satisfactory

    Adimre Construction 25534 Sasmuan Port Development Project 08/20/09 DOTC 2.871 60 C 0.459 0.200 0.300 - - - 95.90 95.90% V. Satisfactory

    Adimre Construction 25534 Hagonoy Port Development Project 10/02/09 DOTC 0.949 30 C 0.460 0.200 0.300 - - - 96.00 96.00% Outstanding

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page30

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    Adimre Construction 25534 Baguio Airport Development Project 04/04/09 DOTC 861.940 60 C 0.435 0.181 0.300 - - - 91.60 91.60% V. Satisfactory

    Adimre Construction 25534

    Dumaguete Airport Dev't Project (Completion of Imprv't of Terminal Building and Purchase/ Installation

    of Bagage Conveyor)

    01/21/10 DOTC 13.500 90 C 0.402 0.199 0.300 - - - 90.10 90.10% V.Satisfactory

    Adimre Construction 25534Tuguegarao Airport Dev't Project

    (Continuation of Widening of Runway)

    03/04/10 DOTC 9.588 90 C 0.452 0.200 0.300 - - - 95.20 95.20% V.Satisfactory

    Adimre Construction 25534

    Tuguegarao Airport Dev't Project (Continuation of Widening of

    Runway and Improvement of Fire Station Building)

    03/04/10 DOTC 12.490 90 C 0.458 0.200 0.300 - - - 95.80 95.80% V.Satisfactory

    Adimre Construction 25534

    Laoag Airport Development Project (Upgrading of Radar Area,

    Continuation of Perimeter Fence Construction of Drainage System)

    04/09/10 DOTC 9.604 120 C - 0.419 0.200 0.300 - - 91.90 91.90% V. Satisfactory

    Adimre Construction 25534Laoag Airport Development Project

    (Improvement of Fire Station Building)

    04/09/10 DOTC 4.821 120 C 0.464 0.200 0.300 - - - 96.40 96.40% Outstanding

    Adimre Construction 25534Laoag Airport Development Project

    (Shoulder Grade Correction including Drainage System)

    04/09/10 DOTC 4.793 75 C 0.410 0.200 0.300 - - - 91.00 91.00% V. Satisfactory

    Adimre Construction 25534Tuguegarao Airport Development Project (Repair/Rehabilitation of

    Terminal Building)09/10/10 DOTC 1.927 90 C 0.449 0.200 0.300 - - - 94.90 94.90% V. Satisfactory

    Adimre Construction 25534 Canalate Port Development Project (Improvement of Port) 12/03/10 DOTC 1.919 60 C 0.458 0.200 0.300 - - - 95.8095.80%

    V. Satisfactory

    Adimre Construction 25534Const. of Standard One Classroom

    School Building (Modified) at GITMES

    09/05/09 III 0.526 24 C 0.442 0.133 0.300 - - - 87.50 *87.50% Satisfactory

    Adimre Construction 25534

    Camiguin Ports Cluster Project (Construction of Seawall Enclosure

    at Benoni Port and Repair of Causeway at Catarman Port)

    02/17/11 DOTC 6.231 60 C 0.419 0.200 0.300 - - - 91.90 91.90% V. Satisfactory

    * 1st/Final* For DPWH, only the region and PMO office are listed 15th CPES Release Page31

  • CIAP-PDCB CONSTRUCTORS PERFORMANCE SUMMARY REPORTCPES Reports-On-going and Completed Projects from July 01, 2010 to June 30, 2012

    ESH RDRSTATUSCPES VISIT

    RATINGWMS MTL TIME FACPROJECT DATE OF EVALUATION

    FINAL RATING/ QUALITATIVE DESCRIPTION

    AMOUNT (Php, M) DUR (C.D.)

    CONTRACT*IMPL.

    AGENCYNAME OF

    CONSTRUCTORLICENSE

    NO.

    ADP Const. & Supply 3466 Impvt./Conc. of Access Road, Tubalan Port, Tubalan 04/01/11 XI 58.261 320 C 0.135 0.200 0.000 - - - 33.5061.25% Poor

    Adriot Construction 11169 Const. of Bridge, Brgy. Conversion 08/11/11 III 1.137 45 C 0.467 0.200 0.300 - - - 96.70 *96.70% Outstanding

    Adroit Construction 11169 Const. of 2-CL, Sta. Barbara E/S 04/08/11 III 1.324 60 C 0.45 0.048 0.300 - - - 79.80 *79.80% Unsatisfactory

    Adroit Construction 11169 Completion of Bridge, General Luna 2nd Phase 03/02/09 III 3.026 30 C 0.332 0.200 0.300 - - - 83.20*83.20%

    Satisfactory

    Adroit Construction 11169 Concreting of Brgy. Maligaya Road 03/02/09 III 1.867 25 C 0.404 0.133 0.300 - - - 83.70 *83.70%Satisfactory

    Advance Foundation Const. System Corp. /

    Abulug Developer Builders Const. Inc. (JV)

    JV-09-289 Const. of Gov. Edgar R. Lara Bridge along Cagayan-Apayao Road 03/30/11 II 112.029 240 O 0.360 0.300 0.000 0.023 0.051 0.017 75.10 -

    Advanced Foundation - IBC (JV) JV-09-265

    Replacement of E. Marcos Bridge, Km.28+310 along Maasin-Cabatuan

    Roa